Supreme Court dismisses cassation complaints in a construction contract dispute over unpaid engineering services.
Sintesi Legislator
Generato dall'IAThe Supreme Court dismissed both the plaintiff's and defendant's cassation complaints regarding a dispute over unpaid engineering services. The lower courts ruled that the plaintiff failed to prove the existence of a valid contract or the specific amount owed. Consequently, the court upheld the final judgment against the plaintiff's claim for payment.
Regesto Legislator
Generato dall'IAArt. 385 § 1 pkt 1 k.p.c.; Art. 386 § 1 pkt 1 k.p.c.: The Supreme Court dismisses cassation complaints when the lower court's judgment is based on a correct application of law and undisputed facts, or when the complaint fails to demonstrate a violation of the law.
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IATesto completo
Sygn. akt III CSK 108/20 POSTANOWIENIE Dnia 17 kwietnia 2021 r.Sąd Najwyższy w składzie: SSN Grzegorz Misiurek w sprawie z powództwa Przedsiębiorstwa Robót Inżynieryjnych "K.”sp. j. w M. przeciwko E. S.A. w S. o zapłatę,na posiedzeniu niejawnym w Izbie Cywilnej w dniu 17 kwietnia 2021 r.,na skutek skargi kasacyjnej strony pozwanej oraz skargi kasacyjnej strony powodowej od wyroku Sądu Apelacyjnego w (…)z dnia 12 września 2019 r., sygn. akt I AGa (…), przyjmuje obie skargi kasacyjne do rozpoznania.