Legislator Giurisprudenza & Legislazione
II PK 358/04 Generato dall'IA

Supreme Court held the seven-day work readiness deadline is a substantive right not subject to extension under procedural law.

Numero d'incarto II PK 358/04
Autorità giudiziaria
Giurisdizione Polonia (PL)
Data della decisione
Esito del giudizio Parzialmente accolto (Partially Allowed)

Sintesi Legislator

Generato dall'IA

The Supreme Court reversed the lower court's dismissal of the employee's claim regarding a missed seven-day deadline to report work readiness. The employee argued the delay was caused by his lawyer failing to inform him of a reinstatement judgment, while the employer contended the delay was attributable to the employee. The court ruled that the deadline is a substantive right governed by material law, meaning procedural extensions do not apply, but the employee can still prove the delay resulted from independent causes.

Regesto Legislator

Generato dall'IA

Art. 48 § 1 k.p.; Art. 168, 169 k.p.c.: The seven-day deadline for reporting readiness to resume work is a substantive right that does not admit of extension under procedural law, though the employee may demonstrate the delay occurred due to causes independent of them.

Parole chiave

Generato dall'IA
substantive right deadline work readiness reporting procedural extension bar independent cause defense labor reinstatement legal representation fault material law priority

Disposizioni normative citate

Generato dall'IA
Art. 48 § 1 k.p.
Art. 168 k.p.c.
Art. 169 k.p.c.
Art. 393 § 15 k.p.c.
art. 48 § 1 k.p
art. 39315 k.p.c

Giurisprudenza citata

Generato dall'IA

Ti chiedi come si applica questa sentenza alla tua fattispecie?

Analizza questa decisione insieme alla legislazione federale e cantonale, ai commentari e alla giurisprudenza successiva in Legislator AI.

Apri in Legislator →

Testo completo