Consequences of phased construction of development facilities and provisional measures on contribution levies

Numéro de cause 9 B 24/15, 9 B 24/15 (9 C 21/15)
Autorité / Tribunal
Juridiction Allemagne (DE)
Date de la décision
Issue du litige Admis (Allowed)

Synthèse Legislator

Généré par l'IA

The Federal Administrative Court (BVerwG) dismissed the defendant's objection, upholding the lower court's decision to allow the appeal on points of law (Revision) and provisionally setting the amount in dispute for the appeal proceedings. The dispute concerned public construction law, specifically the levying of development contribution fees (Erschließungsbeiträge) in a case involving the phased creation of a development facility accompanied by the execution of provisional measures. The court granted the appeal under § 132 Abs. 2 Nr. 1 VwGO, determining that the matter has fundamental significance because it requires the appellate senate to clarify the legal consequences of incrementally constructing development infrastructure and implementing interim solutions. The provisional determination of the litigation value was based on § 47 Abs. 1 Satz 1, § 52 Abs. 3, and § 63 Abs. 1 Satz 1 GKG.

Regeste Legislator

Généré par l'IA

§ 132 Abs. 2 Nr. 1 VwGO, § 63 Abs. 1 Satz 1 GKG, § 47 Abs. 1 Satz 1 GKG, § 52 Abs. 3 GKG; Consequences of phased construction of development facilities and provisional measures on contribution levies: The dispute concerned public construction law, specifically the levying of development contribution fees (Erschließungsbeiträge) in a case involving the phased creation of a development facility accompanied by the execution of provisional measures. The court granted the appeal under § 132 Abs. 2 Nr. 1 VwGO, determining that the matter has fundamental significance because it requires the appellate senate to clarify the legal consequences of incrementally constructing development infrastructure and implementing interim solutions. The provisional determination of the litigation value was based on § 47 Abs. 1 Satz 1, § 52 Abs. 3, and § 63 Abs. 1 Satz 1 GKG.

Mots-clés

Généré par l'IA
subvention pour la construction litige en matière de contributions publiques mesures provisoires procédure de révision honoraires d'avocat contributions d'équipement

Dispositions légales citées

Généré par l'IA
§ 132 Abs. 2 Nr. 1 VwGO
Main ground for admitting the appeal on points of law due to the fundamental significance of the legal issue.
§ 63 Abs. 1 Satz 1 GKG
Procedural basis cited for the provisional calculation of the amount in dispute.
§ 47 Abs. 1 Satz 1 GKG
Procedural basis for the provisional determination of the amount in dispute in the appeal proceedings.
§ 52 Abs. 3 GKG
Procedural basis cited for the provisional calculation of the amount in dispute.
Généré par l'IA

Questions juridiques clés extraites par Legislator

Généré par l'IA
§ 132 Abs. 2 Nr. 1 VwGO

Main ground for admitting the appeal on points of law due to the fundamental significance of the legal issue.

§ 47 Abs. 1 Satz 1 GKG

Procedural basis for the provisional determination of the amount in dispute in the appeal proceedings.

§ 52 Abs. 3 GKG

Procedural basis cited for the provisional calculation of the amount in dispute.

§ 63 Abs. 1 Satz 1 GKG

Procedural basis cited for the provisional calculation of the amount in dispute.

Vous souhaitez savoir comment cet arrêt s'applique à votre dossier ?

Analysez cette décision avec la législation fédérale, le droit cantonal, la doctrine et la jurisprudence subséquente dans Legislator AI.

Ouvrir dans Legislator →

Texte complet

Revisionszulassung; schrittweise Herstellung einer Erschließungsanlage; provisorische Maßnahmen

[GRUENDE]

Die Beschwerde der Beklagten ist zulässig und begründet. Die Revision ist gemäß § 132 Abs. 2 Nr. 1 VwGO wegen grundsätzlicher Bedeutung der Rechtssache zuzulassen. Sie kann dem Senat Gelegenheit zur Klärung der erschließungsbeitragsrechtlichen Folgen einer schrittweisen Herstellung einer Erschließungsanlage einschließlich der damit einhergehenden Durchführung provisorischer Maßnahmen geben.

Die vorläufige Festsetzung des Streitwerts für das Revisionsverfahren folgt aus § 47 Abs. 1 Satz 1, § 52 Abs. 3, § 63 Abs. 1 Satz 1 GKG.