Technical Study Office Liability for Water Infiltration Despite Contractual Limitation

Numéro de cause 78-15366
Autorité / Tribunal
Juridiction France (FR)
Date de la décision
Issue du litige Rejeté (Dismissed)

Synthèse Legislator

Généré par l'IA

A technical study office responsible for inspection and monitoring during real estate construction was held partially liable for water infiltration damage in terraces, despite a contractual clause limiting its liability after acceptance of the works. The appellate court found that the office gravely failed in its contractual obligation to examine the quality of the work as it progressed, as a simple site visit before concrete pouring would have revealed a fundamental error in the waterproofing technique used, constituting gross negligence that precluded the office from relying on the contractual limitation of liability clause.

Regeste Legislator

Généré par l'IA

Technical Study Office Liability for Water Infiltration Despite Contractual Limitation: The appellate court found that the office gravely failed in its contractual obligation to examine the quality of the work as it progressed, as a simple site visit before concrete pouring would have revealed a fundamental error in the waterproofing technique used, constituting gross negligence that precluded the office from relying on the contractual limitation of liability clause.

Mots-clés

Généré par l'IA
responsabilité pour dégâts d'eau négligence grave obligations contractuelles biens immeubles étude du travail qualité de l’eau
Généré par l'IA

Questions juridiques clés extraites par Legislator

Généré par l'IA
REJETTE LE POURVOI FORME CONTRE L'ARRET RENDU LE 27 JUIN 1978 PAR LA COUR D'APPEL DE PARIS.

This is the dispositive order rejecting the appeal.

Vous souhaitez savoir comment cet arrêt s'applique à votre dossier ?

Analysez cette décision avec la législation fédérale, le droit cantonal, la doctrine et la jurisprudence subséquente dans Legislator AI.

Ouvrir dans Legislator →

Texte complet

SUR LE MOYEN UNIQUE :

ATTENDU QUE LE BUREAU D'ETUDES TECHNIQUES DE CONSTRUCTIONS (BETC) QUI A ETE CHARGE D'UNE MISSION DE CONTROLE ET DE SURVEILLANCE DANS LA REALISATION D'UN ENSEMBLE IMMOBILIER POUR LE COMPTE DE LA SOCIETE RESIDENCE DE L'HORIZON, FAIT GRIEF A L'ARRET ATTAQUE (PARIS, 27 JUIN 1978) DE L'AVOIR, EN ECARTANT UNE CLAUSE DU CONTRAT DECLARE PARTIELLEMENT RESPONSABLE DES DOMMAGES CAUSES PAR LE DEFAUT D'ETANCHIETE DE CERTAINES TERRASSES, ALORS, SELON LE MOYEN, "QUE, D'UNE PART, LE BUREAU D'ETUDES ETANT CHARGE EXCLUSIVEMENT DE LA COORDINATION DES TRAVAUX DES ENTREPRISES ET DE LA SURVEILLANCE DE LEURS TRAVAUX, LES JUGES D'APPEL ONT MECONNU ET DENATURE LES OBLIGATIONS DES PARTIES EN REPROCHANT AU BUREAU D'ETUDES UN MANQUE DE CONTROLE DE LA CONCEPTION DES TRAVAUX BIEN QUE SA MISSION SOIT LIMITEE A LEUR EXECUTION ; QUE, D'AUTRE PART, LA SEULE MAUVAISE EXECUTION DE LA MISSION CONFIEE A UN BUREAU D'ETUDES N'EST PAS CONSTITUTIVE D'UNE FAUTE LOURDE ET QUE LE BUREAU D'ETUDES AVAIT ATTIRE L'ATTENTION DU MAITRE D'X... SUR LES VICES DE L'ETANCHEITE REALISEE" ;

MAIS ATTENDU QUE L'ARRET RELEVE, HORS LA DENATURATION ALLEGUEE, QUE LE BETC ETAIT CONTRACTUELLEMENT TENU DE PROCEDER A L'EXAMEN DE LA QUALITE DES OUVRAGES AU FUR ET A MESURE DE L'AVANCEMENT DES TRAVAUX AFIN DE FAIRE IMMEDIATEMENT APPORTER REMEDE AUX DEFECTUOSITES PAR LES ENTREPPRISES CONCERNEES, ET QU'IL A MANQUE GRAVEMENT A CETTE OBLIGATION PUISQU'UNE SIMPLE VISITE DU CHANTIER, AVANT LA POSE DES DALLES DE BETON, LUI AURAIT REVELE QU'UN SEUL PROCEDE D'ETANCHEITE AVAIT ETE UTILISE AU LIEU DE DEUX ET LUI AURAIT PERMIS DE DECELER UNE ERREUR ELEMENTAIRE POUR UN TECHNICIEN ; QUE LA COUR D'APPEL DEVANT LAQUELLE N'ETAIT PAS CONTESTEE LA VALIDITE DE LA CLAUSE DU CONTRAT STIPULANT QUE LA RESPONSABILITE DU BETC "NE POURRAIT ETRE RECHERCHEE APRES RECEPTION DES OUVRAGES" A PU ADMETTRE QUE CE BUREAU D'ETUDES AVAIT AINSI COMMIS UNE FAUTE LOURDE LUI INTERDISANT DE SE PREVALOIR DE CETTE CLAUSE ; D'OU IL SUIT QUE LE MOYEN N'EST PAS FONDE ;

PAR CES MOTIFS :

REJETTE LE POURVOI FORME CONTRE L'ARRET RENDU LE 27 JUIN 1978 PAR LA COUR D'APPEL DE PARIS.