Contractor Liability for Delayed Performance Despite Authority Modification

Numéro de cause JURITEXT000006962542
Autorité / Tribunal
Juridiction France (FR)
Date de la décision
Issue du litige Rejeté (Dismissed)

Synthèse Legislator

Généré par l'IA

A party, obligated by a contract to complete construction work by a specified date, sought to invoke the doctrine of *force majeure* to be excused from liability for delays, claiming that a subsequent, unforeseen modification of the plans by the contracting authority constituted an insurmountable obstacle. The court rejected this appeal, reasoning that while the authority's modifications did alter the execution conditions, they did not render the performance absolutely impossible, thus the contractor remained responsible for timely completion despite the changes.

Regeste Legislator

Généré par l'IA

Contractor Liability for Delayed Performance Despite Authority Modification: The court rejected this appeal, reasoning that while the authority's modifications did alter the execution conditions, they did not render the performance absolutely impossible, thus the contractor remained responsible for timely completion despite the changes.

Mots-clés

Généré par l'IA
responsabilité de l'entrepreneur notion de pouvoir adjudicateur obligation de construire contrat de sous-traitance obligation de prester de l'assureur retard injustifié
Généré par l'IA

Vous souhaitez savoir comment cet arrêt s'applique à votre dossier ?

Analysez cette décision avec la législation fédérale, le droit cantonal, la doctrine et la jurisprudence subséquente dans Legislator AI.

Ouvrir dans Legislator →

Texte complet