Contractor loses rights under Art. 54 for failing to report potential cost influence within 30 days.
Synthèse Legislator
Généré par l'IAThe contractor was declared time-barred from invoking Article 54 of the Royal Decree of 14 January 2013 regarding public procurement. The contractor failed to notify the contracting authority of a written order potentially influencing the contract's cost within the required thirty-day window. The court ruled that the obligation to report applies to the mere possibility of such influence, not its actual occurrence, and the delay rendered the claim inadmissible.
Regeste Legislator
Généré par l'IAA.R. du 14 janvier 2013, Art. 52; A.R. du 14 janvier 2013, Art. 54: A contractor loses the rights granted by Article 54 if it fails to report a written order from the contracting authority that could influence the contract's execution or cost within thirty days of becoming aware of the possibility of such influence.
Mots-clés
Généré par l'IADispositions légales citées
Généré par l'IADécisions connexes
Généré par l'IATexte complet
Fiche
L'adjudicataire est déchu des droits que lui accorde l'article
54 de l'arrêté royal du 14 janvier 2013 en raison d'un ordre
écrit du pouvoir adjudicateur susceptible d'avoir une influence
sur le déroulement et le coût du marché, s'il ne l'a signalée
dans les trente jours du moment où il a pu ou aurait dû apprécier,
non cette influence, mais l'éventualité de celle-ci (1). (1) Voir
les concl. du MP.
Thésaurus Cassation:
MARCHES PUBLICS (TRAVAUX. FOURNITURES. SERVICES)
Bases légales:
A.R du 14 janvier 2013 établissant les règles générales d'exécution des marchés publics - 14-01-2013 - Art. 52 - 09
Lien ELI No pub 2013021005
A.R du 14 janvier 2013 établissant les règles générales d'exécution des marchés publics - 14-01-2013 - Art. 54 - 09
Lien ELI No pub 2013021005