HEALTH AND SAFETY AT WORK (MINIMUM HEALTH AND SAFETY REQUIREMENTS FOR WORK AT CONSTRUCTION SITES) REGULATIONS
Table of Provisions (32)
Statutory Text (32 Articles)
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
SUBSIDIARY LEGISLATION 646.27
HEALTH AND SAFETY AT WORK (MINIMUM
HEALTH AND SAFETY REQUIREMENTS FOR
WORK AT CONSTRUCTION SITES) REGULATIONS
7th September, 2025
LEGAL NOTICE 52 of 2025, as amended by Legal Notice 109 of 2026.
(1)
The title of these regulations is the Health and
Safety at Work (Minimum Health and Safety Requirements for Work
at Construction Sites) Regulations.
(2)
The scope of these regulations is to establish the
minimum health and safety requirements for work at construction sites
and to implement amongst others the requirements of Council
Directive 92/57/EEC.
(3)
These regulations shall not apply to drilling and
extraction in the extractive industries including the activities of
prospecting and of extraction in the strict sense of the word as well as
of preparation of extracting materials for sale (crushing, screening,
washing) but they shall apply to the processing of such extracted
material.
(4)
The provisions of the General Provisions for Health and
Safety at Work Places Regulations shall be applicable mutatis
mutandis to these regulations, without prejudice to more stringent and,
or specific provisions contained in these regulations.
(regulation 2)
NON-EXHAUSTIVE LIST OF BUILDING AND CIVIL
ENGINEERING WORKS
1. Excavation
2. Earthworks
3. Construction
4. Assembly and disassembly of prefabricated elements
5. Conversion or fitting-out
6. Alterations
7. Renovation or restoration
8. Repairs
9. Dismantling
10. Demolition
11. Upkeep
12. Maintenance – painting and cleaning work
13. Drainage
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
In these regulations, unless the context otherwise
requires
"Act" means the Health and Safety at Work Act;
"the Authority" means the Occupational Health and
Safety Authority established by article 4 of the Act;
"client" means any natural or legal person for whom a
project is carried out;
"client representative" means any natural or legal person
appointed by and responsible for the design and/or execution
and, or supervision of the execution of a project, on behalf of
the client, and to carry out the duties specified in these
regulations; who shall fully assume responsibility and appear
for the client;
"competent person" means a person possessing adequate
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
qualifications and minimum accreditations in terms of law or
administrative instruments, suitable training and sufficient
knowledge, experience and skill for the safe performance of the
specific task or work required, and who provides advice with
regard to the health and safety at work preventive and protective
measures required to be taken, and whose name appears in the
competent person register administered or otherwise delegated
by the Authority in relation to such matters which are regulated
by the Authority;
"construction site" means any construction site at which
building or civil engineering works are carried out, a non-
exhaustive list of which is provided for in Schedule I;
"contractor" means a contractor, a sub-contractor, or
employer whose workers undertake, carry out or manage
construction work, including but not limited to the supply of
materials and, or labour to carry out such work. A contractor
shall also include a self-employed person unless expressly
otherwise specified;
"domestic client" means a client for whom a project is
being carried out which is not in the course or in furtherance of
the business of such client and is a person carrying out minor
works in a premises belonging to him or in premises lawfully
occupied by him;
"duty holder" means a person upon whom a duty is
imposed by virtue of these regulations, and shall include a
client, a client representative, a project supervisor for health
and safety matters, an employer, a contractor, a self-employed
person and a worker, as the case may be;
"EEA" means the members of the European Union,
Iceland, Norway and Liechtenstein;
"health and safety file" means a file containing relevant
health and safety information to be taken into account during
any subsequent works;
"health and safety plan" means a document establishing
the rules and information applicable to the construction site and
the specific measures concerning work which falls within one
or more categories of Schedule II;
"project" means any development which includes or is
intended to include any construction work from commencement
until completion of construction including finishing works;
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
"project supervisor for health and safety matters" means
any natural or legal person appointed by the client or the
client’s representative as the case may be, to carry out the duties
and exercise the powers specified in these regulations
throughout the project and whose name appears in the register
for competent persons administered or otherwise delegated by
the Authority;
"scaffold" or "scaffolding" means any temporary
structure on, or from which persons may perform work in
connection with an activity to which these regulations apply,
and any temporary structure which enables persons to obtain
access to, or which enables materials to be taken to any place at
which such work is performed, and includes any working
platform, gangway, plank, ladder or step-ladder (other than an
independent ladder or step-ladder which does not form part of
such a structure) together with any guard-rail, toe-board or
other safeguards and all accessories, but shall not include a
lifting appliance or a structure used only to support such an
appliance or to support other machinery or plant;
"self-employed person" means any person, other than a
person in employment, traineeship or apprenticeship of a
contractor, whose professional activity contributes to the
completion of the entire project.
Duties of client
(Regulations 2, 8 and 12)
NON-EXHAUSTIVE LIST OF WORK INVOLVING
PARTICULAR RISKS TO THE HEALTH AND SAFETY OF
WORKERS
1. Work which puts workers at risk of burial under earth
falls, engulfment in swampland or falling from a height, where the risk
is particularly aggravated by the nature of the work or processes used
or by the environment at the place of work or site.
2. Work which puts workers at risk from chemical or
biological substances constituting a particular danger to the health and
safety of workers or involving a legal requirement for health
monitoring.
3. Work with ionizing radiation requiring the designation of
controlled or supervised areas.
(a)
Controlled area means an area subject to special
rules for the purposes of protection against ionizing radiation
and to which access is controlled.
(b)
Supervised area means an area subject to
appropriate supervision for the purpose of protection against
ionizing radiation.
4. Work near high voltage power lines.
5. Work exposing workers to the risk of drowning.
6. Work on wells, underground earthworks and tunnels.
7. Work carried out by drivers having a system of air
supply.
8. Work carried out by workers in caisson with a
compressed-air atmosphere.
9. Work involving the use of explosives.
10. Work involving the assembly or dismantling of heavy
prefabricated components.
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
(1)
It shall be the duty of a client to appoint, in
respect of a project as is applicable under these regulations, a project
supervisor for health and safety matters, and any such appointment
may be terminated, changed or renewed provided that another project
supervisor for health and safety matters is appointed to carry out such
duties throughout the duration of the project.
(2) The client may act as project supervisor for health and
safety matters if he himself is competent to undertake the duties as
outlined under these regulations and provided that his name appears in
the register for competent persons administered or otherwise delegated
by the Authority.
(3)
Upon or prior to the appointment of the project
supervisor for health and safety matters, an engagement agreement in
writing regulating the appointment of the project supervisor for health
and safety matters shall be entered into between the client or, where
applicable, the client representative and the project supervisor for
health and safety matters.
(4)
Work-related to a project shall not commence or progress
unless a project supervisor for health and safety matters is validly
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
appointed by the client in accordance with these regulations and such
appointment shall be notified to the Authority by the client on such
form as may be prescribed by the Authority.
(5)
In case of demise of the project supervisor for health and
safety matters, the client shall notify the Authority in writing within
fifteen (15) days of their demise in such form as prescribed by the
Authority, during which time, work related to a project shall not
progress unless a new project supervisor for health and safety matters
is validly appointed by the client in accordance with these regulations.
(6)
Where the appointment is terminated, for whatever
reason, the project supervisor for health and safety matters shall notify
the Authority in writing within fifteen (15) days of such termination,
in such form as prescribed by the Authority, about such termination.
The termination shall only be effective upon notice to the Authority
and for avoidance of doubt the project supervisor for health and safety
matters shall remain responsible for his duties and obligations in
accordance with these regulations until such notice is served.
(7)
Upon receiving the written and signed notice of
termination, the Authority shall acknowledge the receipt of the notice
in writing and notify the client in writing of the effective date of
termination in accordance with sub-regulation (6). Work related to a
project shall not progress unless a new project supervisor for health
and safety matters is validly appointed by the client in accordance with
these regulations.
(8)
If the client commences or progresses work related to the
project before a competent project supervisor for health and safety
matters is appointed, the client shall be guilty of an offence against the
Act.
(9)
The client shall take into account any directions given by
the project supervisor for health and safety matters, maintaining a safe
environment on the project particularly with regards to any health and
safety matters under these, or any other regulations under the Act. The
client shall ensure that any directions given by the project supervisor
for health and safety matters in ensuring a safe and, or healthy place of
work, are implemented and the client shall take all reasonable
measures to ensure that duty holders abide by their obligations within
the limits of their respective responsibilities.
(10) The client shall keep the project supervisor for health and
safety matters updated on the engagement of new contractors and self-
employed persons.
(regulation 6)
CONTENT OF THE PRIOR NOTICE REFERRED TO IN
REGULATION 6
1. Date of notification.
2. Exact address of the construction site.
3. Clients’ names and addresses.
4. Type of project.
5. Client representatives names and addresses.
6. Name and address of project supervisor for health and
safety matters including a declaration of acceptance duly
signed by the project supervisor for health and safety
matters to the effect that he has undertaken to accept the
role of project supervisor for health and safety matters
and that he is competent to carry out the duties imposed
by these regulations.
7. Date planned for start of works on the construction site.
8. Planned duration of works on the construction site.
9. Estimated maximum number of workers on the
construction site.
10. Planned number of contractors and self-employed
persons on the construction site.
11. Details of contractors already chosen.
(1)
The client shall ensure that a health and safety file
is compiled, kept and made available for inspection, which health and
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
safety files have been prepared in accordance with regulation 13 and
any other relevant information regarding health and safety, for
inspection by any person who may need information in the file for the
purpose of compliance with any statutory obligations.
(2)
When a client disposes of his interests in the project, a
client shall deliver the health and safety file in respect of the project to
that person who acquires such interest in the project, and any
obligations arising out of these regulations remaining for the duration
of the project shall be assumed by such person.
(regulation 19)
MINIMUM HEALTH AND SAFETY REQUIREMENTS
FOR CONSTRUCTION SITES
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
Preliminary remarks
The obligations laid down in this Schedule apply wherever
required by the features of the construction site, the activity, the
circumstances or a hazard. For the purposes of this Schedule, "rooms"
covers, inter alia, hutted accommodation.
PART A: GENERAL MINIMUM REQUIREMENTS FOR ON-
SITE WORKPLACES
1. Stability and solidity
1.1. Materials, equipment and, more generally, any
component which, when moving in any way, may affect the
health and safety of workers shall be stabilized in an
appropriate and safe manner.
1.2. Access to any surface involving insufficiently
resistant materials is not authorized unless appropriate
equipment or means are provided to enable the work to be
carried out safely.
2. Energy distribution installations
2.1. The installations shall be designed, constructed
and used so as not to present a fire or explosion hazard, persons
shall be adequately protected against the risk of electrocution
caused by direct or indirect contact.
2.2. The design, construction and choice of equipment
and protection devices shall take account of the type and power
of the energy distributed, external conditions and the
competence of persons with access to parts of the installation.
3. Emergency routes and exits
3.1. Emergency routes and exits shall remain clear and
lead as directly as possible to a safe area.
3.2. In the event of danger, it shall be possible for
workers to evacuate all workstations quickly and as safely as
possible.
3.3. The number, distribution and dimensions of
emergency routes and exits depend on the use, equipment and
dimensions of the site and of the rooms and the maximum
number of persons that may be present.
3.4. Specific emergency routes and exits shall be
indicated by signs in accordance with the Work Place,
(Provisions of Health and, or Safety Signs) Regulations (S.L.
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
646.09.).
Such signs shall be sufficiently resistant and be
placed at appropriate points.
3.5. Emergency routes and exits, and the traffic routes
and doors giving access to them shall be free from and
obstruction so that they can be used at any time without
hindrance.
3.6. Emergency routes and exits requiring illumination
shall be provided with emergency lighting of adequate intensity
in case the lighting fails.
4. Fire detection and fire fighting
4.1. There shall be provided an adequate number of
appropriate fire-fighting devices and, where required, fire
detectors and alarm systems depending of the characteristics of
the site, the dimensions and use of the rooms, the on-site
equipment, the physical and chemical properties of the
substances present and the maximum potential number of
people present.
4.2. The fire-fighting devices, fire detectors and alarm
systems shall be regularly examined and maintained.
Appropriate tests and drills shall take place at regular intervals.
4.3. Non-automatic fire-fighting equipment be easily
accessible and simple to use. The equipment shall be indicated
by signs in accordance with the Work Place, (Provisions of
Health and, or Safety Signs) Regulations (S.L. 646.09.).
Such signs shall be sufficiently resistant and
placed at appropriate points.
5. Ventilation
5.1
Steps shall be taken to ensure that there is
sufficient supply of fresh air, having regard to the working
methods used and the physical demands placed on the workers.
5.2
If a forced ventilation system is used, it shall be
maintained in working order and shall not expose workers to
draughts which are harmful to health.
5.3
Any breakdown shall be indicated by a control
system where this is necessary for workers' health.
6. Exposure to particular risks
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
6.1
Workers shall not be exposed to harmful levels of
noise or to harmful external influences (e.g. gases, vapours,
dust).
6.2
If workers have to enter an area where the
atmosphere may contain a toxic or harmful substance or to have
an insufficient oxygen level or to be inflammable, the confined
atmosphere shall be monitored and appropriate steps taken to
prevent any hazard.
6.3
A worker may not in any circumstances be
exposed to a high-risk confined atmosphere. He shall at least be
watched at all times from outside and all appropriate
precautions shall be taken to ensure that he can be assisted
effectively and immediately.
7. Temperature
During working hours, the temperature shall be appropriate for
human beings, having regard to the working methods used and the
physical demands placed on the workers.
8. Natural and artificial lighting of workstations, rooms and
traffic routes on the site
8.1. Workstations, rooms and traffic routes shall as far
as possible have sufficient natural lighting and be provided with
appropriate and sufficient artificial lighting at night and when
natural daylight is inadequate, where necessary, portable light
sources that are protected against impact shall be used.
The colour of artificial light used shall not alter or
affect the perception of signals or signposts displaying such
signs.
8.2. Lighting installations for rooms, workstations and
traffic routes shall be placed in such a way that there is no risk
of accident to workers as a result of the type of lighting fitted.
8.3. Rooms, workstations and traffic routes where
workers are especially exposed to risks in the event of artificial
lighting, shall be provided with emergency lighting of adequate
intensity.
9. Doors and gates
9.1. Sliding doors shall be fitted with a safety device
to prevent them from being derailed and falling over.
9.2.
Doors and gates opening upwards shall be fitted
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
with a mechanism to secure them against falling back.
9.3. Doors and gates along escape routes shall be
appropriately marked.
9.4. In the immediate vicinity of gates intended
primarily for vehicle traffic, there shall be doors for pedestrian
traffic unless it is safe for pedestrians to cross; such doors shall
be clearly marked and kept free at all times.
9.5. Mechanical doors and gates shall operate without
any risk of accident to workers. They shall be fitted with
emergency stop devices which are easily identifiable and
accessible and, unless they open automatically in the event of a
power-cut, it shall be possible for them to be opened manually.
10. Traffic routes - danger areas and safe means of access
and egress
10.1. Traffic routes, including stairs, fixed ladders and
loading bays and ramps shall be calculated, located, laid out
and made negotiable to ensure easy, safe and appropriate access
in such a way as not to endanger workers employed in the
vicinity of these traffic routes.
10.2. Routes used for pedestrian traffic and, or goods
traffic including those used for loading and unloading shall be
dimensioned in accordance with the number of potential users
and the type of activity concerned.
If means of transport are used on traffic routes, a
sufficient safety clearance or adequate protective devices shall
be provided for other site users.
Routes shall be clearly marked, regularly verified
and properly maintained.
10.3. Sufficient clearance shall be allowed between
vehicle traffic routes and doors, gates, passages for pedestrians,
corridors and staircases.
10.4. If the site includes limited-access areas, these
shall be equipped with devices to prevent unauthorised workers
from entering.
Appropriate measures shall be taken to protect workers
who are authorised to enter the danger areas.
Danger areas shall be clearly signposted.
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
10.5. Sufficient safe means of access and egress shall
be provided and maintained to and from every workplace at
which any person has at any time to perform any work and
every such place shall be made and kept safe for any person
working and, or being present there.
11. Loading bays and ramps
11.1. Loading bays and ramps shall be adequate for the
dimensions of the loads to be transported.
11.2.
Loading bays shall have at least one exit point.
11.3. Loading ramps shall be sufficiently safe, to
prevent workers from falling off.
12. Freedom of movement at the workstation
The floor area at the workstation shall be such as to allow
workers sufficient freedom of movement to perform their work, taking
account of any necessary equipment or appliances present.
13. First aid
13.1. The contractor shall ensure that first aid can be
provided, and that the staff trained to provide it can be called
upon at any time.
Measures shall be taken to ensure that workers
who have had an accident or have suddenly been taken ill can
be removed for medical treatment.
13.2. One or more first-aid rooms shall be provided
where the scale of the works or the types of activity being
carried out so require.
13.3. First-aid rooms shall be fitted with essential first-
aid installations and equipment and be easily accessible to
stretchers.
They shall be signposted in accordance with the Work
Place, (Provisions of Health and, or Safety Signs) Regulations
(S.L. 646.09.).
13.4. First-aid equipment shall be available at all places
where working conditions so require.
This equipment shall be properly marked and easily
accessible.
The address and telephone number of the local
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
emergency service shall be clearly displayed.
14. Sanitary equipment
14.1.
Changing rooms and lockers.
14.1.1. Appropriate changing rooms shall be
provided for workers if they have to wear special work
clothes and if, for reasons of health or propriety, they
cannot be expected to change in another area.
Changing rooms shall be easily accessible, be of
sufficient capacity and be provided with seating.
14.1.2. Changing rooms shall be sufficiently large
and have facilities to enable each worker, where
necessary, to dry his working clothes as well as his own
clothing and personal effects and to lock them away.
If circumstances so require (e.g. dangerous
substances, humidity, dirt), facilities shall be provided to
enable working clothes to be kept in a place separate
from workers' own clothes and personal effects.
14.1.3. Provisions shall be made for separate
changing rooms or separate use of changing rooms for
different genders.
14.1.4. If changing rooms are not required as
referred to in item 14.1.1, first paragraph, each worker
shall be provided with a place in which he can lock away
his own clothes and personal effects.
14.2.
Showers and washbasins
14.2.1. Suitable showers in sufficient numbers
shall be provided for workers if required by the nature of
the work or for health reasons.
Provisions shall be made for separate shower
rooms or separate use of shower rooms for different
genders.
14.2.2. The shower rooms shall be sufficiently
large to permit each worker to wash without hindrance in
conditions of an appropriate standard of hygiene.
The showers shall be equipped with hot and cold
running water.
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
14.2.3. Where showers are not required as
required by the first paragraph of item 14.2.1, a sufficient
number of suitable washbasins with running water (hot
water if necessary) shall be provided in the vicinity of the
workstations and the changing rooms.
Provisions shall be made for separate
washbasins, or separate use of washbasins for different
genders when so required.
14.2.4. Where the rooms housing the showers or
washbasins are separate from the changing rooms, there
shall be easy access between them.
14.3.
Lavatories and washbasins
Special facilities with an adequate number of lavatories and
washbasins shall be provided for workers in the vicinity of
workstations, rest rooms, changing rooms and rooms housing showers
or washbasins.
Provisions shall be made for separate lavatories or separate use
of lavatories for different genders.
15. Rest rooms and, or accommodation areas
15.1.
Where the safety or health of workers, in
particular because of the type of activity carried out or the
presence of more than a certain number of employees as well as
the remote nature of the site so require, workers shall be
provided with easily accessible rest rooms and, or
accommodation areas.
15.2. Rest rooms and, or accommodation areas shall be
large enough and equipped with an adequate number of tables
and seats with supporting backs for the number of workers
concerned.
15.3. If there are no facilities of this kind, other
facilities shall be provided in which workers can stay during
interruptions in work.
15.4. Fixed accommodation areas unless used only in
exceptional cases, shall have sufficient sanitary equipment, a
rest room and a leisure room.
They shall be equipped with beds, cupboards, tables and
seats with backs taking account of the number of workers, and
be allocated taking account, where appropriate, of the presence
of workers of different genders.
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
15.5. Appropriate measures shall be taken for the
protection of non-smokers against discomfort caused by
tobacco smoke in rest rooms and or accommodation areas.
16. Pregnant women and nursing mothers
Pregnant women and nursing mothers shall be able to lie down
to rest in appropriate conditions.
17. Disabled workers
Workplaces shall be organised to take account of disabled
workers, if necessary.
The provision applies in particular to the doors, passageways,
staircases, showers, washbasins, lavatories and workstations used or
occupied directly by disabled persons.
18. Miscellaneous provisions
18.1. The surroundings and the perimeter of the site
shall be signposted and laid out so as to be clearly visible and
identifiable.
18.2. Workers shall be provided at the site with a
sufficient quantity of drinking water and possibly another
suitable non-alcoholic beverage both in occupied rooms and in
the vicinity of workstations.
18.3.
Workers shall
-
be provided with facilities enabling them to
take their meals in satisfactory conditions,
-
where appropriate, be provided with
facilities enabling them to prepare their meals in
satisfactory conditions.
PART B: SPECIFIC MINIMUM REQUIREMENT FOR ON-
SITE WORKSTATIONS
Preliminary remark
If special situations so dictate, the classification of these
minimum requirements into two sections, as below, shall not be
regarded as binding.
Section I: On-site indoor workstations
1. Stability and solidity
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
Premises shall have a structure and stability appropriate to the
nature of their use.
2. Emergency doors
Emergency doors shall open outwards.
Emergency doors shall not be so locked or fastened that they
cannot be easily and immediately opened by any person who may
require to use them in an emergency.
Sliding or revolving doors shall not be permitted if intended as
emergency exits.
3. Ventilation
If air-conditioning or mechanical ventilation installations are
used, they shall operate in such a way that workers are not exposed to
draughts which cause discomfort. Any deposit or dirt likely to create
an immediate danger to the health of workers by polluting the
atmosphere shall be removed without delay.
4. Temperature
4.1. The temperature in rest areas, rooms for duty
staff, sanitary facilities, canteens and first-aid rooms shall be
appropriate to the particular purpose of such areas.
4.2. Windows, skylights and glass partitions shall not
allow excessive effects of sunlight, having regard to the nature
of the work and the use of the room.
5. Natural and Artificial Lighting
Workplaces shall as far as possible have sufficient natural light
and be equipped with the means of providing artificial lighting which
is adequate for the purposes of protecting workers’ health and safety.
6. Floors, walls, ceilings and roofs of rooms
6.1. The floors of workplaces shall have no dangerous
bumps, holes or slopes and shall be fixed, stable and not
slippery.
6.2. The surfaces of floors, walls and ceilings in rooms
shall be such that they can be cleaned or refurbished to an
appropriate standard of hygiene.
6.3. Transparent or translucent walls, in particular all-
glass partitions, in rooms or in the vicinity of workplaces and
traffic routes shall be clearly indicated and made of safety
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
material or be shielded from such places or traffic routes to
prevent workers from coming into contact with walls or being
injured should the walls shatter.
7. Windows and skylights
7.1. It shall be possible for workers to open, close,
adjust or secure windows, skylights and ventilators in a safe
manner.
When open, they shall not be positioned so as to
constitute a hazard to workers.
7.2. Windows and skylights shall be designed in
conjunction with equipment or otherwise fitted with devices
allowing them to be cleaned without any risk to the workers
carrying out this work or to workers present.
8. Doors and Gates
8.1. The position, number and dimensions of doors
and gates, and the materials used in their construction, shall be
determined by the nature and use of the rooms or areas.
8.2. Transparent doors shall be appropriately marked
at a conspicuous level.
8.3. Swing doors and gates shall be transparent or have
see-through panels.
8.4. If transparent or translucent surfaces in doors and
gates are not made of safety material and if there is a danger
that workers may be injured if a door or gate should shatter, the
surfaces shall be protected against breakage.
9. Traffic routes
Where the use and equipment of rooms so requires for the
protection of workers, traffic routes shall be clearly identified.
10. Specific measures for escalators and travelators
Escalators and travelators shall function safely. They
shall be equipped with any necessary safety devices. They shall be
fitted with easily identifiable and accessible emergency shut-down
devices.
11. Room dimensions and air space in rooms
Workrooms shall have sufficient surface area and height
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
to allow workers to perform their work without risk to their safety,
health or well-being.
Section II: On-site outdoor workstations
1. Stability and solidity.
1.1. High-level or low-level movable or fixed
workstations shall be solid and stable, taking account of
-
the number of workers occupying them;
-
the maximum loads they may have to bear and the
weight distribution;
-
the outside influences to which they may be
subject.
If the support and the other components of these
workstations are not intrinsically stable, their stability is to be
ensured by appropriate and safe methods of fixing to avoid any
untimely or spontaneous movement of the whole or of parts of
the workstations.
1.2.
Verifications
Stability and solidity shall be verified
appropriately and especially after any change in the height or
depth of the workstation.
2. Energy distribution installations
2.1. On-site
energy
distribution
installations,
especially those subject to outside influences, shall be regularly
examined and maintained in good condition.
2.2. Installations existing before the site began shall be
identified, examined and clearly signposted.
2.3. Whenever possible, where overhead electric
power lines exist, either they shall be redirected away from the
area of the site or else the current shall be cut off.
If this is not possible, there will be barriers or
notices to ensure that vehicles and installations are kept away.
Adequate warnings and suspended protections shall be
provided where vehicles have to pass beneath the lines.
3. Atmospheric influences
Workers shall be protected against atmospheric influences
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
which may affect their health and safety.
4. Falling objects
4.1. Wherever technically feasible, workers shall be
protected by collective methods against falling objects.
4.2
Materials and equipment shall be laid out or
stacked in such a way as to prevent their collapsing or
overturning.
4.3. Where necessary, there shall be covered
passageways on the site or access to danger areas shall be made
impossible.
5. Falls from a height
5.1. Work at height shall be properly planned and
carried out on the basis of the measures of article 6(2) of the
Act and regulation 10 of the General Provisions for Health and
Safety at Work Places Regulations;
5.2. Where work is carried out at height, every
employer and, or self-employed person, shall take adequate and
sufficient measures to prevent any person falling a distance
liable to cause injury.
5.3. In principle, work carried out at a height shall be
carried out only with appropriate equipment or using collective
protection devices such as cradles, platforms or safety nets.
Where cradles are used, these shall be solid,
sufficiently high and have at least an end-board, a main handrail
and an intermediate handrail or an equivalent alternative.
If the use of such equipment is not possible
because of the nature of the work, suitable means of access
shall be provided and safety harnesses or other anchoring safety
methods shall be used.
5.4
Protection railings, barriers or other form of
protection shall be fitted around stairwells, stairs, shafts,
balconies, edges, openings and in all other areas where any
person may fall a distance liable to cause injury, or to fall into
any liquid or material so as to involve risk of drowning or
serious injury.
5.5
Protection railings, barriers or other form of
protection shall be of good construction, of suitable and sound
material, of adequate height, and of adequate strength for the
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
purpose of which are used. Protection railings, barriers or other
form of protection shall be placed as to prevent as far as
possible the fall of persons. Where coverings are used, these
shall be so construed as to prevent the fall of persons, materials
or articles, which covering shall be clearly and boldly marked
to show its purpose, be securely fixed in position, be of good
construction and of adequate strength for the purpose for which
are used.
6. Scaffolding and ladders
6.1. All scaffolding shall be properly designed,
constructed and maintained to ensure that it does not collapse or
move accidentally.
6.2. Work platforms, gangways and scaffolding
stairways shall be constructed, dimensioned, protected and used
in such a way as to prevent people from falling or being
exposed to falling objects.
6.3. Scaffolding shall be inspected and certified as
being safe for use by a competent person
(a)
before being put into service;
(b)
subsequently, at periodic intervals;
(c)
after any modification period without use,
exposure to bad weather or seismic tremors, or any other
circumstance which may have affected its strength or
stability.
6.4. Ladders shall be sufficiently strong and correctly
maintained. They shall be correctly used, in appropriate places
and in accordance with their intended purpose.
6.5. Mobile scaffolding shall be secured against
spontaneous movements.
7. Lifting equipment
7.1. All lifting devices and accessories, including their
component parts, attachments, anchorings and supports shall
be
(a)
properly designed and constructed and
sufficiently strong for the use to which they are put;
(b)
correctly installed and used;
(c)
maintained in good working order;
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
(d)
verified and subjected to periodic tests and
inspections in accordance with current legislation;
(e)
operated by qualified workers who have
received appropriate training.
7.2. All lifting devices and accessories shall clearly
display their maximum load values.
7.3. Lifting equipment and accessories may not be
used for other than their intended purposes.
8. Excavating
and
materials-handling
vehicles
and
machinery
8.1. All excavating and materials-handling vehicles
and machinery shall be
(a)
properly designed and constructed taking
account, as far as possible, of the principles of
ergonomics;
(b)
kept in good working order;
(c)
used correctly.
8.2. Drivers and operators of excavating and
materials-handling vehicles and machinery shall be specially
trained.
8.3. Preventive measures shall be taken to ensure that
excavating and materials-handling vehicles and machinery do
not fall into the excavations or into water.
8.4. Where appropriate, excavating machinery and
materials-handling machinery shall be fitted with structures to
protect the driver against being crushed if the machine
overturns, and against falling objects.
9. Installations, machinery, equipment
9.1. Installations, machinery and equipment, including
hand tools whether power-driven or otherwise, shall be
(a)
properly designed and constructed taking
accounts, as far as possible, of the principle of
ergonomics;
(b)
kept in good working order;
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
(c)
used solely for the work for which they
were designed;
(d)
operated by workers who have received
appropriate training.
9.2. Installations and equipment under pressure shall
be examined and subjected to regular tests and inspections in
accordance with existing legislation.
10. Excavations, wells, underground works, tunnels and
earthworks
10.1.
Adequate precautions shall be taken in an
excavation, well, underground, working or tunnel
(a)
using
an
appropriate
support
or
embankment;
(b)
to prevent hazards entailed in the fall of a
person, materials or objects, or flooding;
(c)
to provide sufficient ventilation at all
workstations so as to ensure a breathable atmosphere
which is not dangerous or harmful to health;
(d)
to enable workers to reach safety in the
event of fire or inrush for water or materials.
10.2. Before excavation starts, measures shall be taken
to identify and reduce to a minimum any hazard due to
underground cables and other distribution systems.
10.3.
Safe routes into and out of the excavation shall be
provided.
10.4. Piles of earth, materials and moving vehicles
shall be kept away from the excavation; appropriate barriers
shall be built if necessary.
11. Demolition work
Where the demolition of a building or construction may present
a danger
(a)
appropriate precautions, methods and procedures
shall be adopted;
(b)
the work shall be planned and undertaken only
under the supervision of a competent person.
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
12. Metal or concrete frameworks, shutterings and heavy
prefabricated components.
12.1. Metal or concrete frameworks and their
components, shutterings, prefabricated components or
temporary support, and buttresses shall be erected and
dismantled only under the supervision of a competent person.
12.2. Adequate precautions shall be taken to protect
workers against risks arising from the temporary fragility or
instability of a structure.
12.3. Shutterings, temporary supports and buttresses
shall be devised and designed, installed and maintained so as to
safely withstand any strains and stresses which may be placed
on them.
13. Cofferdams and caissons
13.1.
All cofferdams and caissons shall be
(a)
well constructed, of appropriate, solid
materials of adequate strength;
(b)
appropriately equipped so that workers can
gain shelter in the event of an irruption of water and
materials.
13.2. The construction, installation, transformation or
dismantling of a cofferdam or caisson shall take place only
under the supervision of a competent person.
13.3. All cofferdams and caissons shall be inspected by
a competent person at regular intervals.
14. Work on roofs
14.1. Where necessary to avert a risk or where the
height or the slope exceed set values, collective preventive
measures shall be taken to prevent workers, and tools or other
objects or materials, from falling.
14.2. Where workers have to work on or near a roof or
any other surface made of fragile materials through which it is
possible to fall, preventive measures shall be taken to ensure
that they do not inadvertently walk on the surface made of
fragile materials, or fall to the ground.
The client shall ensure that prior to the setting up of a
construction site, a health and safety plan is drawn up in accordance
with regulation 12.
In the case of construction sites on which work is
scheduled to last longer than thirty (30) working days and on which
more than twenty (20) workers are occupied simultaneously, or on
which the volume of work is scheduled to exceed five hundred (500)
person-days, the client shall communicate a prior notice drawn up in
accordance with Schedule III to the Authority, along with any other
document or information required by the Authority from time to time,
at least four (4) calendar weeks before work starts on the project. Once
any work activity on the project commences, a copy of the prior notice
in such form as prescribed by the Authority shall be clearly displayed
on the construction site by the client and, if necessary, periodically
updated by the project supervisor for health and safety matters.
The client shall take account of the general principles of
prevention concerning health and safety referred to in the Act and in
any other law, as may be appropriate, during the various stages of
designing and preparing the project, in particular
(a)
when decisions on the architectural, technical and,
or organisational aspects are being taken, in order to plan the
various items or stages of work which are to take place
simultaneously or in succession;
(b)
when estimating the period required for
completing such work or work stages, account shall also be
taken, each time this appears necessary, from all health and
safety plans and from files drawn up in accordance with
regulations 12(1) and 13(1) or adjusted in accordance with
regulations 12(2) and 13(2).
Where the client is a domestic client, regulation 3 shall
not apply if the following conditions are met
(a)
the project does not require a prior notice in
accordance with regulation 6; and
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
(b)
only one (1) contractor for the whole project will
be present; and
(c)
work does not involve particular risks as listed in
Schedule II.
Client Representative
(1)
The client may appoint in respect of every project,
a client representative who acts for the Client and who shall be
responsible for the design, execution and, or supervision of the
execution of a project and who shall be responsible, on the client’s
behalf, to carry out the duties imposed by these regulations on the
client, mutatis mutandis and any such appointment may be terminated,
changed, or renewed as necessary
Provided that only persons resident in the European
Union or the EEA, legal persons incorporated in the European Union
or the EEA or entities which are branches recognised in the European
Union or the EEA may be appointed as client representative.
(2)
When a client representative has been appointed in
accordance with these regulations, the obligations imposed by these
regulations on the client shall apply mutatis mutandis and shall be
carried out by such client representative instead of the client in
accordance with these regulations.
(3)
The client representative shall be appointed only if the
following information is submitted to the Authority
(a)
the
date
of
appointment
of
the
client
representative;
(b)
the address of the construction site;
(c)
a brief description of the project and the
construction work that it entails;
(d)
the contact details of the client including name,
identity card number, address, telephone and, or mobile phone
number and an email address;
(e)
the contact details of the client representative
including name, identity card number, address, telephone and,
or mobile phone number and an email address;
(f)
a declaration in such form as prescribed by the
Authority of acceptance duly signed by the client representative
that he has undertaken to accept the role of client representative
and to carry out the duties imposed by these regulations on the
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
client; and
(g)
a declaration in such form as prescribed by the
Authority duly signed by the client and the client’s
representative whereby they are expressly consenting to the
processing, handling and transmitting of personal data held by
the Authority.
(4)
Where, during the period of works, the client
representative resigns or changes for any reason, he shall be obliged to
give notice thereof in writing to the Authority. Until such notice is
received and approved in writing by the Authority, he shall still be
presumed to be the appointed client representative for the site.
(5)
In default of an appointment of a client representative in
accordance with these regulations, the client shall remain responsible
for fulfilling the duties pertaining to the client under these regulations.
Responsibilities of client or client representative
(1)
Where the client or client representative has
appointed a project supervisor for health and safety matters to perform
the duties and exercise the powers under these regulations, this shall
not relieve the client or the client representative of their
responsibilities in that respect.
(2)
The implementation of these regulations shall not affect
the principle of employers' responsibility as provided for in the Act or
in any other law.
(3)
In order to preserve health and safety on the construction
site, the client shall take into account any report given in writing by the
project supervisor for health and safety matters and shall take all
reasonable measures to ensure that duty holders abide by their
obligations within the limits of their respective responsibilities.
Duties of the Project supervisor for health and safety matters
project preparation stage
The project supervisor for health and safety matters shall
coordinate the implementation of the provisions of regulation 7.
(1)
The project supervisor for health and safety
matters shall draw up a health and safety plan setting out the rules
applicable to the construction site concerned, taking into account,
where necessary, of the industrial activities taking place on the site.
The said plan shall also include specific measures concerning work
which falls within one or more of the categories of Schedule II.
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
(2)
The project supervisor for health and safety matters shall
make any adjustments required to the health and safety plan to take
account of the progress of the work and any changes which have
occurred.
(1)
The project supervisor for health and safety
matters shall prepare a file appropriate to the characteristics of the
project containing relevant health and safety information to be taken
into consideration during any subsequent works.
(2)
The project supervisor for health and safety matters shall
make any adjustments required to the health and safety file to take
account of the progress of the work and any changes which have
occurred.
Duties of the project supervisor for health and safety matters
Project Execution Stage
(1)
The project supervisor for health and safety
matters shall coordinate the implementation of the general principles
of prevention and safety
(a)
when technical and, or organizational aspects are
being decided, in order to plan the various items or stages of
work which are to take place simultaneously or in succession;
(b) when estimating the
period
required
for
completing such work or work stages.
(2)
The project supervisor for health and safety matters shall
coordinate the implementation of the relevant provisions of these
regulations in order to ensure that contractors, employers and, if
necessary for the protection of workers, self-employed persons
(a)
apply the principles referred to in regulation 18 in
a consistent manner;
(b)
where required, follow the health and safety plan
referred to in regulation 12;
(c)
make and, or cause to be made, any adjustments
required to the health and safety plan referred to in regulation
12 and the file referred to in regulation 13 to take account of the
progress of the work and any changes which have occurred.
In order to preserve health and, or safety on the
construction site, the project supervisor for health and safety matters
shall
(a)
coordinate the implementation of the relevant
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
provisions of these regulations or any other provisions under
the Act, in order to ensure that employers offer the highest
protection by applying the principles referred to in regulation
18 or any other regulation made under the Act in a consistent
manner;
(b)
coordinate the implementation of the relevant
provisions of these regulations in order to ensure that
employers and, if necessary for the protection of workers, self
employed persons follow the health and safety plan referred to
in regulation 12;
(c)
organize cooperation between contractors,
including successive contractors on the same site, coordination
of their activities with a view to protecting workers and
preventing accidents and occupational health hazards and
reciprocal information, as provided for in regulation 7 of the
General Provisions for Health and Safety at Work Places
Regulations, ensuring that self-employed persons are brought
into this process where necessary;
(d)
take the steps necessary to ensure that only
authorized persons are allowed onto the construction site;
(e)
carry out as often as necessary a thorough
inspection of the whole construction site and work practices to
identify the measures being undertaken by the contractors,
employers or any self-employed persons in identifying any
potential hazards, and recommend the necessary preventive and
protective measures in line with the general principles of
prevention laid down in the Act, or any other regulations made
under the Act
Provided that the frequency of inspections shall be
commensurate with the size of the construction site, the nature
and extent of the hazards and risks at the construction site, and
the type of works being carried out;
(f)
issue and submit without undue delay to the
relevant duty holders involved in the construction project, an
inspection report in writing highlighting the measures being
undertaken by the contractors, employers or any self-employed
persons in identifying any potential hazards and risks and any
unaddressed hazards and risks noted during the inspection
carried out under these regulations and the required preventive
and corrective measures to be taken by the relevant duty
holders to address the identified hazards and risks and, or
manage health and safety
Provided that for the purpose of this paragraph
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
"duty holders" shall not include "workers";
(g)
give directions to duty holders and other relevant
persons, in the interest of occupational health and, or safety;
(h)
coordinate, monitor the implementation of and
ensure the execution of the required preventive and corrective
measures indicated in the inspection report prepared under
these regulations, and any other measures required to render the
site safe;
(i)
coordinate, monitor the implementation of and
ensure the execution of, the preventive and protective measures
indicated in the health and safety plan prepared in terms of
these regulations;
(j)
carry out as often as necessary, follow-up
inspections to ensure the implementation of the preventive and
protective measures indicated in the inspection report and any
directions made and given out under these regulations;
(k)
give a written copy of the health and safety plan
prepared in terms of these regulations, or a relevant extract
thereof to all duty holders in terms of these regulations
Provided that for the purpose of this paragraph
"duty holders" shall not include "workers";
(l)
consult and liaise on matters relating to
occupational health and, or safety with respect to the
construction project, with any designated persons and, or
external services appointed by the employer in terms of
regulation 9 of the General Provisions for Health and Safety at
Work Places Regulations.
Powers and other duties of project supervisor for health and safety
matters
In order to preserve health and, or safety on the
construction site, the project supervisor for health and safety matters
shall have the following powers
(a)
to inspect at any time of day or night the
construction site to which he has been appointed to act as
project supervisor for health and safety matters to fulfil the
duties made under these regulations;
(b)
to make such examination, interview and
investigation as may in any circumstances be necessary in the
interest of occupational health and, or safety;
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
(c)
to take such measurements, photographs, video
recording and, or any other recordings, including the use of
monitoring equipment and atmospheric sampling, as the project
supervisor for health and safety matters considers necessary for
the purpose of fulfilling the duties under these regulations
Provided that the handling and storage of personal
data resulting from the said activities shall conform to the
provisions of the Data Protection Act.
(d)
to order that work or any activity be halted or to
give such orders in relation to the carrying out of duties by any
employee or self-employed persons on the site if there is a
reasonable concern that the carrying out of work and, or activity
could likely expose any person present on the construction site
to a serious risk to their health and, or safety, emanating from
an immediate or imminent exposure to a hazard
Provided that the project supervisor for health and
safety matters shall, without undue delay, notify in writing the
duty holders involved in the construction project. The project
supervisor for health and safety matters shall inform the
Authority of any order made in accordance with this paragraph
in such instances where such orders are not observed or
complied with
Provided further that for the purpose of this
paragraph "duty holders" shall not include "workers";
(e)
to require any article, substance, material,
equipment, machinery, installation, structure, apparatus, tool
and any other thing at the construction site that he may
reasonably consider to be a risk to occupational health and, or
safety to be dismantled and, or removed from the site and, or
rectified and, or subjected to any process or test at the expense
of the relevant duty holder;
(f)
(i)
to receive and register any report made by
any person in relation to any matter which may give rise to
suspicion of a breach of these regulations, or the Act or any
regulations made thereunder
Provided that if a worker or any person, whether
acting on his own behalf or on behalf of a worker, report a
matter in terms of this regulation to the project supervisor for
health and safety matters, then the project supervisor for health
and safety matters shall prepare his written report in relation to
such a matter within fifteen (15) days from the date on which
such matter was reported to him in writing, and after having
heard the client, including any client representative engaged by
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
the client, any worker or person making a report in terms of this
sub-paragraph. Once completed, such report shall be provided
to the client and the worker or any person, whether acting on his
own behalf or on behalf of a worker, accordingly. Where
deemed necessary by the project supervisor for health and
safety matters, the report shall indicate such measures which
shall need to be implemented by the client in order to address
any particular matter taking into account the obligations of the
client under the Act. Failure to present such a report shall be
considered to be an offence under the Act;
(ii)
to register any matter reported in terms of
this regulation and the matter shall be considered to be
conclusively determined provided that any measure
specified by the project supervisor for health and safety
matters in terms of these regulations is implemented
accordingly within stipulated time-frames
Provided that if the measures specified by
the project supervisor for health and safety matters not be
implemented or adhered to in terms of these regulations,
the project supervisor for health and safety matters shall
inform the Authority accordingly and the client shall be
guilty of an offence under the Act in such instances
Provided further that in the case that the
project supervisor for health and safety matters has failed
to make the correct recommendations to the client in
accordance with the Act and the regulations made
thereunder, then in such instances the project supervisor
for health and safety matters shall be guilty of an offence
under the Act.
Provided further that, except where
required by law or deemed necessary, the project
supervisor for health and safety matters shall ensure the
anonymity of any person who reports any matter which
may give rise to suspicion of a breach of these regulations,
or the Act or any regulations made thereunder. The
identity of the said person may be disclosed only with their
explicit written consent.
Project supervisor for health and safety matters: non-liability
Civil action or other proceedings for damages shall not
lie or be instituted by a client, contractor, employer, self-employed
person, or worker involved in the construction project against the
project supervisor for health and safety matters for
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
(a)
an act done in pursuance of these regulations
unless the project supervisor for health and safety matters acted
in a negligent manner or otherwise did not observe his duties as
provided under the Act and these regulations;
(b)
an act done or omitted to be done in the
performance of his functions where it is sufficiently proven that
the client or the contractor, the employer or the self-employed
person failed to comply with the necessary measures as
instructed by the project supervisor for health and safety
matters.
Implementation of General Provisions for Health and Safety at
Work Places Regulations (S.L. 646.11.)
When the work is being carried out, the principles set out
in regulations 4 to 8 of the General Provisions for Health and Safety at
Work Places Regulations shall be applied, in particular as regards
(a)
keeping the construction site in good order and in
a satisfactory state of cleanliness;
(b)
choosing the location of workstations, particularly
how to access these workplaces is obtained, and determining
routes or areas for the safe passage and movement of
equipment;
(c)
the conditions under which various materials are
handled;
(d)
technical
maintenance,
pre-commissioning
verifications and regular verifications on installations and
equipment with a view to correcting any faults which might
affect the health and safety of workers;
(e)
the demarcation and laying-out of areas for the
storage of various materials, in particular where dangerous
materials or substances are concerned;
(f)
the conditions under which the dangerous
materials used are removed;
(g)
the storage and disposal or removal of waste and
debris;
(h)
the adaptation, based on progress made on the
site, of the actual period that shall be allocated for the various
types of work or work stages;
(i)
cooperation
between
contractors
and
self-
employed persons;
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
(j)
interaction with industrial activities at the place
within which or in the vicinity of which the construction site is
located.
Duties of contractors
In order to preserve health and safety on the construction
site, contractors shall
(a)
co-operate with the project supervisor for health
and safety matters in the interest of occupational health and, or
safety;
(b)
co-operate with the project supervisor for health
and safety matters to enable compliance with the duties
pertaining to such project supervisor for health and safety
matters under these regulations;
(c)
promptly provide to the project supervisor for
health and safety matters any necessary information which may
be requested in the interest of occupational health and, or
safety;
(d)
comply without undue delay with the directions
given by the project supervisor for health and safety matters
under these regulations, which directions if carried out, would
ensure occupational health and, or safety;
(e)
comply without undue delay, with the directions
given by the designated person and, or external services
appointed in terms of regulation 9 of the General Provisions for
Health and Safety at Work Places Regulations;
(f)
comply with the relevant preventive and
protective measures listed in the health and safety plan which
measures if implemented, would ensure a safe and, or healthy
place of work, and that are applicable to the contractor or to the
contractor’s workers;
(g)
bring to the attention of the contractor’s workers
any rules applicable to them contained in the health and safety
plan;
(h)
not commence and, or not progress any work
related to the project before a project supervisor for health and
safety matters has been appointed by the client in terms of
regulation 3;
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
(i)
(i)
notwithstanding anything stated in the Act
or any regulations thereof, carry out or ensure that a written,
suitable, sufficient and systematic risk assessment of all the
occupational health and safety hazards which may be present at
the construction site and the resultant risks involved concerning
all aspects of the work activity in the construction site, is
carried out for each project being under taken, and that all
workers are informed of its contents in order to be aware of any
hazards on a construction. Such assessments shall consider the
risks to the health and safety of workers and of self-employed
persons to which they are exposed whilst at work in a
construction site, as well as the risks to the health and safety of
other persons, including visitors to the construction site which
risks arise out of, or in connection with the work being carried
out, or by the conduct of the undertaking
Provided that when carrying out such
assessments, a contractor shall also take into
consideration changes to the work activities being carried
out and to the workplace, and shall take appropriate
action;
(ii)
the contractors shall keep in their
possession written or retrievable electronic copies of
such assessments and shall ensure that they are updated
regularly;
(iii) the contractors shall decide on the
protective measures appropriate to the nature of the work
being carried out which are required to be taken
following these assessments and, if necessary, the
protective equipment to be used;
(iv) the assessments referred to in this
regulation shall be reviewed whenever there is any major
change in working conditions, or whenever the
contractors have reason to suspect that they are no longer
valid;
(j)
comply without undue delay, with the preventive
and protective measures indicated by the risk assessment
carried out under these regulations and, or any other relevant
regulations made under the Act;
(k)
ensure that training, information and instructions
provided in terms of regulation 14 of the General Provisions for
Health and Safety at Work Places Regulations and, or any other
relevant regulations made under the Act, are given to workers
in a comprehensible manner;
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
(l)
in particular when implementing regulation 18,
take measures that are in line with the minimum requirements
set out in Schedule IV;
(m)
comply in particular with the following, mutatis
mutandis
(i)
the requirements of regulations 7 and 15(2)
of the General Provisions for Health and Safety at Work
Places Regulations and regulation 8 and Schedule IV;
(ii)
the Minimum Requirements for the Use of
Personal Protective Equipment at Work Regulations;
(iii) the Work Equipment (Minimum Safety and
Health Requirements) Regulations.
Duties of workers
Without prejudice to the foregoing regulations, in order
to preserve health and safety on the construction site, the worker shall
(a)
co-operate with the project supervisor for health
and safety matters in the interest of occupational health and, or
safety;
(b)
co-operate with the project supervisor for health
and safety matters to enable compliance with the duties
pertaining to such project supervisor for health and safety
matters under these regulations;
(c)
promptly provide to the project supervisor for
health and safety matters any necessary information which may
be required to enable compliance with the duties of such project
supervisor for health and safety matters;
(d)
comply without undue delay with the directions
given by the project supervisor for health and safety matters
under these regulations, which directions if carried out, would
ensure occupational health and, or safety;
(e)
comply without undue delay, with the preventive
and protective measures indicated by the risk assessment
carried out under regulation 19(i) and, or any other relevant
regulations made under the Act;
(f)
comply with the relevant preventive and
protective measures listed in the health and safety plan prepared
under these regulations, which measures if implemented, would
ensure occupational health and, or safety.
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
Information for workers
(1)
Without prejudice to regulation 12 of the General
Provisions for Health and Safety at Work Places Regulations, workers
and, or their representatives shall be informed of all the measures that
shall be taken concerning their health and safety on the construction
site.
(2)
The information shall be comprehensible to the workers
concerned.
Consultation and participation of workers
Consultation and participation of workers and, or of their
representatives shall take place in accordance with regulation 13 of the
General Provisions for Health and Safety at Work Places Regulations
on matters covered by regulations 14 and 18 ensuring whenever
necessary proper coordination between workers and, or workers'
representatives in undertakings carrying out their activities at the
workplace, having regard to the degree of risk and the size of the work
site.
General provisions
(1)
Every person on whom a duty is placed by these
regulations in relation to the design, planning and preparation of a
project shall take into account the general principles of prevention
referred to in the Act in the performance of those duties.
(2)
Every person on whom a duty is placed by these
regulations in relation to the construction phase of a project shall take
into account the general principles of prevention referred to in the Act
in the performance of those duties.
(3)
The client shall take reasonable steps to ensure that the
arrangements referred to in sub-regulation (1) are maintained and
reviewed throughout the project.
In any proceedings for the imposition of an
administrative penalty or an offence under these regulations consisting
of a failure to comply with a duty or requirement to do something in
accordance with the Act and, or any regulations issued thereunder, it
shall be for the accused to prove, as the case may be, that it was not
practicable or not reasonably practicable to do more than was in fact
done to satisfy the duty or requirement, or that there was no better
practicable means than was in fact used to satisfy the duty or
requirement.
Any person who knowingly or recklessly interferes with
the process of providing a safe and healthy place of work, shall be
guilty of an offence under the Act.
AND SAFETY REQUIREMENTS FOR WORK AT
CONSTRUCTION SITES)
The Workplace (Minimum Health and Safety
Requirements for Work at Construction Sites) Regulations are hereby
repealed without prejudice to anything done or omitted to be done
thereunder.
Any action, decision or proceeding, taken or commencing
before the coming into force of the Health and Safety at Work
(Minimum Health and Safety Requirements for Work at Construction
Sites) Regulations, 2025 shall continue to be regulated by the
provisions of the regulations specified in regulation 26, as in force
prior to the coming into force of the Health and Safety at Work
(Minimum Health and Safety Requirements for Work at Construction
Sites) Regulations, 2025.