PROCUREMENT OF PROPERTY REGULATIONS
Table of Provisions (62)
Statutory Text (62 Articles)
PROCUREMENT OF PROPERTY
SUBSIDIARY LEGISLATION 601.12
PROCUREMENT OF PROPERTY REGULATIONS
30th April, 2020
LEGAL NOTICE 163 of 2020.
The title of these regulations is the Procurement of
Property Regulations.
Interpretation and scope
For the purposes of these regulations -
"authorities responsible for the administration of government
land and properties" shall mean the Lands Authority as established
under article 5 of the Lands Authority Act and the Joint Office as
established under article 4 of the Ecclesiastical Entities (Properties)
Act;
"bodies governed by public law" means bodies that have all of
the following characteristics
(a)
they are established for the specific purpose of
meeting needs in the general interest, not having an industrial
or commercial character;
(b)
they have legal personality; and
(c)
they are financed, for the most part, by the State,
regional or local authorities, or by other bodies governed by
public law; or are subject to management supervision by those
bodies or authorities; or have an administrative, managerial or
supervisory board, more than half of whose members are
appointed by the State, regional or local authorities, or by
other bodies governed by public law;
"black listed person" means a black-listed person as defined
under the Public Procurement Regulations;
"conflicts of interest" shall at least mean any situation where
any person, including staff members of the contracting authority or of
a procurement service provider acting on behalf of the contracting
authority, who are involved in the conduct of the procurement
procedure or who may influence the outcome of that procedure have,
directly or indirectly, a financial, economic or other personal interest
which might be perceived to compromise their impartiality and
independence in the context of the procurement procedure;
"contracting authorities" means the State, regional or local
authorities, bodies governed by public law or associations formed by
one or more such authorities or one or more such bodies governed by
public law;
"Contracts Committees" means the General Contracts
Committee as defined under the Public Procurement Regulations;
"direct contracts" means contracts awarded without the need to
publish a prior call for competition;
"Director" means the Director of Contracts as established
under the Public Procurement Regulations;
"economic operator" means any natural or legal person or
public entity or group of such persons and, or entities, including any
temporary association of undertakings who submitted a bid under,
and regulated by, these regulations;
"Evaluation Committee" means boards or committees
appointed by contracting authorities with the purpose of evaluating
tenders received and for making recommendations thereon;
"government’s e-procurement platform" means the electronic
platform for procurement as established by the Director;
"Minister" means the Minister responsible for Finance;
"modification" means any change, variation or amendment to
the original terms of the contract including, but not limited to, the
introduction of new conditions and to the removal or replacement of
existing conditions;
"procurement document" means any document produced or
referred to by the contracting authority to describe or determine
elements of the procurement or the procedure, including the technical
specifications, the descriptive document, proposed conditions of
contract, formats for the presentation of documents by tenderers,
information on generally applicable obligations and any additional
documents including clarifications;
"procurement of property" means the acquisition by whatever
title, whether real or personal, of immovable property by a
contracting authority;
"Review Board" means the Public Contracts Review Board as
established under the Public Procurement Regulations;
"the Schedule" means Schedule 1 - List of Contracting
Authorities - annexed to the Public Procurement Regulations.
The scope of these regulations is to regulate the manner
in which government carries out the procurement of property.
These regulations shall not apply to the following;
(a)
the procurement of property which is regulated
by any other law;
PROCUREMENT OF PROPERTY
(b)
the procurement of property outside the territory
of Malta;
(c)
the procurement of property between contracting
authorities or bodies governed by public law;
(d)
the procurement of property by whatever title
that is declared to be secret or is accompanied by special
security measures in accordance with the laws, regulations or
administrative provisions in force in Malta, as long as the
essential interests concerned cannot be guaranteed by less
intrusive measures; and
(e)
the procurement of property authorized under a
government scheme published in the Gazette.
These regulations shall apply to the procurement of
property carried out after the date of entry into force of these
regulations.
(1)
Without prejudice to the applicability of the
other provisions of these regulations, the procurement process
regulated under these regulations
(a)
that has an estimated value which does not
exceed the threshold of five hundred thousand euro (€500,000)
has to be published, administered and determined by the
contracting authority on its own without the need to involve
the Director;
(b)
that has an estimated value of which exceeds the
threshold of five hundred thousand euro (€500,000)) shall be
published, administered and determined by the Director on
behalf of the contracting authority.
(2) The Minister shall, from time to time, by regulations
determine the thresholds applicable under these regulations.
The Office of the Director of Contracts
Regulations 10 and 11 of the Public Procurement
Regulations shall mutatis mutandis apply to these regulations.
(1)
Unless otherwise provided for in these
regulations, it shall be the duty of the Director to carry out the
following functions
(a)
to monitor procurement of property with the aim
of ensuring adherence to these regulations;
(b)
to establish and regulate the procedure to be
followed
during meetings of the General Contracts
Committee, the Departmental Contracts Committee and the
Evaluation Committee, and during the issue and publication of
calls for tenders, receipt of offers, opening of bids, evaluation
of tenders and award of contracts in accordance with the rules
herein set out;
(c)
to obtain information from all the contracting
authorities or bodies governed by public law on the award and
performance of contracts regulated by these regulations as he
may deem necessary;
(d)
to draw up and maintain a list of persons who
have been black-listed.
(2) Where the Director or his delegate identify, on their own
initiative or upon the receipt of information, specific violations or
systematic problems, they shall be empowered to report this matter to
the appropriate authority.
(3) When the Director becomes aware that the conditions
established under these regulations are not adhered to he may take
any action necessary including directing the contracting authority to
cancel the procurement procedure, or to terminate or rescind the
ensuing contract.
Regulation 13 of the Public Procurement Regulations
shall mutatis mutandis apply to these regulations.
(1)
The Director has the right to cancel the award of
a contract at any time during a call for tenders even after the
recommended bidder has been chosen and the time established to file
an appeal before the Public Contracts Review Board has lapsed, if it
is found that such a contract has been awarded in breach of these
regulations.
(2) The decision leading to the cancellation of a
procurement procedure has to be made in writing and must include
the findings and the reasoning that led to this decision.
(3) A copy of this decision must be notified to each bidder
who participated in that particular call, and the bidder shall have the
right to contest the decision by filing a complaint before the Review
Board.
(4) The procedure mentioned in regulation 276 of the Public
Procurement Regulations shall mutatis mutandis apply to this
regulation.
(5) There shall be an appeal to the Court of Appeal from the
decision of the Review Board.
The Contracting Authority
PROCUREMENT OF PROPERTY
(1)
It shall be the duty of all contracting authorities
(a)
to observe and abide by these regulations;
(b)
to draw up procurement documents and all
relevant supporting documentation as well as to publish and
administer, without the involvement of the Director, calls for
tenders, where the estimated value of such tenders is in
accordance with the threshold established under regulation
6(1)(a);
(c)
to forward the procurement document and all
relevant supporting documentation to the Director so that they
may be vetted, published and administered by the latter when
the estimated value of the procurement process is in
accordance with the threshold established under regulation
6(1)(b);
(d)
to publish all calls for tenders, through
government’s e-procurement platform, unless otherwise
provided for in these regulations;
(e)
to take appropriate measures to effectively
prevent, identify and remedy conflicts of interest arising in the
conduct of procurement procedures so as to avoid any
distortion of competition and to ensure equal treatment of all
bidders;
(f)
to indicate in their procurement documents that
the award of the contract is subject to the review procedure as
set out in these regulations and to include an extract of the
relevant part of the appeals process in the said documents for
the guidance of the bidders;
(g)
to administer and implement all contracts
awarded by them or on their behalf and to defend before a
board or tribunal any dispute that might arise in the execution
of the contract;
(h)
to effect all payments resulting from the
execution of the contract;
(i)
to forward immediately to the Director any
information which the latter may request.
(2) Contracts which result from tenders the estimated value
of which is in accordance with the threshold established under
regulation 6(1)(a) shall be signed by the head of the contracting
authority.
The Evaluation Committee and the evaluation report
(1)
The evaluation of a call for tenders shall be
carried out by an Evaluation Committee which shall be appointed as
follows
(a)
for tenders which have an estimated value which
is in accordance with the threshold established under
regulation 6(1)(a), the Evaluation Committee shall be
approved by the head of the contracting authority;
(b)
for tenders which have an estimated value which
is in accordance with the threshold established under
regulation 6(1)(b), the Evaluation Committee shall be
recommended by the head of the contracting authority and
approved by the Director.
(2) The Evaluation Committee shall evaluate the offers
submitted by the bidders in reply to the publication of a procurement
document and make recommendations through the evaluation report.
(3)
The evaluation report shall be communicated as follows
(a)
for tenders with an estimated value which is in
accordance with the threshold established under regulation
6(1)(a), the Evaluation Committee shall communicate the
report to the Departmental Contracts Committee which is
empowered to make definitive recommendations on the award
or cancellation of the procurement process;
(b)
for tenders with an estimated value which is in
accordance with the threshold established under regulation
6(1)(b), the Evaluation Committee shall communicate the
report to the Director who shall be empowered to make
definitive recommendations on the award or cancellation of
the procurement process.
Contracting authorities shall, for every tender, draw up a
written report which shall include at least the following
(a)
the name and address of the contracting
authority, the subject-matter and value of the call for tenders;
(b)
where applicable, the results of the qualitative
selection;
(c)
the names of the selected tenderer and the
reasons for his selection;
(d)
the names of the tenderers rejected or excluded
and the reasons for their rejection or exclusion;
(e)
where applicable, the reasons why the
contracting authority has decided not to award a contract.
Classification of Contracting Authorities and Joint Procurement
(1)
For the purposes of these regulations, the
Schedule lists the contracting authorities or bodies governed by
public law which are obliged to follow these regulations.
(2) A body governed by public law or a contracting
authority, which is not listed under the Schedule, shall have the same
obligations of an authority listed under the said Schedule.
(1)
After obtaining the prior written approval of the
Director and subject to the conditions the latter may impose, two or
more contracting authorities may jointly procure property in terms of
these regulations.
(2) The procurement procedure shall be administered by the
contracting authority or by the Director, as the case may be, in terms
of regulation 6 depending on the estimated value of the joint
procurement.
(3) Where the conduct of a procurement procedure in its
entirety is carried out jointly in the name and on behalf of all the
contracting authorities concerned, they shall be jointly responsible
for fulfilling their obligations pursuant to these regulations.
(4) Where the conduct of a procurement procedure is not in
its entirety carried out in the name and on behalf of the contracting
authorities concerned, they shall be jointly responsible only for those
parts carried out jointly. Each contracting authority shall have sole
responsibility for fulfilling its obligations pursuant to these
regulations.
The Contract Value
(1)
The calculation of the estimated value of a
procurement procedure shall be based on the total amount payable,
excluding any tax, as estimated by the contracting authority,
including any form of option and any renewals of the contracts as
explicitly set out in the procurement documents.
(2) The estimated value referred to in sub-regulation (1)
shall be valid at the moment at which the call for competition is sent,
or, in cases where a call for competition is not foreseen, at the
moment at which the contracting authority commences the
procurement procedure, for instance, where appropriate, by
contacting bidders in relation to the procurement.
(3) Where a procurement process for the procurement of
property may result in contracts being awarded in the form of
separate lots, in order to determine the estimated value the
contracting authority shall take into account the cumulative value of
all lots when applying the provisions of regulation 6.
Contracts into Lots
Contracting authorities may decide to award a contract
in the form of separate lots and may determine the size and subject
matter of such lots, indicating in the procurement document whether
the offer can be submitted for one, for several or for all of the lots.
Contracting authorities may, even where tenders may be
submitted for several or all lots, limit the number of lots that may be
awarded to one tenderer, provided that the maximum number of lots
per tenderer is stated in the procurement document.
General Principles
(1)
The procurement document shall be written in
clear and unambiguous terms so as to enable all interested parties to
understand properly the terms and conditions of the process.
(2) If requested in good time, the contracting authorities
shall supply to all tenderers taking part in the procurement procedure
additional information relating to the specifications and any
supporting documents not later than four days before the time limit
fixed for the receipt of tenders.
(3) The authority administering the procurement process
may publish clarification notes to explain certain matters, to give
additional information, to remove or amend certain inconsistencies or
errors and to fill in missing information contained in the procurement
document.
(4) When published in the clarification notes, the additional
information and the supporting document shall automatically form an
integral part of the procurement document.
(1)
Contracting authorities shall treat bidders
equally and shall act in a transparent and proportionate manner.
(2) The tenderer must be selected in a transparent manner
and according to a prescribed procedure in these regulations and in
the procurement documents.
(1)
Subject to the obligations established under
these regulations and, or any other law, a contracting authority or the
Director shall not disclose information forwarded to it by bidders
which information they have designated as confidential.
(2) Without prejudice to the other provisions of these
regulations, the following information shall not be considered as
confidential
(a)
the name of the bidders and the individual names
of the members of a group of economic operators who
submitted a particular tender and any information related to
the bidders’ capacity to qualify for a particular procurement
procedure;
(b)
the premises procured under these regulations;
(c)
the price for which the contract is awarded; and
(d)
information which is already available to the
public.
(3) Contracting authorities may impose on bidders
requirements aimed at protecting the confidential nature of
information which the contracting authorities make available
throughout the procurement procedure.
(1)
The authority responsible for the tendering
process shall, unless otherwise approved by the Director, by
electronic means offer unrestricted and full direct access free of
charge to the procurement documents from the date of publication of
the procurement documents on the government’s e-procurement
platform.
(2) Where the Director approves that the publication be
carried out without using government’s e-procurement platform, the
authority responsible for the tendering process is still obliged to offer
unrestricted and full direct access free of charge to the procurement
documents from the date after the publication in the Gazette.
(1)
The technical specifications and use of the
property to be used shall be set out in the procurement documents
which shall lay down the characteristics required in the said property.
(2) Technical specifications shall afford equal access of
bidders to the procurement procedure and shall not have the effect of
creating unjustified obstacles.
(3) The technical specifications shall as far as possible be
formulated in terms of performance or functional requirements,
including environmental characteristics or location, provided that the
parameters are sufficiently precise to allow tenderers to determine the
subject-matter of the contract and to allow contracting authorities to
award the contract.
(4) Where a label, standard or brand is quoted, the
contracting authority must ensure that the reference to such
standards, labels or brands is accompanied by the words ‘or
equivalent’.
The Tenderer
A tenderer may either be a natural or a legal person or a
public entity or group of such persons and, or entities provided that
such person is allowed at law to dispose of the property which is the
subject of the tender.
Groups of economic operators, including temporary
associations, may participate in procurement procedures.
The Selected Offer
(1)
A procurement procedure published under these
regulations shall be awarded on the basis of the award criteria set out
by the authority responsible for the tendering process provided that
all the following conditions are fulfilled
(a)
the offer complies with the
minimum
requirements set in the procurement document;
(b)
the tenderer is not excluded from participating in
the award procedure in accordance with Part VI of the Public
Procurement Regulations; and
(c)
the tenderer is not black listed in terms of Part
VI of the Public Procurement Regulations.
(2) The minimum requirements referred to in sub-regulation
(1)(a) shall inter alia include conditions and characteristics
(particularly technical, physical, functional and legal) that any tender
should meet or possess.
(1)
Without prejudice to Part VI of the Public
Procurement Regulations, the authority responsible for the tendering
process must ensure that a bidder must ab initio be eligible to qualify
for a tender and must consequently be in possession of all the
requirements stipulated in the procurement documents by the closing
date for the submission of the same.
(2) Where information or documentation to be submitted by
bidders is or appears to be incomplete or erroneous or where specific
documents are missing, contracting authorities may, in terms of the
procurement document, request the bidder concerned to submit,
supplement, clarify or complete the relevant information or
documentation within an appropriate time limit
Provided that such requests shall be made in full
compliance with the principles of equal treatment and transparency.
(3) The financial bid cannot be changed with the exception
of the correction of evident arithmetical errors as may be allowed in
the procurement document.
Where a tenderer either directly or indirectly has advised
the contracting authority or the authority responsible for the
tendering process, on the future procurement of property, such
tenderer shall be precluded from participating in the ensuing
procurement procedure.
Part II
Boards, Committees and Tribunals
General Contracts Committee
Regulations 64 to 72 of the Public Procurement
Regulations shall mutatis mutandis apply to these regulations.
Departmental Contracts Committee
There shall be a Departmental Contracts Committee
which shall be responsible, unless otherwise regulated in these
regulations, to make final recommendations for the award of
procurement processes where the estimated value of such process is
in accordance with the threshold established under regulation 6(1)(a).
The Departmental Contracts Committee shall be
composed of three members, as follows
(a)
a chairman, who shall be the Head of the
Department responsible for Corporate Services, or his
representative;
(b)
one member appointed by the Permanent
Secretary of the Ministry concerned; and
(c)
one member representing the Director of
Contracts, which member may also be a member of the
General Contracts Committee.
The Departmental Contracts Committee shall be assisted
by a Secretary who shall be appointed by the Permanent Secretary of
the Ministry concerned.
The Departmental Contracts Committee shall send a
copy of its recommendation to the Director.
Public Contracts Review Board
Regulations 80 to 94 of the Public Procurement
Regulations shall mutatis mutandis apply to these regulations.
Part III
Publication, Tendering Procedure and Time Limits
(1)
Before publishing a procurement procedure,
contracting authorities must consult with the authorities responsible
for the administration of government land and properties.
(2) If such authorities are of the opinion that they have in
their portfolio a property which at least fulfils the requirements of the
contracting authority, the latter shall be obliged to make use of such
property instead of issuing a call for tenders.
(3) If the authorities responsible for the administration of
government land and properties are of the opinion that in their
portfolio there is no such property, they shall declare so and the
contracting authority shall be authorised to carry on with such
procurement in line with what is established under these regulations.
(1)
Before publishing a procurement procedure,
contracting authorities may conduct market consultations with a view
to preparing the procurement and informing bidders of their
procurement plans and requirements.
(2) Contracting authorities may, for instance, seek or accept
advice from independent experts or authorities or from market
participants. That advice may be used in the planning and conduct of
the procurement procedure, provided that such advice does not have
the effect of distorting competition and does not result in a violation
of the principle of transparency and equal treatment.
(1)
The authority responsible for the tendering
process shall have the freedom to organise the procedure leading to
the choice of a successful bidder provided such choice complies with
these regulations.
(2) Such procedure must be clearly identified in the
procurement document.
(3) The design of the procurement process shall ensure that
information is not provided in a discriminatory manner which may
give some tenderers an advantage over others.
(4) Unless otherwise approved by the Director the tendering
process for the procurement of property shall be published using
government’s e-procurement platform.
(5) Where the Director approves that the tendering process
is not published through the government’s e-procurement platform,
such tendering process is to be advertised at least on the Gazette.
The authority responsible for the tendering process shall
provide for appropriate recording of the stages of the procedure using
the means it deems appropriate.
(1)
If the tender document provides for it, the
contracting authority may hold negotiations with tenderers.
(2)
The tender document must identify which clauses and
requirements are subject to negotiations. In determining these areas
the authority administering the procurement process shall ensure that
the subject-matter of the procurement process, the award criteria and
the minimum requirements shall not be changed during the course of
the negotiations.
(1)
When fixing the time limits for the receipt of
tender offers, the authority responsible for the tendering process shall
take into account in particular the complexity of the requirements
established in the procurement documents without prejudice to the
minimum time limits set out in this regulation.
(2) The tendering process may be either in a single stage or
in successive stages.
(3) The minimum time limit for the receipt of tender offers
in the case of a single stage process or for the initial submission in the
case of a tender with successive stages, shall be thirty days from the
date on which the procurement document was published on the
government’s e-procurement platform or from the next day on which
an advert has been published on the Gazette, as the case may be.
(4) When the estimated value of a procurement procedure is
in accordance with the threshold established under regulation 6(1)(a),
the contracting authority must obtain the prior written approval of the
Permanent Secretary responsible for it, or any person delegated by
him in writing, to reduce the time limits established under sub-
regulation (3) by fifteen days
Provided that the Permanent Secretary or his delegate
may, in granting such an approval, impose any condition he may
deem fit.
(5) When the estimated value of a tendering process is in
accordance with the threshold established under regulation 6(1)(b), a
contracting authority must obtain the prior written approval of the
Director to reduce the time limit established under sub-regulation (3)
by fifteen days
Provided that the Director may, in granting such an
approval, impose any condition he may deem fit.
Notwithstanding anything included under these
regulations, a contracting authority may procure property through a
direct contract upon obtaining the prior written approval as provided
hereunder
(a)
when the estimated value of a tendering process
is in accordance with the threshold established under
regulation 6(1)(a), a contracting authority must obtain prior
written approval of the Minister who may delegate his
authority in writing to the Permanent Secretary or any other
senior official in his Ministry;
(b)
when the estimated value of a tendering process
is in accordance with the threshold established under
regulation 6(1)(b), a contracting authority must obtain prior
written approval of the Director.
Part IV
Exclusion and Black Listing of Economic Operators
Part VI of the Public Procurement Regulations shall,
mutatis mutandis, apply to these regulations.
Part V
Eligibility, Choice of participants and award of contracts
Eligibility
(1)
The authority responsible for the tendering
process shall in the procurement document request bidders to declare
that they do not fall under any grounds established under regulation
42. (2) Contracting authorities may at any stage of the
procurement process require the certificates, statements and other
means of proof as evidence for the absence of grounds for exclusion
and for the fulfilment of the selection criteria and the award criteria.
(3) Contracting authorities may also at any stage of the
procurement process require proof of title over the proposed property
subject to the procurement and capacity to dispose such property.
Choice of Participants
Contracting authorities may impose selection criteria in
order to ensure that bidders are suitable for the execution of the
contract.
As to suitability, contracting authorities may inter alia
impose requirements ensuring that the property being procured is
covered by the licences and permits necessary for the intended use of
the property.
The authority responsible for the tendering process shall
indicate the required conditions of participation which may be
expressed as minimum levels, together with the appropriate means of
proof, in the procurement documents.
Award
(1)
Tenders shall be awarded on the basis of
objective criteria which comply with the principles set out in these
regulations and which ensure that tenders are assessed in conditions
of effective competition so as to identify an overall economic
advantage for the contracting authority.
(2) The award criteria shall be linked to the subject-matter
of the contract, and shall not confer an unrestricted freedom of choice
on the contracting authority.
(3) The award criteria are to be published in the
procurement document.
(4) The award criteria may include, inter alia,
environmental, social or innovation-related criteria and location of
the property.
(5) The award criteria shall be accompanied by
requirements, which allow the information provided by the tenderers
to be effectively verified.
(6) The contracting authority shall verify whether tenders
properly meet the award criteria and shall detail its reasoning in the
evaluation report.
(7) Once established, the award criteria cannot be altered
under any circumstance.
(1)
The authority administering the procurement
process shall as soon as possible inform each tenderer of decisions
taken concerning the award of a call issued under these regulations.
The issued information shall include the name of the successful
tenderer, the grounds for any decision to reject his tender and the
grounds for any decision not to award a contract for which there has
been a public call.
(2) Further to the provisions of sub-regulation (1), on
request from the party concerned, the authority responsible for the
administration of the procurement process shall as quickly as
possible, and in any case within fifteen days from receipt of a written
request, inform any tenderers that have submitted a tender of the
characteristics and relative advantages of the tender selected.
(3) The authority responsible for the administration of the
procurement process may decide to withhold certain information
referred to in sub-regulation (1), regarding the contract, where the
release of such information would impede law enforcement, would
otherwise be contrary to the public interest, would prejudice the
legitimate commercial interests of bidders, whether public or private,
or might prejudice fair competition between such operators.
Part VI
Rules on Performance of Contracts
Application of contractual obligations
Contracting authorities shall ensure that the obligations
established in a call for tenders and the ensuing contract are adhered
to.
Modifications
(1)
Modifications to the contracts are to be limited
as far as practicable; however contracting authorities may, subject to
the following conditions, carry out modifications to the contracts.
(2) In the case of call for tenders with an estimated value
which is in accordance with the threshold established under
regulation 6(1)(a), the contracting authority may carry out
modifications to the contract provided that it obtains the written prior
approval of its Permanent Secretary or his delegate.
(3) In the case of call for tenders with an estimated value
which falls under regulation 6(1)(b), the contracting authority may
carry out modifications to the contract provided that it obtains the
written prior approval of the Director.
In its request for approval the contracting authority shall
provide the following information
(a)
the reasons which brought about the need for the
modification;
(b)
the effect on the total cost of the tender and any
effect on the recurrent expenditure that will ensue;
(c)
the written consent of all the parties to the
contract to carry out the modification.
(1)
In granting or refusing a request for a
modification, the Permanent Secretary or the Director, as the case
may be, shall assess whether the request is justified and whether the
modification is cost-effective.
(2) The Permanent Secretary or the Director, as the case
may be, is to keep a full record of the process of modification
requests, including the respective approval therefor.
(3) The decision of the Permanent Secretary or the Director,
as the case may be, relating to the refusal of a modification shall be
final and shall not be contested by the contracting authority in a court
or tribunal.
(4) In granting or refusing a request for a modification, the
Permanent Secretary or the Director, as the case may be, may issue
any instruction they may deem fit to the contracting authority who
shall be obliged to implement such instructions.
When a modification is carried out without seeking the
prior written approval of the Director or of the respective Permanent
Secretary, as the case may be, the Director or the Permanent
Secretary cannot be requested to give a retroactive approval of the
modification and thus shall abstain from taking any cognisance of it.
The responsibility of this unapproved modification shall vest in the
head of that contracting authority in accordance with the Fiscal
Responsibility Act.
Any modification carried out against the express refusal
of the Permanent Secretary or the Director, as the case may be, shall
be deemed to be founded on an unlawful consideration and the other
parties in the contract shall have no right for compensation with
respect to that modification unless they show that they were unaware
of the refusal of the Permanent Secretary or the Director.
Following a request by the Permanent Secretary or the
Director, as the case may be, the State Advocate may, on behalf of the
government, institute civil proceedings in a court of law for the
restoration of payments received by an owner in bad faith in relation
to modifications which have been prohibited in terms of these
regulations. Such action shall not be subject to any prescriptive
period.
An owner shall desist from acceding to a modification
which requires the prior written approval of the Director or the
Permanent Secretary, as the case may be, unless the contracting
authority provides him with a written confirmation of the said
approval. If the owner agrees to the modification nonetheless, he
shall be deemed to have acted in bad faith and thus he shall not be
entitled to any compensation with respect to that modification, so
long as such modification was not approved in terms of these
regulations or when the contracting authority proceeded with the
modification without seeking the prior written approval of the
Director or the respective Permanent Secretary, as the case may be.
Any payments received by the owner in this regard may be restored
in the same manner as provided in regulation 55.
Termination or Rescission of a Contract
(1)
The Director has the right to issue a decision
terminating or rescinding any contract or agreement that could have
been reached or signed with an owner if it transpires that the award of
that contract has been made in breach of these regulations.
(2) The decision leading to the termination or rescission of
the contract in accordance with this regulation shall be made in
writing and must include the findings and the reasons.
(3) A copy of the decision must be delivered to the owner,
who has the right to contest it by filing a complaint before the Review
Board as provided for in regulation 60.
(4) The termination or rescission of the contract will remain
suspended as long as the time limit for the submission of the
complaint before the Review Board or the Court of Appeal lapses and
during the duration of these same proceedings.
(5) The owner shall have no right to be compensated for the
actual loss or loss of profits, where the decision to terminate the
contract is confirmed, with the exception that the owner shall have
the right to receive compensation he deserves for the occupation of
the property until the decision of termination is confirmed.
(6) Should the decision of rescission of the contract be
confirmed, then the effects of rescission as provided for under the
Civil Code shall apply.
Part VII
Appeals
Remedies before closing date of a call for competition
Regulations 262 to 269 of the Public Procurement
Regulations shall mutatis mutandis apply to these regulations.
Appeals from Decisions taken after the Closing Date
for the Submissions of an Offer
Regulations 270 to 276 of the Public Procurement
Regulations shall mutatis mutandis apply to these regulations.
Appeal from a Decision terminating or rescinding a Contract.
Regulation 283 of the Public Procurement Regulations
shall mutatis mutandis apply to these regulations.
Court of Appeal
Regulations 284 to 290 of the Public Procurement
Regulations shall mutatis mutandis apply to these regulations.