ACTION ON ILLEGAL DEPOSIT OF MATERIAL ON LAND AND ILLEGAL RECLAMATION OF LAND REGULATIONS
Table of Provisions (8)
Statutory Text (8 Articles)
AND ILLEGAL RECLAMATION OF LAND
SUBSIDIARY LEGISLATION 552.29
ACTION ON ILLEGAL DEPOSIT OF MATERIAL ON
LAND AND ILLEGAL RECLAMATION OF LAND
REGULATIONS
23rd April, 2019
LEGAL NOTICE 83 of 2019.
The title of these regulations is the Action on Illegal
Deposit of Material on Land and Illegal Reclamation of Land
Regulations.
(1)
In these regulations, unless the context otherwise
requires
"afforestation" means the planting of trees or vegetation on non-
forested land;
"the Act" means the Development Planning Act or the
Environment Protection Act as the context may require;
"the Authority" shall have the same meaning as that assigned to
it by the Act;
"contravener" means any person who has been notified with an
enforcement notice which has been rendered executable, or a stop and
compliance order, where such enforcement notice or order relates to
the illegalities specified in regulation 3;
"inert waste" shall have the same meaning as that assigned to it
in the Waste Regulations;
"invasive alien species" shall have the same meaning as that
assigned to it in the Flora, Fauna and Natural Habitats Protection
Regulations;
"protected area" means any area protected through the
Environment Protection Act, or scheduled for ecological and scientific
reasons under the Development Planning Act.
(2)
In these regulations, words and expressions defined in
the Act shall have the same meaning as assigned to them in the Act.
These regulations shall apply to any land subject to
enforcement action, issued prior or after the entry into force of the Act
or prior or after the entry into force of these regulations, which
enforcement action relates to any illegality which constitutes, or refers
to:-
(a)
land rendered derelict to the extent of constituting
an injury to amenity, provided that such illegality appears on
AND ILLEGAL RECLAMATION OF LAND
the Authority’s aerial photographs of the year 2012 but does not
appear on the Authority’s aerial photographs of the year 1994;
or
(b)
the illegal deposit, dumping or tipping of any
material on any land, provided that such illegality appears on the
Authority’s aerial photographs of the year 2012 but does not
appear on the Authority’s aerial photographs of the year 1994;
or
(c)
the illegal reclamation of any land, provided that
such illegality appears on the Authority’s aerial photographs of
the year 2012 but does not appear on the Authority’s aerial
photographs of the year 1994. Where the illegal reclamation of
land appears on the Authority’s aerial photographs of the year
1994 and the Authority’s aerial photographs of year 2012
confirm that further illegal reclamation of land took place after
the year 1994, the Authority shall have the right to execute the
necessary action in terms of these regulations both in relation to
the illegal reclamation of land which appears on the aerial
photographs of the year 1994 as well as any illegal reclamation
of land which took place subsequent to that year and which
appears on Authority’s aerial photographs of year 2012.
Land subject to enforcement action relating to any
illegality specified in regulation 3 shall be regenerated either by being
restored to its original state or afforested. The Environment and
Resources Authority shall identify the most suitable regeneration
method for land subject to enforcement action as specified in regulation
3, and where the site is of cultural value it shall consult the
Superintendence for Cultural Heritage.
(1)
The Authority shall order the contravener to
prepare a method statement, according to the terms of reference in the
Schedule, for the restoration of the land to its original state, or
afforestation as relevant, to the satisfaction of the Environment and
Resources Authority, and where the site is of cultural value, to the
satisfaction of the Superintendence of Cultural Heritage. The
Environment and Resources Authority and the Superintendence of
Cultural Heritage shall have the right to request the method statement
to address other issues over and above those defined in the Schedule.
(2)
The Authority shall duly notify the contravener, in terms
of the Act, of the requirement to submit a method statement in terms of
sub-regulation (1). The Authority’s notification shall specify the
requirements and the terms of reference for the proposed method
statement, which shall also include those as requested by the
Environment and Resources Authority and the Superintendence of
Cultural Heritage, and the time-frame within which such method
statement is to be submitted by the contravener to the Authority.
AND ILLEGAL RECLAMATION OF LAND
(3)
A method statement submitted in terms of sub-regulation
(2) shall be endorsed by the Environment and Resources Authority and
where applicable the Superintendence of Cultural Heritage
Provided that the same method statement fully addresses
all the requirements laid down in the terms of reference notified to the
contravener in accordance with sub-regulation (2). In its endorsement,
and without prejudice to any other legislation, the Authority may
impose any additional requirements or conditions it may deem fit to
impose.
(4)
The contravener shall be duly notified in terms of the Act
of the endorsed method statement. The date of notification of the
endorsed method statement shall be deemed to constitute the date upon
which the works specified in the same method statement are to
commence.
(1)
In those cases where the contravener:-
(a)
fails to submit the method statement within the
time-period imposed by the Authority in accordance with
regulation 5(2) and consequently the same method statement is
prepared by the Authority; or
(b)
submits a method statement which is not to the
satisfaction of the Environment and Resources Authority and,
where applicable, the Superintendence of Cultural Heritage; or
(c)
fails to execute the necessary works authorised by
the Authority in the endorsed method statement or fails to
complete such works within the time-frame imposed in the
endorsed method statement; or
(d)
executes works in a manner which is not in
accordance with the terms and conditions of the endorsed
method statement,
the Authority, without prejudice to other legislation, shall have
the right to exercise all powers conferred to it by the Act so as
to enter the land in question and execute all the works necessary
in order to implement the method statement to the satisfaction
of the Environment and Resources Authority and the
Superintendence of Cultural Heritage.
(2)
In cases where the land subject to enforcement action
refers to an unknown owner and occupier or land which is Government
property and subject to enforcement action which refers to an
unknown occupier, the Authority shall be responsible to prepare the
appropriate method statement and shall have the same powers
conferred to it in terms of sub-regulation (1).
AND ILLEGAL RECLAMATION OF LAND
(3)
The Authority shall supervise the work and certify
compliance in relation to the works carried out.
(4)
The Authority may, without prejudice to any other
legislation, also impose an administrative fine on the contravener,
which fine shall be calculated on the basis of the estimated expenses for
the maintenance of the land for the first five (5) years by the Authority
in terms of sub-regulation (1).
(5)
The costs imposed upon the contravener in instances of
non-compliance with these regulations shall include all expenses
incurred by the Authority
(a)
planning;
(b)
procurement;
(c)
ground preparation;
(d)
uprooting of alien species, if any;
(e)
planting;
(f)
irrigation;
(g)
weeding;
(h)
beating up;
(i)
staking of trees; and
(j)
any other operation necessary
for
the
successful
implementation of the method statement.
(1)
Where a site is afforested and the afforestation is
not suitably maintained, or else material is deposited illegally on any
land after the entry into force of these regulations, the Authority shall
notify the Government of any such breach and the Government may
proceed either to
(a)
terminate the occupancy agreement to which the
land is subject, if the land in question is a Government owned
land; or
(b)
expropriate the land, if the land in question is a
privately owned land; and this in order to ensure that the relative
afforested land is suitably maintained and, or the relative land is
protected from further illegal deposit of material.
(2)
Following action taken under sub-regulation (1) the
Minister responsible for the environment may enter into a guardianship
deed in line with the Environment Protection Act.
AND ILLEGAL RECLAMATION OF LAND
Schedule
Outline Requirements and Terms of Reference
for the Method Statement
1. Outline Requirements
1.1
Use of Trees and other vegetation
(a)
Trees and vegetation used for the rehabilitation
shall be indigenous species which are native to
the area/site concerned and compatible and
appropriate to the adjacent habitats. The method
statement shall indicate the species, in Latin,
Maltese and English names; the number; and the
approximate location of the relative trees and/or
vegetation.
(b)
The choice of species shall be guided by the
policy document "Guidelines on Trees, Shrubs
and Plants for Planting and Landscaping in the
Maltese Islands" of the year 2002 as amended,
and the "Guidelines on managing non-native
plant invaders and restoring native plant
communities in terrestrial settings in the Maltese
Islands (MEPA, 2011)", as amended or any other
related approved document. If any alien invasive
species are already growing on site, these must be
uprooted and destroyed as part of the
rehabilitation procedures. Such works are to be
undertaken in a manner to prevent further damage
to the environment and reduce the possibility of
re-sprouting of invasive alien species.
2. Terms of Reference
The method statement is required to identify how the
interventions to re-instate a site should be carried out with the
least possible damage on the site and its surroundings. The
likely environmental impacts of the interventions and mitigation
measures should be included in the method statement. The
method statement shall include the following basic information
in addition to other specific site re-instatement and ecological
requirements as determined by the Environment and Resources
Authority on a case-by-case basis
A.
Organization and responsibilities
Proposed project management arrangements during all phases of
the development are to be presented in the document, which
should include the following
AND ILLEGAL RECLAMATION OF LAND
(a)
the description of the timing of the works defining
the expected duration of the whole project,
including start date and end date, and for each
respective phase;
(b)
an identification and contact details of the site
manager (as approved by the Environment and
Resources Authority) that shall be responsible for
overseeing the completion of works in accordance
with the method statement on behalf of the
responsible party;
(c)
a description of how the progress of works will be
monitored and recorded, e.g.: photographic means
(before, during and after). After the completion of
works, a copy of the photographs shall be
submitted to the Environment and Resources
Authority for record-keeping purposes; and
(d)
a description of the maintenance of the trees and
vegetation planted on site covering a period of five
years, including any maintenance agreements
entered into by the person/entity carrying out the
afforestation. This shall consider appropriate
watering, pruning, de-weeding and any additional
interventions that may be required to ensure
proliferation of the trees and vegetation planted as
part of the afforestation.
B.
Description of site and its surroundings
(a)
a site plan including a clear outline of the extent
of the site boundary and surrounding area(s)
which may be affected;
(b)
details, including maps and drawings, are to be
provided of the site topography, geology and
hydrology, as well as natural habitats/ecology and
other natural features within (or under) the site
and its surrounding area of influence;
(c)
details of any other trees, vegetation or natural or
other feature to be affected by the proposed works,
such as retaining walls, topography and other
relevant site characteristics; and
(d)
a description of the material currently or
historically dumped or deposited on site or spilling
over from it, including details of any likely
pollution or contamination on, under or around the
AND ILLEGAL RECLAMATION OF LAND
site, as a direct or indirect result of such dumping,
deposition or spillage.
C.
Description of works
(a)
a site plan indicating the location of the material,
interventions and/or illegalities to be removed;
(b)
a description of the nature of the material,
interventions and/or illegalities to be removed;
(c)
a description of the interventions that are required
to remedy environmental damage and to re-
instate/rehabilitate the site in particular, but not
solely limited to the following, as may be
relevant
(i)
plans, elevations and sections detailing
the proposed operations/works to be
undertaken and any other interventions (if
relevant);
(ii)
a list of machinery (including vehicles)
and/or tools to be deployed and for each
machinery/tool the intended use;
(iii)
a description of how the site is going to be
accessed (including travel routes to and
form the site, and/or within the site) and
how any machinery and/or tools shall be
brought on site and subsequently
removed - both for demolition and carting
away of material;
(iv)
a site plan indicating where machinery
(including vehicles), equipment and /or
tools shall be kept once works are in
progress;
(v)
a site plan indicating which areas shall be
cordoned off before, during or after the
required works and for which purpose;
(vi)
a description of the type of hoarding to be
employed for cordoned off areas;
(vii)
a description of how the offending
material is to be removed from site and
the location of its final disposal and/or
other recovery operations. In the case of
temporary storage and/or deposition of
AND ILLEGAL RECLAMATION OF LAND
the offending material prior to its removal,
a site plan indicating which area shall be
utilised for such purpose is to be provided;
(viii)
a list of mitigation measures to ensure that
no spillage of material due to agents such
as wind, runoff, wave action, subsidence
or collapse, anthropogenic factors, or a
combination of the foregoing factors
occurs during any phase of the project;
(ix)
an indication of any species to be planted
in connection with the works, also taking
into account the habitat previously
existing on site prior to the illegal
reclamation or degradation as well as the
surrounding natural habitats;
(x)
any mitigation measures deployed to
contain as much as possible any murkying,
silting, smothering, scouring and pollution
of any features, habitats and water bodies
(terrestrial, underground or marine)
located further downslope or downstream;
(xii)
a list of mitigation measures to ensure that
no deleterious impacts to the natural and
physical environment occurs during any
phase of the project, in particular to ensure
that no trampling, disturbance, mechanical
damage and/or spillages or leakages of
fuels, oils or other substances occur;
(xiii)
any additional measures (e.g. finishing
works) that will be undertaken to restore
the site as much as possible to a pristine
natural condition;
(xiv)
clarification of any additional conditions
required to ensure recovery of the site
environment
and/or
to
prevent
deterioration or degradation of the site and
its surrounding environment both during
and after the works;
(xv)
an undertaking by the contravener to
notify the Authority at least three weeks in
advance of any changes in the work
schedule in the approved method
statement;
AND ILLEGAL RECLAMATION OF LAND
(xvi)
an undertaking by the contravener not to
carry out any works unless under the
supervision of officials from the
Authority or other persons acting under
the Authority’s instructions;
(xvii)
identification of which parts of the
proposed works or interventions require
prior authorisation from the Environment
and Resources Authority under the
respective environmental regulations;
(xviii) a contingency plan to prevent accidental
risks of environmental damage from the
proposed works or interventions.