11th May, 2025
LEGAL NOTICE 53 of 2025, as amended by Legal Notice 233 of
2025. PART I
INTERPRETATION AND APPLICABILITY
(1)
The title of these regulations is the Environmental
Permitting (Procedure for Applications and their Determination)
Regulations.
(2)
These regulations provide a framework for
environmental permits, laying down the thresholds and procedure and
serve as guidance for the Environment and Resources Authority to
authorise and regulate any activity, operation or intervention that may
have an effect on the environment.
Operations, interventions and activities for which clearance in accordance to
regulation 35(4) may be granted
The following operations, interventions and activities shall require clearance
within six (6) months from entry into force of these regulations, and subsequently
clearance under these regulations. The level type and application fee payable for
each category shall be applicable as indicated in the table
The following note shall be interpreted as follows
APPLICATIONS AND THEIR DETERMINATION)
#
Identifies those categories that at the stage of renewal of the clearance
as a permit are to be published on the Authority’s website for representations in
accordance with regulations 9(3) and 13(1) and which require a decision to be taken
in public in accordance with regulation 15(2);
Cate-
Operation, Intervention or
Type of application
Fee for a
gory
Activity
orpermit
new appli-
cation
€2,500 and
Reclamation on land or at sea,
a fee per
using inert waste or stabilised
metre cubed
waste that has reached end-of-
(m 3 ) as
2.1
Level III
waste status, in association with
established
Category 1.13 where reclamation
by the
or dumping is at sea (#)
Authority
2.2
Animal slaughterhouse (#)
Level II
€1,500
2.3
Rendering plant (#)
Level II
€1,500
Quarrying operations not covered
2.4
Level II
€1,500
by category 1.4 or 1.31 (#)
Manufacture of computer, elec-
2.5
tronic and electrical equipment
Level II
€1,500
and optical products
Manufacture or processing of
asphalt or other non-metallic min-
2.6
eral products, including batching
Level II
€1,500
plants, but excluding temporary
plants (#)
Manufacture and blending of
chemical and fuel products and
man-made fibres, excluding dilu-
2.7
tion with water only and not
Level II
€1,500
involving chemical or biological
processes, and also excludes fire-
works factories (#)
2.8
Operations involving galvanising
Level II
€1,500
or sand blasting of materials
exceeding 10 tonnes every day (#)
2.9
Manufacture of rubber and plastic
Level II
€1,500
products
2.10
Manufacture of animal feed with a
Level II
€1,500
production of more than 10 tonnes
every day (#)
APPLICATIONS AND THEIR DETERMINATION)
2.11
Yards and other premises on land
Level II
€1,500
for repair and maintenance of
vessels, aircraft and other
transport, exceeding 1000 square
meters and not covered by
Category 1.40
2.12
Operations with a discharge of
Level II
€1,500
trade effluent to sea, land, storm
or rainwater drains or culverts,
falling within the scope of the
Water
Policy
Framework
Regulations (S.L. 549.100)
Note: Trade effluent means any
liquid, with or without other
material in suspension or
dissolved in it, which is
discharged from trade premises,
other than uncontaminated storm
water run-off and domestic
sewage.
2.13
Marine container terminals (#)
Level III
€2,500
2.14
Shipyards and ancillary operations
Level III
€2,500
(#)
2.15
Wholesale of solid, liquid and
Level III
€2,500
gaseous fuels, industrial gases and
related products (#)
2.16
Cement packaging facility (#)
Level II
€1,500
2.17
Cement terminal (#)
Level III
€2,500
APPLICATIONS AND THEIR DETERMINATION)
2.18
Manufacture of pharmaceutical
Level III
€2,500
products and pharmaceutical
preparations, excluding
(a) production of active
pharmaceutical
ingredients
and intermediates; and
(b) operations that are
limited to repackaging only.
(1)
In these regulations, unless the context otherwise
requires
"Act" means the Environment Protection Act;
"activity", "intervention" or "operation" means any
practice, operation, physical works or event that may affect the
environment or that otherwise relates to any matter falling
within the scope of the Act, and which thus requires a permit
from the Authority in accordance with these regulations;
"applicant" means a person or entity who submits an
application for a permit in accordance with these regulations;
"application" means an application for a permit
submitted in accordance with these regulations;
"Authority" means the Environment and Resources
Authority as established in article 6 of the Act;
"cessation" means the intent of a permit holder to
permanently halt any activity, intervention or operation covered
by a valid permit;
"dismiss" means the Authority’s dismissal of an
application in accordance with these regulations;
"emergency permit" means a permit issued by the
APPLICATIONS AND THEIR DETERMINATION)
Authority for an activity, intervention or operation which
requires immediate authorisation in accordance with these
regulations;
"electronic system" means the Environment Resources
Information System (ERIS), or any other electronic system in
use by the Authority in connection with the management and
processing of applications;
"grant" means the approval of a permit subject to any
terms, conditions and, or limitations deemed appropriate by the
Authority;
"IPPC" means integrated pollution prevention and
control;
"interested third party" means a person who has duly
submitted representations on an application within the
applicable time frame in accordance with regulation 13;
"operator" means a person or entity who operates or
controls in whole or in part the operations, or to whom decisive
control over the functioning of the installation, site or plant has
been delegated;
"partial grant" means the approval of a permit for part or
parts of the activity, intervention or operation subject to all
terms, conditions and, or limitations deemed appropriate by the
Authority;
"permit" means a permit issued by the Authority in
accordance with these regulations;
"permit holder" means a person or entity who has been
granted a permit by the Authority;
"renewal" means the extension of the validity period of an
existing and valid permit, without any changes to the authorised
activity, intervention, operation or site;
"Tribunal" means the Environment and Planning Review
Tribunal established by article 3 of the Environment and
Planning Review Tribunal Act;
"validation" means the initial acceptance by the
Authority, of an application following satisfactory adherence to
the requirements for further processing of the application.
(2)
In matters of interpretation of any term or provision of
these regulations, or as to whether an activity, intervention or operation
causes or is likely to cause harm to the environment, or whether it
APPLICATIONS AND THEIR DETERMINATION)
meets any requirement of these regulations, whether explicit or
implied, the interpretation of the Authority shall prevail.
These regulations shall apply for any application for a
permit processed by the Authority. In the event of any conflict between
these regulations and any other legislation issued under the Act, these
regulations shall prevail
Provided that in the event of any conflict between these
regulations and the Industrial Emissions (Integrated Pollution
Prevention and Control) Regulations, the latter regulations shall
prevail.
PART II
GENERAL PROVISIONS
(1)
No person shall carry out an activity, intervention
or operation set out in the First Schedule or Second Schedule unless he
is in possession of a permit issued by the Authority in accordance with
these regulations. Such permits shall fall under the following
categories as identified in the First and Second Schedule, as the case
may be
(a)
Level I;
(b)
Level II; and
(c)
Level III.
(2)
A permit granted in accordance with these regulations
shall not relieve any person from the need to obtain any permit, license
or authorisation as may be required by any other law, or any relevant
consent from third parties.
(3)
The Authority may issue additional documentation to
supplement the Schedules on its website.
The Authority may grant, partially grant or refuse any
application for a permit.
(1)
In the granting or partial granting of a permit, the
Authority shall include any condition, approved specification and, or
limitation as it deems appropriate.
(2)
The Authority may also include pre-requisites for the
execution of the permit, including pre-operational requirements,
financial or other guarantees, environmental legal obligations or
otherwise, rectification of existing infringements, settlement of
outstanding fines and, or other requirements as it deems appropriate. If
the applicant fails to fulfil such pre-requisites within the period
specified in the Authority’s decision or, in the absence of any such
stipulated period, within six (6) months from the date of such decision,
APPLICATIONS AND THEIR DETERMINATION)
the decision shall be dismissed ipso facto without the requirement for
any action by the Authority.
(3)
The Authority may include conditions relating to
rehabilitation, restoration, after-use, monitoring, remedial action and,
or compensatory action, to be carried out before, during or after the
cessation of an activity, intervention or operation covered by a permit.
In such instances
(a)
the permit holder shall not be exonerated from
such conditions after the permit has expired; and
(b)
any guarantee in favour of the Authority related to
a permit shall not be released until the Authority is satisfied that
the conditions of the permit have been duly complied with and
that the actions requested by the Authority have been duly
undertaken to prevent, mitigate or offset the adverse impact of
the activity, intervention or operation covered by a permit.
In addition to the terms, conditions, specifications and
limitations of the permit, the Authority may also require one (1) or
more of the following, as it deems necessary to address circumstances
that may affect the surrounding environment, and such requirements
shall be carried out at the expense of the permit holder
(a)
additional monitoring;
(b)
engagement of consultants or specialists;
(c)
review of operational practices;
(d)
conduction or commissioning of audits;
(e)
abatement measures; and
(f)
setting of limits on emissions, discharges,
effluents, waste streams or resource consumption associated
with the activity, intervention or operation covered by a permit.
PART III
PERMITTING PROCEDURES
(1)
A person intending to carry out an activity,
intervention or operation falling within the scope of these regulations
shall submit an application for a permit in the form established and
published on the website of the Authority.
(2)
When submitting an application, the applicant shall
follow the format prescribed by the Authority and shall comply with
any guidance and terms of reference issued and published on the
website of the Authority. The applicant shall also submit any other
APPLICATIONS AND THEIR DETERMINATION)
information, correction or clarification required by the Authority as
part of the application process.
(1)
An application for a permit shall be valid if the
applicant has duly fulfilled the requirements of regulation 8 and has
paid to the Authority the applicable fee as stipulated in the respective
Schedule.
(2)
Upon the validation of an application, the Authority shall
issue a confirmation to the applicant.
(3)
Following validation, those applications falling within
those categories indicated within the First Schedule shall be published
on the Authority’s website for any person to declare an interest and
make representations in accordance with regulation 13
Provided that this sub-regulation shall also apply to those
categories identified in the Second Schedule in case of an application
for the renewal of a permit on which clearance has been given in
accordance with the proviso to regulation 35(7).
(4)
An application which is not in conformity with this
regulation shall be deemed as incomplete and shall not be processed
by the Authority. The Authority may dismiss an application that has
remained incomplete and invalid for a period exceeding six (6)
months.
(1)
The Authority shall assess the validated
application and process it for a decision. The Authority may also
require the submission of additional information or documents and, or
the carrying out of studies or investigations.
(2)
The applicant shall comply with requirements and any
associated time-frames as may be stipulated by the Authority. Failure
to submit requested information, documents or other requirements to
the Authority’s satisfaction and within the stipulated period shall be
construed as a refusal by the applicant to comply with the Authority’s
request, and the Authority shall proceed to process the application with
the submissions made available to it, or to dismiss the application in
accordance with these regulations, as it considers appropriate.
(1)
The time limit for the processing of applications
shall start to run on the date of publication on the Authority’s website
of the validated application by the said Authority and shall be a
maximum period as follows
(a)
fifteen (15) days for categories 1.1, 1.13, 1.18,
1.30 and 1.31 of the First Schedule;
(b)
ninety (90) days for other Level I applications;
APPLICATIONS AND THEIR DETERMINATION)
(c)
one hundred and twenty (120) days for other Level
II applications; and
(d)
two hundred and seventy (270) days for Level III
applications.
(2)
When an application includes more than one (1) activity,
intervention or operation listed in the First or Second Schedule, the
longest of the processing time periods listed in this regulation shall
apply, unless the Authority agrees to a phased processing of the
application, and in such case the time period shall be apportioned as the
Authority deems appropriate.
(3)
The Authority may extend the processing time whenever
there are any modifications to the proposal and, or when external
consultation on specific technical matters is required for the processing
of the application, and in such instance it shall inform the applicant in
writing. In any case, such extension shall not exceed a total period of
twelve (12) months for Level I applications and eighteen (18) months
for Level II or Level III applications.
(4)
The processing of an application for an activity, operation
or intervention that may require assessment, screening or any other
submission or action in accordance with other environmental
legislation, including but not limited to the Flora, Fauna and Natural
Habitats Protection Regulations and the Environmental Impact
Assessment Regulations, shall be suspended until such time that such
requirements have been duly fulfilled to the satisfaction of the
Authority.
(1)
In the processing of an application, the Authority
may consult any other public entity as may be required. In the event
that a permit is granted, any condition proposed by such entities and
included in the permit shall be enforced by the respective entity.
(2)
If the Authority does not receive any feedback from the
consulted entity within the stipulated time-frame, it shall be construed
as a no objection from such entity.
(1)
Any person may make representations on
applications falling within those categories indicated within the First
Schedule as well as for those categories indicated in the Second
Schedule in case of an application for the renewal of a permit on which
clearance has been given according to the proviso to regulation 35(7).
The consultation periods shall be ten (10) days for Level I applications,
twenty (20) days for Level II applications and thirty (30) days for Level
III applications, which in all cases shall start to run on the date of
publication in accordance with regulation 9(3). Such time-frames shall
also be applicable to consultations indicated in regulation 12, but may
be shortened to seven (7) days in urgent cases as may be indicated in
APPLICATIONS AND THEIR DETERMINATION)
the aforesaid publication.
(2)
The representations shall be submitted in writing through
the electronic system, in Maltese or English. Representations that are
submitted outside the period stipulated in these regulations shall not be
considered by the Authority.
(3)
The Authority shall ensure that due account is taken of
the matters raised in the representations, insofar as relevant to the
merits of the application and falling within its remit
Provided that such representations shall not be binding
on the Authority.
(1)
The processing of an application may be
suspended upon the request of the applicant, for not more than two (2)
calendar years in aggregate, which shall start to run on the date of the
respective written communication. The request shall be subject to the
Authority’s approval, which may be granted, partially granted or
dismissed.
(2)
The applicant may reactivate the application at any time
by withdrawing his request for suspension in writing. In the absence of
such reactivation, the application shall be dismissed ipso facto upon
the expiry of the suspension period established in sub-regulation (1)
and no further processing by the Authority shall be required.
(3)
The processing of an application may be suspended by
the Authority, inter alia for the following reasons
(a)
if in the Authority’s opinion, the proposal or the
situation on site, or both, have been modified or updated in a
substantial manner such that the details currently being
assessed are superseded, outdated, insufficient or no longer
reflecting the actual situation; or
(b)
if any material flaw, malpractice or distortion is
discovered with regard to the already-initiated processing or the
actual situation on site, or both.
(4)
At any stage following the suspension in accordance with
sub-regulation (3), the Authority may, as it deems most appropriate,
while taking into account the factors that led to the suspension
(a)
reactivate the processing, subject to any required
clarifications, updates or corrections;
(b)
direct that the process be resumed at an earlier
stage;
(c)
proceed
to
a
decision
with
the
available
APPLICATIONS AND THEIR DETERMINATION)
information; or
(d)
dismiss the application.
(1)
The Authority shall take a decision on an
application that falls within the scope of these regulations.
(2)
Decisions on applications as identified in the First
Schedule shall be taken in public
Provided that this sub-regulation shall also apply to those
categories identified in the Second Schedule in case of an application
for the renewal of a permit on which clearance has been given in
accordance with the proviso to regulation 35(7).
(3)
Decisions taken by the Authority on applications shall be
made available to the public through the Authority’s website.
(1)
A permit which is granted or partially granted shall
remain valid for such a time as specified by the Authority in such
permit.
(2)
A permit shall continue to be valid unless
(a)
the validity period established in sub-regulation (1)
expires;
(b)
cessation occurs in accordance with regulation 24;
or
(c)
it is revoked in whole or in part, in accordance
with regulation 21 and articles 65 and 66 of the Act.
(1)
An application for an emergency permit may be
submitted to the Authority in cases requiring immediate action due to
(a)
threat to the environment or national heritage;
(b)
circumstances which are likely to endanger life,
health or public safety;
(c)
circumstances
which
may
increase
the
environmental risk or environmental impact of other projects,
situations, actions or accidents if authorisation is delayed; or
(d)
significant national importance as declared by the
Minister.
(2)
Such applications for emergency permits shall be
accompanied by a report prepared by a warranted engineer or architect
or other duly qualified expert in the field, as may be relevant. The
report shall certify the nature of the emergency that merits such a
APPLICATIONS AND THEIR DETERMINATION)
permit. This provision shall be without prejudice
(a)
to the undertaking of any further studies or
investigations that may be mandatory or otherwise essential;
(b)
to the Authority’s decision to grant, refuse or
partially grant the permit; and
(c)
to the specifications, limitations and conditions
that the Authority may deem appropriate.
(3)
When processing applications for emergency permits, the
Authority may deviate from the processing and consultation time-
frames as it deems appropriate for effective and timely addressing of
the situation. In such instances, regulations 9(3), 13, 15(2) and 32 shall
not be applicable.
(4)
An emergency permit shall be valid for a period of time
as determined by the Authority which shall not exceed six (6) months.
(1)
A permit holder may apply for the renewal of the
permit during its period of validity as may be specified in the permit
conditions
Provided that permits falling within the scope of
Categories 1.13, 1.16 and 1.17 in the First Schedule shall not be
renewed.
(2)
The Authority may decide to grant, partially grant or
refuse the renewal of a permit, and may also vary and, or modify any
condition. The Authority may also request any further information or
detail from the permit holder as may be required for the renewal
process.
(3)
The permit shall only be considered as renewed once the
Authority issues the renewed permit. The processing of renewal
applications shall follow the processing time periods stipulated in
regulation 11.
(1)
The Authority may, at any time, vary the
conditions laid down in a permit where such a variation is of a minor
or administrative nature such as typographical corrections or changes
to applicant details, or where it is necessary to comply with new or
revised environmental legislation or where the permit needs to be
adapted to meet technical advancements. In such instances, the
Authority shall notify the permit holder of such a decision by issuing a
variation notice.
(2)
A permit holder may also submit a request to the
Authority for a variation in accordance with sub-regulation (1).
APPLICATIONS AND THEIR DETERMINATION)
(3)
In the cases stipulated in this regulation, regulations 9(3),
13 and 15(2) shall not be applicable.
(1)
A permit holder may request a modification to a
permit which is in force in accordance with article 62 of the Act.
(2)
The applicant shall submit an application for modification
as well as
(a)
the details of the proposed changes, including
relevant drawings, plans and photographs, in a manner that may
be easily compared to what was already covered by the permit;
and
(b)
an assessment of the possible effects on the
environment.
(3)
In cases where more than one (1) modification is
requested, a consolidated application shall be submitted to the
Authority clearly reflecting all the requested changes. In such case the
processing time frame shall restart accruing from the date of validation
of the consolidated application, provided that the Authority is satisfied
that such consolidation would be beneficial for environmental or
administrative reasons or that it would not significantly affect the case
processing.
(4)
Sub-regulation (3) shall not be applicable to applications
falling within the scope of Regulation (EU) 2024/1157 of the European
Parliament and of the Council of 11 April 2024 on shipments of waste,
amending Regulations (EU) No 1257/2013 and (EU) 2020/1056 and
repealing Regulation (EC) No 1013/2006 and the Waste Management
(Shipments of Waste) Regulations.
The Authority may, by a decision, modify or revoke any
permit granted on the grounds of articles 65 and 66 of the Act,.
Without prejudice to any action taken by the Authority in
accordance with Part VII of the Act, the Authority may consider
applications for the continuation of an activity or operation undertaken
fully or partly without authorisation
Provided that such activity or operation is not causing or
has not caused adverse environmental effects
Provided further that in such cases the Authority shall
impose an environmental legal obligation or otherwise in its decision.
(1)
A permit shall not be transferred from the permit
holder to another person without prior notification to the Authority and
confirmation of receipt by the Authority. The transfer shall be made by
APPLICATIONS AND THEIR DETERMINATION)
means of a joint notification by the permit holder and the transferee,
on the form prescribed and published on the website of the Authority.
(2)
Upon the Authority’s acknowledgement of the transfer,
all rights, obligations and liabilities shall be transferred onto the
transferee from the date of acknowledgement.
(1)
A permit holder may submit an application to the
Authority for cessation of an operation, activity or intervention
covered by a permit.
(2)
An application for cessation shall not be accepted by the
Authority until such time that all the studies, reports and submissions
required by the Authority are submitted to the satisfaction of the
Authority.
(3)
Prior to the cessation of a permit, the Authority shall
verify that the permit holder is compliant with the conditions and
approved specifications in the permit, particularly but not limited to
any decommissioning, closure, cessation, dismantling, and
remediation obligations as may be relevant. The permit holder shall
retain all the responsibilities for the operations, interventions and
activities until the Authority officially approves the cessation of the
permit in writing.
(4)
Without prejudice to regulation 6(3), any guarantee in
favour of the Authority shall not be released until the Authority
approves the request for cessation.
(5)
Regulations 9(3), 13 and 15(2) shall not be applicable to
cessation of permits.
PART IV
FEES, GUARANTEES AND CONTRIBUTIONS
(1)
The Authority shall charge the fees prescribed in
the respective Schedule for the processing of an application in
accordance with these regulations. The fees shall be paid by the
applicant upon submission of the application, and the Authority shall
not process the application further until the application fee is settled
Provided that the Authority may exempt the payment of
the application fee for certain applications as identified in the First
Schedule due to research or educational purposes when the application
has been submitted by, or on behalf of an educational institution.
(2)
If the fee due has not been paid after the lapse of ninety
(90) days from submission of the application, the application shall be
dismissed.
(3)
In the case of emergency applications, non-payment of
APPLICATIONS AND THEIR DETERMINATION)
the fee shall not suspend the validation stage.
(4)
Unless otherwise indicated in sub-regulation (5), the fees
due to the Authority shall be
(a)
half of the application fee stipulated in the
respective Schedule, in the case of applications for renewal or
for a substantial modification;
(b)
double the application fee stipulated in the
respective Schedule, in the case of applications under regulation
22. (5)
Notwithstanding the provisions of sub-regulation (4)
(a)
in the case of operations falling within the scope of
the Industrial Emissions (Integrated Pollution Prevention and
Control) Regulations, the applicable fees shall be those specified
in the said regulations;
(b)
in the case of applications that include more than
one (1) operation falling within the scope of the Industrial
Emissions (Integrated Pollution Prevention and Control)
Regulations, the fees prescribed in the said regulations shall
apply cumulatively, and the fees prescribed in the First Schedule
shall not be applicable;
(c)
in the case of operations falling within the scope of
the Limitation of Emissions of Certain Pollutants into the air
from Medium Combustion Plants Regulations, the fees
established in the said regulations shall also be applicable in
addition to the fees prescribed in the respective Schedules; and
(d)
the fee for a modification shall not be payable if
the modification is imposed by the Authority and not requested
by the permit holder.
(6)
When the Authority refuses or dismisses an application,
or if a permit is only partially granted, or if an application is withdrawn
by the applicant, the fee paid shall not be refunded.
(7)
When an application for a permit includes more than one
(1) activity, operation or intervention listed in the First or Second
Schedule, the highest of the corresponding fees shall be applicable
together with a fee of one hundred euro (€100) for every additional
activity, operation or intervention.
(1)
The Authority may impose the provision of a
financial guarantee or equivalent safeguard as a condition of the
permit, after considering the impacts and risks associated with any
aspect of the activity, intervention or operation.
APPLICATIONS AND THEIR DETERMINATION)
(2)
When the holder of a permit fails to comply with any of
the conditions laid down in the permit, the Authority may withdraw
the guarantee in full or in part, as it may deem appropriate.
(3)
In cases where the Authority withdraws the guarantee
either in part or in full, the operator shall ensure that this is replenished
within a period not exceeding thirty (30) days from date of withdrawal.
Failure to replenish the guarantee within this period shall be construed
as a breach of the permit and of these regulations.
(4)
The Authority may release part of the guarantee as it may
deem appropriate in the event of partial compliance, if it is satisfied
that this would not prejudice the effectiveness of the respective permit
conditions and approved specifications.
(1)
When granting permits the Authority may impose
an environmental legal obligation or otherwise in accordance with
article 64 of the Act. Such obligations shall be distinct from any fee or
guarantee attached to the application or to the permit.
(2)
In cases where the environmental legal obligation or
otherwise requires a sum to be paid to the Authority in accordance
with article 64(2)(e) of the Act, such sum shall be deposited in the
Environmental Fund established under article 32 of the Act.
PART V
RECONSIDERATION & APPEALS
(1)
An applicant may apply for a reconsideration of a
decision by the Authority within thirty (30) days from the date of the
decision, and an administrative fee of fifty euro (€50) shall be due to
the Authority
Provided that reconsideration shall not be applicable for
those decisions taken in public by the Board of the Authority
Provided further that the reconsideration decision shall
be taken by the Board of the Authority in public.
(2)
Requests for reconsideration shall only be valid if done
on the application form prescribed and published on the website of the
Authority. The request for a reconsideration shall not be valid if the
request relates to a change in operations or in the proposal, or a change
in the documentation submitted to the Authority as part of the
processing of the application, or if the request is submitted by any
third party including any entity consulted in accordance with
regulation 12.
APPLICATIONS AND THEIR DETERMINATION)
(3)
When an appeal has been filed before the Tribunal by any
person other than the applicant and the applicant submits a request for
reconsideration in accordance with this regulation, the procedures
before the Tribunal shall be suspended until the request for the
reconsideration is determined and the Authority has submitted a copy
of the decision to the Tribunal, and any time periods established under
the provisions of Environment and Planning Review Tribunal Act in
relation to the procedures before the Tribunal shall start to run from the
date of receipt by the Tribunal of the reconsideration decision.
An appeal from a decision taken by the Authority may be
filed before the Tribunal within thirty (30) days from the publication of
the decision on the Authority’s website by
(a)
an applicant, in relation to an application filed by
him; or
(b)
a registered interested third party, only in relation
to the applications falling within the scope of regulation 13.
(1)
The execution and validity of a permit which was
subject to public consultation in accordance with regulation 13 and for
which representations from interested third parties were submitted,
shall be automatically and temporarily suspended for thirty (30) days
from publication of the decision on the Authority’s website, and no
works, interventions, operations or activities may commence before the
lapse of such period.
(2)
The permit may subsequently remain suspended if the
Tribunal so decides in accordance with the Environment and Planning
Review Tribunal Act.
(3)
The suspension prescribed in sub-regulations (1) and (2)
shall not be applicable to the following permits
(a)
emergency permits;
(b)
renewed permits;
(c)
clearance issued in accordance to regulation 35(4);
(d) permits which were not subject to an Environmental
Impact Assessment and, or IPPC permit and which in the
opinion of the Minister
(i)
are of strategic significance or of significant
national importance;
(ii)
are related to any obligation ensuing from
European Union legislation;
APPLICATIONS AND THEIR DETERMINATION)
(iii) affect national security or the interests of
other governments; or
(iv) affect response to civil or environmental
emergencies.
PART VI
MISCELLANEOUS PROVISIONS
(1)
The Authority shall retain all information required
from the applicant for the processing of the application and shall
publish the details of the applicant consisting of the following
(a)
the name and surname of the applicant;
(b)
the proposed operation, intervention or activity;
(c)
the location, if applicable; and
(d)
the decision of the Authority.
(2)
Upon the request of the applicant, the Authority may
censor financially or commercially sensitive information.
(1)
The offices of the Authority shall be closed
between the 23rd of December of every year and the 1st of January of
the following year, both days included.
(2)
One week prior to Easter Sunday and the period between
the 8th and 22nd of August of every year shall be considered as
inactive periods.
(3)
The Authority may establish other periods during the
year as inactive periods. Such periods shall be published on the
Authority’s website and in the Gazette.
(4)
During such inactive periods, processing times shall be
suspended.
The Authority shall not be held liable for any loss or
damage suffered by any person by reason of anything done or omitted
to be done in good faith in the course of administering these
regulations.
The Authority may, from time to time, publish any
documentation or guidance in relation to matters falling within the
scope of these regulations or ancillary thereto.
PART VII
TRANSITORY PROVISIONS
(1)
Permits which have been issued by the Authority
APPLICATIONS AND THEIR DETERMINATION)
prior to the coming into force of these regulations and which are still
valid, shall be construed as authorised under these regulations, unless
they have expired or have been superseded by a permit issued in
accordance with these regulations.
(2)
The provisions of sub-regulation (1) shall also be
applicable to conditions, specifications and obligations related to such
permit, including any requirement to renew the validity of the permit.
(3)
Applications that have been submitted before the coming
into force of these regulations shall be exempt from the fee prescribed
in the respective Schedule, unless a fee was already applicable in
accordance with any other regulations issued under the Act.
(4)
Where it is proven to the satisfaction of the Authority that
the operation, intervention or activity specified in the Second Schedule,
was already exercised prior to the coming into force of these
regulations, such operation, intervention or activity may be deemed
cleared by the Authority subject to such terms and conditions as the
Authority may impose.
(5)
An application for clearance of an operation, intervention
or activity specified in sub-regulation (4) and in the Second Schedule
shall be submitted to the Authority within six (6) months from the
coming into force of these regulations.
(6)
The Authority shall determine an application for
clearance for an operation, intervention or activity specified in sub-
regulation (4) and the Second Schedule without delay and may refuse
any such application on any grounds valid at law
Provided that the determination of an application for
clearance shall not be subject to appeal, except by the applicant, from a
refusal of a clearance or from a condition imposed in the clearance.
(7)
A clearance issued in terms of sub-regulation (4) shall be
valid for four (4) years
Provided that prior to the expiration of the clearance, the
applicant shall apply for a permit to cover the operation, intervention or
activity subject of the clearance, which application shall be deemed as
an application for the renewal of a permit for all intents and purposes of
these regulations
Provided further that upon expiration of the clearance, the
operation, intervention or activity shall continue subject to a permit
issued under these regulations and in line with any such conditions
stipulated in the permit.
APPLICATIONS AND THEIR DETERMINATION)
First Schedule
Operations, Interventions And Activities Falling Within The
Scope Of These Regulations
(Regulations 4, 9, 11, 13, 15, 18, 25)
The following operations, interventions and activities shall
require a permit in accordance with these regulations, and the level
type and application fee payable for each category shall be applicable
as indicated in the table
The following notations shall be interpreted as follows
#
Identifies those categories which shall be published on
the Authority’s website for representations in accordance with
regulations 9(3) and 13(1) and which require a decision to be taken in
public in accordance with regulation 15(2);
†
Identifies those categories which may be exempt from
the application fee for reasons of research or educational purposes as
stipulated in regulation 25.
Category
Operation, intervention or
Type of
Fee for a new
activity
application or
application
permit
Waste management operations
€100 for each
Consignment authorisation on
1.1
Level I
Consignment
land
Mobile unit for treatment of
1.2
Level I
waste on the site of generation
Storage of hazardous wastes in
1.3
quantities of more than 5 tonnes
Level II
per day (#)
Quarry operations, which may
include stone extraction and, or
1.4
the recycling of inert waste or
Level II
construction and demolition
waste (#)
APPLICATIONS AND THEIR DETERMINATION)
Backfilling of excavation voids
as defined by the Waste
Management (Management of
1.5
Level II
€1,000
Waste
from
Extractive
Industries and Backfilling)
Regulations (S.L. 549.50.) (#)
Category 1.5 operations which
1.6
include crushing prior to
Level II
€750
backfilling (#)
1.7
Civic amenity site (#)
Level II
€1,500
€500 or as otherwise
Producer
Responsibility
established in
1.8
Level II
Organisation
relevant subsidiary
legislation
Other
waste
management
operations, not listed elsewhere
in this Schedule, and other
operations within the scope of
the Waste Regulations (S.L.
1.9
549.63), except works requested
Level II
€1,500
by the Authority for the purpose
of
site
remediation
or
restoration, stabilisation of
material or other environmental
improvement (#)
APPLICATIONS AND THEIR DETERMINATION)
Non-hazardous waste collection,
treatment, disposal, temporary
storage and, or preparation for
reuse (including packaging,
1.10
Level II
€1,500
sorting and, or processing of
waste prior to reuse or
recovery),
except
waste
generated on the same site (#)
Depot carrying out temporary
storage of construction and
1.11
demolition
waste
and
Level II
€1,500
preparation for reuse, recycling
or recovery of such waste (#)
Hazardous waste collection,
temporary storage, treatment,
(including packaging sorting
and, or processing of waste prior
1.12
to preparation for reuse, recy-
Level III
€2,500
cling or recovery), preparation
for reuse, recycling and, or dis-
posal except waste generated on
the same site (#)
Consignment and disposal at
€1,500 and a fee per
1.13
sea, including operations in
Level II
tonne as established
association with Category 2.1
by the Authority
Waste incineration or co-incin-
1.14
Level III
€2,500
eration (#)
APPLICATIONS AND THEIR DETERMINATION)
Decontamination
and,
or
disposal as regulated by the
Waste
Management
1.15
Level III
€2,500
(Polychlorinated Biphenyls and
Polychlorinated
Terphenyls)
Regulations (S.L. 549.28.) (#)
Transboundary movements of
waste subject to the prior
informed consent procedure
pursuant to Regulation (EU)
2024/1157 of the European
As established in
Parliament and of the Council of
the Waste
11 April 2024 on shipments of
Trans-frontier
Management
1.16
waste, amending Regulations
shipment permit
(Shipments of
(EU) No 1257/2013 and (EU)
Waste) Regulations
2020/1056
and
repealing
(S.L. 549.65.)
Regulation (EC) No 1013/2006
and the Waste Management
(Shipments
of
Waste)
Regulations (S.L. 549.65.)
Modifications
to
written
consents for transboundary
movements of waste subject to
the prior informed consent
procedure
pursuant
to
Regulation (EU) 2024/1157 of
the European Parliament and of
the Council of 11 April 2024 on
€100 for every
1.17
Not applicable
shipments of waste, amending
amendment
Regulations (EU) No 1257/2013
and (EU) 2020/1056 and
repealing Regulation (EC) No
1013/2006
and the Waste
Management (Shipments of
Waste)
Regulations
(S.L.
549.65)
APPLICATIONS AND THEIR DETERMINATION)
Interventions and activities in relation to biodiversity and the natural environment
APPLICATIONS AND THEIR DETERMINATION)
As established in the
Trees and
Registration as licensed tree
Woodlands
1.18
specialist
Protection
Regulations (S.L.
549.123.)
Activity involving fifty (50)
€100
persons or more, or other
Provided that clean-
activities falling with the scope
up activities may, at
1.19
of the Flora, Fauna and Natural
the discretion of the
Habitats Protection Regulations
Authority, be
(S.L. 549.44) within a protected
exempt from paying
area (†)
such fee.
Operations,
structural
or
1.20
permanent interventions, in a
€100
protected area (†)
Taking of species protected
under the Flora, Fauna and
Natural Habitats Protection
1.21
Regulations (S.L. 549.44.) (†),
€ 20
other than hunting, trapping,
scientific ringing or geo-tagging
of birds
Level I
Interventions on up to 10
1.22
€20
protected trees
Interventions on more than 10
1.23
€100
protected trees (#)
Importation of, and operations
related to, invasive alien species
of national or European concern,
other than the control or
1.24
€100
removal of such species in
accordance
with
the
methodology approved by the
Authority (#) (†)
Interventions and activities for
the purpose of access to genetic
1.25
resources
through
prior
€100
informed consent for wildlife,
except birds (#) (†)
APPLICATIONS AND THEIR DETERMINATION)
Use of genetically modified organisms
Notification of the following as defined in the Contained Use of Genetically Modified Micro-
Organisms Regulations (S.L.549.49) and the Deliberate Release into the Environment of
Genetically Modified Organisms Regulations (S.L. 549.60)
First-time use of premises for
As established in the
1.26
contained use of genetically
Contained Use of
modified organisms (#)
Genetically
Level I
Modified Micro-
Individual contained use of
Organisms
1.27
genetically modified organisms
Regulations
(#)
(S.L.549.49) and the
Deliberate Release
Deliberate release of genetically
into the
1.28
modified organisms, other than
Environment of
placing on the market (#)
Genetically
Level III
Modified Organisms
Placing on the market of
Regulations (S.L.
1.29
genetically modified organisms
549.60)
(#)
Others
€100 for
Hull cleaning and propeller
registration;
1.30
polishing on vessels greater than
Level I
€50 for every
30 metres
notification
Renewal of existing quarrying
1.31
Level I
€800
licence
As established in the
Limitation of
Operations covered by the
Emissions of
Limitation of Emissions of
Certain Pollutants
Certain Pollutants into the air
1.32
Level II
into the air from
from Medium Combustion
Medium
Plants
Regulations
(S.L.
Combustion Plants
549.122)
Regulations (S.L.
549.122)
APPLICATIONS AND THEIR DETERMINATION)
Fuel terminals including those
within scope of the Control of
Volatile Organic Compound -
1.33
VOC Emissions (Storage and
Level III
€2,500
Distribution of Petrol from
Terminals to Service Stations)
Regulations (S.L. 549.52) (#)
Retail and wholesale of fuel,
including petrol stations covered
by the Control of Volatile
Organic Compound - VOC
1.34
Level III
€2,500
Emissions
(Storage
and
Distribution of Petrol from
Terminals to Service Stations)
Regulations (S.L. 549.52) (#)
Operations covered by the
1.35
Urban Waste Water Treatment
Level III
€2,500
Regulations (S.L. 549.22)
Treatment plants of domestic
sewage, industrial effluent or
1.36
Level II
€1,500
farmyard waste, not covered by
Category 1.35 (#)
Ancillary aquaculture facilities
1.37
Level II
€1,500
(#)
Marine aquaculture, including
1.38
Level III
€2,500
fish farms (#)
1.39
Onshore aquaculture (#)
Level III
€2,500
APPLICATIONS AND THEIR DETERMINATION)
Operations covered by the
Industrial Emissions (Limitation
1.40
of Emissions of Volatile
Level III
€2,500
Organic
Compounds)
Regulations (S.L. 549.79)
1.41
Crematorium (#)
Level III
€2,500
As established in
Operations falling within scope
regulation 23 and
of Schedule 1 to the Industrial
Schedule 5 to the
Emissions (Integrated Pollution
Industrial Emissions
Prevention
and
Control)
1.42
IPPC permit
(Integrated Pollution
Regulations (S.L. 549.77) and
Prevention and
the
Industrial
Emissions
Control)
(Framework)
Regulations
Regulations (S.L.
(S.L.549.76) (#)
549.77)
Extended Producer Responsibility not covered under Category 1.8
Category
Activity
Type of
Fees
application or
permit
1.43
Producer
€500 + €20 per
Responsibility
Level I
producer
for
Organisation
for
every
year
Batteries
thereafter
1.44
Self-compliant
€100 + €20 for
producer for Batteries
Level I
every
year
thereafter