CONSTRUCTION AND DEMOLITION WASTE FRAMEWORK REGULATIONS
Table of Provisions (16)
Statutory Text (16 Articles)
FRAMEWORK
SUBSIDIARY LEGISLATION 549.161
CONSTRUCTION AND DEMOLITION WASTE
FRAMEWORK REGULATIONS
29th February, 2024
LEGAL NOTICE 311 of 2023.
(1)
The title of these regulations is the Construction
and Demolition Waste Framework Regulations.
(2)
The scope of these regulations is to establish a
framework regulating the management of waste resulting from
demolition, excavation and construction activities.
(3)
The Environment and Resources Authority may issue
guidelines or criteria to provide information, guidance or impose
restrictions in order to better implement these regulations.
(4)
To implement these regulations, the Environment and
Resources Authority may request information from any public entity
and from any actor depending on his role as outlined in regulation 3.
(5)
Regulation 5(4) shall come into force on 1st January
2026.
PRE-DEMOLITION AUDIT
(regulation 5(4))
The pre-demolition audit shall include
1. identification of all waste streams foreseen to be
generated;
2. estimated quantities of the identified waste streams;
3. which materials can be separated at source;
4. which materials are not suitable for re-use or recycling;
5. information on the management of the hazardous and
non-hazardous waste fractions;
6. information on the recycling possibilities of demolition,
excavation and construction;
7. an estimate of the percentage (%) re-use and recycling
potential of material or waste to be generated; and
8. a reason for the need to demolish the existing structure.
In these regulations, unless the context otherwise
requires
"Act" means the Environment Protection Act;
"application" means any form of application made to the
Planning Authority in terms of the Development and Planning
Act;
"Authority" or "competent authority" means the
Environment and Resources Authority as established by article
6 of the Act;
"client" or "developer" means the person in whose name
the application had been submitted for a development permit in
accordance with the provisions of the Development Planning
Act or in accordance with the provisions of the regulations
made thereunder;
"commencement notice" shall have the same meaning as
assigned to it in article 2 of the Development Planning Act;
"construction" shall have the same meaning as assigned to it
in article 2 of the Building and Construction Authority Act;
FRAMEWORK
"demolition" shall have the same meaning as assigned to
it in article 2 of the Building and Construction Authority Act;
"development" shall have the same meaning as assigned
to it in article 2 of the Development Planning Act;
"excavation" shall have the same meaning as assigned to
it in article 2 of the Building and Construction Authority Act;
"major application" means any application listed in Schedule
1 to the Development Planning (Procedure for Applications and
their Determination) Regulations;
"Planning Authority" means the Planning Authority
established under article 5 of the Development Planning Act;
"site" shall have the same meaning as assigned to it in
article 2 of the Building and Construction Authority Act;
"site manager" shall have the same meaning as assigned
to it in regulation 3 of the Construction Management Site
Regulations; and
the words "backfilling", "carrier", "collection",
"construction and demolition waste", "hazardous waste",
"material recovery", "non-hazardous waste", "preparing for re-
use", "recovery", "recycling", "re-use", "separate collection",
"treatment" and "waste" shall have the same meaning as
assigned to them in regulation 4 of the Waste Regulations.
ADMINISTRATIVE PENALTIES FOR NON-ATTAINMENT OF
WASTE MANAGEMENT TARGETS
(regulations 9(1) and 13)
In cases where the developer fails to meet the targets, the
applicable administrative penalty shall be calculated as follows
(a)
for targets specified in paragraphs (a) and (b) of
regulation 9(1)
A = total material or waste generated, in tonnes
B = % target
C = actual material re-used or waste prepared for
re-use or recycled, in tonnes
D = five euro (€5) in case of high-density residential
FRAMEWORK
developments serving sixteen (16) or more units, three
euro (€3) for major developments
((A x B) - C) x D = applicable penalty in euro
(b)
for targets specified in paragraphs (c) and (d) of
regulation 9(1)
A = construction material used, in tonnes
B = % target
C = actual construction material used in the
development that has been re-used or recycled, in tonnes
D = five euro (€5) in case of high-density residential
developments serving sixteen (16) or more units, three
euro (€3) for major developments
((A x B) - C) x D = applicable penalty in euro
These regulations outline the roles of the different actors
involved in the construction and demolition industry with respect to
waste management
(a)
the developer or anyone acting on his behalf
involved in the design stage of a development shall ensure that
measures to prevent and minimise the generation of waste are
integrated in any development and that any such measures are
implemented throughout the lifetime of the development;
(b)
the client, developer or anyone acting on his behalf
shall ensure that demolition and excavation are also carried out
in line with paragraph 3(a) of the Fourth Schedule to the
Construction Management Site Regulations;
(c)
the contractors engaged by the client or developer
shall ensure the prevention and minimisation of waste throughout all
on site activities. The contractors shall make efforts to segregate
waste at source and ensure that any collection and transport of
waste generated on site is carried out by duly authorised waste
carriers;
FRAMEWORK
(d)
the waste carrier shall ensure that any waste
collected is transported in accordance with the Waste
Management (Activity Registration) Regulations, to authorised
facilities permitted under the Waste Regulations. To this end,
the waste carrier shall provide documentary proof when
requested;
(e)
the site manager shall ascertain that any
development is carried out in accordance with these regulations
and that the actors involved fulfil their roles.
(1)
These regulations shall be read in conjunction
with the requirements set out under Regulation (EU) No 305/2011 of
the European Parliament and of the Council of 9 March 2011 laying
down harmonised conditions for the marketing of construction
products and repealing Council Directive 89/106/EEC, as
implemented at national level through the Construction Products
(Implementation) Regulations.
(2)
Waste which has undergone a recycling or other recovery
operation, is considered to have ceased to be waste if it has achieved
an end-of-waste status in accordance with regulation 6 of the Waste
Regulations.
(1)
Without prejudice to regulations 12 and 12A of
the Waste Regulations, the actors identified in regulation 3 shall take
the necessary measures to ensure that all waste generated during
demolition, excavation and construction activities is managed in an
environmentally sound manner and in accordance with the waste
hierarchy as laid down in regulation 4A of the Waste Regulations.
(2)
In order to fulfil the requirements laid down in sub-
regulation (1), the actors identified in regulations 3 shall in accordance
with their role, as a minimum
(a)
take the necessary measures to prevent the
generation of waste across all stages of construction, as far as
possible. Such stages include but are not limited to design,
demolition, excavation, construction and finishing;
(b)
prioritise the re-use of uncontaminated excavated
material, both on-site and off-site;
(c)
separate the waste at source in line with regulation
6, where site specific characteristics allow;
(d)
ensure that any collection and transport of waste
resulting from demolition, excavation and construction
activities is carried out by means of an authorised waste carrier;
(e)
obtain documentary proof that the waste is
FRAMEWORK
transferred to a facility that is authorised to accept such waste.
To this end, the waste carrier shall provide such documentary
proof to the developer;
(f)
make use of facilities or undertakings duly
permitted by the Authority to carry out the treatment of
construction and demolition waste in accordance with the Waste
Regulations.
(3)
In order to ensure compliance with the requirements laid
down in sub-regulations (1) and (2), the Authority may require the
developer or anyone acting on his behalf to submit any information and
documentation on the re-use of suitable materials and on the
management of the waste generated during the activities referred to in
sub-regulation (1).
(4)
From 1st January 2026, any major application or
application for high-density residential developments serving sixteen
(16) or more units, shall include the submission of a pre-demolition
audit prior to the issuance of the commencement notice of works. The
Building and Construction Authority shall only issue clearance to
commence works following clearance of the pre-demolition audit by
the competent authority. The pre-demolition audit shall contain the
information included in Schedule 1 and shall be carried out by a
warranted perit, surveyor or a duly qualified environmental consultant,
approved by the competent authority and in the format established by the
competent authority.
(1)
Without
prejudice
to
the
Construction
Management Site Regulations and where site specific characteristics
allow, the contractor shall endeavour to separate demolition,
excavation and construction materials or waste at source in order to
facilitate the re-use of material and to prepare for re-use, recycling and
recovery of waste, including but not limited to mineral fractions, metal,
glass, wood and plastic waste.
(2)
Where site specific characteristics do not allow,
demolition, excavation and construction materials or waste may be
separated at any establishment or undertaking duly authorised by the
Authority.
(3)
Any hazardous waste generated on site shall be managed
in accordance with regulation 14(2) of the Waste Regulations.
(4)
In order to facilitate preparation for re-use, recycling and
other recovery operations, waste separated in accordance with this
regulation shall not be mixed with other waste or other materials with
different properties, including during its collection stage.
FRAMEWORK
(1)
Demolition, excavation and construction waste
shall only be recycled or otherwise recovered at an establishment or
undertaking duly permitted by the Authority.
(2) For the purpose of environmental protection and to
promote high-quality recycling, the Authority may set out additional
quality guidelines for the collection and treatment of construction and
demolition waste.
(3)
Subject to obtaining a permit issued by the competent
Authority, any person may establish and operate storage depots
intended for, sorting or storage of construction and demolition
materials or waste prior to eventual reuse, preparing for re-use,
recycling, other recovery operations, or disposal.
(4)
Any shipment of construction and demolition waste shall
be carried out in conformity with Regulation (EC) No 1013/2006 of
the European Parliament and of the Council of 14 June 2006 on
shipments of waste and the Waste Management (Shipments of Waste)
Regulations, and with any other applicable legislation.
(5)
The Authority may take measures to encourage
establishments or undertakings which carry out waste treatment
operations to introduce certified environmental management systems
in accordance with Regulation (EC) No 1221/2009 of the European
Parliament and of the Council of 25 November 2009 on the voluntary
participation by organisations in a Community eco-management and
audit scheme (EMAS), repealing Regulation (EC) No 761/2001 and
Commission Decisions 2001/681/EC and 2006/193/EC.
(1)
Rehabilitation of an excavation void shall only be
carried out if duly permitted and by waste which is considered suitable
by the Authority.
(2)
In order to demonstrate compliance with the
requirements established in sub-regulation (1), the holder of a permit
granted by the Authority for the backfilling of an excavation void shall
submit to the Authority an annual declaration prepared by an
independent body together with the annual environmental report
prepared and submitted in accordance with regulation 33A of the
Waste Regulations.
(1)
By not later than 1st January 2028, any developer
submitting an application with the Planning Authority for a major
development or high-density residential development serving sixteen
(16) or more units shall take the necessary measures to ensure that the
following targets are achieved for each development
(a)
a minimum of forty percent (40%) of excavated
material shall be re-used or recycled
FRAMEWORK
Provided that developers may also achieve such
target through set-off from any other developments as long as an
adequate audit trail is provided to the satisfaction of the
Authority;
(b)
a minimum of forty percent (40%) by weight of
non-hazardous waste generated during demolition activities
shall be prepared for re-use, recycled and, or other forms of
material recovery excluding backfilling operations;
(c)
a minimum of fifteen percent (15%) of
construction material including that used in finishes shall be
made up of re-used or recycled material; and
(d)
a minimum of twenty-five percent (25%) of the
granular material used for construction shall be made up of
recycled aggregates. The percentage share of recycled
aggregates used shall contribute towards attaining the fifteen
percent (15%) target for re-use and recycled materials as listed
in paragraph (c).
(2)
Within three (3) months from the issuance of a
compliance certificate by the Planning Authority, all developers of any
development falling within the scope of this regulation, shall submit to
the competent Authority a declaration indicating the percentage rate
achieved for each of the targets listed in sub-regulation (1) according to
the format established by the competent authority
Provided that the Authority may require the auditing of
declarations submitted.
Documentation specified in regulations 5(2)(e) and 9(2)
shall be kept by the developer for a minimum period of five (5) years
following the issuance of the compliance certificate and shall be made
available to the competent authority upon request.
(1)
The competent authority may carry out inspections
to ensure that the obligations set out in these regulations are adhered to.
(2)
Any relevant actors shall keep up-to-date records of their
operations in accordance with these regulations and make them
available for any inspection by the competent authority.
The competent authority shall establish a register of
authorised establishments and undertakings dealing with material and,
or waste resulting from the construction and demolition industry. Such
register shall be periodically updated and made publicly available.
(1)
Any developer who fails to reach the targets
specified in regulation 9(1) shall be subject to an administrative penalty
as specified in Schedule 2.
FRAMEWORK
(2)
Any developer who fails to abide with any provision of
these regulations shall be subject to an administrative penalty
depending on the nature and severity of the breach, not exceeding forty
thousand euro (€40,000).