ELECTRICITY CONNECTION AND SUPPLY REGULATIONS
Table of Provisions (35)
Statutory Text (35 Articles)
SUBSIDIARY LEGISLATION 545.41
ELECTRICITY CONNECTION AND SUPPLY
REGULATIONS
29th October, 2024
LEGAL NOTICE 282 of 2024.
(1)
The title of these regulations is the Electricity
Connection and Supply Regulations.
(2)
These regulations establish the rules and conditions for
the connection of customers to the distribution system for the
generation of electricity, importing and, or exporting of electricity
from, or to the network and the supply of electricity to final customers.
(regulation 24)
1. Maximum Consumption Tariffs
(1)
The supply of electricity to a residential premises shall be
billed, for any period as the distribution system operator may, from
time to time determine, i n a c c o r d a n c e w i t h the fees and
tariffs which shall not exceed the following
(a)
without prejudice to the other provisions of these
regulations, the supply of electricity to residential premises
shall be subject to an annual service fee of
(i)
sixty-five euro (€65) for a 40 Amps single
phase network connection; and
(ii)
a fee of one hundred and forty euro (€140)
for a 40 Amps three phase network connection; and
(iii) a fee of one hundred and ninety-five euro
(€195) for a 60 Amps or more three phase network
connection;
(b)
without prejudice to the other provisions of these
regulations, the supply of electricity to a residential premises
shall be subject to the following maximum consumption tariff,
which may be billed on a pro rata basis. The said maximum
consumption tariff shall be based on a cumulative consumption,
which shall consist of the amounts derived from the cumulative
application of each of the following thresholds every year
For every kWh of the first 2,000 kWh
€0.1047;
For every kWh of the next 4,000 kWh
€0.1298;
For every kWh of the next 4,000 kWh
€0.1607;
iv.
For every kWh of the next 10,000 kWh
€0.3420;
v.
For
every
kWh
of
the
remaining
€0.6076.
consumption
(2)
Without prejudice to the other provisions of these
regulations, a residential premises three phase network connection
exceeding 60 Amps per phase shall also be subject to a maximum
demand tariff at the rate of twenty-one euro and five cents (€21.05) per
annum per kW of the maximum demand in any period during the year.
2. Methodology for Calculation of Tariffs for residential
premises
(1)
The distribution system operator shall be entitled to use
its own discretion as to how to calculate and bill the amounts derived
from the application of the maximum consumption tariff in item
1(1)(b) on a pro rata basis
Provided that
(a)
the amount which is billed by the distribution
system operator for a period of a calendar year shall not exceed
the amounts derived from the application of the maximum tariff
as established by the Regulator in accordance with regulation
24 and within the limits prescribed in section 1; and
(b)
the distribution system operator shall keep the
Regulator informed of any methodology it adopts in calculating
and billing the consumption tariff on a pro rata basis.
(2)
Notwithstanding the provisions of item 2(1)(a), and that
the distribution system operator may adopt an adjustment mechanism
to ensure compliance with the provisions of item 2(1)(a), any bill
issued by a distribution system operator, whether for a pro rata period
of any calendar year or otherwise, shall be due to be paid on the date as
indicated on the bill by the distribution system operator,
notwithstanding that such bill may only refer to a part of a calendar
year.
(3)
In order to give effect to the provisions of item 2(1), the
distribution system operator shall use all reasonable endeavours and
procedures, in accordance with the provisions of these regulations, to
obtain a reading of actual consumption incurred by the customer.
Where the distribution system operator is unable to obtain the said
reading of the actual consumption incurred for reasons beyond its
control, it may thereafter rely on estimates of the actual consumption
incurred by the customer.
(4)
Where the supply of electricity to a residential premises is
only provided for a part of a calendar year, the maximum consumption
tariff shall be calculated by applying the cumulative thresholds
referred to in item 1(2) proportionately to the days during which a
residential electricity is actually supplied by the distribution system
operator, so that each of the units (kWh) referred to in item 1(2) shall
be divided by the number of days in a calendar year and applied
accordingly to the days during which a residential premises service is
actually provided.
(5)
Without prejudice to the other provisions of these
regulations, the supply of electricity to a residential premises, which is
provided to the primary residence of an individual, shall be eligible for
an eco-reduction of the amount due for consumption of electricity for
the billing period in question, which shall be calculated in accordance
with the following rates, on a pro rata basis of the relative billing
period
(a)
when only one ( 1 ) individual is registered on a
residential premises network connection, the customer shall be
eligible for an eco-reduction of twenty-five per cent (25%) of
all the amount due for consumption of electricity for the billing
period in question if the consumption does not exceed the pro
rata equivalent consumption of two thousand kWh (2,000
kWh) every year; or
(b)
when more than one (1) individual is registered
on a residential premises network connection, the customer
shall be eligible for the following eco- reduction
(i)
where the consumption for the billing
period in question d o e s not exceed the pro rata
equivalent of one thousand kWh (1,000 kWh) every year
per individual registered, an eco-reduction of twenty-five
percent (25%) of all the amount due for consumption
of electricity for the period in question shall apply; or
(ii)
where the consumption for the billing
period in question exceeds the pro rata equivalent of one
thousand kWh (1,000 kWh) every year per individual
registered but does not exceed, nor is equal to, the pro
rata equivalent consumption of one thousand seven
hundred and fifty kWh (1,750kWh) every year per
individual registered, an eco-reduction of twenty-five per
cent (25%) for that part of the consumption which is the
pro rata equivalent of one thousand kWh (1,000 kWh)
every year per individual registered and of fifteen per
cent (15%) for the remainder which is the pro rata
equivalent consumption of up to seven hundred and
fifty kWh (750kWh) every year per individual registered
for the period in question shall apply
Provided that no individual shall be registered on more
than one (1) residential premises at the same time and that the eco-
reduction shall only apply to the primary residence of an individual
registered in accordance with regulation 24(15)
Provided further that an eco-reduction shall only be
calculated on the basis of an actual reading of the consumption taken
by a representative of the distribution system operator or by a
customer reading provided to a representative of the distribution
system operator through an established procedure by the customer
registered on the connection account, and notwithstanding the
provisions of any other law, if an actual reading or a customer
reading as defined in this proviso are not be available for the
billing period in question, the customer’s eligibility for an eco-
reduction on the relevant premises for such billing period shall be
forfeited permanently.
(6)
All the rates in this Schedule are inclusive of Value
Added Tax.
(1)
In these regulations, unless the context otherwise
requires
"Act" means the Regulator for Energy and Water
Services Act;
"agency agreement" means a contract whereby the
distribution system operator appoints an agent to provide
services in connection with a specific location or premises, as
specified in these regulations and in the relevant contract, for
and on behalf of the distribution system operator;
"applicant" means a person who submits an application
to the distribution system operator;
"application" means an application submitted to the
distribution system operator, as may be required from time to
time, for services provided by the distribution system operator,
including for those services referred to in regulation 5(4);
"authorised provider" shall have the same meaning as
assigned to it in the Electrical Installations Regulations;
"building unit" means a building or part of a building,
section, floor or apartment within a building which is designed
or altered to be used separately and which has a separate
connection to the network;
"bulk network connection" means a three phase
connection to the network in excess of sixty (60) Amps per
phase, provided through one (1) meter;
"CHP" or "cogeneration" means the simultaneous
generation in one (1) process of thermal energy and electrical or
mechanical energy;
ELECTRICITY CONNECTION AND SUPPLY
"commodatum agreement" means a gratuitous loan for
use, for a specified time or purpose, subject to the obligation of
the borrower to restore the thing itself as regulated by the
relevant agreement and the Civil Code ;
"connection" or "network connection" means the
connection of a customer to the distribution network for the
purposes of importing electricity from and, or exporting
electricity to the distribution network and, or the connection of
a temporary installation
Provided that a customer may be registered with
the distribution system operator with respect to more than one
(1) connection to the distribution network
Provided further that each premises or temporary
installation may only have one (1) connection to the
distribution network;
"customer" means any person connected or entitled to be
connected to the network by the distribution system operator
and who imports electricity from and, or exports electricity to
the distribution network;
"day consumption" means the consumption registered
between 06:00 hours and 22:00 hours of the same day;
"developer" means, in relation to a development or a
single building unit, as applicable, any person who
(i)
owns the land on which the development
is, or shall be, situated;
(ii)
is constructing a development or a single
building unit;
(iii) is indicated in the planning permission
application in respect of the relevant development; and,
or
(iv) submits an application for a new load or
upgrade with a distribution system operator;
"development" means a building or structure consisting
of two (2) or more building units, provided that for the purpose
of these regulations, one (1) or more buildings or structures
which are subject to more than one (1) development planning
applications shall be considered as a single (1) development if
the relevant buildings or structures are either physically
internally interconnected with each other, at any level, or the
distribution system operator determines that they form part of
one (1) project;
"distribution system operator" shall have the same
meaning as assigned to it in the Electricity Regulations and any
function to be performed, decision to be taken and, or discretion
to be exercised by the distribution system operator in
accordance with these regulations shall be performed, taken
and, or exercised, as applicable, by such person or persons that
the board of directors of the distribution system operator
authorises for such purpose, and in accordance with the terms
and conditions as the said board of directors deems appropriate.
For the purposes of these regulations a reference to the
distribution system operator shall also be construed, where
required, as being a reference to any subsidiary or associated
company of the distribution system operator, or to any other
entity, however so described, duly authorised in writing by the
distribution system operator to perform any of the functions
that the distribution system operator may undertake in
accordance with these regulations including, without limitation,
a service provider and, or an agent acting under an agency
agreement, in each case in relation to the relevant functions of
the distribution system operator;
"domestic premises" means a premises which includes
private dwellings with no persons registered with the
distribution system operator as residing in them, such as
secondary residence, or private garages, not exceeding fifty
(50) square metres, and common areas including roofs, stairs,
lifts, terraces and gardens which are used solely for private
dwellings;
"electric vehicle" or "EV" shall have the same meaning
assigned to it in the Publicly Accessible Electric Vehicle
Charging Infrastructure Regulations;
"electrical installation" means a system of electrical
wirings and equipment intended for conveying electricity and the
disconnecting apparatus located on the customer’s side of the
electricity service meter;
"energy storage facility" shall have the same meaning as
assigned to it in the Electricity Regulations;
"EN 50549" means the European standard covering the
requirements for generating plants that are connected in parallel
with the distribution network;
"EV meter" means an electricity meter installed or
approved by the distribution system operator for the purpose of
ELECTRICITY CONNECTION AND SUPPLY
measuring the consumption of electricity for the charging of an
EV;
"generator" means a person or a body who generates
electricity in accordance with a licence or exemption or
otherwise, in accordance with the Electricity Regulations;
"high voltage" or "HV" means voltage of nominal RMS
value greater than thirty three kV (33kV) in relation to
alternating current between any conductor;
"HV contribution" means a contribution fee towards the
high or medium voltage kVA capacity costs;
"institutional households" shall include the following
buildings
(a)
healthcare institutions such as buildings
used as a hospital, nursing home or as any institution
providing medical or nursing care;
(b)
institutions for retired, elderly or disabled
persons, including buildings used as a home for the
retired or elderly persons or persons with any disability;
(c)
educational institutions including buildings
used as a boarding school or for similar purposes;
(d)
care institutions including buildings used
as orphanages, shelter homes, open centres for refugees
or for similar purposes;
(e)
religious institutions including buildings
used as convents, retreat houses or for similar purposes;
(f)
military
institutions
such
as
military
barracks; and
(g)
other institutions including buildings used
as boarding houses, penal or correctional facilities or for
similar purposes;
"kV" means kilo Volt;
"kVA" means kilo Volt Ampere;
"kVAh" means kilo Volt Ampere hour;
"kW" means kilo Watt;
"kWh" means kilo Watt hour;
"low voltage" or "LV" means voltage of nominal RMS
value equal or less than one kV (1kV) in relation to alternating
current between any conductor;
"maximum demand in any period" means twice the
highest demand in kWh or kVAh supplied during any thirty (30)
consecutive minutes during the year, or quarter of the year, as
the case may be, as registered by the maximum demand
indicator or register of the meter installed in such premises by
the distribution system operator
Provided that
(a)
where the seal of a maximum demand
indicator of the meter is found broken or tampered with,
the indicator shall be conclusively deemed to have
registered the highest demand in kW or kVA, depending
on the applicable tariff, which the meter is capable of
registering; or
(b)
where a maximum demand indicator or
register of the meter is found to be defective, for reasons
other than breaking or tampering, the maximum demand
supplied made in any period during the last preceding
year or, as the case may be, during the last preceding
corresponding trimester shall, unless it is otherwise
agreed between the distribution system operator and the
customer, apply to the year or, as the case may be, to the
trimester in relation to which such indicator or register is
found to be defective, until the indicator or register is
repaired or replaced by the distribution system operator
Provided further that, without prejudice to the
other provisions of these regulations and for the purposes of
this definition only, "year" means a period of approximately
twelve (12) consecutive months ending on such day not earlier
than the 24th March and not later than the 7th April on which a
reading is carried out;
"medium voltage" or "MV" means voltage of nominal
RMS value greater than one kV (1kV) up to thirty three KV
(33kV) in relation to alternating current between any conductor;
"meter" means the electricity meter and any other
associated equipment and wiring provided and installed, or
approved, by the distribution system operator to register the
electricity generated and, or imported and, or exported by a
customer and, where applicable, the maximum demand in the
relevant premises or temporary installation;
ELECTRICITY CONNECTION AND SUPPLY
"network" means the electricity distribution system;
"network code" shall have the same meaning as assigned
to it in regulation 29 of the Electricity Regulations;
"night consumption" means the consumption of
electricity registered between 22.00 hours of one (1) day and
(regulation 24)
1. Maximum Consumption Tariffs
The supply of electricity to a non-residential premises shall be
billed, for any period as the distribution system operator may from
time to time determine, in accordance with fees and tariffs which shall
not exceed the following
(1)
without prejudice to the other provisions of these
regulations the supply of electricity to a non-residential single phase
network connection shall be subject to an annual service fee of
(i)
one hundred and twenty euro (€120) for a 40
Amps single phase network connection;
(ii)
two hundred and forty euro (€240) for a 40 Amps
three phase network connection; and
(iii) three hundred and sixty euro (€360) for a 60
Amps or more three phase network connection;
(2)
without prejudice to the other provisions of these
regulations, the supply of electricity to a non-residential premises shall
be subject to one (1) of the following annual consumption tariffs which
may be billed on a pro rata basis
(a)
electricity consumption shall be metered in kWh
ELECTRICITY CONNECTION AND SUPPLY
and shall be billed at the following maximum tariffs
For every kWh of the first 2,000 kWh
€0.1215;
For every kWh of the next 4,000 kWh
€0.1275;
For every kWh of the next 4,000 kWh
€0.1373;
For every kWh of the next 10,000 kWh
€0.1485;
For every kWh of the next 40,000 kWh
€0.1613;
For every kWh of the next 40,000 kWh
€0.1500;
For every kWh of the next 900,000 kWh
€0.1403;
For every kWh of the next 4,000,000 kWh
€0.1275;
For every kWh of the remaining consumption
€0.1080;
(b)
a customer in a non-residential premises with a
consumption exceeding 5,000,000kWh may apply to be billed
at day and night kWh rates at the following maximum tariffs
(i)
day consumption shall be subject to the
following tariffs
For every kWh of the first 2,000 kWh
€0.1230;
For every kWh of the next 4,000 kWh
€0.1290;
For every kWh of the next 4,000 kWh
€0.1388;
For every kWh of the next 10,000 kWh
€0.1500;
For every kWh of the next 40,000 kWh
€0.1628;
For every kWh of the next 40,000 kWh
€0.1515;
For every kWh of the next 900,000 kWh
€0.1418;
For every kWh of the next 4,000,000 kWh
€0.1290;
For every kWh of the remaining consumption
€0.1095;
(ii)
night consumption shall be subject to the
following tariffs
For every kWh of the first 2,000 kWh
€0.0953;
For every kWh of the next 4,000 kWh
€0.1013;
For every kWh of the next 4,000 kWh
€0.1110;
For every kWh of the next 10,000 kWh
€0.1223;
For every kWh of the next 40,000 kWh
€0.1350;
For every kWh of the next 40,000 kWh
€0.1238;
For every kWh of the next 900,000 kWh
€0.1140;
For every kWh of the next 4,000,000 kWh
€0.1013;
ix.
For every kWh of the remaining consumption
(c)
a customer in a non-residential premises that is
rated at 100 Amps or more per phase may apply to be metered
and billed in kVAh at the following maximum tariffs
i.
For every kVAh of the first 2,000 kVAh
€0.1118;
ii.
For every kVAh of the next 4,000 kVAh
€0.1170;
iii.
For every kVAh of the next 4,000 kVAh
€0.1260;
iv.
For every kVAh of the next 10,000 kVAh
€0.1365;
v.
For every kVAh of the next 40,000 kVAh
€0.1485;
vi.
For every kVAh of the next 40,000 kVAh
€0.1380;
vii.
For every kVAh of the next 900,000 kVAh
€0.1290;
viii.
For every kVAh of the next 4,000,000 kVAh
€0.1170;
ix.
For every kVAh of the remaining consumption
€0.0990;
(d)
a customer in a non-residential premises that is
rated at 100 Amps or more per phase and has a consumption
exceeding 5,500,000 kVAh may apply to be metered and billed
at day and night kVAh rates at the following maximum tariffs
(i)
day consumption shall be subject to the
following tariffs
i.
For every kVAh of the first 2,000 kVAh
€0.1113;
ii.
For every kVAh of the next 4,000 kVAh
€0.1185;
iii.
For every kVAh of the next 4,000 kVAh
€0.1275;
iv.
For every kVAh of the next 10,000 kVAh
€0.1380;
v.
For every kVAh of the next 40,000 kVAh
€0.1500;
vi.
For every kVAh of the next 40,000 kVAh
€0.1395;
vii.
For every kVAh of the next 900,000 kVAh
€0.1305;
viii.
For every kVAh of the next 4,000,000 kVAh
€0.1185;
ix.
For every kVAh of the remaining consumption
€0.1005;
(ii)
night consumption shall be subject to the
following tariffs
i.
For every kVAh of the first 2,000 kVAh
€0.0855;
ii.
For every kVAh of the next 4,000 kVAh
€0.0908;
iii.
For every kVAh of the next 4,000 kVAh
€0.0998;
iv.
For every kVAh of the next 10,000 kVAh
€0.1103;
For every kVAh of the next 40,000 kVAh
€0.1223;
For every kVAh of the next 40,000 kVAh
€0.1118;
For every kVAh of the next 900,000 kVAh
€0.1028;
For every kVAh of the next 4,000,000 kVAh
€0.0908;
For every kVAh of the remaining consumption
€0.0728.
(3)
Without prejudice to the other provisions of these
regulations, a non-residential premises three phase network connection
exceeding 60 Amps per phase shall also be subject to a maximum
demand tariff at the following annual cumulative consumption rates
(a)
where consumption does not exceed or is equal to
5,000,000 kWh, at a rate of twenty euro and fifty cents (€20.50)
per kW of the maximum demand in any period during the year;
(b)
where consumption does not exceed or is equal
to 5,500,000kVAh, at a rate of nineteen euro and twenty cents
(€19.20) per kVA of the maximum demand in any period
during the year;
(c)
where consumption exceeds 5,000,000 kWh or
5,500,000 kVAh, at a rate of seventeen euro and twenty cents
(€17.20) of the maximum demand in any period during the
year.
(4)
All the above rates are exclusive of value added tax.
2. Methodology for the Calculation of Tariffs
(1)
The distribution system operator shall be entitled to use
its own discretion as to how to calculate and bill the amounts derived
from the application of the consumption tariffs for supply of electricity
to a non-residential premises in item 1(2) on a pro rata basis, such that
the distribution system operator shall also be entitled to apportion the
relative thresholds in each of the consumption tariffs referred to in item
1(2) to specific billing periods throughout a year at its discretion, and
apply such thresholds accordingly, on a pro rata basis
Provided that the distribution system operator shall keep
the Regulator informed of any methodology it adopts in calculating
and billing the consumption tariffs on a pro rata basis.
(2)
Any bill issued by the distribution system operator for
supply of electricity to a non-residential premises, whether for a pro
rata period of any calendar year or otherwise, shall be due to be paid
on the date as indicated on the bill by the distribution system operator,
notwithstanding that such bill may only refer to a part of a calendar
year.
(3)
In order to give effect to the provisions of item 2(1), the
distribution system operator shall use all reasonable endeavours and
procedures, in accordance with the provisions of these regulations, to
obtain a reading of actual consumption incurred by the customer.
Where the distribution system operator is unable to obtain such a
reading of the actual consumption incurred for reasons beyond its
control, it may thereafter rely on estimates of the actual consumption
incurred by the customer.
(4)
Where supply of electricity to a non-residential premises
is only provided for a part of a calendar year, the maximum
consumption tariffs shall be computed by applying the cumulative
thresholds referred to in item 1(2) proportionately to the days during
which supply of electricity to a non-residential premises is actually
provided by the distribution system operator, such that each of the
units (kWh or kVAh) referred to in item 1(2) shall be divided by the
number of days in a calendar year and applied accordingly to the
applicable billing period during which supply of electricity to a non-
residential premises is actually provided.
(1)
L-operatur tas-sistema ta’ distribuzzjoni għandu,
bla ħsara għall-konformità ma’ dawn ir-regolamenti u l-ħlas tad-dritt
stipulat fil-partita 1 tas-Sitt Skeda, jikkonnettja fond mas-sistema ta’
distribuzzjoni permezz ta’ konnessjoni man-network meta jintalab
jagħmel dan minn kwalunkwe persuna li tkun sid jew tamministra jew
li jkollha taħt il-kontroll tagħha l-fond, jew persuna li tipprovdi
dikjarazzjoni li tgħid li s-sid ta’ dak il-fond ikun ta l-awtorizzazzjoni
dovuta, sabiex l-elettriku jkun jista’ jiġi importat minn u, jew esportat
lejn in-network
Iżda l-operatur tas-sistema ta’ distribuzzjoni jista’ wkoll
jikkonnettja installazzjoni temporanja man-network meta jintalab
jagħmel dan permezz tal-proċeduri xierqa ta’ applikazzjoni.
(2)
Id-dmir ta’ operatur tas-sistema ta’ distribuzzjoni
jinkludi d-dmir li jipprovdi u jżomm l-konnessjoni kif jista’ jkun
meħtieġ sabiex tippermetti li din il-konnessjoni tintuża għall-iskopijiet
li għalihom tkun meħtieġa mill-klijent.
(3)
Id-dmirijiet ta’ operatur tas-sistema ta’ distribuzzjoni
għandhom ikunu soġġetti għad-dispożizzjonijiet ta’ dawn ir-
regolamenti.
(regulation 24)
1. Maximum Consumption Tariffs
The supply of electricity to a domestic premises shall be billed,
for any period as the distribution system operator may from time to
time determine, in accordance with fees and tariffs which shall not
exceed the following
(1)
Without prejudice to the other provisions of these
regulations the supply of electricity to domestic premises shall be
subject to the following annual service fee of
(a)
sixty-five euro (€65) for a 40 Amps single-phase
network connection;
(b)
one hundred and forty euro (€140) for a 40 Amps
three phase network connection; and
(c)
one hundred and ninety-five euro (€195) for a 60
Amps or more three phase network connection.
(2)
Without prejudice to the other provisions of these
regulations a domestic premises network connection shall be subject to
the following maximum consumption tariff which may be billed on a
pro rata basis. The said maximum consumption tariff shall be based on
a cumulative consumption, which shall consist of the amounts derived
from the cumulative application of each of the following thresholds,
per annum
i.
For every kWh of the first 2,000 kWh
€0.1365;
ii.
For every kWh of the next 4,000 kWh
€0.1673;
iii.
For every kWh of the next 4,000 kWh
€0.2023;
iv.
For every kWh of the next 10,000 kWh
€0.4180;
v.
For
every
kWh
of
the
remaining
€0.6860.
consumption
(3)
Without prejudice to the other provisions of these
regulations, a domestic premises three phase network connection
exceeding 60 Amps per phase shall also be subject to a maximum
demand tariff at the rate of twenty-one euro and five cents (€21.05) per
annum per kW of the maximum demand in any period during the year.
(4)
All the above indicated rates are inclusive of value added
tax.
2. Methodology for the Calculation of Tariffs
(1)
The distribution system operator shall be entitled to use
its own discretion as to how to calculate and bill the amounts derived
from the application of the consumption tariff in item 1(2) on a pro
rata basis
Provided that
(a)
the amount which is billed by the distribution
system operator for a period of a calendar year shall not exceed
the amounts derived from the application of the maximum tariff
as established by the Regulator in accordance with these
regulations and within the limits prescribed in item 1; and
(b)
the distribution system operator shall keep the
Regulator informed of any methodology it adopts in calculating
and billing the consumption tariff on a pro rata basis.
(2)
Notwithstanding the provisions of item 2(1)(a) and that
the distribution system operator may adopt an adjustment mechanism
to ensure compliance with the provisions of item 2(1)(a), any bill
issued by the distribution system operator, whether for a pro rata
period of any calendar year or otherwise, shall be due to be paid on the
date as indicated on the bill by the distribution system operator,
notwithstanding that such bill may only refer to a part of a calendar
year.
(3)
In order to give effect to the provisions of item 2(2), the
distribution system operator shall use all reasonable endeavours and
procedures, in accordance with the provisions of these regulations, to
obtain a reading of actual consumption incurred by the customer.
Where the distribution system operator is unable to obtain the said
reading of the actual consumption incurred for reasons beyond its
control, it may thereafter rely on estimates of the actual consumption
incurred by the customer.
(4)
Where supply of electricity to a domestic premises is
only provided for a part of a calendar year, the maximum consumption
tariff shall be computed by applying the cumulative thresholds referred
to in item 1(2) proportionately to the days during which supply of
electricity to a domestic premises is actually provided by the
distribution system operator, such that each of the units (kWh) referred
to in item 1(2) shall be divided by the number of days in a calendar
year and applied accordingly to the days during which supply of
electricity to a domestic premises is actually provided.
(1)
Il-konnessjonijiet li ġejjin
għandhom jiġu
pprovduti lill-klijenti indivdwali mill-operatur tas-sistema ta’
distribuzzjoni
(a)
konnessjoni standard man-network; jew
(b)
bulk network connection.
(regulation 24)
(1)
Without prejudice to the other provisions of these
regulations, a service for the charging of electric vehicles in a non-
residential premises shall be subject to the payment of the following
monthly fees
(a)
six euro (€6) per month service fee (inclusive of
value added tax) in case of a single phase network connection;
and
(b)
eight euro (€8) per month service fee (inclusive
of value added tax) in case of a three phase network connection.
In the case of public EV charging stations, the service fees and
tariffs listed in the Second Schedule shall not apply and the service
fees and tariffs listed in this Schedule shall apply instead.
(2)
Without prejudice to the other provisions of these
regulations, the consumption for the charging of electric vehicles in a
non-residential premises, as measured by the EV meter installed for
such purpose, and during the time periods between 00:00 and 05:59
and between 12:00 and 15:59, and Sundays all day from 00:00 to
23:59 of the same day, shall be billed at the rate of zero point one, two,
nine, eight per kWh (€0.1298/kWh), which is inclusive of value added
tax.
(3)
The consumption of electricity for the charging of
electric vehicles in a non-residential premises as measured by the EV
meter outside the time periods between 00:00 and 05:59, between
12:00 and 15:59 and Sundays all day between 00:00 to 23:59 of the
same day, and as measured by the meter installed for such purpose,
shall be billed at the rate of zero point one, four, eight, five per kWh
(€0.1485/kWh), which is inclusive of value added tax.
(4)
Where the EV meter is installed as a supplementary
meter to the main consumption meter supplying the premises, the
consumption as measured by the EV meter shall be deducted for
billing purposes from the consumption measured by the main
consumption meter.
(5)
In the case of public EV charging stations, only the
service fees and the tariffs listed in this Schedule shall apply.
(1)
Kwalunkwe persuna li jkollha sjieda jew
tamministra jew li jkollha taħt il-kontroll tagħha fond jew
installazzjoni temporanja, jew persuna li tipprovdi dikjarazzjoni li
tgħid li s-sid tal-imsemmi fond ikun ta l-awtorizzazzjoni dovuta, jew
kwalunkwe persuna li teħtieġ li ssir klijent, tista’ tagħmel talba lill-
operatur tas-sistema ta’ distribuzzjoni għal konnessjoni man-network
jew għal bidla f’konnessjoni eżistenti man-network. Meta jintalab li
ssir konnessjoni mill-operatur tas-sistema ta’ distribuzzjoni skont ir-
regolament 3, il-klijent għandu jissottometti applikazzjoni lill-operatur
tas-sistema ta’ distribuzzjoni.
(2)
L-applikazzjoni msemmija fis-subregolament (1)
għandha ssir f’dik il-forma u l-manjiera, u għandha tinkludi, jew tkun
akkumpanjata minn, dik l-informazzjoni u dokumenti kif jista’ jkun
preskritt mill-operatur tas-sistema ta’ distribuzzjoni fuq is-sit
elettroniku tiegħu. L-applikazzjoni għandha tkun akkumpanjata wkoll
mid-dritt applikabbli stabbilit fis-Sitt Skeda.
(3)
Id-dettalji li jinsabu fl-applikazzjoni għandhom ikunu
soġġetti għal verifika mill-operatur tas-sistema ta’ distribuzzjoni, u
wara dan l-operatur tas-sistema ta’ distribuzzjoni jista’
(a)
jitlob aktar informazzjoni mingħand l-applikant
fir-rigward tal-konnessjoni meħtieġa; u
(b)
iwettaq spezzjoni tal-installazzjoni temporanja, il-
fond u, jew l-installazzjoni elettrika li għaliha tirrelata l-
applikazzjoni.
(4)
Talba għal kwalunkwe servizz ipprovdut mill-operatur
tas-sistema ta’ distribuzzjoni għandha tiġi sottomessa bl-użu tal-
formola ta’ applikazzjoni xierqa jew proċedura oħra stabbilita mill-
operatur tas-sistema ta’ distribuzzjoni minn żmien għal żmien, li
għandha timtela kollha u tiġi sottomessa lill-operatur tas-sistema ta’
distribuzzjoni bil-mod preskritt. Is-servizzi pprovduti mill-operatur
tas-sistema ta’ distribuzzjoni li jeħtieġu s-sottomissjoni ta’ formola ta’
applikazzjoni jew tali proċedura oħra jinkludu dan li ġej
(a)
talba għal konnessjoni ġdida man-network; jew
(b)
talba għal żieda jew tnaqqis tal-kapaċità jew
modifika għall-konnessjoni tan-network eżistenti;
(ċ)
talba għal konnessjoni temporanja man-network
ta’ installazzjoni temporanja;
(d)
talba għal bidla fit-tariffa;
(e)
talba għal bidla fin-numru ta’ persuni dikjarati li
jirrisjedu fil-fond residenzjali;
(f)
talba għal trasferiment ta’ kont;
(g)
talba għal konnessjoni ta’ ġeneraturi distribwiti
inklużi dawk li joperaw bħala RES jew koġenerazzjoni;
(h)
kwalunkwe applikazzjoni oħra li tista’ tkun
meħtieġa minn żmien għal żmien għal servizzi pprovduti mill-
operatur tas-sistema ta’ distribuzzjoni
Iżda fejn klijent li jkun diġà rreġistrat mal-operatur tas-
sistema ta’ distribuzzjoni fir-rigward ta’ kwalunkwe fond jew
installazzjoni temporanja jitlob konnessjoni għal fond differenti u, jew
installazzjoni temporanja, l-imsemmija applikazzjoni għandha titqies
li hija applikazzjoni għal konnessjoni ġdida, anke jekk tali fond ieħor
u, jew installazzjoni temporanja kienu preċedentement konnessi man-
network mill-operatur tas-sistema ta’ distribuzzjoni.
(5)
Djar, appartamenti, flettijiet, fabbriki, lukandi, ħwienet
kummerċjali, uffiċċji u kwalunkwe bini ieħor li huwa fiżikament
interkonness internament, għandhom jiġu pprovduti b’konnessjoni
waħda (1) biss man-network sakemm ma jkunx awtorizzat mod ieħor
mill-operatur tas-sistema ta’ distribuzzjoni.
(6)
Applikazzjoni għal konnessjoni man-network jew l-
aġġornament ta’ konnessjoni eżistenti man-network sottomessa lill-
operatur tas-sistema ta’ distribuzzjoni għandha tiġi ffirmata minn
provditur awtorizzat li jkollu l-awtorizzazzjoni meħtieġa għat-tip ta’
installazzjoni elettrika skont ir-Regolamenti dwar l-Installazzjonijiet
Elettriċi
Iżda
l-applikazzjonijiet
għall-konnessjoni
tal-
installazzjonijiet elettriċi b’rating tal-kurrent ta’ tliet mitt (300) Amp
jew aktar fi kwalunkwe phase għandhom jiġu ffirmati minn inġinier
elettriku bil-warrant li jkun debitament awtorizzat skont ir-rekwiżiti
tar- Regolamenti dwar l-Installazzjonijiet Elettriċi.
(7)
L-applikazzjoni
lill-operatur
tas-sistema
ta’
distribuzzjoni għandha tinkludi dikjarazzjoni li tgħid li l-installazzjoni
elettrika ġiet spezzjonata u ttestjata skont dawn ir-regolamenti, ir-
Regolamenti dwar l-Installazzjonijiet Elettriċi, il-kodiċi tan-network,
l-istandard EN 50549 u r-regoli u l-proċeduri tekniċi l-oħra kollha
applikabbli u li l-installazzjoni elettrika rilevanti hija konformi
magħhom.
(8)
L-operatur tas-sistema ta’ distribuzzjoni għandu
jivverifika l-informazzjoni li tinsab fl-applikazzjoni u d-
dokumentazzjoni relatata sottomessa skont dan ir-regolament. Fejn
applikazzjoni titqies mill-operatur tas-sistema ta’ distribuzzjoni bħala
mhux kompluta, jew li tonqos milli tikkonforma mar-rekwiżiti ta’
dawn ir-regolamenti, jew fejn l-installazzjoni elettrika soġġetta għall-
applikazzjoni tinstab li mhijiex konformi mar-rekwiżiti ta’ dawn ir-
regolamenti, l-applikazzjoni għandha tiġi miċħuda u riferuta lura lill-
applikant, li għandu jkun responsabbli għall-ħlas ta’ dritt kif stipulat
fil-partita 5 tas-Sitt Skeda.
(9)
L-iżviluppatur u, jew is-sid u, jew l-applikant għandhom
jikkonsultaw mal-operatur tas-sistema ta’ distribuzzjoni matul
(i)
id-disinn ta’ żvilupp ġdid; u, jew
(ii)
alterazzjonijiet ta’ bini jew żvilupp eżistenti; u,
jew
(iii) alterazzjonijiet ta’ installazzjoni elettrika eżistenti
li jeħtieġu aġġornament fil-konnessjoni tal-provvista tal-
elettriku; u, jew
(iv)
il-proċess
sabiex
jinkiseb
il-permess
għall-
iżvilupp;
billi jipprovdi l-load breakdown neċessarju u informazzjoni oħra
li tista’ tkun meħtieġa mill-operatur tas-sistema ta’ distribuzzjoni. Ir-
riżultat tal-konsultazzjoni għandu jiġi rreġistrat bil-miktub u pprovdut lill-
iżviluppatur, u, jew lis-sid u, jew lill-applikant.
(regulation 24)
1. Without prejudice to the other provisions of these
regulations, a service for the charging of electric vehicles in a
residential premises shall be subject to the payment of the following
monthly service fees
(a)
four euro (€4) per month in case of a single-
phase EV meter installation; and
(b)
six euro (€6) per month in case of a three-phase
EV meter installation.
2. Without prejudice to the other provisions of these
regulations, the consumption for the charging of electric vehicles in a
residential premises, as measured by the meter installed for such
purpose, and during the time periods between 00:00 and 05:59 and
between 12:00 and 15:59 and Sundays all day between 00:00 to 23:59
of the same day shall be billed at the rate of zero point one, two, nine,
eight per kWh (€0.1298/kWh), which is inclusive of value added tax.
Any consumption of electricity for the charging of electric
vehicles in a residential premises, as measured outside the time periods
between 00:00 and 05:59 and between 12:00 and 15:59 and Sundays
all day between 00:00 to 23:59 of the same day shall be added to the
normal consumption of the residential premises service for the
respective billing period and charged in accordance with the First
Schedule.
The consumption measured during the time periods between
00:00 and 05:59 and between 12:00 and 15:59 and Sundays all day
between 00:00 to 23:59 of the same day by the EV meter installed as a
supplementary meter to the main consumption meter supplying the
premises, shall be deducted for billing purposes from the consumption
measured by the main consumption meter.
00 hours of the following day;
"non-residential premises" means any premises which
may be provided with a connection to the network and which is
not a domestic premises or a residential premises;
"person" means a natural or legal person;
"physically internally interconnected" means premises
that are internally physically accessible without one having the
need to pass through public ways including
(a)
common areas;
(b)
basement garages; or
(c)
interconnected dwelling places;
"premises" means any site, area, land, development,
building, structure, building unit, single building unit,
institutional household, vehicle, installation and, or device,
which may be connected to the network through a separate
network connection for the purposes of import and, or export of
electricity and includes, without limitation any residential
premises, domestic premises and non-residential premises;
"primary residence" means the dwelling place in which
an individual habitually resides as his principal place of abode
in Malta, as may be established by documentary evidence
Provided that a dwelling place shall not be
considered as a primary residence if the property is also
predominantly used for commercial, industrial or
manufacturing purposes or for any form of trade or profession;
"public charging station" means for the purpose of these
regulations, an EV charging station located within a public road
or public space where the demand relates only to EV charging;
"residential premises" means any premises used solely
and regularly as a private dwelling where at least one (1) person
is registered with the distribution system operator as residing in
it, but does not include institutional households;
"reading" means a reading of the electricity generated,
imported from and, or exported to the network and registered
by a meter, by a person authorised by the distribution system
operator to undertake the said readings, or through a remote
reading mechanism, or in the manner indicated in the proviso to
regulation 22(16);
"Regulator" means the Regulator for Energy and Water
Services established by article 3 of the Act;
"RES" means energy from renewable non-fossil sources,
namely wind, solar such as solar thermal and solar photovoltaic
and geothermal energy, ambient energy, tide, wave and other
ocean energy, hydropower, biomass, landfill gas, sewage
treatment plant gas and biogas;
"RMS" means root-mean square of the AC voltage value;
"route length" means when referring to an extension with
overhead lines or by underground cable, the horizontal distance
from the nearest suitable low voltage connection point, or
suitable substation, as the case may be, to the meter box along a
cable and, or aerial line through a publicly accessible road or
passageway;
"secondary residence" means any immovable property
used solely for residential purposes, other than that which
serves as an individual’s primary residence;
"single building unit" means a premises consisting of an
entire building or structure having a single connection to the
network, excluding any other network connection for the export
of electricity;
"smart meter" means an advanced electricity meter that
stores data related to the consumption and export of electricity
enabling two-way transfer of data through a network, primarily
for monitoring and billing purposes;
"special readings of meters" means the reading of a meter
made at the request of the customer;
"standard material" means cables, transformers
accessories normally stored and used by the distribution system
operator to extend network connections;
"standard network connection" means a network
connection through one (1) meter which may be any one (1) of
the following
(a)
single phase network connections of forty
ELECTRICITY CONNECTION AND SUPPLY
(40) Amps;
(b)
three phase network connections of forty
(40) Amps per phase; and
(c)
three phase network connections of sixty
(60) Amps per phase;
"suitable low voltage connection point" means an
existing connection point on the low voltage network from
where extensions can be connected using the standard materials
used by the distribution system operator and which is the least-
cost technically acceptable connection, wherever possible,
which meets the requirements of the network code;
"suitable substation" means an existing non-dedicated
substation where the peak load of the substation at the time of
the application and, or consultation stage including the
additional load shall not exceed seventy-five per cent (75%) of
the transformer rating, as long as the transformer cannot be
replaced by one with a larger rating;
"substation" means an enclosure housing the equipment
and, or apparatus for either transforming or converting energy
to, or from high voltage to low voltage, or vice versa, or for
switching, controlling or regulating the energy at high voltage,
and includes the equipment and apparatus therein;
"substation land" means the area over which a substation
is built or the area which has been identified for a substation to
be built on;
"temporary installation" means an electrical installation
which is not of a permanent nature and which may include but
is not limited to, decorative street lighting, public entertainment
facilities, outdoor mobile units, cranes and any construction
sites.
(2)
Unless the context otherwise requires, words and phrases
used in these regulations which are not herein defined shall have the
same meaning as that assigned to them in the Act and in the Electricity
Regulations.
3. (1)
The distribution system operator shall, subject to
compliance with these regulations and payment of the fee stipulated in
Section 1 of the Sixth Schedule, connect a premises to the distribution
system through a network connection when requested to do so by any
person who owns or administers or has under its control the premises,
or a person who provides a declaration stating that the owner of such
premises has granted due authorisation, to enable electricity to be
imported from and, or exported to the network
Provided that the distribution system operator may also
connect a temporary installation to the network when requested to do
so by means of the appropriate application procedures.
(2)
The duty of the distribution system operator includes a
duty to provide and maintain the connection as may be necessary to
enable such connection to be used for the purposes for which it is
required by the customer.
(3)
The duties of the distribution system operator shall be
subject to the provisions of these regulations.
4. The following connections to individual customers shall
be provided by the distribution system operator
(a)
standard network connection; or
(b)
bulk network connection.
5. (1)
Any person who owns or administers or has under
its control a premises or temporary installation, or a person who
provides a declaration stating that the owner of the said premises has
granted due authorisation, or any person who requires to become a
customer, may make a request to the distribution system operator for a
network connection or for an alteration to an existing network
connection. When a connection is requested to be made by the
distribution system operator in pursuance of regulation 3, the customer
shall submit an application to the distribution system operator.
(2)
The application referred to in sub-regulation (1) shall be
made in such form and manner, and shall contain, or be accompanied
by, such information and documents as may be prescribed by the
distribution system operator on its website. The application shall also
be accompanied by the applicable fee set out in the Sixth Schedule.
(3)
The particulars contained in the application shall be
subject to verification by the distribution system operator, following
which the distribution system operator may
(a)
request further information from the applicant in
relation to the required connection; and
(b)
carry out an inspection of the temporary
installation, premises and, or the electrical installation to which
the application relates.
(4)
A request for any service provided by the distribution
system operator shall be submitted using the appropriate application
form or other procedure established by the distribution system
operator from time to time, which shall be completed in full and
submitted to the distribution system operator in the manner so
prescribed. Services provided by the distribution system operator that
require the submission of an application form or such other procedure
include the following
(a)
a request for a new network connection;
(b)
a request for an addition or reduction of capacity
or a modification to an existing network connection;
(c)
a request for temporary network connection of a
temporary installation;
(d)
a request for a change of tariff;
(e)
a request for a change in number of persons
declared as residing in the residential premises;
(f)
a request for transfer of account;
(g)
a request for connection of distributed generators
including those operating as a RES or cogeneration; or
(h)
any other application which may be required from
time to time for services provided by the distribution system
operator
Provided that where a customer already registered with
the distribution system operator with respect to any premises or
temporary installation requests a connection for a different premises
and, or temporary installation, the said application shall be deemed to
be an application for a new connection, even if such other premises
and, or temporary installation were previously connected to the
network by the distribution system operator.
(5)
Houses, apartments, flats, factories, hotels, commercial
outlets, offices and any other buildings which are physically internally
interconnected shall be provided with only one (1) network connection
unless otherwise authorised by the distribution system operator.
(6)
An application for a network connection or the upgrade
of an existing network connection submitted to the distribution system
operator shall be signed by an authorised provider holding the required
authorisation for the type of electrical installation in accordance with
the Electrical Installations Regulations
Provided that applications to connect electrical
installations with a current rating equal to or greater than three
hundred (300) Amps on any phase, shall be signed by a warranted
electrical engineer duly authorised in accordance with the
requirements of Electrical Installations Regulations.
(7)
The application to the distribution system operator shall
include a declaration stating that the electrical installation has been
inspected and tested in accordance with these regulations, the
Electrical Installations Regulations, the network code, EN 50549
standard and all other applicable rules and technical procedures and
that the relevant electrical installation is in conformity thereto.
(8)
The distribution system operator shall verify the
information contained in the application and the related documentation
submitted in accordance with this regulation. Where an application is
deemed by the distribution system operator to be incomplete, or fails
to comply with the requirements of these regulations, or where the
electrical installation subject of the application is found to be non-
compliant with the requirements of these regulations, the application
shall be rejected and referred back to the applicant, who shall be liable
to the payment of a fee as stipulated in item 5 of the Sixth Schedule.
(9)
The developer, and, or owner and, or applicant shall
consult with the distribution system operator during
(i)
the design of a new development;
(ii)
alterations of an existing building or development;
(iii) alterations of an existing electrical installation
that requires an upgrade of the electricity supply connection;
and, or
(iv) during the process to obtain the development
permission,
by providing the necessary load breakdown and other
information that may be required by the distribution system operator.
The outcome of the consultation shall be recorded in writing and
provided to the developer and, or owner and, or applicant.
6. (1)
The distribution system operator may require any
customer who requests, or who has already been provided with, a
connection, to provide a deposit by way of security for all amounts
which may become due to the distribution system operator in
connection with the supply of electricity to the customer. The deposit
shall be in such amount as established in item 1 of the Sixth Schedule.
(2)
A deposit made in accordance with sub-regulation (1)
shall be refunded to the depositor upon his ceasing to be a customer,
provided that all amounts due to the distribution system operator in
respect of the supply of electricity in connection with his account have
been paid.
(3)
The distribution system operator may, instead of
requiring a deposit to be made in accordance with sub-regulation (1),
require a customer to produce an undertaking by a third party
acceptable to the distribution system operator to bind himself in
solidum with the customer for the regular payments of all amounts that
may become due to the distribution system operator in connection with
the supply of electricity to the account of the said customer.
(4)
If a person fails to provide a deposit by way of security
required in accordance with sub-regulation (1) or produce an
undertaking by a third party in accordance with sub-regulation (3), the
distribution system operator may
(a)
if the connection has not been made, refuse to
provide the connection as long as compliance is not achieved;
or
(b)
if the connection has been provided, suspend the
connection or disconnect the connection in question.
(1)
L-operatur tas-sistema ta’ distribuzzjoni jista’
jeħtieġ lil kwalunkwe klijent li jitlob, jew li diġà ġie pprovdut
b’konnessjoni, li jipprovdi depożitu bħala garanzija għall-ammonti
kollha li jistgħu jsiru dovuti lill-operatur tas-sistema ta’ distribuzzjoni
b’konnessjoni mal-provvista tal-elettriku lill-klijent. Id-depożitu
għandu jkun f’tali ammont kif stabbilit fil-partita 1 tas-Sitt Skeda.
(2)
Depożitu magħmul skont is-subregolament (1) għandu
jitħallas lura lid-depożitant malli jieqaf ikun klijent, diment li l-
ammonti kollha dovuti lill-operatur tas-sistema ta’ distribuzzjoni fir-
rigward tal-provvista tal-elettriku b’rabta mal-kont tiegħu jkunu
tħallsu.
(3)
L-operatur tas-sistema ta’ distribuzzjoni jista’, minflok
ma jitlob li jsir depożitu skont is-subregolament (1), jeħtieġ li klijent
jipproduċi impenn minn parti terza aċċettabbli għall-operatur tas-
sistema ta’ distribuzzjoni li jorbot lilu nnifsu in solidum mal-klijent
għall-ħlas regolari tal-ammonti kollha li jistgħu jsiru dovuti lill-
operatur tas-sistema ta’ distribuzzjoni b’rabta mal-provvista tal-
elettriku lill-kont tal-imsemmi klijent.
(4)
Jekk persuna tonqos milli tipprovdi depożitu bħala
garanzija meħtieġa skont is-subregolament (1) jew tipproduċi impenn
minn parti terza skont is-subregolament (3), l-operatur tas-sistema ta’
distribuzzjoni jista’
(a)
jekk il-konnessjoni ma tkunx saret, jirrifjuta li
jipprovdi l-konnessjoni sakemm ma tintlaħaqx konformità; jew
(b)
jekk il-konnessjoni tkun ġiet ipprovduta,
jissospendi l-konnessjoni jew jiskonnettja l-konnessjoni
inkwistjoni.
(1)
The application fees for a new network connection are as
follows
A single-phase network connection
€300
A 40 A three phase network connection
€600
A 60 A three phase network connection
€900
RES (PV, CHP, Wind Turbine) for single
€50
phase
RES (PV, CHP, Wind Turbine) for three
€150
phase
EV single phase charging connection in a
€50
residential and, or non-residential premises with
an existing single or a three phase network
connection
EV three phase charging connection in a
€80
residential and, or non-residential premises with
an existing three phase network connection
Deposit that may be requested by the
€500
distribution system operator in accordance with
regulation 6(1)
(2)
The application fees for the alteration of a connection are
as follows
Replacement of single phase with 40 A three €600 for every
phase (addition)
meter
Replacement of single phase with 60 A three €900 for every
phase (addition)
meter
Replacement of three phase with single €300 for every
phase (reduction)
meter
Shifting of meter
€200 for every
meter
Addition and shifting
€900 for every
meter
Addition of photovoltaic panels on same
€50
single phase network connection
Addition of photovoltaic panels on same
€150
three phase network connection
(3)
The application fee for the removal and, or the
replacement of a network connection as requested by customer is fifty-
five (€55).
(4)
The fees for a temporary connection are as follows
Type of temporary
Application Application Deposit on
Renewal of
Renewal of
service connection
fee for one fee for six consumption
network
network Removal
(1) month (6) months
connection for connectio-n
one (1)
for (6)
month
months
Construct 40A single
€250
€1,000
€120
phase
40A three
€500
€1,500
€150
phase
60A three
€750
€2,500
€200
phase or
greater
Boathous 40A single
€460
€500
phase
40A single
€30
€180
€30
€30
€180
phase
40A three
€40
€240
€40
€40
€240
phase
60A three
€60
€360
€60
€60
€360
phase
Greater
€550
€3300
€450
€60
€360
than 60A
three phase
(5)
The fees for non-compliant applications are as follows
Application found non-compliant during vetting
€50
Application found non-compliant during the
€50
provision of network connection
(6)
A minimum fee of three hundred euro (€300) is charged
for an installation that has been found defective and has not been
rendered fit for connection to the network within one (1) month from
date of first test.
(7)
A fee of fifty euro (€50) is charged for each subsequent
test after the first test when the installation was first found to be
defective.
(8)
The fees for a network connection study are as follows
RES capacity
Fee
for
network
connection study
>11kW and ≤ 40kW
€0
>40kW and ≤ 100kW
€150
> 100kW and ≤ 500kW
€350
> 500kW and ≤ 3.2MW
€750
> 3.2MW and ≤ 8MW
€1,500
> 8MW and ≤ 30MW
€2,500
> 30MW
by quotation
(9)
The HV contribution is two hundred euro (€200) per
kVA.
(10) Refund of HV contribution in the case of a substation
fully financed by the customer is two hundred euro (€200) per kVA
extended to new applicants.
(11) The amount of compensation for substation land shall be
determined in accordance with regulation 14.
(12) The fee for a missing meter is one thousand and five
hundred euro (€1,500).
(13) The fee for testing of a meter wherein it is found to be
registering correctly is seventy euro (€70)
(14)
The fees for a special meter reading are as follows
Reading between 7am and 5pm
€25
Reading between 5pm and 9pm
€50
Reading between 9pm and 7am
€100
Reading taken on non-working days
Above indicated fees shall be
doubled
The above indicated fees shall be doubled for special reading
falling, even if in part, on a Saturday, Sunday or public and, or national
holiday in Malta.
(15)
The fees for the reconnection to the network are as
follows
Reconnection to the network after suspension related to
€140
payments and refusal to replace meter
Reconnection to the network following suspension due to
€70
safety
(16)
The fees for rescheduling an appointment related to a
ELECTRICITY CONNECTION AND SUPPLY
request for network connection are as follows
Reschedule an appointment between 8am and 4pm
€0
on any day from Monday to Friday, not being a public
holiday and not beyond the period of fifteen (15)
working days of the first scheduled visit
Reschedule an appointment between 4pm and 8pm
€25
on any day from Monday to Friday, not being a public
holiday or between 8am and 4pm as long as appointment
is not beyond the period of fifteen (15) working days of
the first scheduled visit
Reschedule an appointment between 8am and 4pm
€50
on a Sunday or public holiday, or beyond the period of
fifteen (15) working days of the first scheduled visit
(17) The fees for the repair consisting of the replacement of a
fuse are as follows
Fuse changing in customer premises
€25
Fuse changing more than once
€35
Fuse changing in substation
€35
Fault due to customer’s internal installation
€50
(18) The administration fee for meter found tampered by
means of the indication sticker or security alarm is one hundred and
forty euro (€140)
(19)
The replacement cost for a broken meter is as follows
Single phase meter
€300
Three phase meter up to 100A
€900
LV three phase meter over 100A
€2,000
HV meter
€2,000
(20) HV and MV connection losses per LV side meter are
calculated as zero point three, five per cent (0.35%) of the registered
kWh units. (0.35% x kWh units).
(21) The cost of an installation and HV contribution to be
carried out by the distribution system operator shall be paid as follows
(a)
estimates up to two thousand and five hundred
euro (€2,500) shall be paid in full on contract;
(b)
estimates above two thousand and five hundred
euro (€2,500) shall be paid fifty per cent (50%) on contract and
fifty per cent (50%) prior to energising of extension, subject to
a minimum deposit of two thousand and five hundred euro
(€2,500).
(22) Where the customer requests the distribution system
operator to reschedule an appointment in any of the following
instances
(a) between 08:00 and 16:00 on any day from
Monday to Friday, not being a public holiday and not beyond
the period of fifteen (15) working days of the first scheduled
visit, the distribution system operator shall not request any
charges;
(b)
between 16:00 and 20:00 on any day from
Monday to Friday not being a public holiday, or between 08:00
and 16:00 on a Saturday, as long as the appointment is not
beyond the period of fifteen working days of the first scheduled
visit, the distribution system operator may request a charge
equivalent to an after hours fee of ten euro (€10); and, or
(c)
between 08:00 and 16:00 on a Sunday or a public
holiday, or beyond the period of fifteen working days of the
first notified visit, the distribution system operator may request
a charge equivalent to an after hours fee of twenty-five euro
(€25).
(23) The maximum variation of +10% on the distance element
is calculated as follows
Maximum allowed distance = 30,000 Am divided by the
requested fuse rating.
If the actual measured distance divided by the maximum
allowed distance is less or equal to 1.10, then the network connection
is provided with the requested fuse rating.
If it is greater than 1.10, repeat calculations using the next lower
fuse rating, until the result is less or equal to 1.10.
(1)
A one-time installation fee as stipulated in item 1
of the Sixth Schedule shall be due with every application for
(a)
an additional single-phase meter for the charging
of electric vehicles in any premises that is already provided
with a single phase or three phase network connection; and
(b)
an additional three phase meter for the charging of
electric vehicles in a premises already provided with a three-
phase network connection
Provided that only one (1) additional meter for the
charging of electric vehicles may be provided on any single phase or
three phase consumption connection and account
Provided further that the additional meter for the
charging of electric vehicles installed as a supplementary meter of the
main consumption meter and on an existing network connection shall
be installed in close proximity of the consumption meter in a suitable
location as may be determined by the distribution system operator.
(2)
An application for a new electricity network connection
or upgrade or modification of an existing network connection to a
public charging station shall be provided in accordance with the
applicable fees stipulated in item 1 of the Sixth Schedule.
(3)
The installation from the EV meter, up to and including
the EV charging point, shall be the sole responsibility of the customer
and shall be compliant with any requirement of these regulations and
with any other applicable regulations.
(4)
Any electrical installation from the EV meter up to, and
including the EV charging point shall be supplied from the same
connection and account supplying the EV meter.
(5)
Without prejudice to the foregoing, the distribution
system operator may install additional control equipment or other
apparatus to the EV meter as it may deem appropriate.
(6)
The electricity supplied through an EV meter shall only
be used for EV charging purposes. Any other use of such electricity
and, or the tampering with an EV meter shall constitute a breach of
these regulations and the provisions of regulations 21(4) and 26 shall
apply mutatis mutandis. In such circumstances, the distribution system
operator shall also be entitled to suspend the supply to the relevant
premises or temporary installation.
(7)
In the case of private communal car parking or reserved
private car spaces within the boundary of a development, the
installation of an EV meter, as a supplementary meter of the main
consumption meter of the premises or temporary installation, to supply
an EV charging point on a residential or domestic account shall only
be allowed where
(a)
the private communal car parking or reserved
private car spaces shall have the same electrical source
supplying the main consumption meter of the premises or
temporary installation to which the residential or domestic
account refers;
(b)
the supplementary EV meter shall be installed in
proximity to the main consumption meter of the respective
premises or temporary installation;
(c)
the electrical installation from the EV meter to the
charging point shall not pose any obstruction or danger to third
parties;
(d)
proper labelling shall be affixed to the charging
point, the EV meter and the electrical installation referred to in
paragraph (c) to indicate that the EV charging installation is
sourced from a different electricity meter than the communal
meter supplying the common parts of the development and the
common parking areas; and
(e)
the electrical installation supplied from the EV
meter shall be solely used for EV charging.
(8)
In the case of private communal car parking or reserved
private car spaces within the boundary of a development, and where
the user of a private communal car parking area or reserved private car
space does not have a residential or domestic account and, or does not
own or occupy a building unit within the said development, the
installation of an EV meter to supply an EV charging point for private
non-commercial purposes shall only be allowed where
(a)
the new EV meter shall have the same electricity
source supplying the meters of the common parts of the private
communal car parking area or reserved private car spaces and
the distribution system operator determines that the said EV
meters may be provided in accordance with these regulations
Provided that the customer registered as the
account holder for the connection to the common parts shall not
be responsible for the connection to the EV charging point, and
that the customer in whose name the EV meter is registered
shall bear sole responsibility;
(b)
the EV meter shall be installed in proximity to the
consumption meters of the common parts;
(c)
the electrical installation supplied from the EV
meter shall not pose any obstruction or danger to third parties;
and
(d)
the electrical installation supplied from the EV
meter shall be solely used for EV charging.
(1)
New standard network connections or alteration to
an existing standard connection not exceeding 60 Amps on any phase
shall be provided to the applicant in the case of a single building unit
by the distribution system operator by extending the network
infrastructure from the nearest suitable low voltage connection point
or suitable substation, as determined by the distribution system
operator, to the single building unit.
(2)
Any civil works that may be required for the provision of
the network connection, such as but not limited to trenching and laying
of underground cables, may be carried out by the applicant
(a) in conformity with the specifications provided by
the distribution system operator;
(b) following approval by the distribution system
operator; and
(c)
under
the
distribution
system
operator’s
supervision.
(3)
Where the route length is beyond one hundred and fifty
metres (150m) from the nearest suitable low voltage connection point
or suitable substation, the applicant and, or developer, as applicable
shall pay for the full cost of the low voltage extension, including any
civil works which may be required, less the applicable connection fee
stipulated in item 1 of the Sixth Schedule
Provided that the distribution system operator may opt to
extend the low voltage connection on a cost-sharing basis with the
applicant and, or developer, which cost sharing is to be applied on a
pro rata basis on the proportion of the kVA load used on one hand by
the distribution system operator and on the other hand by the applicant
and, or developer, as applicable. In such a case the distribution system
operator shall retain the right to extend network connections from the
said extension to third parties without making any additional payment
or compensation to the applicant.
(4)
Extensions that exceed one hundred and fifty metres
(150m) shall be made using the standard materials used by the
distribution system operator, which shall be provided by the
distribution system operator only if the voltage regulation is within the
limits established in the network code. Where the voltage regulation
goes beyond the limits established in the network code, a new
substation shall be required for the network connection to the single
building unit.
(5)
When the low voltage extension referred to in this
regulation has been fully financed by the applicant and, or the
developer, the said applicant and, or developer, as applicable, upon
submitting a request to the distribution system operator, shall be
entitled to a refund, in accordance with the mechanism established and
published by the distribution system operator in advance, for every
new connection provided by the distribution system operator to other
customers through the utilisation of the same low voltage extension
Provided that
(a)
the entitlement to the said refund shall apply only
up to ten (10) years from the commissioning date of the low
voltage extension;
(b)
the maximum cumulative refund to which the
relevant applicant shall be entitled to shall not exceed sixty-five
percent (65%) of the depreciated total amount paid by the said
applicant for the low voltage extension;
(c)
the costs of any trenching and laying of
underground cables, carried out by the applicant and, or
developer, as applicable, shall be included in the cost used to
calculate the refund referred to in paragraph (b); and
(d) the costs of any trenching and laying of underground
cables referred to in paragraph (c) shall be calculated by a perit
appointed by the distribution system operator who shall base
the calculation on the rates charged by the Authority for
Transport in Malta and, or Infrastructure Malta or their
successors at law for trenching contracts at the time the original
works were carried out. The applicant and, or developer shall
also provide the original invoice and bill of quantity for the said
works and any related documents that the distribution system
operator may reasonably require.
(1)
For the purposes of these regulations, multiple
customers within one (1) development may consist of residential
premises, non-residential premises, domestic premises, or a mixture of
residential premises and, or non-residential premises and, or domestic
premises. The connection fees payable for each network connection up
to 60 Amps as established in the Sixth Schedule shall be applicable in
respect of each network connection not exceeding 60 Amps to each
building unit within a development with multiple customers.
(2)
Where the number of connection units in a development
with multiple customers does not exceed eighteen (18), and where the
route length does not exceed three hundred metres (300m) from the
nearest suitable substation, the network connection may by extended
from the nearest suitable low voltage connection point or suitable
substation, as determined by the distribution system operator.
(3)
Where the number of connection units in a development
with multiple customers does not exceed eighteen (18) and the route
length is beyond three hundred metres (300m) from the nearest
suitable low voltage connection point, the applicants shall pay for the
full cost of the extension, including any civil works which may be
required, less the applicable connection fee stipulated in item 1 of the
Sixth Schedule. Where the voltage regulation goes beyond the limits
established in the network code, a new substation shall be required for
the network connection to the said development with multiple
customers.
(4)
New network connections for developments with
multiple customers shall be provided by the distribution system
operator by extending the network infrastructure from the nearest
suitable substation, as determined by the distribution system operator,
to the development, if all of the following criteria are satisfied
(a)
the number of connection units is more than
eighteen (18) but does not exceed fifty (50);
(b)
the route length from the nearest suitable
substation does not exceed three hundred metres (300m);
(c)
the product of the number of connection units and
the route length in metres does not exceed six thousand and six
hundred (6,600) connection unit metres;
(d)
the peak load of the existing substation at the time
of the application or consultation and the additional load
estimated at the diversified load given in regulation 9(7), when
taken into account in the aggregate, do not exceed seventy-five
per cent (75%) of the transformer rating, as long as the
transformer cannot be replaced by one with a larger capacity;
and
(e)
the development is within a building development
zone
Provided that when all the conditions in this regulation
are satisfied, the connection fees payable for each network connection
up to 60 Amps, as established in the Sixth Schedule, shall be
applicable in respect of each network connection to each building unit
within the development.
(5)
Any civil works, such as but not limited to trenching and
laying of cables, that may be required for the provision of a network
connection pursuant to sub-regulation (4), and is other than bulk
network connection, shall be carried out by the distribution system
operator.
(6)
Where the number of connection units in a development
with multiple customers is more than eighteen (18) and any one (1) or
more of the criteria in sub-regulation (4) are not satisfied, a new
substation shall be required to provide the network connection to the
relevant development with multiple customers, unless the distribution
system operator determines, in its discretion, that a network
connection extended from an existing substation, or another technical
alternative, is adequate to
(a)
meet the total demand of the whole multiple
customer development; and
(b)
comply with the requirements of the network
code.
(7)
The number of connection units and load in a multiple
customer development shall be calculated using the following
parameters
(a)
a single phase 40 Amps network connection is
considered as one (1) connection unit;
(b)
a three phase 40 Amps network connection is
considered as equivalent to three (3) connection units;
(c)
a three phase 60 Amps network connection is
considered as four-and-a-half (4.5) connection units;
(d)
an industrial and, or commercial building unit
shall be considered as four-and-a-half (4.5) connection units
even when the application is for a single phase 40 Amps
network connection;
(e)
a car garage or parking space of up to fifty square
metres (50m 2 ) shall be considered as one-half (0.5) connection
units; and
(f)
the diversified load for one (1) connection unit is
taken as 16 Amps.
(8)
A network connection for an individual customer within
a multiple customer development shall be treated as a bulk network
connection if it requires more than 60 Amps three phase and shall be
extended in accordance with regulation 10
(a)
from an existing substation within the multiple
customer development; and
(b)
from a substation not within the multiple customer
development
Provided that the distribution system operator shall
extend the low voltage connection to the multiple customer
development on a cost-sharing basis with bulk network connection
applicants and, or the developer, as applicable, which cost sharing is to
be applied on a pro rata basis on the proportion of the kVA load used
by the distribution system operator on one hand and the bulk network
connection applicants and, or developer on the other hand
Provided further that a fee per kVA supplied shall be paid
by each bulk network connection applicant as HV contribution as
stipulated in item 9 of the Sixth Schedule and payment is to be effected
in accordance with item 21 of the Sixth Schedule.
Provided further that in such a case the distribution system
operator shall retain the right to extend network connections from the
said extension to third parties without making any additional payment
or compensation to the applicant.
(9)
In the case of a multiple customer development that
requires a mix of one or more bulk network connections and one or
more standard network connections, the total current requested for the
multiple customer development is computed as the sum of the bulk
network connections current required and the number of building units
multiplied by the diversified load as set out in sub-regulation (7)
evenly distributed on the three phase as applicable. The network
connection for the multiple customer development shall be rated
according to the total current calculated and then provided using the
same criteria found in regulation 10.
(1)
A new network connection to a multiple customer
development having a total load exceeding 60 Amps on any phase as
calculated in regulation 9(9) or a new bulk network connection shall
be provided by the distribution system operator by extending the
network infrastructure from the nearest suitable low voltage
connection point or suitable substation on the network, as determined
by the distribution system operator, when all the following criteria are
satisfied
(a)
the amount required in Amps per phase
multiplied by the distance in metres between the metering point
on the applicant’s premises and the low voltage panel in the
nearest suitable substation shall not exceed 30,000 Amp metre
with a maximum variation of +10% on the distance element.
For this purpose, the current requested shall consist of one of
the following standard values: 100 Amps, 125 Amps, 160
Amps, 200 Amps, 250 Amps, 315 Amps, 355 Amps, 400 Amps,
450 Amps, 500 Amps;
(b)
the route length in metres between the metering
point on the applicant’s premises and the low voltage panel in
the nearest suitable substation does not exceed three hundred
metres (300m); and
(c)
the bulk network connection required does not
exceed 500 Amps per phase.
(2)
A bulk network connection shall not be extended from
overhead lines or from underground cables which are themselves
supplied from an overhead line.
(3)
The full cost of the low voltage equipment and works,
including the civil works, trenching and cable laying, required for the
provision of the bulk network connection to the applicant and, or
developer, as applicable, shall be charged to the applicant and, or
developer, as applicable. In addition, a fee per kVA supplied shall be
paid by the applicant as HV contribution as stipulated in item 9 of the
Sixth Schedule and payment is to be effected in accordance with item
21 of the Sixth Schedule
Provided that the applicant may opt to carry out, at his
own expense, any trenching and cable laying in accordance with the
distribution system operators’ requirements and direction.
(4)
The low voltage extension shall remain the property of
the distribution system operator until the whole amount due in respect
of the said low voltage extension has been paid. The customer in
whose premises or temporary installation the low voltage extension
has been installed shall be bound by a declaration in writing that
neither the said customer, nor any successors in title, shall offer any
opposition to the removal of the said low voltage extension by the
distribution system operator in the event that the amounts due to the
distribution system operator in respect of the low voltage extension,
including interest thereon as calculated in accordance with regulation
20(4), are not settled in full and the distribution system operator
determines that such removal is appropriate in the circumstances.
(5)
The maximum variation of +10% on the distance element
as referred to in regulation 10(1)(a) is calculated as stipulated in item
23 of the Sixth Schedule.
(6)
If any one (1) or more of the criteria in regulation 10(1)
are not satisfied, the distribution system operator shall have the right to
require a new substation for the provision of the bulk network
connection in accordance with regulation 12.
(1)
Where an existing customer or new customer
requires to connect a generation unit to the network or increase the
capacity of an existing generation unit, an application shall be
submitted to the distribution system operator in accordance with
regulation 5 and in the said application the applicant shall indicate the
type of RES.
(2)
The application submitted in accordance with sub-
regulation (1) shall be accompanied by a copy of the licence and, or
other relevant documentation issued by the Regulator for such purpose
in accordance with the Electricity Regulations as applicable, and the
applicable fee stipulated in item 1 of the Sixth Schedule. The
distribution system operator shall, subject to the requirements of the
network code, connect the generator to the network and provide the
necessary metering equipment once all applicable charges and fees are
paid.
(3)
(a)
A RES or CHP generation unit or energy storage
facility that is intended to be connected to the network that is not
equipped with automatic volt/var control and where the total
continuous steady state AC rating exceeds the 3.68kW (16 Amps) on
any phase, the customer shall request prior confirmation, in the
established manner, from the distribution system operator that such
capacity may be connected to the network
Provided that no prior confirmation from the distribution
system operator shall be required where the RES or CHP generator is
equipped with automatic volt-var control and the total continuous
steady state AC rating does not exceed 4.6kW (20 Amps) on any
phase
Provided further that the distribution system operator
may carry out a network connection study and depending on the
findings of such study, may reject or accept the request
Provided further that in the case of a rejection, the
distribution system operator shall provide the applicant with a written
justification for such rejection.
(b)
Where a network connection study is required to be
carried out in accordance with paragraph (a), the applicable fee
specified in item 8 of the Sixth Schedule shall be due by the customer.
(c)
Once the request for connection is approved by the
distribution system operator, the customer shall submit an application
for the required connection to the network;
(d)
Where the network connection study in paragraph (b)
results in a new connection or an upgrade of an existing connection
being required to connect the generation capacity, regulations 8, 10
and 12 shall apply for the upgrade or for the new connection.
(e)
The distribution system operator shall publish the
procedure, including the relative timeframes, for the connection of
RES generators, CHP and energy storage facilities to the network.
(4)
An increase in capacity of an existing RES or CHP or
energy storage facility shall be deemed to be a new application for the
purposes of these regulations and such application shall be subject to
the fees stipulated in item 2 of the Sixth Schedule.
(1)
Unless the distribution system operator
determines otherwise, having regard to the particular circumstances of
a case, and in accordance with objective criteria which are published in
advance, a new substation shall be required in any one (1) of the
following circumstances
(a)
within any new development with multiple
customers where the number of connection units is more than
eighteen (18), none of which requires a bulk network
connection, when any one (1) or more of the five (5) criteria set
out in regulation 9(4) are not satisfied;
(b)
for a network connection exceeding 60 Amps on
any phase when any one (1) or more of the criteria set out in
regulation 10(1) are not satisfied; or
(c)
with respect to a single building unit, when there
is no suitable low voltage connection point and no suitable
substation in the vicinity from which it is technically possible to
extend a network connection to the relevant single building
unit.
(2)
An applicant and, or developer, as applicable, shall be
bound to provide a suitable substation room within a development
where this is required in terms of this regulation.
(3)
Substations shall be financed as follows
(a)
in the case of a development with multiple
customers which development requires a substation in
accordance with regulation 9(6), the distribution system
operator shall
(i)
finance all costs relating to the civil works
and, or any structural alterations; and
(ii)
compensate the owner of the substation
land for providing the substation land, where this is
granted to the distribution system operator in full
ownership
Provided that customers within the development with
multiple customers that do not require a network connection exceeding
60 Amps on any phase shall pay the applicable fees for the connection
of each building unit to the network stipulated in the Sixth Schedule
Provided further that bulk network connections within
the multiple customers development shall be treated in accordance
with regulation 9(8)
Provided further that the distribution system operator
shall however retain the right to extend network connections from the
said substation to applicants outside the development wherein the
substation is situated, without making any additional payment or
compensation to the applicant;
(b)
in the case of bulk network connections
(i)
by
the
applicant
or
developer,
as
applicable; or
(ii)
by the applicant or developer, as applicable
and the distribution system operator on a cost-sharing
basis where, at the time the substation is commissioned,
the distribution system operator requires the utilisation of
the substation to provide connections to third parties. In
such a case the distribution system operator shall retain
the right to extend network connections from the said
substation to applicants inside or outside the
development wherein the substation is situated, without
making any additional payment or compensation to the
applicant;
(c)
in the case of a network connection for a single
building unit requiring a new substation, the substation shall be
financed entirely by the applicant and, or the developer, as
applicable.
(4)
The distribution system operator shall obtain title over
the substation land in accordance with the criteria set out in regulation
(5)
Notwithstanding the title held by the distribution system
operator over a substation and, or the substation land
(a)
the ownership of all the equipment and apparatus
contained therein shall be and remain of the distribution system
operator; and
(b)
access to the substation shall be given at all times
to personnel, officers and contractors of the distribution system
operator.
(6)
Where the distribution system operator and the applicant
and, or the developer, as applicable, share the substation costs, the cost
sharing shall be applied on a pro rata basis on the proportion of the
kVA load used by each of the distribution system operator on the one
hand, and the applicant and, or the developer, as applicable, on the
other.
(7)
Where the applicant and, or the developer, as applicable,
provides the substation land and, or civil works and, or any structural
alterations to the substation land, the applicant and, or the developer, as
applicable, shall be compensated in accordance with regulation 14.
(8)
The amount of compensation to be paid by the
distribution system operator for the relevant substation land shall be
determined as follows
(a)
any compensation paid by the distribution system
operator shall be added to the cost to connect and equip the
relevant substation for the purpose of cost sharing under
regulation 12(6), as the case may be;
ELECTRICITY CONNECTION AND SUPPLY
(b)
when the relevant substation has been totally
financed by the applicant and, or the developer, as applicable,
the applicant and, or the developer, shall be entitled to
compensation at the rate specified in item 11 of the Sixth
Schedule;
(c)
when the relevant substation has been totally
financed by the applicant and, or the developer, as applicable,
additional compensation as stipulated in item 10 of the Sixth
Schedule shall also be due to the applicant and, or the
developer, as applicable where the distribution system operator
decides to extend low voltage connections to third parties from
the relevant substation. The refund in accordance with this
paragraph shall continue to apply only for up to ten (10) years
from the commissioning date of the relative substation; or
(d)
when the substation has been financed on a cost-
sharing basis by the distribution system operator on the one
hand, and the applicant and, or the developer, as applicable, on
the other hand, the latter shall not be entitled to any of the
compensation referred to in paragraphs (b) and (c).
(9)
Civil works maintenance within the substation land and
the substation itself shall be carried out by the applicant and, or the
developer, as applicable or distribution system operator depending on
the title held by the distribution system operator over a substation at
any point in time
(a)
where the distribution system operator holds the
substation in full ownership it shall be responsible for civil
works maintenance; or
(b)
where the distribution system operator holds the
substation by title of lease or commodatum, the owner of the
substation land, the applicant and, or the developer, as
applicable shall be responsible for civil works maintenance.
(10) As long as the substation is used exclusively for the
applicant and, or the developer, as applicable, the energy consumption
shall be measured as follows
(a)
from the high voltage side of the transformer;
(b)
from both the high voltage side and low voltage
side of the transformer where this is required and the difference
between HV/MV meter reading and the sum of the individual
low voltage meters readings, shall be paid by the applicant and,
or the developer, as applicable; and
(c)
from the low voltage side of the transformer and
the connection losses shall be calculated as set out in item 20 of
the Sixth Schedule
Provided that the distribution system operator
may require customers to enter into a loss-sharing agreement to
regulate such matters.
(11) Extensions for network connections at 11kV or above
shall be charged at cost in addition to a high voltage contribution for
existing infrastructure use.
13. (1)
The distribution system operator shall acquire the
substation land on which a substation has been or is to be developed,
in full ownership, under title of lease, or on commodatum, at its
discretion, except where a specific title is required in accordance with
these regulations.
(2)
Where the substation is to be used to extend one (1) or
more connections to a person other than the owner of the substation
land, the distribution system operator shall acquire the substation land
by title of full ownership. Irrespective of the title which the
distribution system operator originally acquires over a substation,
where a substation is subsequently required or used to extend one (1)
or more connections to a person other than the owner of the substation
land, the distribution system operator shall, on demand made to the
owner of the substation land, acquire the substation land by title of full
ownership.
(3)
Any substation land over which the distribution system
operator does not hold any title, as at the date of the coming into force
of these regulations, shall be transferred to the distribution system
operator either by absolute ownership, lease or commodatum in
accordance with the requirements of this regulation, upon demand
made by the distribution system operator to the owner of the substation
land. In such cases, the value of the land shall be valued in accordance
with regulation 14.
(4)
The substation land acquired under title of lease or
commodatum, in accordance with these regulations shall, where such
substation land is no longer required by the distribution system
operator, be transferred back to the owner subject to the cessation of
the annual payment of rent or other recognised payment, as the case
may be, and subject to the repossession of the substation equipment by
the distribution system operator. No such rights shall subsist, where
the substation land was acquired by distribution system operator by
title of full ownership, in which case, the distribution system operator
shall remain the absolute owner thereof, provided that the distribution
system operator may elect to transfer ownership of the substation and
the substation land exclusive of any substation equipment in exchange
for fair compensation being paid to the distribution system operator.
(1)
In those circumstances where the distribution
system operator is required to compensate the owner for the transfer of
such substation land in full ownership, the value of the relevant
substation land shall be determined following a valuation made by a
perit in accordance with this regulation. If the valuation does not
satisfy the requirements referred to in this regulation, the valuation
shall be deemed invalid and shall be carried out again
Provided that the valuation shall be carried out by an
independent perit appointed as agreed upon by the distribution system
operator and the owner of the substation land.
(2)
Every valuation report prepared by a perit appointed by
the distribution system operator shall include the methodology used to
estimate the value. During the preparation of the valuation report, the
perit may seek the aid of other experts in different areas, which aid
shall then be indicated in the valuation report.
(3)
The valuation report made by the perit shall include the
following information
(a)
the date of the valuation;
(b)
the state of the property on the date of valuation;
(c)
the method used to make such valuations; and
(d)
the declaration of the perit and also other experts
involved in the valuation, stating that they do not have any
conflict of interest as of the date of the valuation.
(4)
The fees of the perit appointed externally by the
distribution system operator shall be calculated in accordance with
Tariff K of the Code of Organization and Civil Procedure
Provided that the individual fees for each valuation shall
not exceed the amount of two thousand and five hundred euro (€2,500)
for each report.
(5)
The fees of the perit shall be divided and borne equally
between the distribution system operator and the owner of the
substation land.
(1)
Electrical installations intended to be connected to
the network or any alterations, extensions or modifications on
electrical installations already connected to the network shall be
carried out and certified in accordance with the Electrical Installations
Regulations.
(2)
Effective balancing on a three phase connection within a
margin of ten per cent (10%) of the connected load shall be maintained
on all electrical installations for lighting, power, heating and RES for
any new loads or RES generators connected after the coming into force
of these regulations.
(3)
Any connection that is found to be unsafe shall be
suspended by the distribution system operator and shall only be
reconnected to the network upon certification by an authorised
provider that the electrical installation has been rendered safe. A
reconnection fee as stipulated in item 15 of the Sixth Schedule shall
apply.
(4)
Electrical installations, or parts thereof, duly connected
to and, or forming part of the distribution system may be tested by the
distribution system operator at any time and if such electrical
installation is found to be non-conforming with any requirements of
these regulations, the Electrical Installation Regulations, the network
code or EN 50549, the connection may be suspended by the
distribution system operator until the required alterations and repairs
have been carried out at the customer’s expense and duly certified by
an authorised provider
Provided that this sub-regulation shall also apply to the
network connections referred to in regulation 21(7).
(5)
Unless the non-conforming or defective electrical
installation is rendered compliant within one (1) month from the
performance of the test referred to in sub-regulation (4), the customer
shall be liable for the costs, which shall not be less than the fees
established in the Sixth schedule, incurred by the distribution system
operator in providing the connection, including any extension of its
infrastructure.
(6)
In the case of an electrical installation requiring re-
testing, the customer shall be charged the costs of such tests in
accordance with item 7 of the Sixth Schedule.
(7)
Loads such as electrical equipment, appliances or
machines above 1.5kW shall not be connected to the network unless
the said equipment is equipped to operate at a power factor not less
than 0.9 lagging unless otherwise stipulated in the network code.
(1)
A temporary installation shall have means of
disconnection and protection as stipulated in the Electrical
Installations Regulations.
(2)
Disconnection, protection and other necessary control
equipment for temporary installations shall be housed within an
insulated weatherproof enclosure (IP 54 or better) which shall also
house the electricity meter and supply fuses installed by the
distribution system operator. The applicant shall make arrangements to
have the insulated weatherproof enclosure installed close to the
distribution system operator supply point and beyond reach. The
customer and, or the applicant shall be responsible for the insulated
weatherproof enclosure, protection and control equipment together
with the wiring from the insulated weatherproof enclosure to the point
of consumption and shall ensure that the wiring does not present any
obstruction or danger to third parties.
(3)
The distribution system operator shall be responsible to
connect the input cable to the source of supply and to disconnect it
again after the event for which the application was made. Incoming
and outgoing cables shall enter and leave respectively the insulated
weatherproof enclosure from below and shall be glanded.
(4)
Temporary service connections to temporary installations
shall be provided for the duration and for the applicable fee as
stipulated in item 4 of the Sixth Schedule.
(1)
Any electrical equipment and motors shall comply
with the Network Code.
(2)
The starting and accelerating current drawn from the line
shall not exceed two-and-a-half times full-load current for motors
rated 1.5kW to 7.5kW, and twice full-load current for motors rated
7.5kW to 30kW
Provided that it shall be at the discretion of the
distribution system operator to specify the current-limiting conditions
under which a network connection shall be given for the purpose of
running motors rated 30kW or more
Provided further that where the instantaneous current
withdrawn from the distribution network including starting current and
accelerating current of motors exceeds the limits established by this
regulation, the connection of the equipment and, or motor shall be
subject to the approval of the distribution system operator.
(1)
Any officer or other person authorised by the
distribution system operator may at all reasonable times enter any
premises for the purpose of
(a)
installing new network connection;
(b)
modifying or repairing existing connection;
(c)
reading, testing, removing or replacing of meter;
(d)
inspecting, testing, disconnecting or removing any
network connection or other electrical plant including main
fuses owned by the distribution system operator;
(e)
carrying out inspections;
(f)
carrying out inspection of the premises for the
purpose of ascertaining the load installed in the premises;
(g)
carrying out any other act as may be deemed
necessary or desirable by the distribution system operator, in
the performance of its functions
(2)
The power of entry may not be exercised unless written
notice of at least four (4) working days has been given to the owner or
occupier of the premises. The said notice shall include the date,
approximate time and purpose for the visit and the contact details of
the representative of the distribution system operator.
(3)
The customer may request the distribution system
operator to reschedule the visit notified in sub-regulation (2)
Provided that the said request shall be made at least two
(2) working days before the scheduled visit and failing which, the
distribution system operator may, in its sole discretion, retain the
original date and time indicated in the notice sent to the customer in
sub-regulation (2)
Provided further that the new date shall not extend
beyond seven (7) working days from the original date, unless the
distribution system operator considers appropriate to extend the date
further, based on documentation or other evidence which demonstrates
that the customer shall not be able to be present. Notwithstanding the
foregoing, in no instance may the customer request a rescheduling
beyond the period of sixty (60) working days from the date of the
original appointment.
(4)
In the case of an emergency arising from faults in
electrical installations, entry may be made in accordance with sub-
regulation (1) without the notice required in sub-regulation (2) but
notice shall then be given as soon as possible after the occurrence of
the emergency.
(5)
Without prejudice to any other law, a person may only
exercise a power of entry conferred by these regulations on production
of a duly authenticated document showing his identity and his
authority to act on behalf of the distribution system operator. Such
person shall always carry and keep with him when visiting any
premises an identification card issued by the distribution system
operator
Provided that customers may refuse access to any person
who fails to produce such identification pass when visiting the
premises.
(6)
The requirements in sub-regulations (2), (3) and (4) shall
not apply to regulation 27.
(1)
The distribution system operator may require the
lessor of a leased premises to be bound in solidum with the lessee for
the regular payment of all amounts that may become due to the
distribution system operator.
(2)
The lessor who, in accordance with sub-regulation (1) is
bound in solidum with the lessee, shall be deemed to be the customer
for the purposes of these regulations.
(3)
Where a leased premises is occupied by two (2) or more
unrelated persons and is served by one (1) meter, the lessor shall be
deemed to be the customer for the purposes of these regulations.
(4)
A lessor who leases any premises supplied with
electricity by the distribution system operator for a period exceeding
three (3) months to persons not permanently resident in Malta, shall
give written notice thereof to the distribution system operator. The
notice shall contain the full name of the lessee, and the agreed period
of the lease, and any other information as may reasonably be requested
by the distribution system operator
Provided that where the lessor fails to give the said
notice, or the information contained in the notice is incorrect, the
lessor shall, without prejudice to the provisions of sub-regulation (5),
be liable in solidum with the lessee for any debt incurred by the lessee
in connection with the supply of electricity to the premises.
(5)
Where a premises supplied by the distribution system
operator is leased to any person, expressly or tacitly, by the week, by
the month or for less than three (3) months, or where the premises is
let for more than three (3) months but is only occupied by the tenant
for a period less than three (3) months, the lessor shall be liable in
solidum with the lessee for any debt incurred by the lessee in
connection with the supply of electricity to the premises.
(6)
For the purposes of regulation 6, the lessor of the
premises shall be deemed to be the customer and the distribution
system operator may require the relevant deposit and, or security from
the lessor, unless otherwise agreed by the distribution system operator.
(1)
Bills shall be issued to customers for such periods
as the distribution system operator may determine either generally or
with respect to specific customers or classes of customers.
(2)
The distribution system operator may request provisional
payment on account from any customer. The said provisional
payments shall be calculated on the basis of
(a)
the estimated average daily consumption of the
customer; or
(b)
the estimated average daily consumption of
customer of a similar class as that of the customer
Provided that the interval between such requests for
provisional payment may not be less than one (1) month and the
distribution system operator, on a request made by a customer, may
modify such requests for provisional payment in the light of the
circumstances of the particular case.
(3)
For the purposes of calculating any bill to be issued to
request payments from a customer, fractions of less than one cent in
the total amount due by the customer shall not be considered.
(4)
Interest at the rate of zero point seven five per cent
(0.75%) per month, calculated daily, shall be charged to customers on
all amounts due irrespective of the period to which the invoice refers if
the amount indicated in such invoice is not settled within forty-five
(45) days of the date specified therein
Provided that for all amounts still due at the expiry of the
aforementioned forty-five (45) days interest shall only be charged after
the fifteenth day, for the final thirty (30) days of the said forty-five
(45) day period, and thereafter, for each additional thirty (30) days or
part thereof.
(1)
Where a customer has not, within the requisite
period, paid all charges due by him to the distribution system operator
in respect of the supply of electricity to any premises or temporary
installation or the provision of an electricity meter, the distribution
system operator may suspend the supply
Provided that where the distribution system operator
exercises its discretion to suspend supply to and, or disconnect a
customer, such discretion shall be exercised in accordance with the
procedure published by the distribution system operator for such
purpose, to complement the provisions of this regulation
Provided further that the distribution system operator
shall not suspend supply of electricity to, nor disconnect, vulnerable
customers where this is prohibited in terms of the Electricity
Regulations.
(2)
Where payment of the charges referred to in sub-
regulation (1) are delayed for a period of more than three (3) months,
the distribution system operator may disconnect the network
connection and remove the meter.
(3)
Where the connection to a premises or temporary
installation is suspended pursuant to sub-regulation (1), the customer
shall be required to pay a reconnection fee in accordance with item 15
of the Sixth Schedule in order for the connection to be reinstated. The
distribution system operator shall reconnect the premises or temporary
installation within twenty-four (24) hours from when payment is
effected by the customer, except where this is not practical due to
reasons outside the distribution system operator’s control, such as
inclement weather conditions.
(4)
Where the distribution system operator is authorised by
sub-regulation (2) to disconnect any premises or temporary installation
or remove a meter, any officer or other person authorised by the
distribution system operator may at all reasonable times enter the
premises or other location where the temporary installation is situated
for the purposes of disconnecting the premises or temporary
installation or removing the meter
Provided that the said power of entry may only be
exercised if at least two (2) working days’ notice has been given to the
owner or occupier of the premises or other location.
(5)
Whenever access to the premises or other location, for
purposes of disconnection and removal of the meter in accordance
with sub-regulations (2) and (4) is not possible either because of
opposition offered from the customer, or due to the building or
temporary installation unit being found inaccessible on more than one
occasion, the distribution system operator shall be entitled to suspend
the connection without any previous notice by disconnecting the
electrical installation at the main source, whether this is located above
or below ground and the distribution system operator may recover any
expenses incurred in doing so from the customer.
(6)
The powers of the distribution system operator under
sub-regulations (1) and (2) may not be exercised with respect to any
amount which is disputed by the customer in good faith, and unless
written notice of not less than seven (7) days has been given to the
owner or occupier of the premises or temporary installation of the
distribution system operator’s intention to exercise the said powers.
(7)
Without prejudice to the other provisions of these
regulations, where the network connection of any customer and, or the
use thereof, is deemed to be detrimental to the services rendered by the
distribution system operator to other customers, including without
limitation in case of fluctuations of voltage and generation of
harmonics, such customer shall be required to install at its expense, the
necessary corrective and, or protective equipment within the relevant
premises or temporary installation and shall produce a test certificate
as may be required by the distribution system operator
Provided that this sub-regulation shall also apply to the
network connections to which the electrical installations referred to in
regulation 15(4) are connected.
(1)
The generation, electricity import from and, or
export to the distribution network for billing purposes shall be
measured by a meter, or metering equipment, provided and maintained
in proper working order by the distribution system operator
Provided that the distribution system operator shall
approve the installation of meters by an agent acting on its behalf
while retaining the right to test or request any test to ensure the proper
functioning of the said meters.
(2)
The meters shall at all times remain the property of the
distribution system operator.
(3)
The meter shall be installed in the premises or temporary
installation by the distribution system operator and shall be fixed in a
location which is convenient and easy to access, and as close as
reasonably practicable to the main entrance of the premises or
development as may be determined by the distribution system
operator.
(4)
If the distribution system operator considers it necessary,
safety measures shall be taken for the protection of the meter, which
measures shall be at the customer’s expense. The meters shall be
enclosed in a wooden or non-metal enclosure if placed indoors, or a
suitable insulated weatherproof enclosure if placed outdoors. Metal
parts that may form part of the enclosure shall be earthed to the
building earthing system. The meter installation height and space
requirements shall not be less than one metre (1m) and not more than
one point eight, five metres (1.85m) from the finished floor level. The
width requirements for every meter rated sixty Amps (60A) or less
shall be at least thirty centimetres (30cm). In case of bulk network
connections, a space of at least one (1) meter width and one point
eight-five meter (1.85m) length shall be provided for each service-
meter. The meters shall be segregated by use of separate enclosures
from any water meters
Provided that the requirement for electricity meters to be
segregated from any water meters shall, with respect to electricity
meters installed before the date of coming into force of these
regulations, be effective and enforceable twelve (12) months as from
the date of coming into force of these regulations.
(5)
Pre-payment meters shall be installed at the discretion of
the distribution system operator instead of the ordinary meters.
(6)
Where a customer supplies, or allows the supply of,
ELECTRICITY CONNECTION AND SUPPLY
electricity passing through such customer’s meter to another building
unit and, or premises and, or location and, or in any other manner or
for any other purpose outside the said customer’s building unit,
premises or location where the temporary installation or meter is
located and intended for, or an area already supplied with electricity
from another connection point or has physical access or intended to be
used from a premises supplied with electricity from another
connection point, the distribution system operator may disconnect the
network connection of the customer for such period as the distribution
system operator may determine or until such situation is rectified
Provided that this regulation shall not apply when such
electricity supply is to and, or from
(a)
a private garage which is adjacent to, or within the
precints of the residential premises occupied by the said
customer, whether or not it has direct access to and from such
residential premises, and is used solely by the said customer, or
persons residing in the residential premises, but no other person
has a right, on payment, to make use of the same garage;
(b)
outside areas authorised by the relevant competent
authorities to be used for commercial purposes, and which are
adjacent to the customer’s premises, such as, but not limited to,
outdoor seating areas forming part of a catering establishment,
provided that extensions of supply from a premises to an area
separated from that premises by a public road or third party
private property shall not be allowed;
(c)
an electricity supply extended from a building unit
hosting a ministry or government department to EV charging
points, authorised by the relevant competent authorities, located
on public pavements;
(d)
photovoltaic systems connected to meters in a
building unit which is not internally physically connected to the
roof hosting the photovoltaic system within the same building
block;
(e)
airconditioning outdoor units, water pressure
pumps and other electrical equipment located on the roof area
connected to meters in a building unit which is not internally
physically connected to the roof hosting the equipment within
the same building block
Provided further that in all the cases provided for in
paragraphs (a), (b), (c), (d) and (e) the electrical installation shall be
compliant with the Electrical Installations Regulations.
(7)
The distribution system operator may, in certain
circumstances and for a specified period, upon the request of a
customer, allow the supply of electricity through the customer’s meter
to one (1) or more premises and, or areas other than the customer’s
premises or temporary installation.
(8)
The distribution system operator may, upon the request
of a customer, provide supply other than through a meter in such
circumstances as may be prescribed. The said arrangement shall be
regulated by agreement between the customer and distribution system
operator, in accordance with terms agreed by both parties.
(9) The distribution system operator may, at its discretion,
give an unmetered supply to a customer pursuant to sub-regulation (8),
subject to the following conditions
(a)
the design load on each connection is at all times a
constant load;
(b)
the cyclic loading and the fast fluctuating loads
for each connection is in accordance with the network code or
other standards established by the distribution system operator;
(c)
the distribution system operator may, from time to
time, measure consumption to benchmark the system as a
whole, and to test the accuracy of calculations for billing
purposes; and
(d)
the customer pays the distribution system
operator, on a quarterly basis, an amount based on the
calculated consumption
Provided that the distribution system operator shall have
the right at the end of each calendar year to adjust any calculation for
that past calendar year made as provided for in paragraphs (a), (b), (c)
and (d) on the basis of any test carried out under paragraph (c) and to
charge the customer accordingly.
(10) A fee as stipulated in item 3 of the Sixth Schedule shall
be charged by the distribution system operator for the replacement or
removal of a meter, when such meter shall have been removed or
replaced at the request of the customer applying for its removal or
replacement.
(11) A customer may, at any time, by submitting the
appropriate application to the distribution system operator, request to
have the connection to its premises or temporary installation
disconnected and the meter registered on the customer’s name
removed
Provided that the customers shall remain responsible for
the payment of the meter charge and any amount due with respect to
consumption of electricity registered by the meter until such time as
either the meter is removed from the premises or temporary
installation by the distribution system operator or a declaration is made
by the registered customer that the connection is not in use from such a
date as shall be stated by the customer in the relevant application, and
after the customer has paid any amount that may be due under these
regulations with respect to that connection.
(12) A customer at whose request a connection has been
provided by the distribution system operator pursuant to these
regulations shall, without prejudice to the payment of applicable fees
in the Sixth Schedule, be required to pay to the distribution system
operator the expenses reasonably incurred in providing the connection
or undertaking the works required to provide the connection, where the
customer either fails to accept the installation of the meter within a
period of one (1) week after written notification to the customer of the
intention of the distribution system operator to install such meter, or
requires disconnection of the installation and removal of the meter
within a period of one (1) year from the date of connection.
(13) If a customer fails to give access to, or otherwise
prevents, the distribution system operator from removing the meter,
whether the meter is removed at the request of a customer or at the
discretion of the distribution system operator, the said customer shall
be liable for payment of a meter charge until the date of its removal.
(14) The meters shall be sealed by the distribution system
operator and such seals shall not be broken, damaged or tampered with
in any way by the customer. The distribution system operator shall be
entitled to charge a fee as stipulated in the Sixth Schedule if any meter
or seal is found upon inspection, to be damaged, tampered with or
missing. Furthermore, the customer shall be required to pay supply
charges based on an estimate of the previous consumption period.
(15) The meters shall be read periodically by the distribution
system operator in accordance with the Electricity Regulations.
(16) When a customer, after being given reasonable notice,
fails to provide access to a person authorised by the distribution
system operator for purposes of reading of the meter, the distribution
system operator, saving the provisions of regulations 18 and 21, shall
continue to charge the customer the meter charge as applicable but
shall not, in the absence of a reasonable explanation for such failure,
credit the customer with any free consumption for periods during
which the premises was not open for the taking of meter readings
Provided that the customer may provide the readings to
the distribution system operator for billing purposes, subject to the
distribution system operator being granted access to the metering
equipment to verify, and if required adjust, the readings provided by
the customer.
(17) If the customer fails or refuses to provide access to his
premises for purposes of reading the meter or to verify readings
provided by him, or if access for the same purpose is rendered difficult
or impossible by the customer, for a period exceeding two (2) months
from the notice provided for in sub-regulation (16), the distribution
system operator may suspend the relevant customer’s connection.
(18) Special readings of meters may be taken on working days
and non-working days at any time as the customer may require, and
the fees applicable in item 14 of the Sixth Schedule shall be charged.
(19) The distribution system operator shall test the meter upon
request by the customer, who may be present for such test. The
distribution system operator shall give the customer a written notice of
not less than two (2) working days by printed or electronic means of
the date and approximate time of the test. The notice shall also contain
the contact details of the representative of the distribution system
operator. If the test is to be carried out in a location other than the
customer’s premises, the test location shall also be indicated in the
notice.
(20) Save for manifest errors, the customer shall accept the
result of the test as final and the consumption of electricity from the
date of the request by the customer for the meter reading up to the date
on which the test is carried out, or the date of removal of the meter for
purpose of testing, shall be calculated in accordance with the results of
the test, and charged accordingly.
(21) When the meter which is tested at the request of a
customer is found to be working correctly, that is, within a limit of
over or under two point five percent (2.5%), the customer shall be
liable to payment of the relevant fee as provided for in item 13 of the
Sixth Schedule.
(22) A customer shall notify in writing the distribution system
operator immediately upon becoming aware that a meter is not
working correctly. The distribution system operator shall, as soon as
practicable repair or replace the meter, and a record of the reading of
the new meter at the time of its installation shall be given to the
customer.
(23) The consumption of electricity in respect of the period
between the reading immediately preceding the reading in relation to
which the meter is found to be defective and the installation of a new
meter or repair of the meter, as the case may be, shall be reckoned in
accordance with sub-regulations (24) or (25), as directed by the
distribution system operator.
(24) Where the distribution system operator directs that the
consumption provided for in sub-regulation (23) is to be reckoned in
accordance with this sub-regulation, the said consumption shall be
reckoned on the basis of the average daily rate of consumption
(a)
during the corresponding period of the last
preceding year;
(b)
during the period between the two (2) readings
immediately preceding the reading in relation to which the
meter was found to be working incorrectly; or
(c)
during the period between the date of the
installation of the new meter or the repair of the meter, as the
case may be, and a subsequent date which shall be determined
by the distribution system operator.
(25) Where the distribution system operator directs that the
consumption provided for in sub-regulation (23) shall be reckoned in
accordance with this sub-regulation, the said consumption shall be
reckoned on the basis of the average daily rate of consumption during
the period between the date of installation of the meter which was
found to be working incorrectly, or the date on which the customer
became accountable with respect to the premises or temporary
installation, whichever is the later, and the last day on which the meter
was working correctly, as may be determined by the distribution
system operator
Provided that in the case of a customer who has changed
residence, where the distribution system operator directs that the
consumption shall be reckoned in accordance with this sub-regulation,
the average daily rate of consumption in respect of the corresponding
period of the last preceding year at the place in respect of which such
customer was last accountable prior to the change of residence, shall
be the basis on which consumption shall be reckoned.
(1)
The main fuse shall be supplied and shall be
placed in such position and location as may be determined by the
distribution system operator.
(2)
The main fuse box or busbar chamber shall be sealed by
the distribution system operator. The distribution system operator shall
be entitled to charge a fee as stipulated in Sixth Schedule if any fuse
box is found upon inspection, to be damaged, tampered with or
missing.
(3)
The main fuse box or busbar chamber shall at all times
remain the property of the distribution system operator.
(4)
Where the customer requires the distribution system
operator to effect repairs consisting only in the replacement of one (1)
or more fuses, or where the fault is due to the customer’s internal
electrical installation, a fee shall be charged in accordance with item
17 of the Sixth Schedule.
(5)
Whenever access to the premises, for the removal of a
main fuse is not possible either on account of the opposition of the
customer, or on account of the premises being found closed on more
than one (1) occasion, the distribution system operator may, after
giving prior written notice by printed or electronic means to the
customer, suspend the network connection by disconnecting the
installation at the mains, whether overhead or underground. The
distribution system operator shall be entitled to charge the customer
for the costs of any work, including excavation works, carried out to
enable the disconnection and removal of the main fuse.
(1)
The distribution system operator shall submit, for
the approval of the Regulator, a set of tariffs for the connection to the
distribution system, and distribution and supply of electricity in
relation to any calendar year. The tariffs shall be such that they provide
sufficient revenue to the distribution system operator and shall in
particular
(a)
cover the costs of the distribution system operator,
including operational, administrative and financial costs,
incurred in connection with the generation, distribution and
supply of electricity, and may include but not be limited to costs
relating to operational asset impairment, non-recoverable tax
and duties, excluding corporate tax on profits, and accumulated
losses;
(b)
be such as to allow the distribution system
operator to meet periodic repayments on long-term
indebtedness to the extent that any such repayment exceeds the
provisions for depreciation;
(c)
provide a reasonable return on equity; and
(d)
be designed to promote end-use energy efficiency
in the domestic and residential sector, as appropriate.
(2)
Tariffs shall be applied to all customers on a non-
discriminatory basis and the distribution system operator shall not
exercise undue preference, or undue discrimination towards any
person or class of persons similarly situated unless the distribution
system operator, having regard to the place and time of connection, the
quantity of energy supplied, the required load and power factor, the
purpose for which the connection is intended and, or utilised, and any
other relevant circumstance, deems it necessary to exercise
preferential or discriminatory treatment.
(3)
The distribution system operator shall, together with the
proposed tariffs, submit to the Regulator all necessary documentation
in support of its proposals, including the methodologies underlying the
calculation of the tariffs and any other information as the Regulator
may request. Any request from the Regulator for the submission of
additional information shall be made within three (3) months from
submission of the proposal by the distribution system operator.
(4)
Any information submitted to the Regulator by the
distribution system operator in accordance with this regulation shall be
considered as confidential and economically sensitive and shall be
handled accordingly.
(5)
The Regulator shall either approve or reject the proposed
tariffs and shall notify its decision to the distribution system operator
within six (6) months from the date of submission of the proposal.
(6)
Without prejudice to sub-regulation (7), where the
Regulator intends to reject the proposed tariffs, it shall notify the
distribution system operator to this effect and shall give the
distribution system operator the opportunity to make representations to
the Regulator prior to making its decision.
(7)
The Regulator may only reject the proposed tariffs when
such tariffs fail to comply with the criteria provided for in sub-
regulation (1). Any decision to reject shall clearly state the reasons for
the rejection.
(8)
Without prejudice to sub-regulation (9), when the
proposed tariffs are rejected by the Regulator pursuant to sub-
regulation (7), the distribution system operator shall take account of
the reasons for rejection set out in the decision and re-submit the tariffs
to the Regulator for approval.
(9)
The Administrative Review Tribunal shall have
jurisdiction to hear and determine appeals from decisions of the
Authority made under these regulations in terms of the Administrative
Justice Act, which appeal shall be filed by not later than twenty (20)
days from the service of the said Authority’s decision, wherein the
aggrieved party shall specify the reasons on the basis of which the said
decision of the Authority should be cancelled or modified.
(10) In determining an appeal, the Administrative Review
Tribunal shall, inter alia, take into account
(a)
the principles established in this regulation;
(b)
the tariff structure proposed by the distribution
system operator and any and all information provided to the
Regulator in connection with such tariffs; and
(c)
any relevant correspondence between the
Regulator and the distribution system operator, and any
legitimate expectation created by law, regulation, or by the
Regulator in favour of the distribution system operator
Provided that any party to the proceedings before the
Administrative Review Tribunal who feels aggrieved by a decision of
the said Tribunal, may appeal to the Court of Appeal on a point of law in
accordance with the Code of Organization and Civil Procedure.
(11) The distribution system operator may submit, for the
approval of the Regulator, a methodology which shall be used for the
calculation of tariffs other than those established by these regulations.
Together with the proposal, the distribution system operator shall
provide all relevant information in relation to the proposed
methodology, including the intended uses of the tariff. Where the
Regulator requires additional information from the distribution system
operator, it shall make the request for such information within three (3)
months from the submission of the proposal.
(12) Where the distribution system operator submits a
proposal in accordance with sub-regulation (11), the provisions of sub-
regulations (4) to (10) shall apply.
(13) The distribution system operator may enter into special
agreements with one (1) or more customers for the charging of rates
and tariffs other than those established by these regulations.
(14) Where, in any special agreement, the rate or tariff to be
charged is different from the tariffs established by these regulations or
is not a variable rate or tariff calculated in accordance with a
methodology approved by the Regulator in accordance with sub-
regulations (11) and (12), the distribution system operator shall obtain
prior approval of the methodology by the Regulator before entering
into the special agreement.
(15) The supply of electricity to a residential, non-residential,
and domestic premises shall be charged in accordance with the First
Schedule, Second Schedule and Third Schedule, respectively.
(16) Notwithstanding the provisions of any other law, the
distribution system operator shall, at any time and in its absolute
discretion, while having regard to the provisions of these regulations,
determine whether a premises is to be deemed a residential premises, a
non-residential premises or a domestic premises for the purposes of
these regulations.
(17) A customer may submit an application to connect one (1)
or more premises to be used solely and regularly as private dwellings,
as may be confirmed by documentary proof, and register such units of
residence as a domestic premises
Provided that supply to the common parts of a
development consisting entirely of building units used exclusively for
residential purposes may also be submitted for registration as domestic
premises
Provided further that, unless otherwise authorised by the
distribution system operator, a customer shall only be entitled to
register as a domestic premises one (1) primary residence, one (1)
secondary residence and one (1) garage which does not exceed fifty
(50) square metres in area and is used exclusively for private and non-
commercial purposes.
(18) The customers may apply to the distribution system
operator to register individuals having their primary residence in Malta
on a residential premises service in relation to the said primary
residence
Provided that no individual shall be registered on more
than one (1) residential premises service at the same time, and that no
individual shall be registered on a garage or on the common parts of a
development as a residential premises service.
(19) A premises which is not registered as a domestic
premises or as a residential premises in accordance with this
regulation, or in relation to which there is no application for
registration as a domestic premises or a residential premises in
accordance with this regulation, shall be considered as a non-
residential premises, unless determined otherwise by the distribution
system operator.
(20) The following provisions shall apply with respect to the
registration of persons on a premises classified as domestic premises
or residential premises
(a)
the customers shall furnish in writing to the
distribution system operator, within such time as may be
stipulated by the distribution system operator, any information
together with any supporting document which may be required
for the purpose of such registration;
(b)
the customers shall notify the distribution system
operator in writing of any change in the circumstances forming
the basis on which the registration is made, and such
notification shall be made by not later than one (1) month from
the occurrence of such change in circumstances;
(c)
any change in the number of persons registered on
a domestic premises or on a residential premises shall be taken
into account, for the purpose of such registration, from the date
of the first periodic meter reading after the change in number of
persons occurs or the date on which the distribution system
operator is notified in writing of such change, at the discretion
of the distribution system operator;
(d)
a person residing in a premises may apply to the
distribution system operator for a premises, other than that in
which such person resides, to be registered as a domestic
premises;
(e)
an application shall be made in such form or
procedure as may be prescribed by the distribution system
operator from time to time, and which shall be completed in full
and submitted to the distribution system operator in the manner
so prescribed; and
(f)
every arrangement made in accordance with this
sub-regulation shall be valid until the 31st December of the
year in which it was made or for which it was renewed, and it
shall be deemed to have been renewed for the next following
year, unless the customer, not later than the last day of
November of the year in which the arrangement is in force,
gives notice in writing to the distribution system operator that
the customer does not want the said arrangement to be renewed.
(21) For the purposes of these regulations, the charging of
electric vehicles for non-residential premises, metered separately, shall
be billed in accordance with the Fourth Schedule.
(22) For the purposes of these regulations, the charging of
electric vehicles in residential premises and domestic premises,
metered separately, shall be billed in accordance with the Fifth
Schedule.
The distribution system operator may enter into an
agency agreement with any person so that the said person would be
appointed as agent of the distribution system operator for purposes of
carrying out, on behalf of the distribution system operator, the tasks
prescribed in the agency agreement. The said tasks may include but
shall not necessarily be limited to the installation and maintenance of
cables and or meters, meter testing, fault repairs, regular meter
readings, collection of dues and transfer of dues to the distribution
system operator.
The officers and employees of the distribution system
operator in the performance of their functions in accordance with the
Act, these regulations or any other law, shall not be liable for any loss
or damage suffered by any person by reason of anything done or
omitted to be done in good faith in the course of the performance of
ELECTRICITY CONNECTION AND SUPPLY
their functions under these regulations.
(1)
Where duly authorised representatives of the
distribution system operator are reasonably satisfied that an electricity
meter and, or any apparatus which is part of the electrical installation
or connection, has been tampered with, or that a customer or a person
has obtained an unlawful connection, or that a customer or a person is
responsible for the theft of electricity, the distribution system operator
shall have the right to immediately access the meter and parts of the
electrical installation or connection and
(a)
immediately suspend the connection to the meter,
electrical installation or connection that was tampered with, or
to the customer or person it determines has obtained the
unlawful network connection or for the theft, until such time as
the customer or person concerned settles all dues to the
distribution system operator or, if such person disputes the
allegation and, or the amount due as determined by the
distribution system operator, until such time as the dispute is
settled;
(b)
require in writing from the customer or persons
concerned payment of the amount which is calculated by the
distribution system operator to be due to it for the supply of
electricity obtained in the unlawful manner provided for in this
regulation, which amount shall be based on a maximum period
of five (5) years, with interests calculated on the basis of the
rate established in regulation 20(4), and interest shall continue
to accrue until all amounts due are settled;
(c)
require in writing from the customer or persons
concerned the additional payment of a settlement charge for
potential damages suffered by the distribution system operator
equivalent to two hundred percent (200%) of the amount due
for the supply of electricity obtained in an unlawful manner;
(d)
require in writing from the customer or persons
concerned the charge due to the distribution system operator for
the removal of the meter which has been tampered with and,
where applicable, the re-installation of the meter; and
(e)
where duly authorised representatives of the
distribution system operator are reasonably satisfied that an
electricity meter has been tampered with through the indication
stickers or the security alarm, an administration fee as
established in item 18 of the Sixth Schedule shall be due by the
customer.
(2)
The distribution system operator shall not be obliged to
restore the connection until such time as all amounts payable are
settled by the customer or persons concerned or until a written
agreement acknowledging the amounts due to the distribution system
operator and setting out a schedule for payment of such amounts, has
been made with the distribution system operator. Where the amounts
due to the distribution system operator are equal to, or in excess of five
thousand euro (€5,000), the written agreement shall be in the form of a
constitution of debt received before a notary public in Malta.
(3)
The distribution system operator shall not be liable for
any damages which may be incurred by the customer or persons
concerned whilst undertaking any action required for removing the
meter or other parts of the electrical installation, or any other action
which is ancillary thereto.
(4)
The findings in accordance with sub-regulation (1)(a)
and the sums due to the distribution system operator in accordance
with sub-regulation (1)(b), (c) and (d) shall be served in writing to the
customer or to the person concerned either by registered mail or by
judicial letter, and any customer or person wishing to contest the
findings or any amount due may file a claim in accordance with the
Fourth Schedule to the Arbitration Act
Provided that any criminal proceedings that may be
instituted against the customer or person concerned shall be
independent of the procedures instituted under this regulation.
(5)
In case of a repeat offender in that the said person had
been found by the distribution system operator on one (1) previous
occasion to be responsible for theft of electricity or of having obtained
an unlawful supply of electricity in accordance with this regulation,
the settlement charge to make good for any potential damages suffered
by the distribution system operator shall amount to twice the charge
which would have been due had the said offence been the first offence
of such person.
(6)
In the event that an offender is a repeat offender in that
the said person had been found by the distribution system operator on
at least two (2) previous occasions to be responsible for theft of
electricity or of having obtained an unlawful supply of electricity in
accordance with this regulation, the settlement charge to make good
for any potential damages suffered by the distribution system operator
shall amount to the charge which would have been due had the said
offence been the first offence multiplied by the number of times that
the offender was found responsible for theft of electricity or of having
obtained an unlawful supply of electricity.
(7)
Without prejudice to regulation 27(1), in the event that a
meter is found broken, the replacement cost provided for in item 19 of
the Sixth Schedule shall be due by the customer.
(8)
Any person who, without reasonable excuse refuses to
allow access to any premises occupied by such person to an officer or
other person authorised by the distribution system operator for any
purpose set out in regulation 18(1), or hinders or obstructs an officer or
other person so authorised in the performance of any act permitted by
regulation 18(1), shall be guilty of an offence against these regulations
and shall be liable to a fine (multa) of not less than two hundred euro
(€200) and not more than one thousand euro (€1,000) for each
occasion on which refusal of access, hindrance and, or obstruction
occurs.