SALE OF ELECTRICITY GENERATED FROM COGENERATION UNITS REGULATIONS
Table of Provisions (17)
Statutory Text (17 Articles)
SUBSIDIARY LEGISLATION 545.29
SALE OF ELECTRICITY GENERATED FROM
COGENERATION UNITS REGULATIONS
26th May, 2015
LEGAL NOTICE 170 of 2015, as amended by Act XXV of 2015, Legal
Notice 370 of 2016, 119 of 2017 158 of 2018, 172 of 2019, 17 and 297 of
2021, 87 of 2022 and 45 of 2023.
(1) The title of these regulations is the Sale of Electricity
generated from Cogeneration Units Regulations.
(2) The purpose of these regulations is to regulate the sale of
electricity generated from cogeneration units and supplied to the
distribution system operator.
(Regulation 7)
Total maximum cogeneration unit electricity capacity MWe that
may be approved for the payment of the proxy for the market price
per annum for any electricity generated and sold to the distribution
system operator from such cogeneration unit capacity shall be
3MWe each year.
(1) Unless otherwise stated in these regulations, the
definitions in the Act shall apply.
(2)
In these regulations, unless the context otherwise requires
"the Act" means the Regulator for Energy and Water Services
Act;
"annual", "annum" or "year" means the period of time commencing
on the 1st January and ending on the 31st December of each year;
"change of use of premises" means the change in the
classification of a premises in terms of these regulations whether
domestic or residential or non-residential or institutional
household;
"co-generation" means the simultaneous generation in one
process of thermal energy and electrical or mechanical energy;
"cogeneration unit" means a unit that is able to operate in
cogeneration mode;
"commissioned" means the first time a cogeneration unit is put
into operation, following the establishment of operational
readiness;
"consumed on site" means consumed on the same premises
where the cogeneration unit is installed;
"distribution" means the transport of electricity on high voltage,
medium voltage and low voltage distribution systems with a view
to its delivery to consumers, but not including supply;
"distribution system" means all the interconnected technical
facilities used for conveying electricity to final customers;
"distribution system operator" means a person responsible for
o p e r a t i n g , e n s u r i n g t h e m a i n t e n a n c e o f a n d , i f n e c e s s a r y,
developing the distribution system in a given area and, where
applicable, its interconnections with other systems and for ensuring
the long-term ability of the system to meet reasonable demands for
the distribution of electricity;
"domestic premises" means premises which include private
dwellings with no persons registered with the distribution system
operator as residing in them such as second homes, or private
garages and common areas including roofs, stairs, terraces, gardens
to buildings which are used solely for private dwellings;
"electricity from cogeneration" means electricity generated in a
process linked to the production of useful heat and calculated in
accordance with the methodology laid down in the First Schedule
of the Energy Efficiency and Cogeneration Regulations;
"installation operator" means the holder of the licence to
generate electricity from the cogeneration unit;
"institutional households" shall include the following premises
(a) healthcare institutions such as premises used as a
hospital, nursing home or as any institution providing
medical or nursing care;
(b) institutions for retired, elderly or disabled persons,
including premises used as a home for the retired or
elderly persons or persons with any disability;
(c) educational institutions including premises used as a
boarding school or for similar purposes;
(d) care institutions including premises used as
orphanages, shelter homes, open centres for refugees
or for similar purposes;
(e) religious institutions including premises used as
convents, retreat houses, or for similar purposes;
(f)
military institutions such as military barracks;
(g) other institutions including premises used as boarding
houses, penal or correctional facilities or for similar
purposes;
"kVAh" means kilo Volt Ampere hour;
"kW" means kilo Watt;
"kWh" means kilo Watt hours;
"metering equipment" means the electricity meters provided by
the distribution system operator including smart meters, any
voltage and current transformers and any other associated
equipment and wiring required to measure the quantity of
electricity supplied or exported;
"the Minister" means the Minister responsible for resources;
"MWe" means the electricity capacity rating of a cogeneration
unit;
"nominal installed capacity" means the nominal electricity rating
MWe as defined on the rating plate of the cogeneration unit;
"non-residential premises" means a building or plot of land
which is used wholly or mainly for the purpose of conducting an
economic activity, but does not include any building such as private
garages or common areas to buildings which are used solely as
private dwellings;
"operational readiness" means the capability to function in
accordance with design and specifications;
"p remi ses code" m eans a uniq ue num ber assigned by t he
distribution system operator identifying a particular premises with
its individual service address and served with electricity and, or
water;
"proxy for the market price" shall have the same meaning as
assigned to it in the Electricity Regulations;
"the Regulator" means the Regulator for Energy and Water
Services as established by the Act;
"renewable energy sources" means renewable non-fossil energy
sources, that is, wind, solar, geothermal, wave, tidal, hydropower,
biomass, landfill gas, sewage treatment unit gas and biogases;
"residential premises" means any premises used solely and
regularly as a private dwelling where at least one person resides but
does not include institutional households;
"scheduled" means in accordance with the scheduled programme
of ARMS Limited for the taking of periodic electricity meter
readings;
"smart meters" shall have the same meaning as in the Electricity
Supply Regulations.
(Regulations 4, 5, 6, 7 and 11)
Repealed by Legal Notice 45 of 2023.
These regulations shall apply to electricity exported to the
distribution system from any cogeneration unit equipped for the
recuperation and utilization of the thermal energy produced and
producing electricity from fossil fuel or renewable energy, installed
either in a residential or domestic premises or non-residential or
institutional household and connected to the distribution system
either directly or indirectly with the appropriate protection and
metering equipment provided by the distribution system operator.
(1) In the case of any cogeneration unit commissioned and
connected to the distribution system in terms of regulation 3, the
installation operator may
(a)
either sell all the electricity generated by the
cogeneration unit to the distribution system operator
and be paid by the distribution system operator the
proxy for the market price established under the
Electricity Regulations; or
(b) generate electricity primarily for own consumption
and be paid by the distribution system operator the
proxy for the market price established under the
Electricity Regulations for any excess electricity
generated and exported to the distribution system
Provided that the consumption of the electricity
generated, in accordance with this paragraph, may only
be done by the installation operator who is a registered
consumer with the distribution system operator with
respect to the same premises code where the cogeneration
unit is installed.
(2)
The electricity generated -
(a) from cogeneration units separately installed shall be
separately metered; and
(b) from solar photovoltaic installations or other
renewable energy sources connected with the same
premises code as cogeneration units installed in terms
of sub-regulation (1) shall also be separately metered.
(3) In the case where the installation operator takes the option
available in terms of sub-regulation (1)(b), the distribution system
operator shall install metering equipment to measure all the
electricity generated by the cogeneration unit in addition to the
import/export metering equipment.
Without prejudice to the generality of the foregoing, subject
to the attainment of the consent of the distribution system operator,
the installation operator may install metering equipment to measure
all the electricity generated by the cogeneration unit as an
alternative to the installation of metering equipment by the
distribution system operator for the purpose of measuring all the
electricity generated by the cogeneration unit.
(4) An installation operator who generates electricity from a
cogeneration unit connected with the same premises code as solar
photovoltaic installations installed primarily for own consumption and
exporting any excess electricity to the distribution system and, or other
installations generating electricity from renewable energy other than
solar photovoltaic installations, being all installed with the option to
generate primarily for own consumption, shall for any excess
electricity generated and exported to the distribution system be paid by
the distribution system operator at the proxy for the market price
established under the Electricity Regulations.
(1) The payment for the electricity produced from the
cogeneration unit and sold to the distribution system operator shall
be due from the date when the cogeneration unit is first connected
to the distribution system as provided in regulation 3.
(2) The payment of the proxy for the market price established
under the Electricity Regulations shall be subject to the approval of the
cogeneration capacity as required in these regulations.
(3) The payment effected by the distribution system operator to
installation operators for electricity generated by cogeneration
units in accordance with regulation 3 shall be deemed to be
inclusive of any compensation for loss of revenue arising from any
planned and unplanned interruption which impedes the export of
electricity from the cogeneration unit to the distribution system.
Any installation operator, who in force of these regulations,
is being paid or may be paid the marginal cost, however so
described, shall, as from the entry into force of this regulation, be
paid the proxy for the market price.
(1) The eligibility for the payment for any electricity
generated by the co-generation unit and sold to the distribution
system operator is subject to
(a) the cogeneration unit obtaining all the necessary
authorisations, licences or permits from the relevant
competent authorities and the distribution system
operator;
(b) the cogeneration unit is equipped with metering
equipment that measures all the electricity generated
by the cogeneration unit in addition to the import/
export metering equipment;
(c) the installation operator’s compliance at all times with
the obligations established in these regulations, the
Network Code and all other applicable legislation.
(2) The payment of the proxy for the market price established
under the Electricity Regulations shall only be applicable up to the
total amount of electricity sold to the distribution system as
measured by the metering equipment provided by the distribution
system operator and to the extent of the cogeneration unit MWe
capacity approved by the Regulator
Provided that the approval of cogeneration MWe capacity
by the Regulator shall be subject to the overall cap for the MWe
capacity that may be approved in any year as established by the
Electricity Regulations.
The total maximum cogeneration electricity capacity MWe
that shall be eligible for the sale of electricity to the distribution
system operator and the payment of the proxy for the market price
established under the Electricity Regulations by the distribution
system operator for exported electricity from such cogeneration
unit after the entry into force of these regulations shall be that
established in the First Schedule.
(1) The distribution system operator may set off amounts
due by an installation operator for the supply of electricity against
amounts due to the installation operator for the exporting of
electricity under these regulations
Provided that such setting off shall only be permissible
where the claims are undisputed or are certain, liquidated and due.
(2) Where a set-off arrangement between the installation
operator and the distribution system operator is in place and the
amounts due to the installation operator for the exporting of
electricity referred to in sub-regulation (1) are in excess of the
amounts due by an installation operator for the supply of electricity
by the distribution system operator, the distribution system
operator shall credit the installation operator the balance due by
means of a credit note
Provided that the installation operator may request to be
paid the balance due by means of such credit note, after four
consecutive scheduled billing periods for the supply of electricity
by the distribution system operator to the installation operator, have
elapsed.
(3) Where no set-off agreement exists between the installation
operator and the distribution system operator and the amounts due
to the installation operator for the exporting of electricity are in
excess of the amounts due by an installation operator for the supply
of electricity by the distribution system operator, the distribution
system operator shall credit the installation operator the balance
due, which shall be paid to the installation operator within sixty
days from the scheduled reading of the metering equipment
Provided that the distribution system operator shall carry
out the reading of the metering equipment within intervals of at
least two months, to be reckoned as from the date of the first
reading of the metering equipment.
Installation operators shall
(a) submit such information
as
the Regulator may
reasonably require;
(b) inform the Regulator and the distribution system
operator, in the form and manner they may reasonable
require, if the cogeneration units have been
disconnected or transferred, sold or in any form
modified in such a way as to change their
performance;
(c)
comply at all times with the provisions of
the applicable legislation, notification, authorisation,
licence conditions and Network Code as approved by
the Regulator;
(d) make available to the distribution system operator and
to the Regulator data required to be recorded for the
purposes of these regulations.
Where an installation operator is deceased, or by reason of
any other act or event, permanently ceases to be the installation
operator, payment for electricity generated by the cogeneration unit
and exported to the distribution system under these regulations may
be transferred to the new installation owner
Provided that
(a) the new installation operator informs the distribution
system operator and the Regulator of such change in
ownership in such form and manner as they may
establish, together with any documentary proof and
information that they may establish for such purposes;
(b) the new installation operator takes over all obligations
held by the previous installation operator;
(c) such person shall not be considered by the distribution
system operator and, or the Regulator as a new
installation operator if such installation operator is not
in compliance with any other law, permit or any
requirement in relation to the cogeneration unit.
(1) Modifications relevant to the cogeneration unit
installation arising from -
(a) change of use of the premises where the cogeneration
unit is located;
(b) change of account holder;
(c) transfer of the cogeneration unit to another different
premises with same use;
(d) transfer of cogeneration unit to another different
premises with different use;
(e) change of the option from "sell all the electricity
generated" to "generate electricity primarily for own
consumption" or vice versa,
shall only be made after obtaining the necessary permits and
clearance from the Regulator and the distribution system operator.
(2) In the case where an installation operator increases the
generation capacity of a cogeneration unit which is connected to
the distribution system, the payment of the proxy for the market
whole unit as extended, provided that the installation operator
obtains all the necessary authorisations, licences and permits.
(3) The changes listed in sub-regulations (1) and (2) shall
become applicable for the payment of the marginal cost from the
date of the first meter reading taken after the date of submission of
an application to the distribution system operator to approve and
take the necessary action.
Installation operators shall not be entitled to any tradable
certificates including tradable guarantees of origin for electricity
generated from the cogeneration unit.
The provisions dealing with access, inspection,
modification or tampering of meters found in the Electricity Supply
Regulations shall mutatis mutandis apply to installation operators
under these regulations in the same manner as provided for in those
regulations.