(1) The title of these regulations is the Electrical
Installations Regulations.
(2) The scope of these regulations is to regulate the provision
of services related to electrical installation works and to establish
an authorisation scheme for service providers carrying out such
activity.
(3) These regulations are being made for the safeguarding of
the public interest and public safety. Any requirements contained
therein including those relating to authorisations and to services are
made for overriding reasons relating to the public interest.
Amended by
L.N. 426 of 2012;
Regulation 5
XXV. 2015.41;
L.N. 45 of 2021;
L.N. 283 of 2024.
Authorisation A Authorisation Application form A
Authorisation B Authorisation Application form B
The relative application form may be obtained from the Regulator for Energy and
Water Services website: http://www.rews.org.mt/#/en/home
Along with this application form, the applicant shall attach and submit
A copy of the applicant’s legally valid identification document;
A letter issued by the Registrar of Examinations showing a pass in the
Wireman’s examination as required for the application to be processed
or any other accepted certificate of qualification as listed above;
Other certificates and testimonials relating to practical experience in
electrical installation, signed by the authorised persons under whom the
experience was attained
In the case of Authorisation A, testimonials shall be endorsed by a person holding
at least a Authorisation A; and
In the case of Authorisation B, testimonials regarding experiences shall be endorsed by
either an Authorisation B holder or a warranted electrical engineer
Provided that warranted electrical engineers applying for an Authorisation B
with at least fifteen (15) years of experience in local electrical installation works may
provide a self-declaration instead of such testimonials.
(1) Unless otherwise stated in these regulations, the
definitions in the Act shall apply.
(2) For the purpose of these regulations and unless the context
otherwise requires
"the Act" means the Regulator for Energy and Water Services
Act;
"ap plicatio n" means an ap plicatio n whi ch is m ad e to t he
Regulator for the issue of an authorisation by the Regulator to a
person for carrying out the activity of electrical installation works
or to a person authorised to exercise such activity;
"authorised provider" means a provider authorised by the
Regulator to carry out the installation, alteration, extension and
certification of single phase electrical installations only or to carry
out the installation, alteration, extension and certification of both
single and three phase installations by virtue of an authorisation
issued in terms of these regulations or a service provider who is
authorised to operate under any law in force in a Member State or a
state which is a participant to the European Economic Area;
"backup equipment" means the additional hardware and control
system other than the anti-islanding protection that disconnects the
generators and/or energy storage from the distribution system and
changes over to a backup operation mode;
"backup operation mode" means the disconnection from the
distribution system and continuing operation of a generator or
e n e rg y s t o r a g e i n t h e e v e n t o f t h e l o s s o f p o w e r f r o m t h e
distribution system with complete effective isolation from the
distribution system while in this mode of operation;
"building unit" shall have the same meaning as assigned to it in the
Electricity Connection and Supply Regulations
"Commission Regulation (EU) 2016/631" means Commission
Regulation (EU) 2016/631 of 14 April 2016 establishing a network
code on requirements for grid connection of generators;
"customers" means wholesale and final customers of electricity;
"distribution system operator" shall have the same meaning as
under the Electricity Regulations;
"electrical installation" or "electrical installations" means a system
of electrical wires and equipment intended for conveying electricity as
well as the disconnecting apparatus located on the customer’s side of
the electricity service meter;
"electrical installation works" means the installation, alteration,
extension and certification of an electrical installation;
"electricity service meter" means the electricity meter and any
associated equipment installed by the distribution system operator
or by the redistributor to register the consumption and maximum
demand on the customer’s premises;
"energy storage" means, in the electricity system, the deferring
of the final use of electricity to a moment later than when it was
generated, or the conversion of electrical energy into a form of
energy which can be stored, the storing of such energy, and the
subsequent reconversion of such energy into electrical energy or
use as another energy carrier;
"energy storage facility" means, in the electricity system, a facility
where energy storage occurs.
"establishment" means the actual pursuit of an economic activity
by a service provider for an indefinite period and through stable
infrastructure from where the business of providing services is
actually carried out;
"IET Wiring Regulations" means the Requirements for Electrical
Installations issued by the Institution of Engineering and Technology
(I.E.T.) - BS 7671 18th Edition, exclusively as published and
applicable on 1st July 2018;
"interface protection system" means an automatic switch that
disconnects the energy storage facility from the distribution system in
the event of loss of supply from the distribution system or deviation of
the voltage or frequency at the supply terminals from values declared
for normal supply;
"kW" means one kilo watt;
"lifelong learning" means all general education, vocational
education and training, non-formal education and informal learning
undertaken throughout life, resulting in an improvement in
knowledge, skills and competences, which may include
professional ethics;
"Member State" means a member state of the European Union;
"Minister" means the Minister responsible for energy;
"MSA EN 50549-1" means MSA EN 50549-1 Requirements for
generating plants to be connected in parallel with distribution
networks - Part 1: Connection to a LV distribution network -
Generating plants up to and including Type B;
"Malta Qualifications Recognition Information Centre" means
the Malta Qualifications Recognition Information Centre as
established under the Mutual Recognition of Qualifications Act;
"multi customer facility" means a facility consisting of more
than one single phase and, or three phase customers;
"Network code" shall have the same meaning as under the
Electricity Regulations;
"new generator" means a power generating module which is not
considered existing within the meaning of Article 4 of Commission
Regulation 2016/631;
"Registrar of Examinations" means the Registrar of
Examinations as appointed under the Education Act;
"the Regulator" means the Regulator for Energy and Water
Services as established by the Act;
"service provider" means any natural person who is a national of
a Member State, or any legal person established in a Member State,
who offers or provides the service of electrical installation works;
"single phase electrical installation" means an electrical
installation designed for alternating current using a system of
wiring consisting of one live wire or phase, a neutral wire and a
separate protective earth conductor;
"technical committee" means a committee established by the
Regulator under the Act and which is composed of competent and
qualified persons for the purpose of assessing and verifying
whether an applicant for an authorisation has sufficient knowledge
and expertise with regard to providing the service of electrical
installation works under these regulations;
"temporary installation" means an electrical installation not of a
permanent nature and may include decorative street lighting, public
entertainment facilities, outdoor mobile units, cranes and
associated construction sites;
"three phase electrical installation" means an electrical
installation designed for alternating current using a system of
wiring consisting of three live wires or phases, a neutral wire and a
separate protective earth conductor;
"the Treaty" means the Treaty establishing the European Union;
"warranted electrical engineer" means an electrical engineer
holding a warrant in accordance with the Inġiniera Act
Provided that for the purposes of these regulations, wherever
there is a reference to a warranted electrical engineer, such warranted
engineer shall also be required to be the holder of an Authorisation B
after the 30th June 2025.
Amended by
XXV. 2015.41;
Regulations 12, 13, 14, 15
L.N. 283 of 2024.
Mandatory Certification
(a) All new installations / re-wires requiring connection / reconnection to
the distribution system operator network;
(b) All alterations to existing installations involving changes to the wiring
between the distribution system operator connection point/meter and the
customer’s main distribution point;
(c) All electrical installations where the distribution system operator has
disconnected supply with the customer’s consent for a period greater
than six months;
(d) As otherwise required by the Electricity Connection and Supply
Regulations and the network code with respect to requirements posed on
electrical installation before their connection to the distribution system
operator network, as amended and approved by the Regulator from time to
time;
(e) All new electrical installations and alterations/extensions to existing
ELECTRICAL INSTALLATIONS
installations shall be verified and certified as complying with the
relevant IET Wiring Regulations and these regulations.
This declaration shall be in the form of a completion certificate recognised by the
Regulator and issued by the authorised provider who constructed and/or tested the
electrical installation (or alterations or extensions to an existing installation) in
question.
Where an electrical installation contains a sub-system provided by another
installer/contractor, a sub-system completion certificate shall be issued by an
installer/contractor in accordance with the relevant IET Wiring Regulations or these
regulations. All such sub-systems shall be covered by sub-system completion
certificates.
(1) These regulations shall apply to all electrical wiring
installations, alterations and extensions at voltage levels 230/400
(+/- 10%) Volts within buildings, factories, places of entertainment,
industrial and sport complexes, social and religious places, or any
other place where an electrical installation is required except for
categories excluded from the scope of these regulations in sub-
regulation (3).
(2) These regulations shall also apply to extensions or
alterations to extensions or alterations to an existing installation.
(3)
These regulations shall not apply to the following
(a) the system of distribution of electricity to the public;
(b) marine craft;
(c) motor vehicles, except those to which the IEE
regulations concerning caravans or mobile units are
applicable;
(d) mobile and fixed offshore installations;
(e) aircraft;
(f)
lightning protection systems.
Electrical installations under these regulations shall be
carried out with the proper materials and in compliance with the
relevant regulations and standards.
(1) The installation, alteration, extension and certification
of single phase and three phase electrical installations shall require
an authorisation. There shall be two classes of authorisations for
electrical installation works
(a) authorisation A for the installation, alteration,
extension and certification of single phase electrical
installations; and
(b) Authorisation B for installation, alteration, extension
and certification of single phase electrical installations
and three phase electrical installations rated less than
300Amps per phase. The holder of an Authorisation B
may also carry out installation, alteration, extension
work on three phase electrical installations rated equal
to or more than 300Amps per phase but may not
certify the said electrical installations
Provided that such holder of an Authorisation B may
only certify such installation works when acting under the supervision
of a warranted electrical engineer and who shall also endorse such
certification
Provided further that such an endorsement shall not be
necessary when the Authorisation B holder certifying the installation
is also a warranted electrical engineer under the Inginiera Act.
(2) Persons who are eligible to apply for an authorisation under
these regulations shall be the following
(a) any person who has passed an examination held for
such purpose by the Registrar of Examinations, and
having completed one year of practical experience in
single phase electrical installation works in the case of
applicants for the issue of an authorisation A and two
years practical experience in three phase electrical
installation works in the case of applicants for the
issue of an authorisation B;
(b) any person qualified as an electrical engineer and
possessing a valid warrant recognized in Malta, and
having one year of experience in single phase
electrical installation works for authorisation A and
two years experience in three phase electrical
installation works for authorisation B; and
(c) any person, although not possessing the qualifications
mentioned in paragraphs (a) and (b), who has the
relevant and equivalent certification and has obtained
a recognition of qualifications statement from the
Malta Qualifications Recognition Information Centre
Provided that with regard to any applicant service
provider from any other Member State, applicant
service providers, in possession of relevant
qualifications, shall obtain an evaluation report on
comparability of qualifications from the Regulator;
(d) any person who has attained the age of eighteen (18)
years at the time of application.
(3) Examinations referred to in sub-regulation (2)(a), shall be
held at least once a year on a date or dates to be fixed by the
Registrar of Examinations and as follows
(a) a notice of the holding of an examination shall be
published in the Gazette not less than two months
before and shall be made public in advance;
(b) the syllabus for the examinations shall be set by the
Regulator; and
(c) any revised syllabus shall be published two years
before any examination is set.
(4) Where the Regulator deems that there exists a substantial
difference regarding professional qualifications in Malta and the
applicant’s professional qualifications and training, the Regulator
shall provide the applicant with the opportunity to prove, by
completing an aptitude test or undergoing an adaptation period, that
the applicant does possess the necessary qualifications.
(5) The applicant may choose between completing an aptitude
test or undergoing an adaptation period.
(6) In the case of an aptitude test, the Regulator shall provide
the applicant with the list of subjects not covered by his
professional qualifications and training.
(7) The aptitude test shall be made in English and the costs
shall be borne by the applicant.
(8) Where an adaptation period is chosen by the applicant, the
applicant shall be required to exercise the activity being pursued
under the responsibility of an authorisation A or an authorisation B
holder, as the case may be, for a limited period of time, which in
case of an authorisation A application, shall be of not more than
one year and in the case of an authorisation B application shall be
of not more than two years, from the date notified by the applicant
as being from when such adaptation period shall commence.
(9) The Regulator shall determine the content of the activities
to be covered during the adaptation period and the method of its
assessment.
(10) It shall be the responsibility of the applicant to make
arrangements with any authorisation holder A or authorisation
holder B to undergo the adaptation period, with or without pay
Provided that, the Regulator shall make available, upon a
request being made by the applicant, a list of authorisation holders
together with their contact details for the purpose of allowing the
applicant to make his own arrangements to undergo the adaptation
period.
(1) Any person, who prior to the entry into force of these
regulations, was engaged in any activity relating to wireman’s
licence A for electricians authorised to carry out single phase
installations only and wirem an’s licence B for electricians
authorised to carry out single and three phase installations and is in
possession o f a valid l icence to d o so u nder the Electricity
Connection and Supply Regulations, may continue to perform such
activities as authorised under existing licence conditions until the
31st December, 2010 or until the grant of a new authorisation,
whichever is the earlier
Provided that any such person shall be required to apply
with the Regulator for a new applicable authorisation as listed in
regulation 5(1) within two months from the day of the sending of a
notice by the Regulator to apply for such an authorisation
Provided further that any such person shall comply with
such authorisation conditions as established in the new
authorisation that may be issued by the Regulator with effect from
such date that the Regulator may establish.
(2) Authorisations issued under these regulations prior to the
31st December 2010, shall be automatically renewed for a further
three years after that date. The applicable annual authorisation fee
shall be due and paid pro rata until that date to the Regulator.
(1) Any person who wishes to apply for an authorisation A
or for an authorisation B, shall submit an application in writing to
the Regulator in such form and manner as the Regulator may
prescribe.
(2) A non-refundable application fee of twelve euro (€12) shall
be paid to the Regulator together with the application for an
authorisation.
(3) The Regulator shall communicate to the applicant in
writing within a reasonable time, which shall not be of more than
three months from the date of receipt of a valid application, any
decision taken concerning an application for an authorisation or
any valid reason impeding the Regulator to reach such a decision.
(4) The Regulator may modify, amend, replace, add or delete
any authorisation condition as the Regulator may consider to be
reasonably justified.
(5) The application shall be accompanied by the documents
listed in the First Schedule.
(6) Any person who applies for the issue of an authorisation in
accordance with this regulation shall sit for an interview before the
technical committee and shall have to be recommended by the
technical committee before becoming eligible to be issued with the
authorisation applied for. In the case that the applicant is not
recommended by the technical committee following the said interview,
the applicant may re-apply to sit for another interview after the lapse
of six (6) months from the date of the last interview.
(1) The holders of an authorisation issued under these
regulations, shall, subject to compliance with authorisation
conditions, have their authorisation automatically renewed.
(2) An authorised provider shall, every three years reckoned
from the 1st day of January of the year in which their authorisation
is granted, pay an authorisation fee of thirty-five euro (€35) in case
of being the holder of an authorisation A and seventy-euro (€70) in
case of being the holder of an authorisation B.
(3) If any authorisation fee payable in accordance with sub-
regulation (2) is not paid within thirty (30) days, an additional fee of
twelve euro (€12) shall also be due to the Regulator as a late payment
fee in addition to the fee due.
(4) If the authorisation fee remains unpaid and any
documentation required for renewal is not submitted, the Regulator
shall inform the authorised provider by registered mail about the
failure to pay the said fee and, or to provide the necessary
documents. The authorisation shall be revoked if the authorisation
fee remai ns unp aid and, or th e req uired do cum en ts are not
submitted after thirty (30) days from the date on which the
communication has been sent by registered mail. Any person who
has had the authorisation revoked and wants to be re-issued with an
authorisation shall be required to submit an application for such
purpose and to be recommended following an interview before the
technical committee. In considering any such application, the
Regulator may take into account the previous failure of the
applicant to pay the authorisation fee and, or to submit the required
renewal documents and of any explanation regarding that failure
which the applicant may submit to the Regulator
Provided that it shall be the duty of the authorised provider to
make available to the Regulator the correct contact details or to accept
or collect the registered mail. Failure to provide the said correct
contact details or to accept or to collect the registered mail shall
exonerate the Regulator from contacting the said authorised provider
by registered mail. In such cases, the Regulator shall publish on its
website a notice directed to the authorised provider instead of using
registered mail.
(5)
Repealed by Legal Notice 283 of 2024.
(6) The Regulator may publish on its website a notice containing
the names and details of authorised providers whose authorisation has
been revoked.
The holder of an authorisation B shall be deemed to be in
possession of an authorisation A.
(1) Without prejudice to the Mutual Recognition of
Qu alification s Act, and t o the Reco gnit ion of P ro fessi onal
Qualifications Regulations, any person established in another
Member State may practice the activity of carrying out electrical
installation works for the purposes of these regulations in Malta on
a temporary and occasional basis provided that such person
(a) is legally established in another Member State, for the
purpose of practising the activity of carrying out
electrical installation works in that Member State; and
(b) has practiced the activity of carrying out electrical
installation works for at least one year during the ten
years immediately preceding the provision of services
where such activity is not regulated in that Member
State.
(2) Persons referred to in sub-regulation (1) shall inform the
Regulator by means of a written declaration to be made in advance
which shall include the following
(a) proof of the nationality of the applicant;
(b) an attestation certifying that the applicant is legally
established in a Member State for the purpose of
pursuing the activities concerned and that such
applicant is not prohibited from practicing the activity
of carrying out electrical installation works even
temporarily, at the moment of delivering the
attestations;
(c) evidence of professional qualifications recognised by
the Malta Qualifications Recognition Information
Centre; and
(d) where applicable, any means of proof that the
applicant has pursued the activity of carrying out
electrical installation works for at least one year
during the previous ten years immediately preceding
the provision of services.
(3) Where the Regulator deems that there is a substantial
difference between the professional qualifications of the applicant
and any of the qualifications and experience required under these
regulations, to the extent that the difference is such as to be
h a r m f u l t o p u b l i c h e a l t h o r s a f e t y, a n d t h a t i t c a n n o t b e
compensated by the service provider’s professional experience or
knowledge, skills and competences acquired through lifelong
learning formally validated to that end by a relevant body, the
Regulator shall give the applicant the opportunity to show, in
particular by means of an aptitude test, that he has acquired the
knowledge, competence or experience which he lacks.
(4) The Regulator shall assess the temporary and occasional
nature of the provision of the service of carrying out electrical
installation works on a case by case basis.
(5) No later than one month after receipt of the declaration and
accompanying documents, referred to in sub-regulation (2), the
Regulator shall inform the applicant of its decision
(a) not to check his professional qualifications; or
(b) having checked his professional qualifications, to
either require the applicant to take an aptitude test or
to allow the provision of services.
(6) Where there is a difficulty which would result in delay in
taking a decision under the paragraph (b) of sub-regulation (5), the
Regulator shall notify the applicant of the reason for the delay
within the same deadline. The difficulty shall be solved within one
month of that notification and the decision finalised within two
months of resolution of the difficulty.
(7) In the event that the Regulator does not give its decision
within the period referred to in sub-regulation (6), the service of
carrying out electrical installation works falling under this
regulation may be provided.
(8) A person exercising the services under this regulation shall
be deemed to be an authorised provider and the provisions of these
regulations shall apply to him in the same manner and to the same
extent as with any other authorised provider.
(1) The Regulator may revoke the authorisation or may
suspend the authorisation for a determinate period of time for any of
the following breaches
(a) breach of these regulations;
(b) failure to comply with the requirements of these
regulations;
(c) failure to comply with the requirements of an
authorisation issued by any authority having
jurisdiction for electrical installation works;
(d) failure to rectify any non-compliance of an electrical
installation or electrical equipment pursuant to a written
warning issued by the Regulator, or any other authority or
by a distribution system operator;
(e) failure to pay any fee due in accordance with these
regulations;
(f)
failure to comply with any direction issued by the
Regulator.
(2) An authorisation suspended in accordance with this
regulation shall be reinstated if the breach or failure is rectified in
accordance with these regulations, authorisation conditions or as
directed by the Regulator.
(3) A person whose authorisation has been revoked shall be
required to re-apply for the authorisation and to sit for an interview
ELECTRICAL INSTALLATIONS
so as to be recommended by the technical committee to be re-issued
with an authorisation
Provided that a re-application for the issue of an authorisation
after a revocation in accordance with this regulation may only take
place after the lapse of six (6) months from the date of revocation of
the authorisation by the Regulator.
No person, other than persons duly authorised under these
regulations, shall certify electrical installations included in the
Second Schedule.
(1) An authorised provider before certifying an electrical
installation, shall in particular ensure that
(a) the insulation resistance between conductors and to
earth is not below that stipulated in the IET Wiring
Regulations;
(b) all single pole switches, circuit breakers and fusible
cut-outs are inserted in the phase conductors only;
(c) where necessary, installation circuits are to be
sectionalised into final circuits and that socket outlets
are wired in final circuits entirely distinct from the
lighting circuits;
(d) all appliances and accessories, unless of the all
insulated type, are effectively earthed and when
portable are connected to earth through three-pin
plugs;
(e) all metal forming part of the electrical equipment in
bathrooms, other than current carrying parts, and all
other exposed fixed metal-work in such rooms
including piping and bath and associated metal fittings
but excluding window frames, door locks and other
similar furnishings are connected together by an earth
continuity conductor which is permanently connected
to earth;
(f)
all accessories and electrical fixtures fitted in
bathrooms are inaccessible to aperson sitting in or on a
bath or under a shower;
(g) steel conduit or metal trunking is not used as an earth
continuity conductor. A separate insulated earth
continuity conductor shall be used with all types of
conduit and trunking installations;
(h) all metal pipes forming part of the water installation
on the premises should bebonded together and
connected to earth;
(i)
the earthing of equipment is in full compliance with
these regulations;
(j)
every accessory or fitting in garages unless of a totally
enclosed type is fixednot less than one metres and
twenty centimetres above floor level.
(2)
Unless otherwise specified in these regulations, electrical
installations shall comply with the IET Wiring Regulations and with
generally accepted principles of good design and safe practices
Provided that the installation of Surge Protection Devices
(SPDs) shall not be mandatory.
On completion of an electrical installation, including the
earthing system and after its testing, a form shall be filled by the
authorised provider or the warranted electrical engineer, as the case
may be, in the manner approved by the Regulator. The authorised
provider or the warranted electrical engineer shall give a copy of
this form together with a schematic and wiring layout of the
electrical installation, including type and composition of circuits
and the means and location of protection and isolation, to the owner
of the electrical installation, certifying compliance with these
regulations.
The design of an electrical installation rated at 300 Amps per
phase or more and the final endorsement of the certification on
completion of the said electrical installation shall be carried out by a
warranted electrical engineer.
(1) Electrical installations, including the earthing system,
shall be periodically inspected and tested by an authorised provider
or a warranted electrical engineer, as the case may be. The owner of
the electrical installation shall ascertain that this installation is so
tested.
(2) The authorised provider shall recommend to the owner of
the electrical installations the frequency of the tests in sub-
regulation (1).
In the case of a temporary electrical installation the
authorised provider shall ensure that
(a) the electrical installation is provided with the
necessary disconnection, protective and other control
equipment housed in an insulated weatherproof
enclosure (IP 54 or better) in particular for outdoor
installations;
(b) electrical installations in public
entertainment
facilities and outdoor mobile units
(i)
are provided with a suitable means of
disconnection and over-current and earth
leakage protection which should be a residual
current device with an operating current not
exceeding 30mA immediately after the
electricity service meter;
(ii) are provided with an effective temporary
earthing system and all exposed metal that could
come into contact with current carrying
conductors is properly bonded to the earth
electrode;
(c) electrical installations for cranes and construction
ELECTRICAL INSTALLATIONS
sites
(i)
are equipped with suitable means for
disconnection and over current and earth
leakage protection (residual current type with an
operating current not exceeding 100mA)
immediately after the electricity service meter;
(ii) hand and mobile tool circuits and security
lighting shall be protected by means of residual
current type devices with operating current not
exceeding 30mA;
(iii) an earth electrode shall be provided and all
exposed metal that can accidentally come into
physical contact with the current carrying
conductors must be bonded to the earth
electrode;
(d) in the case of decorative street lighting installations
(i)
metal clad equipment such as fuse-switches shall
not be used in any part of the installation;
(ii) that reasonable care is taken such that no
installation component could come in physical
contact with any metal structure and objects;
(iii) where it is necessary to support and suspend the
installation components from such structures
and objects as in sub-paragraph (ii) suitable non-
conductive material is used.
Generators intended to be used as standby to supply a fixed
electrical installation which is also connected to the electricity
distribution system
(a) shall be provided with a two pole (for single phase
installations) or a four pole (for three phase
installations) change over switch;
(b) shall not, under no circumstances, come in direct or
indirect connection with the electricity distribution
system.
Generators operating in parallel with the electricity
distribution system shall
(a)
comply with the Network Code; and
(b) a new generator shall comply with Commission
Regulation EU) 2016/631and unless specified
otherwise in the Network Code, shall also comply with
MSA EN 50549-1 or an equivalent standard thereof
when so considered by the Standards and Metrology
Institute within the Malta Competition and Consumer
Affairs Authority;
(c) be provided with backup equipment when designed to
operate in backup operation mode which backup
equipment shall use hardware that physically breaks
the connection with the distribution system. Solid state
relays or other semiconductors to break the connection
are not permitted
Provided that the protection of the internal electrical
installation shall remain functional also when supplied
through the generator operating in backup operation
mode.
The anti-islanding protection in all cases shall
automatically disconnect from the distribution system
in the event of loss of supply from the distribution
system, and/or deviation of voltage and/or frequency
from normal supply conditions.
(d) have appropriate signage indicating the presence on
the premises of a generator equipped with Backup
operation mode function.
An energy storage facility operated in parallel with the
electricity distribution system shall include an interface protection
system
(a) that complies with the Network Code; and
(b) which, unless the Network Code provides otherwise,
complies with MSA EN 50549-1 or an equivalent
standard thereof when so considered by the Standards
and Metrology Institute within the Malta Competition
and Consumer Affairs Authority;
(c) which shall be provided with backup equipment when
designed to operate in backup operation mode which
backup equipment shall use hardware that physically
breaks the connection with the distribution system.
Solid state relays or other semiconductors which break
the connection are not permitted.
Provided that the protection of the internal electrical
installation shall remain functional also when supplied
through the energy storage facility operating in backup
operation mode.
The interface protection system in all cases shall
automatically disconnect from the distribution system
in the event of loss of the supply from the distribution
system, and/or deviation of voltage and/or frequency
from normal supply conditions.
(d) which has appropriate signage indicating the presence
on the premises of an energy storage facility equipped
with backup operation mode function.
(1) Single phase electrical installations and three phase
installations not exceeding 60 Amps per phase shall be provided
with a main double pole switch fuse or circuit breaker or four pole
switch fuse or four pole circuit breaker as applicable immediately
after of the electricity service meter to control the supply input to
the installation.
(2) Fuses and circuit breaker devices shall be graded to provide
over current discrim inatio n with the fuses provi ded by t he
electricity supply service.
(3) The main switch fuse or circuit breaker shall be
mechanically linked so as to effect simultaneous disconnection of
all live conductors phases and neutral.
(4) An overvoltage protective device to detect and protect
against sustained overvoltage shall be installed immediately after
the main switch fuse or circuit breaker
Provided that in the case of a multi-customer facility it shall
be acceptable to install the over voltage protective device at the
supply intake point in the customer’s premises
Provided further that any circuits supplied upstream of the
over voltage protection device shall also be protected by an over
voltage protective device.
(5) One (1) or more residual current devices protecting
individual sub-circuits separately of the appropriate type, taking
into account the presence of any direct current leakage components
and their magnitude with means for periodic inspection and with a
tripping current of 30mA to earth shall be installed immediately
after the over voltage protection device
Provided that in the case of a multi- customer facility it
shall be acceptable to install a residual current device of the
appropriate type, taking into account the presence of any direct
current leakage components and their magnitude, with a tripping
current of not more than 100mA, or a tripping current of 30mA
with time discrimination, near the metering point, followed by a
residual current protection device or more of the appropriate type
taking into account the presence of any direct current leakage
components and their magnitude, protecting individual subcircuits
separately with a tripping current of 30mA, at the supply intake
point in the customer’s premises or parallel circuits supplied from
the same customer meter
Provided further that where in the opinion of the authorised
provider the unintended interruption of supply gives rise to greater
risks, such as the de-energising of life support and emergency
equipment, alternative arrangements for the sub-circuit supplying
such equipment may be made by the authorised provider
Provided further that in the case of circuit-specific loads
with high earth leakage currents, such as in the case of circuits
supplying electronic equipment, which may cause unintended
interruptions of supply, a residual current protection device of the
appropriate type, taking into account the presence of any direct
current leakage components and their magnitude and if necessary
with a tripping current higher than 30mA, as recommended by the
manufacturer, which shall not however exceed 300mA, may be
used at the supply intake after the overvoltage protection to protect
that specific load only, with any other parallel and, or downstream
sub-circuits, including common parts, in particular, those circuits
supplying electrical loads accessible to users to be protected by one
(1) or more residual current devices with a tripping current of
30mA
Provided further that cables supplying specific loads
protected by a residual current device, of the appropriate type,
taking into account the presence of any direct current leakage
components and their magnitude, with a tripping current exceeding
30mA shall be laid in protective conduit or trunking that provides
appropriate mechanical protection. A metallic armoured cable may
also be used as an alternative to the aforementioned arrangement
Provided further that the authorised provider shall ensure that
an appropriate warning sign is provided indicating that the equipment is
protected with a residual current device with a tripping current higher
than 30mA.
(6) In the case of electrical installations in multi-consumer
facilities referred to in sub-regulation (5), the circuit between the main
switch fuse or circuit breaker and the individual customer’s premises
shall consist of main supply cables that run in a separate and individual
protective conduit or in an individual trunking system dedicated for
electricity supply wiring, to the individual customer’s premises.
Separate and independent metallic armoured cable may also be used as
an alternative to the aforementioned arrangement.
(7) Any compartment used in the electrical installation shall be
of the non metallic and non-hygroscopic type.
(1) Three phase installations exceeding 60 Amps per
phase shall be provided with a four pole switch fuse or a four pole
circuit breaker as the intake of the electricity supply service.
(2)
The supply intake shall be adequately protected at least by
(a) an over current device;
(b) an earth fault protection device.
(3) Fuses and circuit breaker devices shall be graded to provide
over current d iscrim inati on w ith the f uses p rov ided b y th e
electricity supply service.
(4) The main switch fuse or circuit breaker shall be
mechanically linked so as to effect simultaneous disconnection of
all live conductor phases and neutral.
(5) Over voltage protective device or devices that detect and
protect against sustained overvoltage may be installed on
downstream sub-circuits.
(6) Residual current device or devices of the appropriate type,
taking into account the presence of any direct current leakage
components and their magnitude, with a tripping current of 30mA
shall be installed on downstream sub-circuits supplying electrical
loads accessible to users
Provided that where in the opinion of the authorised
provider the unintended interruption of supply gives rise to greater
risks, such as the de-energising of life support and emergency
equipment, alternative arrangements for the sub-circuit supplying
such equipment may be made by the authorised provider
Provided further that in the case of circuit- specific loads
with high earth leakage currents, such as in the case of circuits
supplying electronic equipment, which may cause unintended
interruptions of supply, a residual current protection device of the
appropriate type, taking into account the presence of any direct
current leakage components and their magnitude and if necessary
with a tripping current higher than 30mA, as recommended by the
manufacturer, may be used to protect that specific load only
Provided further that cables supplying specific loads
protected by a residual current device, of the appropriate type,
taking into account the presence of any direct current leakage
components and their magnitude, with a tripping current exceeding
30mA shall be laid in protective conduit or trunking that provides
appropriate mechanical protection. A metallic armoured cable may
also be used as an alternative to the aforementioned arrangement
Provided further that the authorised provider shall ensure that an
appropriate warning sign is provided indicating that the equipment is
protected with a residual current device with a tripping current higher than
30mA.
The authorised provider shall ensure that the electrical
installation is provided with a suitable and reliable connection to
earth by
(a) providing an independent connection to earth through
one (1) or more earth electrodes as deemed appropriate,
suitably installed and tested, solidly connected by means
of an insulated and mechanically protected copper
conductor cable of adequate cross-sectional area to the
main earthing terminal to which the protective conductor
of the electrical installation shall be connected;
(b) in addition to the requirement in paragraph (a), the
electrical installation earthing system may also be
connected to the earthing point in a distribution system
operator substation supplying the installation, when
this is technically feasible.
Where an extension of the electrical installation from a
building unit is extended outside the boundaries of the building unit
and where this is allowed in accordance with the Electricity
Connection and Supply Regulations, the authorised provider shall
ensure that
(a)
where the extension of the electrical installation
from a building unit is used to supply a private garage, a manual
mechanical means of isolation of all phases and neutral wire
shall be provided in an accessible position and immediately
after the entrance of the garage. The wiring of the extension
leading to the garage shall pass only through common areas;
(b)
where the extension of the electrical installation is
extended outside the boundaries of a building unit to supply
outside facilities or equipment, a manual mechanical means of
isolation of all phases and neutral wire shall be installed on the
outside wall of the building unit in the immediate vicinity of the
area or equipment being serviced. The isolation means shall not
be of the remotely electrically operated type
Provided that the wiring of the extension shall
(i)
be supplied through a dedicated circuit
provided with the necessary protection;
(ii)
be provided
with
the
appropriate
mechanical protection;
(iii)
not be of obstruction in any way; and
(iv)
be clearly indicated and documented if
buried
Provided further that the earthing system of any
conductive structures or street furniture located within two meters (2)
from the area or equipment being supplied from the premises shall be
bonded with the earthing system of the said premises. The testing of
the earthing system bonding shall be part of the routine testing of the
electrical installation of the premises including the extension;
(c)
where extension of the electrical installation from
a building unit forming part of a building block is extended to
connect electrical equipment on the roof of the same building
block within which the building unit is physically located but
not internally and physically interconnected with the roof
(i)
the said extension shall be supplied through
a dedicated circuit provided with the necessary
protection;
(ii)
the said extension shall be provided with a
manual mechanical means of isolation of all phases and
neutral wire provided in the common area leading to the
roof and located next to the electricity service meters
supplying the units in the block. The isolation means
shall not be of the remotely electrically operated type;
(iii) the earthing system of the building unit
which is not physically interconnected to the common
area of the building block shall be linked to the earthing
system of the block. The testing of the earthing system
bonding shall be part of the routine testing of the
electrical installations physically found within the block;
and
(iv) the means of isolation shall be properly
labelled and documented to indicate the sources of supply
and the location of the electrical equipment serviced. The
earthing system bonding shall be properly labelled and
documented.
(1)
The authorised provider shall ensure that motor
loads above 1.5kW are in compliance with the Electricity Connection
and Supply Regulations.
(2)
Devices inhibiting automatic re-starting of motors shall
be provided wherever in the opinion of the authorised provider the said
restart may cause danger or damage to equipment.
(3) Equipment with three phase motors shall be provided with
phase failure protection and with incorrect phase sequence protection
where in the opinion of the authorised provider an incorrect phase
sequence may cause danger or damage to equipment.
(1) The Regulator may appoint persons duly authorised by
it to inspect electrical installation works, installed, altered,
extended and certified, by an authorised provider, or installed,
altered or extended under the supervision of a warranted engineer
or certified by a warranted engineer.
(2) In the cases when the person appointed in terms of sub-
regulation (1) investigates a report on malpractice by an authorised
provider or a warranted engineer, an inspection shall take place in
the presence of the authorised provider or the warranted engineer
Provided that if the authorised provider or the warranted
engineer fails to be available for the inspection for three times,
after being notified by the Regulator, such inspection may take
place without the presence of the authorised provider or the
warranted engineer
Provided further that an inspection may take place even
without the authorised provider or the warranted engineer being
present in case of imminent danger being present.
(3) If any malpractice is discovered or defects are found in the
inspected electrical installation, the Regulator shall issue a
directive to the authorised provider or the warranted engineer, to
rectify at his expense the defects or the result of the malpractice,
within a definite period of time as required by the Regulator.
(4) The failure by the authorised provider or the warranted
engineer to rectify at his expense the defects or the result of the
malpractice within the definite period of tim e required the
Regulator, may give rise to the imposition by the Regulator of an
administrative fine of two hundred euro (€200) for each day of non-
compliance.
(5) If any non-compliance with these regulations or malpractice
results from the inspection and, or testing of the electrical installation,
the costs incurred by the Regulator for carrying out the inspection and,
or testing shall be borne by the authorised provider or the warranted
engineer, as the case may be, which shall be due as a civil debt to the
Regulator.
(1) The Regulator shall provide each authorised provider
with an identification card which shall serve as prima facie
evidence that the holder is an authorised provider authorised under
these regulations.
(2) Where an authorised provider’s identification card is lost or
destroyed, a replacement shall be issued by the Regulator to the
authorised provider against a payment of a fee of thirty euro (€30).
(3) Any person who purports to be an authorised provider in
terms of these regulations, when not being so authorised, by
making use of an identification card, shall be guilty of an offence
and shall be liable, on conviction, to a fine (multa) of not more than
one thousand euro (€1,000) and of not more than one hundred
thousand euro (€100,000).
(1) The Regulator shall keep a register of authorisations,
which shall be made public in part or in its entirety and which shall
include records of all authorisations granted in accordance with these
regulations.
(2) The contents of the registers to be made public as
mentioned in sub-regulation (1) shall include the following
information
(a) name, surname and identity card number or identity
document number or passport number of the authorised
provider;
(b) authorisation number;
(c) telephone or mobile number of the authorised
provider, if available.
(3) The register or registers of authorisations shall be kept
under review and up to date by the Regulator
Provided that, it shall be the duty of the authorised provider
to inform the Regulator of any change in the information
mentioned in sub-regulation (2).