ELECTRICITY TRANSIT (GRID REQUIREMENTS) REGULATIONS (gridrequirements)
Table of Provisions (10)
Statutory Text (10 Articles)
SUBSIDIARY LEGISLATION 545.10
ELECTRICITY TRANSIT
(GRID REQUIREMENTS) REGULATIONS
*
LEGAL NOTICE 14 of 2003, as amended by Legal Notice 426 of 2007
and Acts XXXIV of 2014 and XXV of 2015.
(1) The title of these regulations is the Electricity Transit
(Grid Requirements) Regulations.
(2)
(a) These regulations shall come into force on such date as
the Minister responsible for resources and
infrastructure may by notice in the Gazette appoint and
different dates may be so appointed for different
provisions and different purposes of these regulations.
(b) A notice under paragraph (a) may make such transitory
provisions as appear to the Minister to be necessary or
expedient in connection with the provisions thereby
brought into force.
(3) These regulations establish measures relating to the transit
of electricity between high-voltage grids.
Amended by
XXXIV. 2014.17.
List of entities and grids covered by these Regulations
Country
Entity/Grid
Belgium
CPTE - Société pour la coordination de la production
et du transport d’énergie électrique
Denmark
Eltra
Elkraft
Germany
Bayernwerk AG
Berliner Kraft- und Licht (Bewag)-AG
EnBW Transportnetze AG
Hamburgische Electricitäts-Werke AG (HEW)
PreussenElektra Aktiengesellschaft
RWE Energie AG
Vereinigte Elektrizitätswerke Westfalen AG (VEW)
VEAG Vereinigte Energiewerke AG
Greece
Public Power Corporation (PPC)
Spain
Spain Red Eléctrica de España, SA
France
Électricité de France
Ireland
Electricity Supply Board
Italy
Edison
Edison Termoelettrica Enel
Luxembourg
Cegedel
Sotel
Malta
Enemalta plc
The Netherlands
SEP
Austria
Österreichische Elektrizitätswirtschaft AG
Tiroler Wasserkraftwerke AG
Vorarlberger Kraftwerke AG
Vorarlberger Illwerke AG
ELECTRICITY TRANSIT (GRID REQUIREMENTS)
Portugal
Rede Eléctrica Nacional SA (REN)
Finland
Suomen Kantaverkko Oyj (Finnish Power Grid PLC)
Sweden
Affarsverket svenska kraftnät
United Kingdom
National Grid Company
Scottish Power
Scottish Hydro-Electric
Northern Ireland Electricity
In these regulations, unless the context otherwise requires
"the Act" means the Regulator for Energy and Water Services
Act;
"competent authority" means the Regulator for Energy and Water
Services;
"electricity transit" means the transport of electricity through
high voltage transmission grids (excluding distribution grids)
situated in Malta and, or in a Member State of the European Union,
and across at least one frontier between these States;
"electricity transit contract" means a contract providing for
electricity transit between high voltage transmission grids;
"high voltage transmission grid", in the case of a grid situated in
Malta or a Member State of the European Union, means a grid
specified in the Schedule;
"entity" means a body responsible for the grids as specified in
the Schedule;
"grid operator" means an entity responsible for operating a high
voltage transmission grid in Malta;
"Minister" means the Minister responsible for resources.
These regulations shall apply where a request for the
transit of electricity is made to a grid operator by another entity.
*Not yet in force.
(1) The competent authority shall take the measures
necessary to facilitate the transit of electricity between high-
voltage grids in accordance with the conditions laid down in these
regulations.
(2) The competent authority shall take the measures necessary
to ensure that any entity under its jurisdiction referred to in the
Schedule acts without delay and fulfils its obligations under
regulation 5.
A grid operator that has received a request for the transit of
electricity shall without delay
(a) notify the competent authority, and any other person or
entity which the competent authority may nominate, of
the request;
(b) open negotiations on the conditions of the electricity
transit requested;
(c) inform the competent authority, and any other person
or authority nominated by the competent authority in
terms of paragraph (a), of the conclusion of an
electricity transit contract; and
(d) in the event that an electricity transit contract is not
concluded within twelve months of receipt of the
request for such transit, inform the competent
authority and any other person or authority nominated
by the competent authority in terms of paragraph (a),
of the reasons for the failure of the negotiations to
result in the conclusion of a electricity transit contract.
(1) Contracts involving transit of electricity between
transm ission gr ids shall be negotiated between the entities
responsible for the relative grids, and for the quality of service
provided and, where appropriate, with the entities responsible for
importing and exporting electricity.
(2)
The conditions of transit -
(a) shall be non-discriminatory and fair for all parties
involved and shall not include unfair clauses or
unjustified restrictions; and
(b) shall not endanger security of supply or quality of
service, and in particular, shall take full account of the
utilisation of reserve production and the most efficient
operation of existing systems.
The conditions to be included in an electricity transit
contract shall, at the request of either the entity seeking electricity
transit or the grid operator, be subject to conciliation by a body set
up and chaired by the competent authority for this purpose. The
competent authority shall establish the rules regulating the
procedure before such body.
(1) Where the competent authority becomes aware,
whether through carrying out an investigation or otherwise, that a
grid operator has failed to comply with any of the obligations set in
regulations 5 and 6, it shall issue a compliance order to the grid
operator involved ordering him to immediately comply with the
provisions of the said regulation. Should the grid operator disobey
such a compliance order, he shall, without prejudice to any other
liability under these regulations, the Act or any other law, be guilty
of an offence and be liable, on conviction, to a fine (multa) of not
less than two hundred and thirty-two euro and ninety-four cents
(€232.94) and not more than two thousand and three hundred and
twenty-nine euro and thirty-seven cents (€2,329.37) for each day
during which the offence subsists
Provided that the aggregate fines (multa) shall, on
conviction, not exceed the amount of twenty-three thousand and
two hundred and ninety-three euro and seventy-three cents
(€23,293.73).
(2) Any person who, when information with respect to these
regulations is requested by the competent authority, knowingly or
recklessly -
(a) gives any false, inaccurate or misleading information;
or
(b) supplies incomplete information; or
(c) fails, without reasonable cause to supply information
requested within the time given; or
(d) prevents or hinders any investigation; or
(e) produces or furnishes, or causes or knowingly allows
to be produced or furnished, any document or
information which he knows to be false in any material
respect,
shall be guilty of an offence and shall, on conviction, be liable to a
fine (multa) of not less than two hundred and thirty-two euro and
ninety-four cents (€232.94) and not more than two thousand and
three hu ndred an d twent y-ni ne euro and thi rty-sev en cen ts
(€2,329.37).
ELECTRICITY TRANSIT (GRID REQUIREMENTS)