The title of this Order is Tariff of Fees Order.
(Article 2)
War damaged buildings
1. For works carried out cost of which is in excess of the
‘permissible amount’ fixed by the War Damage
Commission, involving the preparation of an
alternative plan and of an additional schedule of works
on a modified plan approved by the Director of Public
Works
(i)
33.3% over the usual War Damage Commission
Tariff, on the total cost of works as approved by
the Director of Public Works.
2. For works carried out cost of which falls within the
‘permissible amount’ fixed by the War Damage
Commission, involving the preparation of an
alternative plan and of an additional schedule of
works
(i)
33.3% over the usual War Damage Commission
Tariff, on the total cost of works as approved by
the War Damage Commission.
The tariff of fees payable to architects and civil engineers
for professional work and services rendered in connection with the
erection, reconstruction or repair of buildings affe c ted by new
alignments, key plans or reconstruction schemes shall be as set out
in the Schedule to this Order.
*Repealed by Article 30 of Act XIII of 2021 (Cap. 622).
TARIFF OF FEES
For works carried out cost of which is in excess of the
‘permissible amount’ fixed by the War Damage
Commission, involving only an alternative plan, such
plan not having been submitted for approval by the
Director of Public Works
(i)
10% over the usual War Damage Commission
Tariff, on the ‘permissible amount’ fixed by the
Commission.
CANCELLATION OF A BUILDING CONTROL BOARD
LICENCE
I. WAR DAMAGE WORKS
1. Where works have not been started
(a) for the preparation of plans and for obtaining all
required permits, a schedule of works not having been
submitted to, or approved by, the War Damage
Commission.
(i)
3% of the War Damage Commission Tariff
on the cost of the complete project. (Cost to be
computed by an accepted practical method).
(b) for the preparation of plans, for obtaining all required
permits, and for the preparation of a schedule of
works, which has been approved by the War Damage
Commission.
(ii) 50% of the War Damage Commission Tariff on
the cost of the works as approved.
TARIFF OF FEES
2. Where works have been started
For the preparation of plans, for obtaining all permits
and for the preparation of schedule of works, which
has been approved by the War Damage Commission.
(i)
War Damage Commission Tariff on the cost of
the approved works actually carried out with an
addition of
(ii) 50% of the War Damage Commission Tariff on
the cost of the remaining approved works not yet
carried out.
II. NON-WAR DAMAGE WORKS
1. Where works have not been started
For the preparation of plans and for obtaining all
required permits
33.3% of the amount assessable in accordance
with Tariff K on the cost of the complete
project. (Cost to be computed by an accepted
practical method).
2. Where works had been started
For the preparation of plans and for obtaining all
required permits
(i)
Full fee in accordance with Tariff K on cost of
works carried out, with an addition of
(ii) 33.3% of the fee in accordance with Tariff K on
cost of the works not yet carried out. (Cost to be
computed by an accepted practical method).