BUILDING (PRICE CONTROL) (CONCRETE WORK AND MASONRY WORK) REGULATIONS
Statutory Text (4 Articles)
BUILDING (PRICE CONTROL)
(CONCRETE WORK AND MASONRY WORK)
SUBSIDIARY LEGISLATION 288.01
BUILDING (PRICE CONTROL) (CONCRETE WORK
AND MASONRY WORK) REGULATIONS
12th August, 1980
LEGAL NOTICE 72 of 1980, as amended by Legal Notice 423 of 2007.
The title of these regulations is the Building (Price
Control) (Concrete Work and Masonry Work) Regulations.
L.N. 423 of 2007.
(Regulation 2)
First Column
Second Column
1. Concrete Work
Reinforced concrete suspended slab; 0.15m thick,
1:2:4 mix (Grade 20), including one layer of BRC mesh
€13.74 per m 2
reinforcement No. 106 and all necessary form work ..........
2. Masonry Work
(a) Single Walls - Soft stone ashlar in lime
mortar in single walls 0.15m to 0.23m thick
€9.32 per m 2
fair faced both sides and cut to uniform height
(b) Double Walls - Soft stone ashlar in double
walls from 0.375m to 0.6m thick in lime
mortar consisting of inner and outer skin not
less than 0.15m thick well bonded together,
€17.47 per m 2
fair faced both sides and cut to uniform height
(c) Foundations in Masonry Work -
€8.39 per m 2
(i) for single walls ....................................
€15.72 per m 2
(ii) for double walls ...................................
Notes
(1) The above prices apply to buildings of a height up to two storeys and include
the stairwell leading to the roof thereof, parapet wall surrounding the roof,
ventilators and plain projections, but do not include ornamental work such as
moulded cornices and projections, moulded facias and sills, corbels, arches and
balustrades.
For works above 1st floor level the above rates shall be increased by the
following rates
at 2nd floor level .......................................................
10%
at 3rd floor level ........................................................
15%
17 1 / 2 %
at 4th and 5th floor level ............................................
(2) All openings not exceeding 1.2m in width shall not be deducted in the
calculation of areas. No charge shall be made for lintels, jambs and arrises thereof.
(3) For openings wider than 1.2m which have lintels, jambs and arrises, only the
width exceeding 1.2m shall be deducted in the calculation of areas. A charge shall
only be made for the lintel in excess of 1.2m.
The prices for works specified in the first column of the
Schedule shall be those established in the second column thereof.
BUILDING (PRICE CONTROL)
(CONCRETE WORK AND MASONRY WORK)
Substituted by