on Specified Locations, 2025
Table of Provisions (9)
Statutory Text (9 Articles)
L.N. 86 of 2025
DEVELOPMENT PLANNING ACT
(CAP. 552)
Order for the Notification of Development
on Specified Locations, 2025
IN EXERCISE of the powers conferred by article 55 of the
Development Planning Act, the Executive Council, with the approval
of the Minister responsible for the Planning Authority, has made the
following order:-
The title of this order is the Order for the Notification of Citation.
Development on Specified Locations, 2025.
CLASSES OF PERMITTED DEVELOPMENT
(article 4)
CLASS 1 – Development in zones administered by INDIS Malta
Ltd or Malta Enterprise
(a) The demolition, excavation, construction, re-
development, alteration or extension of an industrial unit or a
unit for any purposes ancillary to the main industrial unit within
industrial zones as indicated in the Subsidiary Plans and which
are administered by INDIS Malta Ltd or Malta Enterprise,
provided that
(i) the predominant use of the industrial unit falls
within one of the industrial, storage and distribution use
Classes of the Development Planning (Use Classes) Order
(S.L. 552.15), and includes any other use which is ancillary
to the predominant use;
(ii) the proposed development does not result in an
industrial unit higher than
-the height stipulated in the relevant map in Schedule
II; and
- fifteen (15) metres within all other zones
administered by INDIS Malta Ltd or Malta Enterprise,
measured from the highest street level along the
external perimeter of the unit;
(iii) the unit does not replace communal landscaped
areas or communal car parking spaces as indicated in the
Local Plans;
(iv) the unit whereby the development is being
proposed does not in any way abut on or is adjacent to any
property that is not administered by INDIS Malta Ltd or
Malta Enterprise, as the case may be;
(v) the proposed development, including the
creation or formation of a new vehicular access or any
changes to the road boundary, shall have the prior approval
of INDIS Malta Ltd or Malta Enterprise, where relevant;
(vi) the height of the industrial unit and the
materials shall have the prior approval of the authority
responsible for Civil Aviation, where deemed relevant by
the Authority;
(vii) it shall be subject to prior clearance of the
Building and Construction Authority;
(viii) where the applicant is not INDIS Malta Ltd or
Malta Enterprise, it shall be subject to prior clearance of
INDIS Malta Ltd or Malta Enterprise, as applicable.
(b) The construction, redevelopment, alteration or
extension of a unit (eg. substation etc.) for any purpose ancillary
to the main industrial use within zones administered by INDIS
Malta Ltd or Malta Enterprise, provided that sub-items (i) to
(viii) under item (a) of this Class shall apply mutatis mutandis.
(1)
In this order, unless the context otherwise requires
Interpretation.
"Act" means the Development Planning Act;
"Authority" means the Planning Board of the Planning
Authority established by article 63 of the Act;
"calendar year" means a period of twelve (12) months
commencing on the day on which the development or use or any
related intervention therewith commences, according to
whichever is the earliest;
"designated areas" means sites and areas identified by the
Strategic Plan for the Environment and Development or
subsidiary plans and policies, for protection, conservation or
preservation of such sites or areas, including areas of
archaeological, ecological, geological, geomorphological,
hydrological, palaeontological, architectural, historic, artistic or
antiquarian importance, or of natural beauty, or scientific
interest, together with any specific areas designated under the
Act. Urban Conservation Areas are excluded from this
definition, without prejudice to any designated areas overlapping
onto such Urban Conservation Areas;
"Development Control Design Policy, Guidance and
Standards" means Development Control Design Policy,
Guidance and Standards 2015, without prejudice to any
subsequent amendments or revisions thereto as may be approved
by the Authority.
(2) Words and expressions used in this order which are
not defined herein, shall have the same meaning as assigned to
them in the Act.
INDIS Malta Ltd Zones
€1.08
(1) (a) Wherever reference is made to a specific period in
this order, such period shall be deemed as excluding the period of
shutdown of the Planning Authority offices.
(b) For the purposes of this order, the period of shutdown
of the Authority offices shall be that period established by
Schedule 4 of the Development Planning (Procedure for
Applications and their Determination) Regulations.
(2) (a) With reference to any scheduled property that already
incorporates a protective buffer zone and Areas of High Landscape
Value, any buffer distance of thirty (30) metres shall not apply.
(b) In the case of an already existing building on property that
is not Outside the Development Zone and that is scheduled or
designated solely on the basis of features located underground, and if
the new development is located entirely above ground, the notification
procedure established in article 6 shall replace any restriction that
would otherwise be entailed by such scheduling or designation.
(c) In the case of property that is not Outside the Development
Zone and that is scheduled or designated solely on the basis of
landscape value, any restriction on permitted development that is
entailed by such scheduling or designation shall not apply in respect
of
(i) trenching operations or other underground works
which do not permanently affect the land surface, provided that
the land is completely and immediately returned to its original
condition once the works have been completed; and
(ii) internal alterations that do not affect the external
appearance of the building. The notification procedure
established in article 6 shall apply.
(d) Wherever there is a difference in opinion between the
Authority and any other party, or any need for interpretation, as to
whether a development
(i) is aesthetically or otherwise compatible with its
location; or
(ii) affects or alters materially the character and, or
permitted development and, or the context of the building or site
and its surroundings; or
(iii) meets any requirements of this order, whether explicit
or implied,
the opinion of the Authority shall prevail.
(1) Development permission hereby granted for the Class Permitted
of development described in Schedule I, shall be subject to the relevant development.
provisions of the Development Planning (Health and Sanitary)
Regulations, the Development Control Design Policy, Guidance and S.L. 552.22.
Standards, the Rural Policy and Design Guidance and all other relevant
approved plans and policies in accordance the Act, exceptions,
conditions, restrictions, rules, limitations and exclusions. The
notification procedure in article 6 shall be required for the Class of
development listed in Schedule I.
(2) The granting of such a permission shall not imply, whether
directly or indirectly, that permission is being granted for any other
development which is ancillary to, or even indispensable or inevitable
for the proper execution of the permitted development, nor does it
exempt it from any other requirement according to law or consent from
third persons, nor provide an exemption from liability or responsibility
to any person breaching any provision of law, whether applicable
during the execution of the permission or subsequent thereto or as
consequential and involuntary damage caused.
(3) The permission granted in accordance with sub-article (1)
shall not provide an exemption from the requirement of any other
permission, licenses or consent as required by law and is without
prejudice to any conditions, limitations and exclusions which may be
imposed by the public health authorities and other competent entities.
(4) (a) This order shall not permit development that is
contrary to, or would in any way prejudice
(i) any condition or limitation imposed by any
development permission granted on an application made in
accordance with Part VII of the Act, unless such development is
permitted on the basis of a change in policy and does not
prejudice any site specific safeguard for which such conditions
or limitations were imposed; or
(ii) any condition or limitation imposed by a clearance or
licence issued in accordance with the Act; or
(iii) any decision taken on any application or request for
such permit, clearance or licence.
(b)
This order shall not permit development that
(i) is already proposed in an application made in
accordance with Part VII of the Act, which is still being
processed, amended, reconsidered or appealed in accordance
with the Act; or
(ii) would prejudice the merits of such processing,
reconsideration or appeal; or
(iii) would prejudice the merits of a request for any
clearance or licence required by the Act, or would prejudice the
merits of an appeal from a decision thereon.
(5) The permission granted by sub-article (1) shall not
authorise any development which
(a) requires or involves the formation, laying out,
substantial widening, expansion, extension or reconstruction of a
means of access to an existing road. This exclusion shall not
apply with regard to development permitted by Class 1 of
Schedule I; or
(b) creates an obstruction to the vision of, or a distraction
to persons using any road used by vehicular traffic, so as to be
likely to cause danger to such persons; or
(c) requires an environmental impact assessment, an
appropriate assessment, a traffic impact statement, or any other
assessment or report required by the Act or any other legislation.
The requirement of a traffic impact statement shall not apply
with regard to development permitted by Class 1 of Schedule I;
(d) in the case of any works connected with the
development, that involve or include the demolition of, or may
foreseeably cause direct or indirect damage to
(i)
any rubble wall or random uniform rubble;
(ii) any dry-stone or any other similar structures
protected in accordance with the Act;
(iii) underground infrastructure;
(iv)
caves;
(v)
fossiliferous or infilled fissures;
(vi) archaeological remains;
(vii) existing historical buildings or monuments, or
archaeological remains and natural stone paving; and, or
(viii) cisterns or water galleries;
(e) results in the destruction, uprooting or damage to
existing trees, unless such works have been approved by the
competent authorities;
(f) involves the hacking, or drastic cleaning of
stonework by means of grit-blasting, high-pressure water jets,
compressed air, extensive sanding or abrasion, or other similar
interventions that may adversely affect any building or structure
of historic value or cultural heritage value.
(6) Any works permitted in accordance with sub-article (1) on
scheduled buildings or buildings which the Authority deems to have
conservation value shall be carried out strictly in accordance with
conservation and restoration methodologies established by the
Authority in official guiding documents and under the supervision of a
restoration architect.
If the Authority is of the opinion that development Power to restrict
described in Schedule I should not be carried out unless it is covered permitted
development.
by a permit issued upon application, the Authority may by notice in the
Gazette direct that the permit granted in accordance with article 4 shall
cease to apply to the development.
(1) Development under this order shall be notified to the Notification
Authority prior to the commencement of any work, on the form procedure.
provided by the Authority. The Authority may require different forms
for different classes of permitted development and different forms may
not require all the information listed under paragraphs (a) to (h). With
this form there shall be attached three (3) copies of all the necessary
plans and elevations, two (2) good-quality colour photographs
properly representative of the site and any other relevant
documentation as provided in this order or as the Authority may deem
necessary, so that the details submitted to the Authority shall clearly
and correctly identify
(a)
the responsible perit;
(b)
the applicant;
(c) the precise location and full extent of the applicant’s
property, and the applicant’s title over the property. Where
considered necessary by the Authority, these shall be confirmed
by a copy of the public deed which demonstrates the respective
title;
(d)
the full nature and full extent of the works;
(e)
the Class of Schedule I permitting such development;
(f)
all previous permits, applications and notifications
affecting the applicant’s property;
(g) any required approval by other relevant public
authorities or entities, as specified in this order. This shall
include an authorisation by the competent authority,
accompanied by a clear site plan, and any other relevant
documents, which is also stamped and endorsed by the
competent authority with a reference to the authorisation; and
(h) access to the site, indicated on a location map, if the
site does not abut on a public street.
(2) Following the validation of the notification, the Executive
Chairperson shall prepare a recommendation, within thirty (30) days
from validation, on whether the application satisfies all the
requirements of this order, which recommendation shall be referred for
authorisation to the Chairperson of the Planning Board or his delegate
who shall decide on whether to grant or refuse the authorisation of the
notification by not later than seven (7) days from the referral of the
recommendation.
(3) When deciding on the authorisation of the notification, the
Chairperson of the Planning Board or his delegate shall apply the
provisions of this order. Furthermore, when the Chairperson of the
Planning Board or his delegate decides to refuse the authorisation, he
shall provide the specific planning reasons provided by him.
(4) The Authority shall issue the decision by an electronic
means of communication within seven (7) days from the decision on
the authorisation for notification.
(5) When the authorisation for notification is granted, the
Authority shall return one endorsed copy of all the plans submitted,
clearly indicating that the works are permitted. In the event of any
discrepancy between any approved plans and the relevant provisions
of the order as communicated in the Authority’s response, the latter
shall prevail.
(6)
If the works are authorised, such authorisation by the
Authority shall be valid for a period of three (3) calendar years
commencing on the date on which the official notice by the Authority
is issued
Provided that the applicant may request an extension of the
period of validity of the authorisation which cannot exceed in
aggregate another three (3) calendar years.
(7) Where development has been carried out without the
notification required in accordance with sub-regulation (1), and that
development complies fully with the relevant exceptions, limitations
and conditions of this order, the notification of that development shall
be deemed to be a notification in accordance with sub-regulation (1),
except where otherwise provided in this order.
(8) Wherever development has been carried out without the
notification required in accordance with sub-regulation (1), or a
notification has been made and the Authority has not issued the
authorisation within the periods specified in sub-articles (2) and (4),
and such development
(a) runs counter to policies, plans or legislation approved
in accordance with the Act or the Environment Protection Act; or Cap. 549.
(b) is not correctly, completely and unequivocally
reflected in the notification,
the Authority shall still have the right to stop works and, or to
take enforcement or other action in accordance with the Act.
(9) Where development is carried out after the validity of the
authorisation stipulated in this order has expired, or after the
Development Order under which it was permitted has been repealed,
the Authority shall still have the right to stop the works and, or to take
enforcement or other action in accordance with the Act.