and their Determination) Regulations, 2025
Table of Provisions (39)
Statutory Text (39 Articles)
L.N. 53 of 2025
ENVIRONMENT PROTECTION ACT
(CAP. 549)
Environmental Permitting (Procedure for Applications
and their Determination) Regulations, 2025
IN EXERCISE of the powers conferred by articles 54 and 55 of
the Environment Protection Act, the Minister responsible for the
environment, after consultation with the Environment and Resources
Authority, has made the following regulations:-
PART I
INTERPRETATION AND APPLICABILITY
(1) The title of these regulations is the Environmental
Permitting (Procedure for Applications and their Determination)
commencement.
Regulations, 2025.
(2) These regulations provide a framework for environmental
permits, laying down the thresholds and procedure and serve as
guidance for the Environment and Resources Authority to authorise
and regulate any activity, operation or intervention that may have an
effect on the environment.
(3) These regulations shall come into force within two (2)
months from their publication in the Gazette.
Operations, interventions and activities falling within the scope of
these regulations
(regulations 4, 9, 11, 13, 15, 18, 25)
The following operations, interventions and activities shall
require a permit in accordance with these regulations, and the level
type and application fee payable for each category shall be applicable
as indicated in the table
The following notations shall be interpreted as follows
#
Identifies those categories which shall be published on the
Authority’s website for representations in accordance with regulations
9(3) and 13(1) and which require a decision to be taken in public in
accordance with regulation 15(2);
†
Identifies those categories which may be exempt from the
application fee for reasons of research or educational purposes as
stipulated in regulation 25.
Category
Operation, intervention or
Type of
Fee for a new
activity
application or
application
permit
Waste management operations
€100 for each
Consignment
authorisation
1.1
Level I
Consignment
on land
Permit;
Mobile unit for treatment of
1.2
waste on the site of
Level I
€750
generation
Storage of hazardous wastes
1.3
in quantities of more than 5
Level II
€1,500
tonnes per day (#)
Quarry operations, which
may include stone extraction
and, or the recycling of inert
Level II
€1,500
1.4
waste or construction and
demolition waste (#)
Backfilling of excavation
voids as defined by the
Waste
Management
1.5
(Management of Waste from
Level II
€1,000
Extractive Industries and
Backfilling)
Regulations
(S.L. 549.50.) (#)
Category 1.5 operations
1.6
which include crushing prior
Level II
€750
to backfilling (#)
1.7
Civic amenity site (#)
Level II
€1,500
€500 or as
otherwise
established in
Producer
Responsibility
1.8
Level II
Organisation
relevant
subsidiary
legislation
Other waste management
operations,
not
listed
elsewhere in this Schedule,
and other operations within
the scope of the Waste
Regulations (S.L. 549.63),
1.9
except works requested by
Level II
€1,500
the Authority for the purpose
of site remediation or
restoration, stabilisation of
material
or
other
environmental improvement
(#)
Non-hazardous
waste
collection,
treatment,
disposal, temporary storage
and, or preparation for reuse
(including
packaging,
Level II
€1,500
1.10
sorting and, or processing of
waste prior to reuse or
recovery), except waste
generated on the same site
(#)
Depot
carrying
out
temporary
storage
of
construction and demolition
1.11
Level II
€1,500
waste and preparation for
reuse, recycling or recovery
of such waste (#)
Hazardous waste collection,
temporary storage, treat-
ment, (including packaging
sorting and, or processing of
waste prior to preparation
Level III
€2,500
1.12
for reuse, recycling or recov-
ery), preparation for reuse,
recycling and, or disposal
except waste generated on
the same site (#)
Consignment and disposal at
€1,500 and a fee
sea, including operations in
per tonne as
1.13
Level II
association with Category
established by the
2.1
Authority
Waste incineration or co-
1.14
Level III
€2,500
incineration (#)
Decontamination and, or
disposal as regulated by the
Waste
Management
1.15
(Polychlorinated Biphenyls
Level III
€2,500
and
Polychlorinated
Terphenyls)
Regulations
(S.L. 549.28.) (#)
Transboundary movements
of waste subject to the prior
informed consent procedure
pursuant to Regulation (EU)
2024/1157 of the European
As established in
Parliament and of the
the Waste
Council of 11 April 2024 on
Management
shipments
of
waste,
Trans-frontier
(Shipments of
1.16
amending Regulations (EU)
shipment permit
Waste)
No 1257/2013 and (EU)
Regulations
2020/1056 and repealing
(S.L. 549.65.)
Regulation (EC) No 1013/
2006 and the Waste
Management (Shipments of
Waste) Regulations (S.L.
549.65.)
Modifications to written
consents for transboundary
movements of waste subject
to the prior informed consent
procedure
pursuant
to
Regulation (EU) 2024/1157
of the European Parliament
and of the Council of 11
€100 for every
Not applicable
1.17
April 2024 on shipments of
amendment
waste,
amending
Regulations (EU) No 1257/
2013 and (EU) 2020/1056
and repealing Regulation
(EC)
No
1013/2006
and the Waste Management
(Shipments
of
Waste)
Regulations (S.L. 549.65)
Interventions and activities in relation to biodiversity and the natural
environment
As established in
the Trees and
Registration as licensed tree
Woodlands
1.18
specialist
Protection
Regulations (S.L.
549.123.)
€100
Provided that
clean-up activities
Activity
involving
may, at the
1.19
persons or more, within a
discretion of the
protected area (†)
authority, be
exempt from
paying such fee
Operations, structural or
1.20
permanent interventions, in a
€100
protected area (†)
Taking of species protected
under the Flora, Fauna and
Natural Habitats Protection
1.21
Regulations (S.L. 549.44.)
€ 20
(†), other than hunting,
trapping, scientific ringing
Level I
or geo-tagging of birds
Interventions on up to 10
1.22
€20
protected trees
Interventions on more than
1.23
€100
10 protected trees (#)
Importation
of,
and
operations
related
to,
invasive alien species of
national
or
European
1.24
concern, other than the
€100
control or removal of such
species in accordance with
the methodology approved
by the Authority (#) (†)
Interventions and activities
for the purpose of access to
1.25
genetic resources through
€100
prior informed consent for
wildlife, except birds (#) (†)
Use of genetically modified organisms
Notification of the following as defined in the Contained Use of Genetically Modified
Micro-Organisms Regulations (S.L.549.49) and the Deliberate Release into the
Environment of Genetically Modified Organisms Regulations (S.L. 549.60)
First-time use of premises
As established in
for contained use of
the Contained Use
1.26
genetically
modified
of Genetically
organisms (#)
Modified Micro-
Level I
Organisms
Individual contained use of
Regulations
1.27
genetically
modified
(S.L.549.49) and
organisms (#)
the Deliberate
Deliberate
release
of
Release into the
genetically
modified
1.28
Environment of
organisms,
other
than
Genetically
placing on the market (#)
Level III
Modified
Placing on the market of
Organisms
1.29
genetically
modified
Regulations (S.L.
organisms (#)
549.60)
Others
€100 for
Hull cleaning and propeller
registration;
1.30
polishing on vessels greater
Level I
€50 for every
than 30 metres
notification
Renewal
of
existing
1.31
Level I
€800
quarrying licence
As established in
the Limitation of
Operations covered by the
Emissions of
Limitation of Emissions of
Certain Pollutants
Certain Pollutants into the
into the air from
1.32
Level II
Medium
air
from
Medium
Combustion
Plants
Combustion
Plants
Regulations (S.L. 549.122)
Regulations (S.L.
549.122)
Fuel terminals including
those within scope of the
Control of Volatile Organic
Compound
-
VOC
1.33
Emissions (Storage and
Level III
€2,500
Distribution of Petrol from
Terminals
to
Service
Stations) Regulations (S.L.
549.52) (#)
Retail and wholesale of fuel,
including petrol stations
covered by the Control of
Volatile Organic Compound
Level III
€2,500
1.34
- VOC Emissions (Storage
and Distribution of Petrol
from Terminals to Service
Stations) Regulations (S.L.
549.52) (#)
Operations covered by the
Urban
Waste
Water
1.35
Level III
€2,500
Treatment Regulations (S.L.
549.22)
Treatment
plants
of
domestic sewage, industrial
1.36
effluent or farmyard waste,
Level II
€1,500
not covered by Category
1.35 (#)
Ancillary
aquaculture
1.37
Level II
€1,500
facilities (#)
Marine
aquaculture,
1.38
Level III
€2,500
including fish farms (#)
1.39
Onshore aquaculture (#)
Level III
€2,500
Operations covered by the
Industrial
Emissions
(Limitation of Emissions of
1.40
Level III
€2,500
Volatile
Organic
Compounds)
Regulations
(S.L. 549.79)
1.41
Crematorium (#)
Level III
€2,500
As established in
Operations falling within
regulation 23 and
scope of Schedule 1 to the
Schedule 5 to the
Industrial
Industrial
Emissions
(Integrated
Pollution
Emissions
IPPC permit
(Integrated
1.42
Prevention and Control)
Regulations (S.L. 549.77)
Pollution
Prevention and
and the Industrial Emissions
(Framework)
Regulations
Control)
(S.L.549.76) (#)
Regulations (S.L.
549.77)
(1)
In these regulations, unless the context otherwise
requires
"Act" means the Environment Protection Act;
"activity", "intervention" or "operation" means any
practice, operation, physical works or event that may affect the
environment or that otherwise relates to any matter falling within
the scope of the Act, and which thus requires a permit from the
Authority in accordance with these regulations;
"applicant" means a person or entity who submits an
application for a permit in accordance with these regulations;
"application" means an application for a permit submitted
in accordance with these regulations;
"Authority" means the Environment and Resources
Authority as established in article 6 of the Act;
"cessation" means the intent of a permit holder to
permanently halt any activity, intervention or operation covered
by a valid permit;
"dismiss" means the Authority’s dismissal of an application
in accordance with these regulations;
"emergency permit" means a permit issued by the
Authority for an activity, intervention or operation which
requires immediate authorisation in accordance with these
regulations;
"electronic system" means the Environment Resources
Information System (ERIS), or any other electronic system in
use by the Authority in connection with the management and
processing of applications;
"grant" means the approval of a permit subject to any
terms, conditions and, or limitations deemed appropriate by the
Authority;
"IPPC" means integrated pollution prevention and control;
"interested third party" means a person who has duly
submitted representations on an application within the applicable
time frame in accordance with regulation 13;
"operator" means a person or entity who operates or
controls in whole or in part the operations, or to whom decisive
control over the functioning of the installation, site or plant has
been delegated;
"partial grant" means the approval of a permit for part or
parts of the activity, intervention or operation subject to all
terms, conditions and, or limitations deemed appropriate by the
Authority;
"permit" means a permit issued by the Authority in
accordance with these regulations;
"permit holder" means a person or entity who has been
granted a permit by the Authority;
"renewal" means the extension of the validity period of an
existing and valid permit, without any changes to the authorised
activity, intervention, operation or site;
"Tribunal" means the Environment and Planning Review
Tribunal established by article 3 of the Environment and
Planning Review Tribunal Act;
"validation" means the initial acceptance by the Authority,
of an application following satisfactory adherence to the
requirements for further processing of the application.
(2) In matters of interpretation of any term or provision of
these regulations, or as to whether an activity, intervention or
operation causes or is likely to cause harm to the environment, or
whether it meets any requirement of these regulations, whether explicit
or implied, the interpretation of the Authority shall prevail.
Operations, interventions and activities for which clearance in
accordance to regulation 35(4) may be granted
The following operations, interventions and activities shall
require clearance within six (6) months from entry into force of these
regulations, and subsequently clearance under these regulations. The
level type and application fee payable for each category shall be
applicable as indicated in the table
The following note shall be interpreted as follows
#
Identifies those categories that at the stage of renewal of
the clearance as a permit are to be published on the Authority’s
website for representations in accordance with regulations 9(3) and
13(1) and which require a decision to be taken in public in accordance
with regulation 15(2);
Cate-
Operation, Intervention or
Type of application
Fee for a
gory
Activity
orpermit
new appli-
cation
€2,500 and
Reclamation on land or at sea,
a fee per
using inert waste or stabilised
metre cubed
waste that has reached end-of-
(m 3 ) as
2.1
Level III
waste status, in association with
established
Category 1.13 where reclamation
by the
or dumping is at sea (#)
Authority
2.2
Animal slaughterhouse (#)
Level II
€1,500
2.3
Rendering plant (#)
Level II
€1,500
Quarrying operations not covered
2.4
Level II
€1,500
by category 1.4 or 1.31 (#)
Manufacture of computer, elec-
2.5
tronic and electrical equipment
Level II
€1,500
and optical products
Manufacture or processing of
asphalt or other non-metallic min-
2.6
eral products, including batching
Level II
€1,500
plants, but excluding temporary
plants (#)
Manufacture and blending of
chemical and fuel products and
man-made fibres, excluding dilu-
2.7
tion with water only and not
Level II
€1,500
involving chemical or biological
processes, and also excludes fire-
works factories (#)
2.8
Operations involving galvanising
Level II
€1,500
or sand blasting of materials
exceeding 10 tonnes every day (#)
2.9
Manufacture of rubber and plastic
Level II
€1,500
products
2.10
Manufacture of animal feed with a
Level II
€1,500
production of more than 10 tonnes
every day (#)
2.11
Yards and other premises on land
Level II
€1,500
for repair and maintenance of
vessels, aircraft and other
transport, exceeding 1000 square
meters and not covered by
Category 1.40
Level II
€1,500
2.12
Operations with a discharge of
trade effluent to sea, land, storm
or rainwater drains or culverts,
falling within the scope of the
Water
Policy
Framework
Regulations (S.L. 549.100)
Note: Trade effluent means any
liquid, with or without other
material in suspension or
dissolved in it, which is
discharged from trade premises,
other than uncontaminated storm
water run-off and domestic
sewage.
2.13
Marine container terminals (#)
Level III
€2,500
2.14
Shipyards and ancillary operations
Level III
€2,500
(#)
2.15
Wholesale of solid, liquid and
Level III
€2,500
gaseous fuels, industrial gases and
related products (#)
2.16
Cement packaging facility (#)
Level II
€1,500
2.17
Cement terminal (#)
Level III
€2,500
2.18
Manufacture of pharmaceutical
Level III
€2,500
products and pharmaceutical
preparations, excluding
(a) production of active
pharmaceutical
ingredients
and intermediates; and
(b) operations that are
limited to repackaging only.
€2.52
These regulations shall apply for any application for a
permit processed by the Authority. In the event of any conflict between
these regulations and any other legislation issued under the Act, these
regulations shall prevail
Provided that in the event of any conflict between these
regulations and the Industrial Emissions (Integrated Pollution
Prevention and Control) Regulations, the latter regulations shall
prevail.
PART II
GENERAL PROVISIONS
(1) No person shall carry out an activity, intervention or
operation set out in the First Schedule or Second Schedule unless he is
in possession of a permit issued by the Authority in accordance with
these regulations. Such permits shall fall under the following
categories as identified in the First and Second Schedule, as the case
may be
(a)
Level I;
(b)
Level II; and
(c)
Level III.
(2) A permit granted in accordance with these regulations shall
not relieve any person from the need to obtain any permit, license or
authorisation as may be required by any other law, or any relevant
consent from third parties.
(3)
The Authority may issue additional documentation to
supplement the Schedules on its website.
The Authority may grant, partially grant or refuse any Granting and
refusal of
application for a permit.
permits.
(1) In the granting or partial granting of a permit, the Conditions and
Authority shall include any condition, approved specification and, or requirements
a permit.
limitation as it deems appropriate.
(2) The Authority may also include pre-requisites for the
execution of the permit, including pre-operational requirements,
financial or other guarantees, environmental legal obligations or
otherwise, rectification of existing infringements, settlement of
outstanding fines and, or other requirements as it deems appropriate. If
the applicant fails to fulfil such pre-requisites within the period
specified in the Authority’s decision or, in the absence of any such
stipulated period, within six (6) months from the date of such decision,
the decision shall be dismissed ipso facto without the requirement for
any action by the Authority.
(3) The Authority may include conditions relating to
rehabilitation, restoration, after-use, monitoring, remedial action and,
or compensatory action, to be carried out before, during or after the
cessation of an activity, intervention or operation covered by a permit.
In such instances
(a) the permit holder shall not be exonerated from such
conditions after the permit has expired; and
(b) any guarantee in favour of the Authority related to a
permit shall not be released until the Authority is satisfied that
the conditions of the permit have been duly complied with and
that the actions requested by the Authority have been duly
undertaken to prevent, mitigate or offset the adverse impact of
the activity, intervention or operation covered by a permit.
In addition to the terms, conditions, specifications and Other
limitations of the permit, the Authority may also require one (1) or requirements.
more of the following, as it deems necessary to address circumstances
that may affect the surrounding environment, and such requirements
shall be carried out at the expense of the permit holder
(a)
additional monitoring;
(b)
engagement of consultants or specialists;
(c)
review of operational practices;
(d)
conduction or commissioning of audits;
(e)
abatement measures; and
(f) setting of limits on emissions, discharges, effluents,
waste streams or resource consumption associated with the
activity, intervention or operation covered by a permit.
PART III
PERMITTING PROCEDURES
(1) A person intending to carry out an activity,
intervention or operation falling within the scope of these regulations
shall submit an application for a permit in the form established and
published on the website of the Authority.
(2) When submitting an application, the applicant shall follow
the format prescribed by the Authority and shall comply with any
guidance and terms of reference issued and published on the website of
the Authority. The applicant shall also submit any other information,
correction or clarification required by the Authority as part of the
application process.
(1) An application for a permit shall be valid if the
applicant has duly fulfilled the requirements of regulation 8 and has
paid to the Authority the applicable fee as stipulated in the respective
Schedule.
(2) Upon the validation of an application, the Authority shall
issue a confirmation to the applicant.
(3) Following validation, those applications falling within
those categories indicated within the First Schedule shall be published
on the Authority’s website for any person to declare an interest and
make representations in accordance with regulation 13
Provided that this sub-regulation shall also apply to those
categories identified in the Second Schedule in case of an application
for the renewal of a permit on which clearance has been given in
accordance with the proviso to regulation 35(7).
(4) An application which is not in conformity with this
regulation shall be deemed as incomplete and shall not be processed by
the Authority. The Authority may dismiss an application that has
remained incomplete and invalid for a period exceeding six (6)
months.
(1) The Authority shall assess the validated application Processing and
and process it for a decision. The Authority may also require the assessment
applications.
submission of additional information or documents and, or the
carrying out of studies or investigations.
(2) The applicant shall comply with requirements and any
associated time-frames as may be stipulated by the Authority. Failure
to submit requested information, documents or other requirements to
the Authority’s satisfaction and within the stipulated period shall be
construed as a refusal by the applicant to comply with the Authority’s
request, and the Authority shall proceed to process the application with
the submissions made available to it, or to dismiss the application in
accordance with these regulations, as it considers appropriate.
(1) The time limit for the processing of applications shall Processing time
start to run on the date of publication on the Authority’s website of the period
applications.
validated application by the said Authority and shall be a maximum
period as follows
(a) fifteen (15) days for categories 1.1, 1.13, 1.18, 1.30
and 1.31 of the First Schedule;
(b)
ninety (90) days for other Level I applications;
(c) one hundred and twenty (120) days for other Level II
applications; and
(d) two hundred and seventy (270) days for Level III
applications.
(2) When an application includes more than one (1) activity,
intervention or operation listed in the First or Second Schedule, the
longest of the processing time periods listed in this regulation shall
apply, unless the Authority agrees to a phased processing of the
application, and in such case the time period shall be apportioned as
the Authority deems appropriate.
(3) The Authority may extend the processing time whenever
there are any modifications to the proposal and, or when external
consultation on specific technical matters is required for the
processing of the application, and in such instance it shall inform the
applicant in writing. In any case, such extension shall not exceed a
total period of twelve (12) months for Level I applications and
eighteen (18) months for Level II or Level III applications.
(4) The processing of an application for an activity, operation
or intervention that may require assessment, screening or any other
submission or action in accordance with other environmental
legislation, including but not limited to the Flora, Fauna and Natural
Habitats Protection Regulations and the Environmental Impact
Assessment Regulations, shall be suspended until such time that such
requirements have been duly fulfilled to the satisfaction of the
Authority.
(1)
In the processing of an application, the Authority
may consult any other public entity as may be required. In the event
that a permit is granted, any condition proposed by such entities and
included in the permit shall be enforced by the respective entity.
(2) If the Authority does not receive any feedback from the
consulted entity within the stipulated time-frame, it shall be construed
as a no objection from such entity.
(1)
Any person may make representations on
applications falling within those categories indicated within the First
Schedule as well as for those categories indicated in the Second
Schedule in case of an application for the renewal of a permit on which
clearance has been given according to the proviso to regulation 35(7).
The consultation periods shall be ten (10) days for Level I
applications, twenty (20) days for Level II applications and thirty (30)
days for Level III applications, which in all cases shall start to run on
the date of publication in accordance with regulation 9(3). Such time-
frames shall also be applicable to consultations indicated in regulation
12, but may be shortened to seven (7) days in urgent cases as may be
indicated in the aforesaid publication.
(2) The representations shall be submitted in writing through
the electronic system, in Maltese or English. Representations that are
submitted outside the period stipulated in these regulations shall not be
considered by the Authority.
(3) The Authority shall ensure that due account is taken of the
matters raised in the representations, insofar as relevant to the merits
of the application and falling within its remit
Provided that such representations shall not be binding on
the Authority.
(1) The processing of an application may be suspended
upon the request of the applicant, for not more than two (2) calendar
years in aggregate, which shall start to run on the date of the respective
written communication. The request shall be subject to the Authority’s
approval, which may be granted, partially granted or dismissed.
(2) The applicant may reactivate the application at any time by
withdrawing his request for suspension in writing. In the absence of
such reactivation, the application shall be dismissed ipso facto upon
the expiry of the suspension period established in sub-regulation (1)
and no further processing by the Authority shall be required.
(3) The processing of an application may be suspended by the
Authority, inter alia for the following reasons
(a) if in the Authority’s opinion, the proposal or the
situation on site, or both, have been modified or updated in a
substantial manner such that the details currently being assessed
are superseded, outdated, insufficient or no longer reflecting the
actual situation; or
(b) if any material flaw, malpractice or distortion is
discovered with regard to the already-initiated processing or the
actual situation on site, or both.
(4) At any stage following the suspension in accordance with
sub-regulation (3), the Authority may, as it deems most appropriate,
while taking into account the factors that led to the suspension
(a) reactivate the processing, subject to any required
clarifications, updates or corrections;
(b)
direct that the process be resumed at an earlier stage;
(c)
proceed to a decision with the available information;
or
(d)
dismiss the application.
(1) The Authority shall take a decision on an application Decisions on
applications for
that falls within the scope of these regulations.
a permit.
(2) Decisions on applications as identified in the First Schedule
shall be taken in public
Provided that this sub-regulation shall also apply to those
categories identified in the Second Schedule in case of an application
for the renewal of a permit on which clearance has been given in
accordance with the proviso to regulation 35(7).
(3) Decisions taken by the Authority on applications shall be
made available to the public through the Authority’s website.
(1) A permit which is granted or partially granted shall
remain valid for such a time as specified by the Authority in such
permit.
(2)
A permit shall continue to be valid unless
(a)
the validity period established in sub-regulation (1)
expires;
(b)
cessation occurs in accordance with regulation 24; or
(c) it is revoked in whole or in part, in accordance with
regulation 21 and articles 65 and 66 of the Act.
(1) An application for an emergency permit may be
submitted to the Authority in cases requiring immediate action due to
(a)
threat to the environment or national heritage;
(b) circumstances which are likely to endanger life,
health or public safety;
(c) circumstances which may increase the environmental
risk or environmental impact of other projects, situations, actions
or accidents if authorisation is delayed; or
(d) significant national importance as declared by the
Minister.
(2) Such applications for emergency permits shall be
accompanied by a report prepared by a warranted engineer or architect
or other duly qualified expert in the field, as may be relevant. The
report shall certify the nature of the emergency that merits such a
permit. This provision shall be without prejudice
(a) to the undertaking of any further studies or
investigations that may be mandatory or otherwise essential;
(b) to the Authority’s decision to grant, refuse or partially
grant the permit; and
(c) to the specifications, limitations and conditions that
the Authority may deem appropriate.
(3) When processing applications for emergency permits, the
Authority may deviate from the processing and consultation time-
frames as it deems appropriate for effective and timely addressing of
the situation. In such instances, regulations 9(3), 13, 15(2) and 32 shall
not be applicable.
(4) An emergency permit shall be valid for a period of time as
determined by the Authority which shall not exceed six (6) months.
(1) A permit holder may apply for the renewal of the Renewal of a
permit during its period of validity as may be specified in the permit permit.
conditions
Provided that permits falling within the scope of Categories
1.13, 1.16 and 1.17 in the First Schedule shall not be renewed.
(2) The Authority may decide to grant, partially grant or refuse
the renewal of a permit, and may also vary and, or modify any
condition. The Authority may also request any further information or
detail from the permit holder as may be required for the renewal
process.
(3) The permit shall only be considered as renewed once the
Authority issues the renewed permit. The processing of renewal
applications shall follow the processing time periods stipulated in
regulation 11.
(1) The Authority may, at any time, vary the conditions Variation of
laid down in a permit where such a variation is of a minor or permits.
administrative nature such as typographical corrections or changes to
applicant details, or where it is necessary to comply with new or
revised environmental legislation or where the permit needs to be
adapted to meet technical advancements. In such instances, the
Authority shall notify the permit holder of such a decision by issuing a
variation notice.
(2) A permit holder may also submit a request to the Authority
for a variation in accordance with sub-regulation (1).
(3) In the cases stipulated in this regulation, regulations 9(3),
13 and 15(2) shall not be applicable.
(1) A permit holder may request a modification to a Modification of
a permit
permit which is in force in accordance with article 62 of the Act.
requested by the
holder.
(2) The applicant shall submit an application for modification
as well as
(a) the details of the proposed changes, including
relevant drawings, plans and photographs, in a manner that may
be easily compared to what was already covered by the permit;
and
(b)
an assessment of the possible effects on the
environment.
(3) In cases where more than one (1) modification is requested,
a consolidated application shall be submitted to the Authority clearly
reflecting all the requested changes. In such case the processing time
frame shall restart accruing from the date of validation of the
consolidated application, provided that the Authority is satisfied that
such consolidation would be beneficial for environmental or
administrative reasons or that it would not significantly affect the case
processing.
(4) Sub-regulation (3) shall not be applicable to applications
falling within the scope of Regulation (EU) 2024/1157 of the European
Parliament and of the Council of 11 April 2024 on shipments of waste,
amending Regulations (EU) No 1257/2013 and (EU) 2020/1056 and
repealing Regulation (EC) No 1013/2006 and the Waste Management
(Shipments of Waste) Regulations.
The Authority may, by a decision, modify or revoke any
permit granted on the grounds of articles 65 and 66 of the Act,.
Without prejudice to any action taken by the Authority in
accordance with Part VII of the Act, the Authority may consider
applications for the continuation of an activity or operation undertaken
fully or partly without authorisation
Provided that such activity or operation is not causing or
has not caused adverse environmental effects
Provided further that in such cases the Authority shall
impose an environmental legal obligation or otherwise in its decision.
(1) A permit shall not be transferred from the permit
holder to another person without prior notification to the Authority and
confirmation of receipt by the Authority. The transfer shall be made by
means of a joint notification by the permit holder and the transferee, on
the form prescribed and published on the website of the Authority.
(2) Upon the Authority’s acknowledgement of the transfer, all
rights, obligations and liabilities shall be transferred onto the
transferee from the date of acknowledgement.
(1) A permit holder may submit an application to the
Authority for cessation of an operation, activity or intervention
covered by a permit.
(2) An application for cessation shall not be accepted by the
Authority until such time that all the studies, reports and submissions
required by the Authority are submitted to the satisfaction of the
Authority.
(3) Prior to the cessation of a permit, the Authority shall verify
that the permit holder is compliant with the conditions and approved
specifications in the permit, particularly but not limited to any
decommissioning, closure, cessation, dismantling, and remediation
obligations as may be relevant. The permit holder shall retain all the
responsibilities for the operations, interventions and activities until the
Authority officially approves the cessation of the permit in writing.
(4) Without prejudice to regulation 6(3), any guarantee in
favour of the Authority shall not be released until the Authority
approves the request for cessation.
(5) Regulations 9(3), 13 and 15(2) shall not be applicable to
cessation of permits.
PART IV
FEES, GUARANTEES AND CONTRIBUTIONS
(1) The Authority shall charge the fees prescribed in the Application
respective Schedule for the processing of an application in accordance fees.
with these regulations. The fees shall be paid by the applicant upon
submission of the application, and the Authority shall not process the
application further until the application fee is settled
Provided that the Authority may exempt the payment of the
application fee for certain applications as identified in the First
Schedule due to research or educational purposes when the application
has been submitted by, or on behalf of an educational institution.
(2) If the fee due has not been paid after the lapse of ninety
(90) days from submission of the application, the application shall be
dismissed.
(3) In the case of emergency applications, non-payment of the
fee shall not suspend the validation stage.
(4) Unless otherwise indicated in sub-regulation (5), the fees
due to the Authority shall be
(a) half of the application fee stipulated in the respective
Schedule, in the case of applications for renewal or for a
substantial modification;
(b) double the application fee stipulated in the respective
Schedule, in the case of applications under regulation 22.
(5)
Notwithstanding the provisions of sub-regulation (4)
(a) in the case of operations falling within the scope of
the Industrial Emissions (Integrated Pollution Prevention and
Control) Regulations, the applicable fees shall be those specified
in the said regulations;
(b) in the case of applications that include more than one
(1) operation falling within the scope of the Industrial Emissions
(Integrated Pollution Prevention and Control) Regulations, the
fees prescribed in the said regulations shall apply cumulatively,
and the fees prescribed in the First Schedule shall not be
applicable;
(c) in the case of operations falling within the scope of
the Limitation of Emissions of Certain Pollutants into the air
from Medium Combustion Plants Regulations, the fees
established in the said regulations shall also be applicable in
addition to the fees prescribed in the respective Schedules; and
(d) the fee for a modification shall not be payable if the
modification is imposed by the Authority and not requested by
the permit holder.
(6) When the Authority refuses or dismisses an application, or
if a permit is only partially granted, or if an application is withdrawn
by the applicant, the fee paid shall not be refunded.
(7) When an application for a permit includes more than one
(1) activity, operation or intervention listed in the First or Second
Schedule, the highest of the corresponding fees shall be applicable
together with a fee of one hundred euro (€100) for every additional
activity, operation or intervention.
(1) The Authority may impose the provision of a
financial guarantee or equivalent safeguard as a condition of the
permit, after considering the impacts and risks associated with any
aspect of the activity, intervention or operation.
(2) When the holder of a permit fails to comply with any of the
conditions laid down in the permit, the Authority may withdraw the
guarantee in full or in part, as it may deem appropriate.
(3) In cases where the Authority withdraws the guarantee
either in part or in full, the operator shall ensure that this is replenished
within a period not exceeding thirty (30) days from date of withdrawal.
Failure to replenish the guarantee within this period shall be construed
as a breach of the permit and of these regulations.
(4) The Authority may release part of the guarantee as it may
deem appropriate in the event of partial compliance, if it is satisfied
that this would not prejudice the effectiveness of the respective permit
conditions and approved specifications.
(1) When granting permits the Authority may impose an Environmental
environmental legal obligation or otherwise in accordance with article contributions.
64 of the Act. Such obligations shall be distinct from any fee or
guarantee attached to the application or to the permit.
(2) In cases where the environmental legal obligation or
otherwise requires a sum to be paid to the Authority in accordance
with article 64(2)(e) of the Act, such sum shall be deposited in the
Environmental Fund established under article 32 of the Act.
PART V
RECONSIDERATION & APPEALS
(1) An applicant may apply for a reconsideration of a Reconsideration.
decision by the Authority within thirty (30) days from the date of the
decision, and an administrative fee of fifty euro (€50) shall be due to
the Authority
Provided that reconsideration shall not be applicable for
those decisions taken in public by the Board of the Authority
Provided further that the reconsideration decision shall be
taken by the Board of the Authority in public.
(2) Requests for reconsideration shall only be valid if done on
the application form prescribed and published on the website of the
Authority. The request for a reconsideration shall not be valid if the
request relates to a change in operations or in the proposal, or a change
in the documentation submitted to the Authority as part of the
processing of the application, or if the request is submitted by any
third party including any entity consulted in accordance with
regulation 12.
(3) When an appeal has been filed before the Tribunal by any
person other than the applicant and the applicant submits a request for
reconsideration in accordance with this regulation, the procedures
before the Tribunal shall be suspended until the request for the
reconsideration is determined and the Authority has submitted a copy
of the decision to the Tribunal, and any time periods established under
the provisions of Environment and Planning Review Tribunal Act in Cap. 551.
relation to the procedures before the Tribunal shall start to run from the
date of receipt by the Tribunal of the reconsideration decision.
An appeal from a decision taken by the Authority may be
filed before the Tribunal within thirty (30) days from the publication of
the decision on the Authority’s website by
(a)
an applicant, in relation to an application filed by
him; or
(b) a registered interested third party, only in relation to
the applications falling within the scope of regulation 13.
(1) The execution and validity of a permit which was
subject to public consultation in accordance with regulation 13 and for
which representations from interested third parties were submitted,
shall be automatically and temporarily suspended for thirty (30) days
from publication of the decision on the Authority’s website, and no
works, interventions, operations or activities may commence before
the lapse of such period.
(2) The permit may subsequently remain suspended if the
Tribunal so decides in accordance with the Environment and Planning
Review Tribunal Act.
(3) The suspension prescribed in sub-regulations (1) and (2)
shall not be applicable to the following permits
(a)
emergency permits;
(b)
renewed permits;
(c)
clearance issued in accordance to regulation 35(4);
(d) permits which were not subject to an Environmental
Impact Assessment and, or IPPC permit and which in the opinion
of the Minister
(i) are of strategic significance or of significant
national importance;
(ii) are related to any obligation ensuing from
European Union legislation;
(iii) affect national security or the interests of other
governments; or
(iv) affect response to civil or environmental
emergencies.
PART VI
MISCELLANEOUS PROVISIONS
(1) The Authority shall retain all information required Disclosure of
from the applicant for the processing of the application and shall information.
publish the details of the applicant consisting of the following
(a)
the name and surname of the applicant;
(b)
the proposed operation, intervention or activity;
(c)
the location, if applicable; and
(d)
the decision of the Authority.
(2) Upon the request of the applicant, the Authority may censor
financially or commercially sensitive information.
(1) The offices of the Authority shall be closed between Inactive periods.
the 23rd of December of every year and the 1st of January of the
following year, both days included.
(2) One week prior to Easter Sunday and the period between
the 8th and 22nd of August of every year shall be considered as
inactive periods.
(3) The Authority may establish other periods during the year
as inactive periods. Such periods shall be published on the Authority’s
website and in the Gazette.
(4) During such inactive periods, processing times shall be
suspended.
The Authority shall not be held liable for any loss or Liability for loss
damage suffered by any person by reason of anything done or omitted or damage.
to be done in good faith in the course of administering these
regulations.
The Authority may, from time to time, publish any Supporting
documentation or guidance in relation to matters falling within the documentation.
scope of these regulations or ancillary thereto.
PART VII
TRANSITORY PROVISIONS
(1) Permits which have been issued by the Authority Transitory
prior to the coming into force of these regulations and which are still provisions.
valid, shall be construed as authorised under these regulations, unless
they have expired or have been superseded by a permit issued in
accordance with these regulations.
(2) The provisions of sub-regulation (1) shall also be
applicable to conditions, specifications and obligations related to such
permit, including any requirement to renew the validity of the permit.
(3) Applications that have been submitted before the coming
into force of these regulations shall be exempt from the fee prescribed
in the respective Schedule, unless a fee was already applicable in
accordance with any other regulations issued under the Act.
(4) Where it is proven to the satisfaction of the Authority that
the operation, intervention or activity specified in the Second
Schedule, was already exercised prior to the coming into force of these
regulations, such operation, intervention or activity may be deemed
cleared by the Authority subject to such terms and conditions as the
Authority may impose.
(5) An application for clearance of an operation, intervention
or activity specified in sub-regulation (4) and in the Second Schedule
shall be submitted to the Authority within six (6) months from the
coming into force of these regulations.
(6) The Authority shall determine an application for clearance
for an operation, intervention or activity specified in sub-regulation (4)
and the Second Schedule without delay and may refuse any such
application on any grounds valid at law
Provided that the determination of an application for
clearance shall not be subject to appeal, except by the applicant, from a
refusal of a clearance or from a condition imposed in the clearance.
(7) A clearance issued in terms of sub-regulation (4) shall be
valid for four (4) years
Provided that prior to the expiration of the clearance, the
applicant shall apply for a permit to cover the operation, intervention
or activity subject of the clearance, which application shall be deemed
as an application for the renewal of a permit for all intents and
purposes of these regulations
Provided further that upon expiration of the clearance, the
operation, intervention or activity shall continue subject to a permit
issued under these regulations and in line with any such conditions
stipulated in the permit.
Sub-regulation (6) of regulation 46 of the Flora, Fauna and
Natural Habitats Protection Regulations shall be deleted.