Regulations, 2025
Table of Provisions (12)
Statutory Text (12 Articles)
L.N. 3 of 2025
REGULATOR FOR ENERGY AND WATER SERVICES ACT
(CAP. 545)
Promotion of Energy from Renewable Sources (Amendment)
Regulations, 2025
IN EXERCISE of the powers conferred by article 37(1) of the
Regulator for Energy and Water Services Act, the Minister responsible
for energy and water services, after consultation with the Minister
responsible for the Planning Authority and with the Regulator for
Energy and Water Services, has made the following regulations:-
The title of these regulations is the Promotion of Energy
from Renewable Sources (Amendment) Regulations, 2025 and these
regulations shall be read and construed as one with the Promotion of
Energy from Renewable Sources Regulations, hereinafter referred to
as the "principal regulations".
Immediately after sub-regulation (2) of regulation 1 of the
principal regulations, there shall be added the following new sub-
regulation
"(3) These regulations furthermore transpose Article
1(1)(a)(1), Article 1(1)(c), and Article 1(7) and partially
transpose Article 1(6) of Directive (EU) 2023/2413 of the
European Parliament and of the Council of 18 October 2023
amending Directive (EU) 2018/2001, Regulation (EU) 2018/
1999 and Directive 98/70/EC as regards the promotion of energy
from renewable sources, and repealing Council Directive (EU)
2015/652.".
Sub-regulation (2) of regulation 2 of the principal
regulations shall be amended as follows
(a) the definition "energy from renewable sources" or
"renewable energy" thereof shall be substituted by the following
new definition
""energy from renewable sources" or "renewable
energy" means energy from renewable non-fossil sources,
namely wind, solar (solar thermal and solar photovoltaic)
and geothermal energy, osmotic energy, ambient energy,
tide, wave and other ocean energy, hydropower, biomass,
landfill gas, sewage treatment plant gas, and biogas;";
(b) the definition "Minister" shall be substituted by the
following new definition
""Minister" means the Minister responsible for
energy and water services, provided that for the purposes of
these regulations which regulate planning matters, it shall
mean the Minister responsible for energy and water
services in consultation with the Minister responsible for
the Planning Authority;";.
(c) the definition "relevant authority" shall be substituted
by the following new definition
""relevant authority" means any authority or
license or permit-issuing or administrative body
responsible for the issuing of authorisations, licenses or
permits, or responsible for the formulation and
publication of general binding rules, insofar as these
authorisations, licenses, permits or rules may directly
impact, or relate to any activity which may impact, the
achievement of the objectives laid down by these
regulations
Provided that for the purpose of these
regulations, the responsible relevant permitting
authorities shall include but not be limited to
(a) the Planning Authority established in
accordance with article 5 of the Development
Planning Act, which shall be responsible to fulfil
its obligations under the said Act; and
(b) the Regulator for Energy and Water
Services established in accordance with article 3
of the Regulator for Energy and Water Services
Act, which shall be responsible to fulfil its
obligations under the said Act;";
(d) immediately after the definition "renewable liquid
and gaseous transport fuels of non-biological origin" thereof
there shall be added the following new definition
""renewables acceleration area" means a specific
location or area, whether on land, sea or inland waters,
which is designated as particularly suitable for the
installation of renewable energy plants;";
(e)
immediately after the definition "SME" thereof there
shall be added the following new definition
""solar energy equipment" means equipment that
converts energy from the sun into thermal or electrical
energy, in particular solar thermal and solar photovoltaic
equipment;";
(f) in the Maltese version only, the definition "tiġdid
(repowering)" shall be deleted;
(g) in the Maltese version only, immediately after the
definition "residwu" there shall be added the following new
definition
""repowering" tfisser it-tiġdid ta’ impjanti tal-
elettriku li jipproduċu l-enerġija rinnovabbli, inkluż is-
sostituzzjoni sħiħa jew parzjali tal-installazzjonijiet jew
tas-sistemi u t-tagħmir tal-operazzjoni għal finijiet tas-
sostituzzjoni tal-kapaċità jew taż-żieda fl-effiċjenza jew fil-
kapaċità tal-installazzjoni;".
Immediately after regulation 18 of the principal regulations
there shall be added the following new regulation
(1) One (1) or more plans may be adopted
"Areas for grid and
to designate dedicated infrastructure areas for the
infrastructure
integrate renewable development of grid and storage projects that are
necessary to integrate renewable energy into the
energy into the
electricity system.
electricity system, in cases where such development is
not expected to have a significant environmental
impact, such an impact can be duly mitigated or, where
such mitigation is not possible, it is compensated for.
(2) The aim of the areas described in sub-
regulation (1) shall be to support and complement the
renewables acceleration areas.
(3) Those plans referred to in sub-regulation (1)
shall
(a) for grid projects, avoid Natura 2000
sites and areas designated under national
protection schemes for nature and biodiversity
conservation, unless there are no proportionate
alternatives for their deployment, taking into
account the objectives of the site;
(b) for storage projects, exclude Natura
2000 sites and areas designated under national
protection schemes;
(c) ensure synergies with the designation
of renewables acceleration areas;
(d) be subject to a strategic environmental
assessment
pursuant
to
the
Strategic
Environmental Assessment Regulations and,
where applicable, to an assessment pursuant to
regulation 19 of the Flora, Fauna and Natural
Habitats Protection Regulations; and
(e) establish appropriate and proportionate
rules, including on proportionate mitigation
measures which shall be adopted for the
development of grid and storage projects in order
to avoid adverse effects on the environment that
may arise or, where it is not possible to avoid such
effects, to significantly reduce them.
(4) Grid and storage projects which are
necessary to integrate renewable energy into the
electricity system may, under justified circumstances,
including where needed to accelerate the deployment of
renewable energy in order to achieve the climate and
renewable energy targets, be exempted from
(a) the environmental impact assessment
pursuant to regulation 6(1) of the Environmental
Impact Assessment Regulations;
(b) an assessment of the implications of
the grid and storage projects for Natura 2000 sites
pursuant to regulation 19 of the Flora, Fauna and
Natural Habitats Protection Regulations; and
(c) the assessment of the implications of
the grid and storage projects on species protection
pursuant to regulations 24 and 25 of the Flora,
Fauna and Natural Habitats Protection
Regulations and regulation 4(1) of the
Conservation of Wild Birds Regulations
Provided that such grid or storage
projects are located in a dedicated infrastructure
area designated in accordance with sub-regulation
(1) and that these comply with the established
rules, including on proportionate mitigation
measures which shall be adopted in accordance
with paragraph (e) of sub-regulation (3), by way
of derogation from regulations 6(1) and 10(2) of
the
Environmental
Impact
Assessment
Regulations and from items 3.4.1.1, 3.4.2.1 and
10.0.2.7 of Schedule I to the said regulations, and
by way of derogation from regulation 19 of the
Flora, Fauna and Natural Habitats Protection
Regulations.
(5) Where grid and storage projects are located
in dedicated infrastructure areas and exempt from the
assessments referred to in sub-regulation (4), they shall
be subject to a screening process which shall be based
on existing data from the strategic environmental
assessment pursuant to the Strategic Environmental
Assessment Regulations, provided that project
applicants may be requested to provide additional
available information.
(6) The screening process referred to in sub-
regulation (5) shall be finalised within thirty (30) days
from its commencement and shall aim to identify if
projects are highly likely to give rise to significant
unforeseen adverse effects, in view of the
environmental sensitivity of the geographical areas
where they are located, which adverse effects were not
identified during the environmental assessment of the
plans designating dedicated infrastructure areas carried
out pursuant to the Strategic Environmental Assessment
Regulations and, where relevant, to the Flora, Fauna
and Natural Habitats Protection Regulations.
(7) Where the screening process referred to in
sub-regulation (5) identifies a project as being highly
likely to give rise to significant unforeseen adverse
effects as referred to in sub-regulation (6), appropriate
and proportionate mitigation measures shall be applied,
on the basis of existing data, to address those effects.
(8) Where it is not possible to apply the
mitigation measures required in accordance with sub-
regulation (7), the operator of the installation shall be
required to adopt appropriate compensatory measures
to address those effects which, if other proportionate
compensatory measures are not available, may take the
form of a monetary compensation for species protection
programmes, in order to ensure or improve the
conservation status of the species affected.
(9) Where the integration of renewable energy
into the electricity system requires a project to reinforce
the grid infrastructure, within or outside dedicated
infrastructure areas, and such a project is subject to a
screening process carried out pursuant to sub-regulation
(5), or to a determination whether the project requires
an environmental impact assessment, or an
environmental impact assessment pursuant to
regulation 10 of the Environmental Impact Assessment
Regulations, such a screening process, determination or
environmental impact assessment shall be limited to the
potential impact arising from the change or extension
compared to the original grid infrastructure.".
5. Regulation 19 of the principal regulations shall be Substitutes
regulation 19 of
substituted by the following new regulation
the principal
regulations.
(1) The permit-granting procedure shall
cover all relevant administrative permits to build,
the permit-granting
repower and operate renewable energy plants, including
those combining different renewable energy sources,
heat pumps and co-located energy storage, including
power and thermal facilities, as well as assets necessary
for the connection of such plants, heat pumps and
storage to the grid and to integrate renewable energy
into heating and cooling networks, including grid-
connection permits and where required, environmental
assessments.
(2) The permit-granting procedure shall
comprise all administrative stages, from the
acknowledgment of the completeness of the permit
application in accordance with sub-regulation (3), up to
the notification of the final decision on the outcome of
the permit-granting procedure by the relevant
competent authority or authorities.
(3)
Every relevant authority which is
responsible for the issuing of any administrative permit
associated with renewable energy plants, shall
acknowledge the completeness of the application or, if
the applicant has not sent all the information required to
process the application, shall request that the applicant
submit a complete application without undue delay
Provided that such acknowledgement or
request as the case may be, shall be provided within
thirty (30) days, for renewable energy plants located in
renewables acceleration areas, and within forty-five
(45) days, for renewable energy plants located outside
renewables acceleration areas, from receipt of an
application for a permit.
(4) The date of acknowledgement of the
completeness of the application by the relevant
authority shall indicate the commencement of the
permit-granting procedure.
(5) An ad hoc set-up made up of the relevant
permitting authorities of which the Regulator of energy
services and the competent authority for development
permitting shall be permanent members, shall act as a
single contact point for the entire administrative permit-
application and permit-granting procedure
Provided that any other relevant permitting
authority may be added to the set-up as required.
(6) The contact point designated in line with
sub-regulation (5) shall, upon the request of the
applicant, guide and facilitate the applicant during the
entire administrative permit-application and permit-
granting procedure and the applicant shall not be
required to contact more than one (1) contact point
during the entire procedure.
(7) The contact point designated in line with
sub-regulation (5) shall guide the applicant through the
administrative permit-application procedure, including
the steps relating to the protection of the environment,
in a transparent manner until the delivery of one or
more decisions by the competent authorities at the end
of the permit-granting procedure, provide the applicant
with all necessary information and where appropriate,
involve other administrative authorities.
(8) The contact point designated in line with
sub-regulation (5) shall ensure that the deadlines for the
permit-granting procedures set out in these regulations
are met.
(9) All relevant authorities shall allow
applicants to submit relevant documents digitally,
provided that by the 21st November 2025, all permit-
granting procedures referred to in sub-regulation (1)
shall be carried out in electronic format.
(10) The contact point designated in line with
sub-regulation (5) shall make available a manual of
procedures for developers of renewable energy plants
and shall provide such information online, addressing
also distinctly small-scale renewable energy projects,
renewables self-consumers projects and renewable
energy communities.
(11) Should more than one (1) contact point be
designated in line with sub-regulation (5), online
information shall indicate the contact point relevant to
the application in question.
(12) Every relevant authority shall ensure that
applicants and the general public have easy access to
simple procedures for the settlement of disputes
concerning the permit-granting procedure and the
issuance of permits to build and operate renewable
energy plants, including where applicable, alternative
dispute resolution mechanisms.
(13) Administrative and judicial appeals in the
context of a project for the development of a renewable
energy plant, the connection of such plant to the grid,
and the assets necessary for the development of the
energy infrastructure networks required to integrate
energy from renewable sources into the energy system,
including appeals related to environmental aspects,
shall be ensured to be subject to the most expeditious
administrative and judicial procedure that is available.
(14) Every relevant authority shall take into
account the planned installed renewable energy
generation capacity provided for in Malta’s integrated
national energy and climate plans submitted pursuant to
Articles 3 and 14 of Regulation (EU) 2018/1999 to
ensure its staff complement is suitably qualified and to
make any plans for upskilling and reskilling which may
be deemed necessary.
(15) Except when it coincides with other
administrative stages of the permit-granting procedure,
the duration of the permit-granting procedure shall not
include
(a) the time during which the renewable
energy plants, their grid connections and, with a
view to ensuring grid stability, grid reliability and
safety, the time during which the related
necessary grid infrastructure, is being built or
repowered;
(b) the time for the administrative stages
necessary for significant upgrades to the grid
required for ensuring grid stability, grid reliability
and grid safety;
(c) the time for any judicial appeals and
remedies, other proceedings before a court or
tribunal and alternative dispute resolution
mechanisms, including complaint procedures and
non-judicial appeals and remedies.
(16) All relevant authorities shall make publicly
available the decisions resulting from the permit-
granting procedures.".
6. Immediately after regulation 19 of the principal
regulations, as substituted, there shall be added the following new
(1) The
permit-granting
procedure
referred to in regulation 19(1) shall not exceed two (2)
years for renewable energy projects located outside
renewables acceleration areas provided that in the case
of offshore renewable energy projects, the permit-
granting procedure shall not exceed three (3) years.
(2) The timeframes referred to in sub-regulation
(1) shall be subject to the project developer complying
with reasonable timeframes established by each
relevant authority for the submission of any required
documentation, provided that, where duly justified on
the grounds of extraordinary circumstances, including
the extension of periods required for assessments in
accordance with the applicable Union environmental
legislation, any of those periods may be extended by up
to six (6) months, and in such case the project developer
shall be clearly informed of the extraordinary
circumstances that justify such an extension.
(3) Where an environmental assessment is
required pursuant to the Environmental Impact
Assessment Regulations or the Flora, Fauna and Natural
Habitats Protection Regulations as part of the permit
granting procedure for renewable energy projects located
outside renewables acceleration areas, it shall be carried
out in a single procedure that combines all relevant
assessments for the given renewable energy project, and
the relevant authority, taking into account the
information provided by the project developer, shall
issue an opinion on the scope and level of detail of the
information to be included by the project developer in
the environmental impact assessment report, of which
the scope shall not be subsequently extended.
(4) Where a renewable energy project has
adopted the necessary mitigation measures, any killing or
disturbance of the species protected in accordance with
regulations 24 and 25 of the Flora, Fauna and Natural
Habitats Protection Regulations and regulation 4(1) of
the Conservation of Wild Birds Regulations shall not be
considered to be deliberate.
(5) Where the mitigation measures to prevent as
much as possible the killing or disturbance of species
protected under the Flora, Fauna and Natural Habitats
Protection Regulations and the Conservation of Wild
Birds Regulations, or any mitigation measures adopted to
prevent any other environmental impact, have not been
widely tested as regards their effectiveness, their use may
be allowed for one (1) or several pilot projects for a
limited time period, provided that the effectiveness of
such mitigation measures is closely monitored and
appropriate steps are immediately taken if they do not
prove to be effective.
(6) The permit-granting procedure shall not
exceed twelve (12) months for land-based, or two (2)
years for offshore projects of the following types when
located outside renewables acceleration areas
(a) the repowering of renewable energy
power plants;
(b) new installations with an electrical
capacity of less than one hundred and fifty
kilowatts (150 kW);
(c) co-located energy storage;
(d) the connection to the grid for the
projects described in paragraphs (a) to (c).
(7) The timeframes established in sub-regulation
(6) shall include any environmental assessments which
may be required by the relevant law and either one may,
where duly justified on the grounds of extraordinary
circumstances, be extended by up to (3) three months
subject to the project developer being clearly informed of
the extraordinary circumstances that justify such an
extension.
(1) Where the repowering of a renewable
energy power plant does not result in an increase of the
capacity of said renewable energy power plant beyond
fifteen percent (15%), and without prejudice to any
assessment of potential environmental impact required
pursuant to sub-regulations (2) and (3), the applicable
timeframe for granting connections to the transmission
or distribution grid shall not exceed three (3) months
following notification to the relevant authority unless
there are justified safety concerns or there is technical
incompatibility of the system components.
(2) Where the repowering of a renewable energy
power plant is subject to a determination as to whether
the project requires an environmental impact assessment,
or to an environmental impact assessment pursuant to
regulation 10 of the Environmental Impact Assessment
Regulations, such a determination or environmental
impact assessment shall be limited to the potential
impact arising from a change or extension compared to
the original project.
(3) Where the repowering of a solar installation
does not entail the use of additional space and complies
with the applicable environmental mitigation measures
established for the original solar installation, the project
shall be exempt from any applicable requirements to
determine whether the project requires an environmental
impact assessment, or the carrying out of an
environmental impact assessment pursuant to regulation
10 of the Environmental Impact Assessment
Regulations.
(1) The relevant authorities shall ensure
that the permit-granting procedure referred to in
installation of solar
regulation 19 for the installation of solar energy
equipment and co-located energy storage, including
building-integrated solar installations, in existing or
future artificial structures, with the exclusion of
artificial water surfaces, shall not exceed three (3)
months, provided that the primary aim of such artificial
structures is not solar energy production or energy
storage.
(2) Certain areas or structures may be excluded
from the application of the timeframe established in
sub-regulation (1) for the purpose of protecting cultural
or historical heritage, national defence interests, or
safety reasons.
(3) By way of derogation from regulation 10(2)
of the Environmental Impact Assessment Regulations,
and from items 3.1.2.1, 3.4.2.1 and 10.0.2.7, alone or in
conjunction with item 13.0.1.1 of Schedule I to the said
regulations, the installation of solar equipment referred
to in sub-regulation (1) shall be exempt from the
requirement, if applicable, to carry out a dedicated
environmental impact assessment pursuant to
regulation 6(1) of the said regulations.
(4) The relevant authorities shall ensure that the
permit-granting procedure for the installation of solar
energy equipment with a capacity of one hundred
kilowatts (100 kW) or less, including for renewables
self-consumers and renewable energy communities,
shall not exceed one (1) month.
(5) In respect of the permit-granting procedure
referred to in sub-regulation (4), the lack of reply by the
relevant authorities or entities within the established
deadline following the submission of a complete
application shall result in the permit being considered
as granted, provided that the capacity of the solar
energy equipment does not exceed the existing capacity
of the connection to the distribution grid.
(6) Where the application of the capacity
threshold referred to in sub-regulation (4) leads to a
significant administrative burden or to constraints to the
operation of the electricity grid, a lower capacity
threshold may be applied, which shall, in all cases,
remain above ten point eight kilowatts (10.8 kW).
(1) The relevant authorities shall ensure
that any permit-granting procedure which may be
applicable to the installation of heat pumps below fifty
megawatts (50 MW) shall not exceed one (1) month,
provided that in the case of ground source heat pumps,
any applicable permit-granting procedure shall not
exceed three (3) months.
(2) The relevant authorities shall ensure that
connections to the transmission or distribution grid
shall be permitted within two (2) weeks of the
notification to the relevant entity for
(a) heat pumps of up to twelve kilowatts
(12 kW) electrical capacity; and
(b) heat pumps of up to fifty kilowatts (50
kW) electrical capacity installed by renewables
self-consumers, provided that the electrical
capacity of a renewables self-consumer’s
renewable electricity generation installation
amounts to at least sixty percent (60%) of the
electrical capacity of the heat pump.
(3) The timeframe laid down in sub-regulation
(2) shall not be applicable where
(a) there are justified safety concerns; or
(b) further works are required for grid
connections; or
(c) there is technical incompatibility of
the system components.
(4) Relevant authorities may exclude certain
areas or structures from the application of sub-
regulations (1) and (2) for the purpose of protecting
cultural or historical heritage, national defence interests
or safety reasons.
(5) Relevant authorities shall make all decisions
resulting from the permit-granting procedure referred to
in this regulation publicly available in accordance with
any applicable laws.
(1) Until climate neutrality is achieved,
the relevant authorities shall ensure that, in the permit-
granting procedure, the planning, construction and
operation of renewable energy plants, the connection of
such plants to the grid, the related grid itself, and
storage assets are presumed as being in the overriding
public interest and serving public health and safety
when balancing legal interests in individual cases for
the purposes of regulation 19(2), regulation 19(3) and
regulation 44(c) of the Flora, Fauna and Natural
Habitats Protection Regulations, regulation 5(7) of the
Water Policy Framework Regulations, and the
dispositions of regulation 9(1)(a) to 9(1)(d) of the
Conservation of Wild Birds Regulations.
(2) In duly justified and specific circumstances,
the application of sub-regulation (1) may be restricted
to certain parts of the Maltese territory, to certain types
of technology or to projects with certain technical
characteristics in accordance with the priorities set out
in Malta’s integrated national energy and climate plans
submitted pursuant to Articles 3 and 14 of Regulation
(EU) 2018/1999, subject to the Commission being
informed of such restrictions, together with the reasons
therefor.".
7. In the Maltese version only of the principal regulations, the General
words "stallazzjoni" u "istallazzjoni", wherever they occur, shall be amendment
the principal
substituted by the word "installazzjoni" and the words regulations.
"stallazzjonijiet" and "istallazzjonijiet", wherever they occur, shall be
substituted by the word "installazzjonijiet".
€1.32