Electricity (Amendment No. 3) Regulations, 2025
Table of Provisions (9)
Statutory Text (9 Articles)
L.N. 236 of 2025
REGULATOR FOR ENERGY AND WATER SERVICES ACT
(CAP. 545)
Electricity (Amendment No. 3) Regulations, 2025
IN EXERCISE of the powers conferred by article 37 of the
Regulator for Energy and Water Services Act, the Minister responsible
for energy and water services, after consultation with the Regulator for
Energy and Water Services, has made the following regulations:-
The title of these regulations is the Electricity (Amendment
No. 3) Regulations, 2025 and these regulations shall be read and
construed as one with the Electricity Regulations, hereinafter referred
to as the "principal regulations".
Regulation 2 of the principal regulations shall be amended
as follows
(a) immediately after the definition "non-frequency
ancillary service" there shall be added the following new
definition
""organised electricity marketplace" means an
electricity exchange, an electricity broker, an electricity
capacity platform or any other system or facility in which
multiple third-party buying or selling interests in wholesale
electricity products interact in a manner that may result in a
transaction and which operates in accordance with
transparent,
non-discriminatory,
and
market-based
principles, subject to applicable regulatory oversight where
required
Provided that an organised marketplace shall be
deemed accessible to a producer when it provides a non-
restrictive and technically feasible, and transparent
mechanism for such producer to offer and sell its electricity
under fair, non-discriminatory and commercially
reasonable terms;";
(b) in the Maltese version only, in the definition "swieq
tal-elettriku" the words "l-iskambji tal-enerġija elettrika" shall be
substituted by the words "electricity exchanges".
In the Maltese version only, in regulation 36(2)(g) of the Amends
principal regulations, the words "skambji ta’ enerġija" shall be regulation
the principal
substituted by the words "power exchanges".
regulations.
In the Maltese version only, in regulation 47(1)(o) of the Amends
principal regulations the words "l-iskambji tal-elettriku" shall be regulation
the principal
substituted by the words "electricity exchanges".
regulations.
In the Maltese version only, in regulation 49(2)(a) of the Amends
principal regulations the words "skambji konġunti tal-elettriku" shall regulation
the principal
be substituted by the words "electricity exchanges konġunti".
regulations.
Sub-regulation (1) of regulation 54A of the principal Amends
regulations shall be substituted by the following new sub-regulation: regulation
of the principal
regulations.
"(1) The distribution system operator shall offer to
purchase all electricity generated and exported to the grid from
any approved installation generating electricity from renewable
energy or high-efficiency cogeneration plant at the proxy for the
market price determined in the Fourth Schedule, until such time
as any organised electricity marketplace in which such producers
are able to sell their electricity becomes accessible
Provided that the distribution system operator shall
continue to offer to purchase all electricity generated and
exported to the grid from any approved small scale installation
generating electricity from renewable energy thereafter
Provided further that for the purposes of this
regulation an installation generating electricity from renewable
energy shall be considered small scale if its capacity is below
(a) 400kW
for
power-generating
facilities
commissioned until 31st December 2025; or
(b) 200kW
for
power-generating
facilities
commissioned from 1 January 2026.".
In the Maltese version only, in item 5 of the First Schedule Amends the
to the principal regulations, the words "elettriku skambjat" shall be First
to the principal
substituted by the words "electricity exchanges" and the words "mill- regulations.
iskambju" shall be substituted by the words "mill-exchange".
Part A of the Third Schedule to the principal regulations, Amends the
Third Schedule
shall be substituted by the following new Part
to the principal
regulations.
"PART A. New generation capacity
1. A producer who
(a)
produces electricity solely for his own use; and
(b)
is not connected in parallel to the distribution system;
and
(c) has installed a total peak generation capacity of less
than 1500 kVA;
shall be exempted from the requirement of an authorisation
to construct the new generation capacity and from the
requirement to hold a licence.
2. A producer producing electricity solely from renewable
energy or cogeneration plant, with a total continuous steady state 230/
400V AC rating up to 3.68kW (16 Amps) on any phase, or up to
4.6kW (20 Amps) on any phase, when the generation capacity is
equipped with automatic volt-var control, shall be exempted from the
requirement of an authorisation to construct the new generation
capacity and from the requirement to hold a licence but shall still be
required to notify the Regulator, in such form and manner as required
by the Regulator prior to construction of such new generation capacity
and submit to the Regulator such information as the Regulator may
request from time to time.".