Construction Sites Insurance Obligations Regulations, 2024
Table of Provisions (7)
Statutory Text (7 Articles)
L.N. 38 of 2024
BUILDING AND CONSTRUCTION AUTHORITY ACT
(CAP. 623)
Construction Sites Insurance Obligations Regulations, 2024
IN EXERCISE of the powers conferred by article 17 of the
Building and Construction Authority Act, the Minister responsible for
the construction industry, after consultation with the Building and
Construction Authority Board, has made the following regulations:-
(1) The title of these regulations is the Construction Sites Citation and
applicability.
Insurance Obligations Regulations, 2024.
(2) These regulations shall apply to any construction work
which commences after the coming into force of these regulations.
In these regulations, unless the context otherwise requires
Interpretation.
"Act" means the Building and Construction Authority Act;
"Authority" means the Building and
Construction
Authority as established by article 5 of the Act;
"certificate of completion of the construction works" means
the declaration of completion of works issued by the responsible
perit of all structural works and other works including the roof,
screed of roofs, terraces and yards, the closure of apertures and
other works to render the building sealed against the ingress of
water;
"Chief Executive Officer" shall have the same meaning as
assigned to it in the Act;
"client" shall have the same meaning as assigned to it in the
Act;
"construction" shall have the same meaning as assigned to
it in the Act;
"construction site" means the site where construction works
are executed and where the equipment and, or materials and
works and services are delivered to, and where workers are
executing their profession for the purpose of the project as
approved. For the purpose of these regulations, construction site
shall also include the site contiguous to the site where
construction works are being carried out, and used for the
purpose of temporary placing of buildings, moveable structures,
works, plants or machinery required in connection with, and for
the duration of the construction works;
"contiguous property" means the immediately adjacent
third party property to the construction site that may divide or
otherwise, a dividing party wall with the construction site,
whether on the side or back of the site, or overlying or
underlying other third party property;
"declaration of insurance cover" means a document which
shall be issued by an authorised insurance undertaking and such
document shall be submitted to the Chief Executive Officer
within two (2) weeks prior to the commencement of any
construction works
Provided that this declaration shall serve only as a
confirmation of the existence of insurance cover and the details
of the terms and conditions on which the insurance has come into
effect, shall be verified and ascertained only from the insurance
contract;
"insurance contract" means a contractual agreement with an
insurance undertaking authorised under the Insurance Business
Act or a European insurance undertaking as defined in the same
Act to cover the works inherent to the project as well as to cater
for the protection and indemnity of any potential losses arising
from the execution of the works as listed on the method
statement to the project, in respect of liability arising to any third
party including injury, death or property damage that may result
from the works
Provided that the insurance contract shall specify that
it is subject to the Laws of Malta, and the Courts of Malta shall
have jurisdiction to hear and decide any proceedings instituted
relating to the insurance contract and any issue ancillary to the
said insurance contract;
"responsible perit" means the perit in charge of the project
and who assumes responsibility for the execution of the project
in its entirety;
"works" shall have the same meaning as assigned to it in
the Act.
Any construction site shall be covered by a valid insurance
policy that provides against any loss, damage, injury or death that may
be sustained by any third party consequent to any act or omission
occasioned or brought about by the construction works or activities
being undertaken by the clients, their contractors and any sub-
contractors engaged to carry out such works, including any works done
or omitted to be done by their employees
Provided that the insurance cover shall cover a third party
liability limit of not less than seven hundred and fifty thousand euro
(€750,000) prior to the issuance of the clearance to commence the
construction works by the Chief Executive Officer. The said insurance
policy shall be maintained or extended or renewed throughout the
duration of the works until the submission of a certificate of
completion of the construction works in accordance with regulation 6.
The extent of liability of cover over the minimum indicated Extent of
in regulation 3 in the insurance policy shall be determined by the liability cover.
insurance contract based on an valid assessment of the risks involved.
The client shall submit a declaration of insurance cover to Declaration of
the Authority in the prescribed form which shall be made available on insurance cover.
the Authority’s website.
(1) On completion of the construction works, the client Certificate of
shall submit to the Chief Executive Officer, within two (2) weeks from completion
the construction
completion of the works, a certificate of completion of the works.
construction works as approved by the responsible perit
Provided that a certificate of completion of the construction
works shall be submitted to the Chief Executive Officer as provided in
sub-regulation (1).
(2) The date of the certificate of completion of the construction
works shall be published on the Authority’s website by the Chief
Executive Officer, and the responsible perit shall within two (2) weeks
from the publication on the website, notify also all the owners and
occupiers of those properties, for which a condition report in
accordance with regulation 7 of the Avoidance of Damage to Third S.L. 623.06.
Party Property Regulations had been submitted by the perit who
compiled the said condition report, with the details of such certificate
regarding the project completion.