from Solar Photovoltaic Installations)
Table of Provisions (15)
Statutory Text (15 Articles)
L.N. 43 of 2023
REGULATOR FOR ENERGY AND WATER SERVICES ACT
(CAP. 545)
Feed-in Tariffs Scheme (Electricity Generated
from Solar Photovoltaic Installations)
(Amendment) Regulations, 2023
IN EXERCISE of the powers conferred by article 37 of the
Regulator for Energy and Water Services Act, the Minister responsible
for energy and water services after consultation with the Regulator, has
made the following regulations:-
(1) The title of these regulations is the Feed-in Tariffs
Scheme (Electricity Generated from Solar Photovoltaic Installations)
(Amendment) Regulations, 2023 and these regulations shall be read
and construed as one with the Feed-in Tariffs Scheme (Electricity
Generated from Solar Photovoltaic Installations) Regulations,
hereinafter referred to as "the principal regulations".
(2) These regulations shall be deemed to have come into force
on 1st January 2023.
Regulation 2 of the principal regulations shall be amended
as follows
(a) immediately after the definition "DC" thereof there
shall be added the following new definition
" "de minimis aid" means aid awarded in accordance
with Commission Regulation (EU) No 1407/2013 of 18
December 2013 on the application of Articles 107 and 108
of the Treaty on the Functioning of the European Union to
de minimis aid;";
(b) the definition "distribution system operator" thereof
shall be substituted by the following new definition
" "distribution system operator" shall have the same
meaning as assigned to it in the Electricity Regulations;";
(c) the definition "the Minister" shall be substituted by
the following new definition
" "Minister" shall have the same meaning as assigned
to it in the Act;";
(d) the definition "operating aid" thereof shall be
substituted by the following new definition
" "operating aid" means the difference between the
feed-in tariffs under the Second Schedule and the proxy
for the market price for electricity established by the
Electricity Regulations;";
(e) the definition "proxy for the market price" thereof
shall be substituted by the following new definition
" "proxy for the market price" shall have the same
meaning as assigned to it in the Electricity Regulations;";
and
(f) the definition "undertaking in difficulty" thereof shall
be deleted.
Regulation 3 of the principal regulations shall be Substitutes
regulation 3 of
substituted by the following new regulation
the principal
regulations.
" Applicability.
3. These regulations shall apply to solar
photovoltaic installations insofar as such solar
photovoltaic installations are installed either in
residential or domestic premises or in non-residential or
institutional households, and which are to be connected to
the distribution system, and which are so connected either
directly or indirectly with the distribution system with the
appropriate protective and metering equipment
Provided that a feed-in tariff in accordance
with these regulations may only be awarded to solar
photovoltaic capacities of less than 40kWp.".
Sub-regulation (6) of regulation 4 of the principal Amends
regulation 4 of
regulations shall be amended as follows
the principal
regulations.
(a) in paragraph (b) thereof, the words "the proxy for the
market price established under the Fourth Schedule;" shall be
substituted by the words "the proxy for the market price
established under the Electricity Regulations;"; and
(b) in paragraph (c) thereof, the words "the proxy for the
market price established under the Fourth Schedule." shall be
substituted by the words "the proxy for the market price
established under the Electricity Regulations.".
In regulation 4A of the principal regulations, the words "the
proxy for the market price established under the Fourth Schedule"
shall be substituted by the words "the proxy for the market price
established under the Electricity Regulations".
In regulation 4C of the principal regulations, the words
"paid to the installation operator." shall be substituted by the words
"paid to the installation operator:" and immediately after there shall be
added the following new proviso
"Provided that this regulation shall only apply in
cases where the original application for a feed-in tariff was
approved with regard to a residential or domestic premises and
subject to such premises being continually categorised for billing
purposes as a residential or domestic premises throughout the
duration of the guaranteed period of payment.".
In the proviso to regulation 6 of the principal regulations,
the words "at the applicable electricity rate as established in the Fourth
Schedule." shall be substituted by the words "at the applicable
electricity rate as established in the Electricity Regulations.".
Regulation 7 of the principal regulations shall be deleted.
Regulation 9 of the principal regulations shall be amended
as follows
(a) in the second proviso to sub-regulation (1) thereof,
the words "at the applicable rate for such electricity as at the time
provided in the Fourth Schedule to these regulations." shall be
substituted by the words "at the applicable rate for such
electricity as at the time provided in the Electricity
Regulations."; and
(b) in sub-regulation (3) thereof, the words "for such
electricity at the rate established in the Fourth Schedule." shall
be substituted by the words "for such electricity at the rate
established in the Electricity Regulations.".
In sub-regulation (2) of regulation 12 of the principal
regulations, the words "the proxy for the market price established
under the Fourth Schedule." shall be substituted by the words "the
proxy for the market price established under the Electricity
Regulations.".
In regulation 13 of the principal regulations, immediately Amends
after the words "tradable green certificate" there shall be added the regulation
words "or guarantees of origin certificate".
The First Schedule to the principal regulations shall be Amends the
amended as follows
(a) item 6 thereof shall be substituted by the following
new item
"6. The solar photovoltaic installation is
commissioned and an application to connect the
installation to the distribution system has been submitted
to the distribution system operator not later than twelve
(12) months from the date of approval of the FIT by the
Regulator. In the case that the solar photovoltaic
installation is not commissioned and an application to
connect the installation to the distribution system is not
submitted to the distribution system operator within the
aforesaid twelve (12) months, the eligibility for a FIT
shall be subject to the beneficiary of the FIT applying to
the Regulator for an extension, which extension shall not
be of more than
(a) twenty-four (24) months, in the case of
feed in tariff applications approved prior to the 1st
January 2023;
(b) twelve (12) months in the case of feed in
tariff applications approved after the 1st January
2023
Provided that any such extension may be
granted only once. The aforesaid extensions, irrespective
of the date of application for the extension, shall be
reckoned to commence as from the first day immediately
following the end of the mentioned first twelve (12)
month period allowed for the commissioning and
submittal of the application for connection to the
distribution system. The rate of the FIT which would be
then applicable shall be that in force at the time of the
submission of the application for said extension by the
beneficiary or, if no such FIT has been established, the
FIT originally allocated to the solar PV installation
reduced by euro 0.005 per kWh."; and
(b) in item 9 thereof, the words "(e) type of aid and
amount of public funding needed for the project. The applicant
for a feed-in tariff must submit, together with the aforesaid
written application, a non-refundable application fee of fifty euro
(€50) in the case of a solar photovoltaic installation in non-
residential premises having a capacity equal or larger than
40kWp and less than 400kWp." shall be substituted by the
words "(e) comprehensive declaration of the de minimis aid
received by the applicant and as required by the application
form."
The Second Schedule to the principal regulations shall be
amended as follows
(a) in item 1 thereof, Table A shall be substituted by the
following new Table
" Table A: Caps and Feed-in Tariffs applicable for solar photovoltaic
installations approved under the FIT scheme
Maximum units allocated
per annum for FIT
Capacity of solar
Feed-in Tariffs
photovoltaic
applicable between
payment to PV systems
installation installed
the 1st January 2023
FIT Scheme
approved under this FIT
in any location
and the 31st December
scheme between the 1st
January 2023 and the
31s t December 2023
=>1kWp and <40kWp 15 cents per kWh
12. 8 GWh per a n n u m
(8MWp) ";
(b) in item 2 thereof, the words "Electricity Market
Regulations (S.L. 545.13)" shall be substituted by the words
"Electricity Regulations (S.L.545.34)"; and
(c) in paragraph (a) of item 4 thereof, the words "1st
January 2022 until the 30th December 2022;" shall be substituted
by the words "1st January 2023 until the 31st December 2023;".
The Third Schedule and the Fourth Schedule to the
principal regulations shall be deleted.
€0.45