L.N. 215 of 2023
DEVELOPMENT PLANNING ACT
(CAP. 552)
Streamlining Measures for Advancing the Realisation
of the Trans-European Transport Network
(TEN-T) Regulations, 2023
IN EXERCISE of the powers conferred by articles 84 and 85 of
the Development Planning Act, the Minister responsible for the
Planning Authority, after consultation with the Planning Authority, has
made the following regulations:-
(1) The title of these regulations is the Streamlining Citation and
Measures for Advancing the Realisation of the Trans-European applicability
Transport Network (TEN-T) Regulations, 2023.
(2) These regulations shall apply to permit-granting procedures
required in order to authorise the implementation of
(a) projects that are part of pre-identified sections of the
core network as listed in the Annex to Directive (EU) 2021/1187
of the European Parliament and of the Council of 7 July 2021 on
streamlining measures for advancing the realisation of the trans-
European transport network (TEN-T); and
(b) projects on the core network corridor "Scandinavian –
Mediterranean", therefore effecting the ports of Valletta and
Marsaxlokk in accordance with Regulation (EU) 2021/1153 of
the European Parliament and of the Council of 7 July 2021
establishing the Connecting Europe Facility and repealing
Regulations (EU) No 1316/2013 and (EU) No 283/2014, with a
total cost exceeding three hundred million euro (€300,000,000)
not exclusively related to telematic applications, new
technologies and innovation within the meaning of Articles 31
and 33 of Regulation (EU) No 1315/2013 of the European
Parliament and of the Council of 11 December 2013 on Union
guidelines for the development of the trans-European transport
network and repealing Decision No 661/2010/EU.
(3) This regulation shall also apply to public procurements in
cross-border projects falling within the scope of these regulations.
(4)
These regulations transpose the provisions of Directive
(EU) 2021/1187 of the European Parliament and of the Council of 7
July 2021 on streamlining measures for advancing the realisation of
the trans-European transport network (TEN-T).
(1) Unless otherwise stated in these regulations, the
definitions prescribed in the Act shall apply.
(2)
In these regulations, unless the context otherwise requires
"Act" means the Development Planning Act;
"authorising decision" means the decision or a set of
decisions, which may be of an administrative nature, taken
simultaneously or successively by the Authority, not including
decisions further to appeal, that determine whether or not a
project promoter is entitled to implement the project on the
geographical area concerned, without prejudice to any decision
taken in the context of an administrative or judicial appeal
procedure;
"the Authority" means the same as the meaning assigned to
it in article 2 of the Act;
"cross-border project" means a project covering a cross-
border section between two (2) or more Member States of the
European Union;
"Directive 2014/24/EU" means Directive 2014/24/EU of
the European Parliament and of the Council of 26 February 2014
on public procurement and repealing Directive 2004/18/EC;
"Directive 2014/25/EU" means Directive 2014/25/EU of
the European Parliament and of the Council of 26 February 2014
on procurement by entities operating in the water, energy,
transport and postal services sectors and repealing Directive
2004/17/EC;
"Directive (EU) 2021/1187" means Directive (EU) 2021/
1187 of the European Parliament and of the Council of 7 July
2021 on streamlining measures for advancing the realisation of
the trans-European transport network (TEN-T);
"joint authority" means an authority established by mutual
agreement between Malta and one (1) or more other Member
States of the European Union to facilitate the permit-granting
procedures related to cross-border projects, including joint
authorities established by designated authorities where those
designated authorities have been empowered by said Member
States to establish joint authorities;
"permit-granting procedure" means any procedure for the
determination of an application, from its validation date, of an
individual project falling within the scope of these regulations in
order to obtain the authorising decision as required by the
Authority under European Union or national law, with the
exception of urban or land use planning, of procedures related to
the award of public procurement contracts, and of steps
undertaken at strategic level that do not refer to a specific
project, such as strategic environmental assessment, public
budgetary planning, as well as national or regional transport
plans;
"project" means a proposal for the construction, adaptation
or modification of a defined section of the transport
infrastructure which aims to improve the capacity, safety and
efficiency of that infrastructure and of which the implementation
has to be approved by means of an authorising decision;
"project promoter" means the applicant for authorisation of
the implementation of a project or the public authority which
initiates a project;
"Regulation (EU) 1315/2013" means Regulation (EU) No
1315/2013 of the European Parliament and of the Council of 11
December 2013 on Union guidelines for the development of the
trans-European transport network and repealing Decision No
661/2010/EU;
"Regulation (EU) 2021/1153" means Regulation (EU)
2021/1153 of the European Parliament and of the Council of 7
July 2021 establishing the Connecting Europe Facility and
repealing Regulations (EU) No 1316/2013 and (EU) No 283/
2014.
(1) The Authority, and any other authority involved in Priority status.
the permit-granting procedure, shall give priority to projects falling
within the scope of these regulations.
(2) National procedures for priority projects shall be applied to
projects falling within the scope of these regulations, without prejudice
to the objectives, requirements and time-limits of these regulations.
(3) Sub-regulations (1) and (2) shall be without prejudice to
any budgetary decisions.
(1)
The Authority shall
(a) take all necessary measures to provide project
promoters for projects falling within the scope of these
regulations with easily available information about its identity;
(b) be the point of contact for information for the project
promoter and for other relevant authorities involved in the
procedure leading to the authorising decision for a given project;
(c) provide the project promoter, where required to do so
under national law, with the detailed outline of the project
application referred to in regulation 6(6), including information
on the indicative time-limits relating to the permit-granting
procedures, in accordance with the four (4) year time-limit
referred to in regulation 5(1);
(d) oversee the timeframe of the permit-granting
procedure, and in particular record any extension of the time-
limit referred to in regulation 5(3);
(e) if requested, provide guidance to the project promoter
concerning the submission of all relevant information and
documents, including all the permits, decisions and opinions
which have to be obtained and provided for the authorising
decision;
(2) The Authority may also provide guidance to the project
promoter as to what additional information and, or documents should
be delivered in the event that the notification referred to in regulation
6(1) has been rejected.
(3) Sub-regulations (1) and (2) shall be without prejudice to the
competence of any other authorities involved in the permit-granting
procedure and to the possibility for the project promoter to contact the
individual authorities for the specific permits, decisions or opinions
which form part of the authorising decision.
(1) The permit-granting procedure, including the
deadlines for that procedure, shall not exceed four (4) years from the
start of the permit-granting procedure.
(2) Sub-regulation (1) shall be without prejudice to obligations
arising from international and European Union law and shall not
include periods necessary to undertake appeal procedures and to seek
judicial remedies before a court or tribunal, as well as any periods
necessary to implement any resulting decisions or remedies.
(3) The Authority shall adopt the necessary measures to ensure
that, in duly justified cases, an appropriate extension of the four (4)
year period referred to in sub-regulation (1) may be granted. The
duration of the extension shall be determined on a case-by-case basis,
be duly justified and be limited to the purpose of completing the
permit-granting procedure and delivering the authorising decision.
When such an extension has been granted, the project promoter shall
be informed of the reasons for granting it. A further extension may be
granted once, under the same conditions.
(4) The Authority shall not be held responsible where the four
(4) year period referred to in sub-regulation (1), as extended in
accordance with sub-regulation (3), is not complied with where the
delay incurred is due to the project promoter.
(1) The project promoter shall notify the project to the Organisation of
Authority or, where appropriate, to the joint authority established in the
granting
accordance with regulation 7(2). The notification of the project by the procedure.
project promoter shall serve as the start of the permit-granting
procedure.
(2) In order to facilitate the assessment of the maturity of the
project, the Authority shall carry out the vetting of the notification to
define the level of detail of information and the relevant documents
which shall be provided by the project promoter when notifying a
project. If the project is not mature, the notification shall be rejected by
a duly justified decision not later than four (4) months after the receipt
of the notification.
(3) The Authority shall take the necessary measures to ensure
that project promoters receive general information as a guide to
notification, adapted, where relevant, to the mode of transport
concerned, containing information about the permits, decisions and
opinions that may be required for the implementation of a project.
(4) That information shall, for each permit, decision or
opinion, include the following
(a) general information about the material scope and the
level of detail of the information which is to be submitted by the
project promoter;
(b) the applicable time-limits or, if there are no such
time-limits, indicative time-limits; and
(c) details of the authorities and stakeholders normally
involved in consultations linked to the different permits,
decisions and opinions.
(5) That information shall be easily accessible to all relevant
project promoters, in particular through electronic or physical
information portals.
(6) In order to facilitate successful notification, the Authority
shall establish a detailed outline of the project application upon request
by the project promoter. This detailed outline shall include the
following information customised for the individual project
(a) the individual stages of the procedure and applicable
time-limits or, if there are no such time-limits, indicative time-
limits;
(b) the material scope and the level of detail of the
information to be submitted by the project promoter;
(c) a list of permits, decisions and opinions which shall
be obtained by the project promoter during the permit-granting
procedure, in accordance with European Union and national law;
(d) the details of the authorities and stakeholders which
shall be involved in connection with the respective obligations,
including during the formal phase of the public consultation.
(7) The detailed outline of the project application shall remain
valid during the permit-granting procedure. Any amendment to the
detailed outline of the project application shall be duly justified.
(8) The Authority may provide the project promoter, on
request, with the information supplementing the elements referred to
in sub-regulation (6).
(9) When the project promoter has submitted the complete full
development application, it shall be validated by the Authority and the
authorising decision shall be adopted within the time-limit referred to
in regulation 5(1).
(10) The authorities involved in the permit-granting procedure
shall notify the Authority that the required permits, decisions, opinions
have been issued.
(1) For projects subject to these regulations that concern
Malta and one (1) or more other Member States of the European
Union, the Authority shall cooperate with the competent authorities of
those Member States with a view to coordinating their timetables and
agreeing on a joint schedule concerning the permit-granting procedure.
(2)
For cross-border projects subject to these regulations, a
joint authority may be established.
(3) Further to the stipulations in sub-regulation (1), the
Authority shall take the necessary measures to ensure that the
European Coordinators designated in accordance with Article 45 of
Regulation (EU) No 1315/2013 receive information on the permit-
granting procedures, and that the European Coordinators may facilitate
contacts between authorities appointed in the context of the permit-
granting procedures for cross-border projects.
(4) The Authority shall, if the time-limit referred to in
regulation 5(1) is not observed, and upon their request, provide the
European Coordinators concerned with information on the measures
taken or planned to be taken in order to enable the permit-granting
procedure to be concluded with the least possible delay.
(1) When procurement procedures are conducted by a Procurement in
joint authority in a cross border project subject to these regulations, the cross-border
projects.
Authority shall take the necessary measures to ensure that the joint
authority applies the national law of one (1) of the participating
Member States of the European Union and, that law shall be
determined in accordance with paragraph (a) of Article 39(5) of
Directive 2014/24/EU or paragraph (a) of Article 57(5) of Directive
2014/25/EU, as applicable, unless an agreement between the
participating Member States provides otherwise. Such an agreement
shall, in any case, provide for the application of the national law of one
(1) of the participating Member States to the procurement procedures
conducted by the joint authority.
(2) For procurement conducted by a subsidiary of a joint
authority, the Authority shall take the necessary measures to ensure
that the subsidiary applies the national law of one (1) of the
participating Member States of the European Union. The Authority
may decide jointly with the competent authorities of the participating
Member States that the subsidiary is to apply the national law
applicable to the joint authority.
(1) These regulations shall not apply to projects for Transitional
which the permit-granting procedures started before 10 August 2023. provisions.
(2) Regulation 8 shall only apply to such contracts for which
the call for competition has been sent, or, in cases where a call for
competition is not foreseen, where the contracting authority or
contracting entity commenced the procurement procedure after 10
August 2023.
(3) Regulation 8 shall not apply to a joint authority set up
before 9 August 2021, if the procurement procedures of that joint
authority continue to be governed by the law applicable to its
procurements on that date.