Malta Government Gazette — Legal Notice 2021 45 · Gazzetta tal-Gvern ta’ Malta Nru. 20,568 - 09.02.2021<P Class=Msonormal — Electrical Installations (Amendment) Regulations, 2021

L.N. 45 of 2021

REGULATOR FOR ENERGY AND WATER SERVICES ACT

(CAP. 545)

Electrical Installations (Amendment) Regulations, 2021

IN EXERCISE of the powers conferred by article 37(1) of the

Regulator for Energy and Water Services Act, the Minister for Energy,

Enterprise and Sustainable Development, after consultation with the

Regulator for Energy and Water Services, has made the following

regulations:-

Malta Government Gazette — Legal Notice 2021 45 · Gazzetta tal-Gvern ta’ Malta Nru. 20,568 - 09.02.2021<P Class=Msonormal — Electrical Installations (Amendment) Regulations, 2021

The title of these regulations is the Electrical Installations Citation.

(Amendment) Regulations, 2021 and these regulations shall be read

and construed as one with the electrical Installations Regulations, S.L. 545. 24.

hereinafter referred to as "the principal regulations".

Malta Government Gazette — Legal Notice 2021 45 · Gazzetta tal-Gvern ta’ Malta Nru. 20,568 - 09.02.2021<P Class=Msonormal — Electrical Installations (Amendment) Regulations, 2021

Regulation 2 of the principal regulations shall be amended Amends

regulation 2 of

as follows

the principal

regulations.

(a) immediately after the definition "authorised

provider", there shall be added the following new definitions

" "backup equipment" means the additional hardware

and control system other than the anti-islanding protection

that disconnects the generators and/or energy storage from

the distribution system and changes over to a backup

operation mode;

"backup operation mode" means the disconnection

from the distribution system and continuing operation of a

generator or energy storage in the event of the loss of

power from the distribution system with complete effective

isolation from the distribution system while in this mode of

operation;

"Commission Regulation (EU) 2016/631" means

Commission Regulation (EU) 2016/631 of 14 April 2016

establishing a network code on requirements for grid

connection of generators;";

immediately after the definition "customers" there

(b)

shall be added the following new definition

" "distribution system" shall have the same meaning

as assigned to it in the Electricity Market Regulations;

(c) immediately after the definition "electricity service

meter" there shall be added the following new definitions

" "energy storage" means, in the electricity system,

the deferring of the final use of electricity to a moment later

than when it was generated, or the conversion of electrical

energy into a form of energy which can be stored, the

storing of such energy, and the subsequent reconversion of

such energy into electrical energy or use as another energy

carrier;

"energy storage facility" means, in the electricity

system, a facility where energy storage occurs.";

(d) immediately after the definition "I.E.E. Regulations"

there shall be added the following new definition

" "interface protection system" means an automatic

switch that disconnects the energy storage facility from the

distribution system in the event of loss of supply from the

distribution system or deviation of the voltage or frequency

at the supply terminals from values declared for normal

supply;

(e) in the definition "Minister", the word "resources"

shall be substituted by the word "energy;" and immediately

thereafter there shall be added the following new definition

" "MSA EN 50549-1" means MSA EN 50549-1

Requirements for generating plants to be connected in

parallel with distribution networks - Part 1: Connection to a

LV distribution network - Generating plants up to and

including Type B;"; and

(f) immediately after the definition "Network code"

there shall be added the following new definition

" "new generator" means a power generating module

which is not considered existing within the meaning of

Article 4 of Commission Regulation 2016/631".

Malta Government Gazette — Legal Notice 2021 45 · Gazzetta tal-Gvern ta’ Malta Nru. 20,568 - 09.02.2021<P Class=Msonormal — Electrical Installations (Amendment) Regulations, 2021

In paragraph (c) of sub-regulation (2) of regulation 5, the Amends

words "from the Regulator." shall be substituted by the words "from regulation

the Regulator;" and immediately thereafter there shall be added the regulations.

following new paragraph

"(d) any person who has attained the age of eighteen (18)

years at the time of application.".

Malta Government Gazette — Legal Notice 2021 45 · Gazzetta tal-Gvern ta’ Malta Nru. 20,568 - 09.02.2021<P Class=Msonormal — Electrical Installations (Amendment) Regulations, 2021

In sub-regulation (2) of regulation 8 of the principal Amends

regulations, the words "per annum" wherever they occur shall be regulation

Malta Government Gazette — Legal Notice 2021 45 · Gazzetta tal-Gvern ta’ Malta Nru. 20,568 - 09.02.2021<P Class=Msonormal — Electrical Installations (Amendment) Regulations, 2021

Regulation 19 of the principal regulations shall be Substitutes

substituted by the following new regulation

Malta Government Gazette — Legal Notice 2021 45 · Gazzetta tal-Gvern ta’ Malta Nru. 20,568 - 09.02.2021<P Class=Msonormal — Electrical Installations (Amendment) Regulations, 2021

Generators operating in parallel with the

electricity distribution system shall

(a) comply with the Network Code; and

(b) a new generator shall comply with

Commission Regulation EU) 2016/631and unless

specified otherwise in the Network Code, shall also

comply with MSA EN 50549-1 or an equivalent

standard thereof when so considered by the

Standards and Metrology Institute within the Malta

Competition and Consumer Affairs Authority;

(c) be provided with backup equipment

when designed to operate in backup operation mode

which backup equipment shall use hardware that

physically breaks the connection with the

distribution system. Solid state relays or other

semiconductors to break the connection are not

permitted

Provided that the protection of the internal

electrical installation shall remain functional also when

supplied through the generator operating in backup

operation mode.

The anti-islanding protection in all cases shall

automatically disconnect from the distribution system in

the event of loss of supply from the distribution system,

and/or deviation of voltage and/or frequency from normal

supply conditions.

(d) have appropriate signage indicating the

presence on the premises of a generator equipped

with Backup operation mode function.".

6. Immediately after regulation 19 of the principal

regulations, there shall be added the following new regulation

Malta Government Gazette — Legal Notice 2021 45 · Gazzetta tal-Gvern ta’ Malta Nru. 20,568 - 09.02.2021<P Class=Msonormal — Electrical Installations (Amendment) Regulations, 2021

An energy storage facility operated in parallel

with the electricity distribution system shall include an

interface protection system

(a) that complies with the Network Code;

and

(b) which, unless the Network Code

provides otherwise, complies with MSA EN

50549-1 or an equivalent standard thereof when so

considered by the Standards and Metrology

Institute within the Malta Competition and

Consumer Affairs Authority;

(c) which shall be provided with backup

equipment when designed to operate in backup

operation mode which backup equipment shall use

hardware that physically breaks the connection

with the distribution system. Solid state relays or

other semiconductors which break the connection

are not permitted.

Provided that the protection of the internal

electrical installation shall remain functional also when

supplied through the energy storage facility operating in

backup operation mode.

The interface protection system in all cases

shall automatically disconnect from the distribution

system in the event of loss of the supply from the

distribution system, and/or deviation of voltage and/or

frequency from normal supply conditions.

(d) which

has

appropriate

signage

indicating the presence on the premises of an

energy storage facility equipped with backup

operation mode function.".

7. In the First Schedule to the principal regulations, the words

"• A birth certificate from the Public Registry;" shall be deleted.