Electricity Regulations, 2021
Table of Provisions (66)
Statutory Text (66 Articles)
L.N. 235 of 2021
REGULATOR FOR ENERGY AND WATER SERVICES ACT
(CAP. 545)
Electricity Regulations, 2021
IN EXERCISE of the powers conferred by article 37(1) of the
Regulator for Energy and Water Services Act, the Minister for Energy,
Enterprise and Sustainable Development after consultation with the
Regulator for Energy and Water Services, has made the following
regulations:-
(1) The title of these regulations is the Electricity
Regulations, 2021.
(2) These regulations transpose Directive (EU) 2019/944 of the
European Parliament and of the Council of 5 June 2019 on common
rules for the internal market for electricity and amending Directive
2012/27/EU (recast). These regulations
(a) establish common rules for the generation,
transmission, distribution, energy storage and supply of
electricity, together with consumer protection provisions, with a
view to creating truly integrated, competitive, consumer-centred,
flexible, fair and transparent electricity markets in the Union;
(b) using the advantages of an integrated market, aim to
ensure affordable, transparent energy prices and costs for
consumers, a high degree of security of supply and a smooth
transition towards a sustainable low-carbon energy system;
(c) lay down key rules relating to the organisation and
functioning of the Union electricity sector, in particular rules on
consumer empowerment and protection, and insofar as they are
applicable, on open access to the integrated market, on third-
party access to transmission and distribution infrastructure,
unbundling requirements, and rules on the independence of the
Regulator;
(d) set out modes for the Regulator and transmission
system operators to cooperate towards the creation of a fully
interconnected internal market for electricity that increases the
integration of electricity from renewable sources, free
competition and security of supply.
(3) These regulations also transpose Articles 4(9) and 4(11) of
Directive 2014/94/EU of the European Parliament and of the Council
of 22 October 2014 on the deployment of alternative fuels
infrastructure.
Minimum Requirements for Billing and Billing Information
(regulation 15)
1. Minimum information to be contained on the bill and in the
billing information
1.1. The following key information shall be prominently
displayed to final customers in their bills, distinctly separate from
other parts of the bill
(a) the price to be paid and a breakdown of the price
where possible, together with a clear statement that all energy
sources may also benefit from incentives that were not financed
through the levies indicated in the breakdown of the price;
(b)
the date on which payment is due.
1.2. The following key information shall be prominently
displayed to final customers in their bills and billing information,
distinctly separate from other parts of the bill and billing information
(a)
electricity consumption for the billing period;
(b)
the name and contact details of the supplier, including
a consumer support hotline and email address;
(c)
the tariff name;
(d)
the end date of the contract, if applicable;
(e) the information on the availability and benefits of
switching;
(f) the final customer's switching code or unique
identification code for the final customer's supply point;
(g) information on final customers' rights as regards out-
of-court dispute settlement, including the contact details of the
entity responsible pursuant to regulation 23;
(h)
the single point of contact referred to in regulation
(i) a link or reference to where comparison tools referred
to in regulation 11 can be found.
1.3. Where bills are based on actual consumption or remote
reading by the operator, the following information shall be made
available to final customers in, with or signposted to within their bills
and periodic settlement bills
(a) comparisons of the final customer's current electricity
consumption with the final customer's consumption for the same
period in the previous year in graphic form;
(b) contact information for consumer organisations,
energy agencies or similar bodies, including website addresses,
from which information may be obtained on available energy
efficiency improvement measures for energy-using equipment;
(c) comparisons with an average normalised
or
benchmarked final customer in the same user category.
2. Frequency of billing and the provision of billing
information
(a) billing on the basis of actual consumption shall take
place at least once a year;
(b) where the final customer does not have a meter that
allows remote reading by the operator, or where the final
customer has actively chosen to disable remote reading in
accordance with national law, accurate billing information based
on actual consumption shall be made available to the final
customer at least every six (6) months, or once every three (3)
months, if requested or where the final customer has opted to
receive electronic billing;
(c) where the final customer does not have a meter that
allows remote reading by the operator, or where the final
customer has actively chosen to disable remote reading in
accordance with national law, the obligations in points (a) and
(b) may be fulfilled by means of a system of regular self-reading
by the final customer, whereby the final customer communicates
readings from the meter to the operator; billing or billing
information may be based on estimated consumption or a flat
rate only where the final customer has not provided a meter
reading for a given billing interval;
(d) where the final customer has a meter that allows
remote reading by the operator, accurate billing information
based on actual consumption shall be provided at least every
month; such information may also be made available via the
internet, and shall be updated as frequently as allowed by the
measurement devices and systems used.
3. Breakdown of the final customer's price
The customer's price is the sum of the following three
components: the energy and supply component, the network
component (transmission and distribution) and the component
comprising taxes, levies, fees and charges.
Where a breakdown of the final customer’s price is presented in
bills, the common definitions of the three components in that
breakdown established under Regulation (EU) 2016/1952 of the
European Parliament and of the Council shall be used.
4. Access to complementary information on historical
consumption
To the extent that complementary information on historical
consumption is available, such information shall be made available, at
the request of the final customer, to the supplier or service provider
designated by the final customer.
Where the final customer has a meter that allows remote reading
by the operator installed, the final customer shall have easy access to
complementary information on historical consumption allowing
detailed self-checks.
Complementary information on historical consumption shall
include
(a) cumulative data for at least the three previous years
or the period since the start of the electricity supply contract, if
that period is shorter. The data shall correspond to the intervals
for which frequent billing information has been produced; and
(b) detailed data according to the time of use for any day,
week, month and year, which is made available to the final
customer without undue delay via the internet or the meter
interface, covering the period of at least the previous twenty-four
(24) months or the period since the start of the electricity supply
contract, if that period is shorter.
5. Disclosure of energy sources
Suppliers shall specify in bills the contribution of each energy
source to the electricity purchased by the final customer in accordance
with the electricity supply contract (product level disclosure).
The following information shall be made available to final
customers in, with, or signposted to within their bills and billing
information
(a) the contribution of each energy source to the overall
energy mix of the supplier (at national level, namely in the
Member State in which the electricity supply contract has been
concluded, as well as at the level of the supplier if the supplier is
active in several Member States) over the preceding year in a
comprehensible and clearly comparable manner;
(b) information on the environmental impact, in at least
terms of CO 2 emissions and the radioactive waste resulting from
the electricity produced by the overall energy mix of the supplier
over the preceding year.
As regards paragraph (a) of this item, with respect to electricity
obtained via an electricity exchange or imported from an undertaking
situated outside the Union, aggregate figures provided by the exchange
or the undertaking in question over the preceding year may be used.
For the disclosure of electricity from high efficiency
cogeneration, guarantees of origin issued under Article 14(10) of
Directive 2012/27/EU may be used. The disclosure of electricity from
renewable sources shall be done by using guarantees of origin, except
in the cases referred to in points (a) and (b) of Article 19(8) of
Directive (EU) 2018/2001.
The Regulator shall take the necessary steps to ensure that the
information provided by suppliers to final customers pursuant to this
point is reliable and is provided at a national level in a clearly
comparable manner.
In these regulations, unless the context otherwise requires
Interpretation.
"Act" means the Regulator for Energy and Water Services Act;
"active customer" means a final customer, or a group of jointly
acting final customers, who consumes or stores electricity generated
within its premises located within confined boundaries, or who sells
self-generated electricity or participates in flexibility or energy
efficiency schemes, provided that those activities do not constitute its
primary commercial or professional activity;
"aggregation" means a function performed by a natural or legal
person who combines multiple customer loads or generated electricity
for sale, purchase or auction in any electricity market;
"ancillary service" means a service necessary for the operation
of a transmission or distribution system, including balancing and non-
frequency ancillary services, but not including congestion
management;
"balancing" means balancing as defined in point 10 of Article 2
of Regulation (EU) 2019/943;
"balancing energy" means balancing energy as defined in point
11 of Article 2 of Regulation (EU) 2019/943;
"balance responsible party" means balance responsible party as
defined in point 14 of Article 2 of Regulation (EU) 2019/943;
"best available techniques" means, in the context of data
protection and security in a smart metering environment, the most
effective, advanced and practically suitable techniques for providing,
in principle, the basis for complying with the Union data protection
and security rules;
"billing information" means the information provided on a final
customer's bill, apart from a request for payment;
"citizen energy community" means a legal entity that
(a) is based on voluntary and open participation and is
effectively controlled by members or shareholders that are
natural persons, local authorities, including municipalities, or
small enterprises;
(b) has for its primary purpose to provide environmental,
economic or social community benefits to its members or
shareholders or to the local areas where it operates rather than to
generate financial profits; and
(c) may engage in generation, including from renewable
sources, distribution, supply, consumption, aggregation, energy
storage, energy efficiency services or charging services for
electric vehicles or provide other energy services to its members
or shareholders;
"congestion" means congestion as defined in point (4) of Article
2 of Regulation (EU) 2019/943;
"contract termination fee" means a charge or penalty imposed on
customers by suppliers or market participants engaged in aggregation,
for terminating an electricity supply or service contract;
"control" means rights, contracts or other means which, either
separately or in combination and having regard to the considerations of
fact or law involved, confer the possibility of exercising decisive
influence on an undertaking, in particular by
(a) ownership or the right to use all or part of the assets
of an undertaking;
(b) rights or contracts which confer decisive influence on
the composition, voting or decisions of the organs of an
undertaking;
"conventional meter" means an analogue or electronic meter with
no capability to both transmit and receive data;
"customer" means a wholesale or final customer of electricity;
"demand response" means the change of electricity load by final
customers from their normal or current consumption patterns in
response to market signals, including in response to time-variable
electricity prices or incentive payments, or in response to the
acceptance of the final customer's bid to sell demand reduction or
increase at a price in an organised market as defined in point 4 of
Article 2 of Commission Implementing Regulation (EU) No 1348/
2014 (17), whether alone or through aggregation;
"Directive" means Directive (EU) 2019/944 of the European
Parliament and of the Council of 5 June 2019 on common rules for the
internal market for electricity and amending Directive 2012/27/EU
(recast);
"direct line" means either an electricity line linking an isolated
generation site with an isolated customer or an electricity line linking a
producer and an electricity supply undertaking to supply directly their
own premises, subsidiaries and customers;
"distributed generation" means generating installations
connected to the distribution system; "distribution" means the
transport of electricity on high-voltage, medium-voltage and low-
voltage distribution systems with a view to its delivery to customers,
but does not include supply;
"distribution system operator" or "DSO" means a natural or legal
person who is responsible for operating, ensuring the maintenance of
and, if necessary, developing the distribution system in a given area
and, where applicable, its interconnections with other systems, and for
ensuring the long-term ability of the system to meet reasonable
demands for the distribution of electricity;
"dynamic electricity price contract" means an electricity supply
contract between a supplier and a final customer that reflects the price
variation in the spot markets, including in the day-ahead and intraday
markets, at intervals at least equal to the market settlement frequency;
"electricity derivative" means a financial instrument specified in
point (5), (6) or (7) of Section C of Annex I to Directive 2014/65/EU
of the European Parliament and of the Council, where that instrument
relates to electricity;
"electricity markets" means markets for electricity, including
over-the-counter markets and electricity exchanges, markets for the
trading of energy, capacity, balancing and ancillary services in all
timeframes, including forward, day-ahead and intraday markets;
"electricity supply contract" means a contract for the supply of
electricity, but does not include electricity derivatives;
"electricity undertaking" means a natural or legal person who
carries out at least one of the following functions: generation,
transmission, distribution, aggregation, demand response, energy
storage, supply or purchase of electricity, and who is responsible for
the commercial, technical or maintenance tasks related to those
functions, but does not include final customers;
"energy efficiency" means the ratio of output of performance,
service, goods or energy, to input of energy;
"energy from renewable sources" or "renewable energy" means
energy from renewable non-fossil sources, namely wind, solar (solar
thermal and solar photovoltaic) and geothermal energy, ambient
energy, tide, wave and other ocean energy, hydropower, biomass,
landfill gas, sewage treatment plant gas, and biogas;
"energy storage" means, in the electricity system, deferring the
final use of electricity to a moment later than when it was generated, or
the conversion of electrical energy into a form of energy which can be
stored, the storing of such energy, and the subsequent reconversion of
such energy into electrical energy or use as another energy carrier;
"energy storage facility’ means, in the electricity system, a
facility where energy storage occurs;
"final customer" means a customer who purchases electricity for
own use;
"fully integrated network components" means network
components that are integrated in the transmission or distribution
system, including storage facilities, and that are used for the sole
purpose of ensuring a secure and reliable operation of the transmission
or distribution system, and not for balancing or congestion
management;
"generation" means the production of electricity;
"horizontally integrated undertaking" means an electricity
undertaking performing at least one of the functions of generation for
sale, or transmission, or distribution, or supply, and another non-
electricity activity;
"household customer" means a customer who purchases
electricity for the customer's own household consumption, excluding
commercial or professional activities;
"imbalance settlement period" means imbalance settlement
period as defined in point (15) of Article 2 of Regulation (EU) 2019/
943;
"independent aggregator" means a market participant engaged in
aggregation who is not affiliated to the customer's supplier;
"integrated electricity undertaking" means a vertically integrated
undertaking or a horizontally integrated undertaking;
"interoperability" means, in the context of smart metering, the
ability of two or more energy or communication networks, systems,
devices, applications or components to interwork to exchange and use
information in order to perform required functions;
"interconnector" means equipment used to link electricity
systems;
"interconnected system" means a number of transmission and
distribution systems linked together by means of one or more
interconnectors;
"market participant" means market participant as defined in point
(25) of Article 2 of Regulation (EU) 2019/943;
"microenterprise" means an enterprise which employs fewer
than ten (10) persons and whose annual turnover and/or annual balance
sheet total does not exceed two million euro (€2,000, 000);
"Member State" means a member state of the European Union;
"Minister" means the Minister responsible for energy;
"near real-time" means, in the context of smart metering, a short
time period, usually down to seconds or up to the imbalance settlement
period in the national market;
"non-household customer" means a natural or legal person who
purchases electricity that is not for own household use, including
producers, industrial customers, small and medium-sized enterprises,
businesses and wholesale customers;
"non-frequency ancillary service" means a service used by a
transmission system operator or distribution system operator for steady
state voltage control, fast reactive current injections, inertia for local
grid stability, short-circuit current, black start capability and island
operation capability;
"person" means any natural or legal person;
"producer" means a natural or legal person who generates
electricity;
"recharging point" means an interface that is capable of charging
one electric vehicle at a time or exchanging the battery of one electric
vehicle at a time;
"regional coordination centre" means a regional coordination
centre established pursuant to Article 35 of Regulation (EU) 2019/943;
"Regulation (EU) 2019/943 " means Regulation (EU) 2019/943
of the European Parliament and of the Council of 5 June 2019 on the
internal market for electricity;
"Regulator" means the Regulator for Energy and Water Services
established by the Act;
"related undertaking" means affiliated undertakings as defined in
point (12) of Article 2 of Directive 2013/34/EU of the European
Parliament and of the Council, and undertakings which belong to the
same shareholders;
"smart metering system" means an electronic system that is
capable of measuring electricity fed into the grid or electricity
consumed from the grid, providing more information than a
conventional meter, and that is capable of transmitting and receiving
data for information, monitoring and control purposes, using a form of
electronic communication;
"supply" means the sale, including the resale, of electricity to
customers;
"switching-related fee" means a charge or penalty for changing
suppliers or market participants engaged in aggregation, including
contract termination fees, that is directly or indirectly imposed on
customers by suppliers, market participants engaged in aggregation or
system operators;
"transmission" means the transport of electricity on the extra
high-voltage and high-voltage interconnected system with a view to its
delivery to final customers or to distributors, but does not include
supply;
"transmission system operator" means a natural or legal person
who is responsible for operating, ensuring the maintenance of and, if
necessary, developing the transmission system in a given area and,
where applicable, its interconnections with other systems, and for
ensuring the long-term ability of the system to meet reasonable
demands for the transmission of electricity;
"security" means both security of supply and provision of
electricity, and technical safety;
"small connected system" means any system that had
consumption of less than 3,000 GWh in the year 1996, where more
than five per cent (5%) of annual consumption is obtained through
interconnection with other systems;
"small enterprise" means an enterprise which employs fewer than
50 persons and whose annual turnover and/or annual balance sheet
total does not exceed ten million euro (€10, 000, 000);
"small isolated system" means any system that had consumption
of less than 3,000 GWh in the year 1996, where less than five per cent
(5%) of annual consumption is obtained through interconnection with
other systems;
"system user" means a natural or legal person who supplies to, or
is supplied by a transmission system or a distribution system;
"vertically integrated undertaking" means an electricity
undertaking or a group of electricity undertakings where the same
person or the same persons are entitled, directly or indirectly, to
exercise control, and where the undertaking or group of undertakings
performs at least one of the functions of transmission or distribution,
and at least one of the functions of generation or supply;
"wholesale customer" means a natural or legal person who
purchases electricity for the purpose of resale inside or outside the
system where that person is established.
Smart Metering Systems
(regulations 16, 17 and 18)
1. The distribution system operator shall be responsible for
the deployment of smart metering systems in Malta which may be
subject to an economic assessment of all of the long-term costs and
benefits to the market and the individual consumer or which form of
smart metering is economically reasonable and cost-effective and
which time frame is feasible for their distribution.
2. Such assessment shall take into consideration the
methodology for the cost-benefit analysis and the minimum
functionalities for smart metering systems provided for in Commission
Recommendation 2012/148/EU (1) as well as the best available
techniques for ensuring the highest level of cybersecurity and data
protection.
3. Subject to that assessment, the distribution system operator
shall prepare a timetable with a target of up to ten years for the
deployment of smart metering systems. Where the deployment of
smart metering systems is assessed positively, at least eighty per cent
(80%) of final customers shall be equipped with smart meters either
within seven years of the date of the positive assessment or by 2024 if
the systematic deployment of smart metering systems has occurred
before 4 th July 2019.
All customers shall be free to purchase electricity from the Free choice of
supplier of their choice and to have more than one electricity supply supplier.
contract at the same time provided that the required connection and
metering points are established
Provided that such rights shall not be exercised until such
time that the derogation under paragraph 5 of Article 66 of the
Directive applies.
Exemptions from the Requirement of an Authorisation or Licence
(regulations 6 and 54)
PART A. Generating stations
1. A producer who
(a)
produces electricity solely for his own use; and
(b)
is not connected in parallel to the distribution system;
and
(c) has installed a total peak generation capacity of less
than 1500 kVA;
shall be exempted from the requirement of an authorisation to
construct the generation station and from the requirement to hold a
licence.
2. A producer with a total peak generation capacity rated up to
and including 16 Amps per phase, single-phase or multi-phase, 230/
400V AC produced solely from renewable sources of energy or
cogeneration plant, shall be exempted from the requirement of an
authorisation to construct the generation station and from the
requirement to hold a licence but shall still be required to notify the
Regulator, in such form and manner as required by the Regulator prior
to construction of such generation plant, and submit to the Regulator
such information as the Regulator may request from time to time.
PART B. Energy Storage
1. Energy storage facilities shall be notified to the Regulator
in such form and manner specified and made public by the Regulator.
€6.75
(1) Suppliers shall be free to determine the price at which Market-based
they supply electricity to customers. The Regulator shall take supply prices.
appropriate actions to ensure effective competition between suppliers
(2) The Minister responsible for social policy shall ensure the
protection of energy poor and vulnerable household customers
pursuant to regulations 25 and 26
Provided that protection of energy poor and vulnerable
household customers shall not be achieved by means of public
interventions in the price setting for the supply of electricity.
(3) By way of derogation from sub-regulations (1) and (2), the
Minister may apply public interventions in the price setting for the
supply of electricity to energy poor or vulnerable household
customers. Such public interventions shall be subject to the conditions
set out in sub-regulations (4) and (5).
(4) Public interventions in the price setting for the supply of
electricity shall
(a) pursue a general economic interest and not go beyond
what is necessary to achieve that general economic interest;
(b) be clearly defined, transparent, non-discriminatory
and verifiable;
(c) guarantee equal
access
for
Union
electricity
undertakings to customers
(d) be limited in time and proportionate as regards their
beneficiaries;
(e) not result in additional costs for market participants
in a discriminatory way.
(5) When applying public interventions in the price setting for
the supply of electricity in accordance with sub-regulation (3) the
Minister shall also comply with point (d) of Article 3(3) and with
Article 24 of Regulation (EU) 2018/1999, regardless of whether there
are a significant number of households in energy poverty.
(6) For the purpose of a transition period to establish effective
competition for electricity supply contracts between suppliers, and to
achieve fully effective market-based retail pricing of electricity in
accordance with sub-regulation (1), the Minister may apply public
interventions in the price setting for the supply of electricity to
household customers and to microenterprises that do not benefit from
public interventions pursuant to sub-regulation (3).
(7) Public interventions pursuant to sub-regulation (6) shall
comply with the criteria set out in sub-regulation (4) and shall
(a) be accompanied by a set of measures to achieve
effective competition and a methodology for assessing progress
with regard to those measures;
(b) be set using a methodology that ensures non-
discriminatory treatment of suppliers;
(c) be set at a price that is above cost, at a level where
effective price competition can occur;
(d) be designed to minimise any negative impact on the
wholesale electricity market;
(e) ensure that all beneficiaries of such public
interventions have the possibility to choose competitive market
offers and are directly informed at least every quarter of the
availability of offers and savings in the competitive market, in
particular of dynamic electricity price contracts, and shall ensure
that they are provided with assistance to switch to a market-
based offer;
(f) ensure that, pursuant to regulations 16 and 18, all
beneficiaries of such public interventions are entitled to, and are
offered to, have smart meters installed at no extra upfront cost to
the customer, are directly informed of the possibility of installing
smart meters and are provided with necessary assistance;
(g) not lead to direct cross-subsidisation between
customers supplied at free market prices and those supplied at
regulated supply prices.
(8) The Minister shall notify the measures taken in accordance
with sub-regulations (3) and (6) to the Commission within one (1)
month after their adoption and may apply them immediately. The
notification shall be accompanied by an explanation of why other
instruments were not sufficient to achieve the objective pursued, of
how the requirements set out in sub-regulations (4) and (7) are fulfilled
and of the effects of the notified measures on competition. The
notification shall describe the scope of the beneficiaries, the duration
of the measures and the number of household customers affected by
the measures and shall explain how the regulated prices have been
determined.
(9) By 1 st January 2022 and 1 st January 2025, the Minister
shall submit reports to the Commission on the implementation of this
regulation, the necessity and proportionality of public interventions
under this regulation, and an assessment of the progress towards
achieving effective competition between suppliers and the transition to
market-based prices. The Minister shall report on the compliance with
the conditions set out in sub-regulation (7) with regard to the
application of regulated prices in accordance with sub-regulation (6),
including on compliance by suppliers that are required to apply such
interventions, as well as on the impact of regulated prices on the
finances of those supplier.
(10) This regulation shall not apply until such time as the
derogations under paragraphs 3 and 5 of Article 66 of the Directive
apply.
(1) (a) All producers and electricity supply undertakings
established within Malta may supply their own premises, subsidiaries
and customers through a direct line, without being subject to
disproportionate administrative procedures or costs.
(b) All customers within Malta, individually or jointly, may be
supplied through a direct line by producers and electricity supply
undertakings
Provided that such rights shall not be exercised until such
time that the derogation under paragraph 5 of Article 66 of the
Directive applies.
(2) The Regulator shall lay down the criteria for the grant of
authorisations for the construction of direct lines in Malta. Those
criteria shall be objective and non-discriminatory.
(3) The possibility of supplying electricity through a direct line
as referred to in sub-regulation (1) shall not affect the possibility of
contracting electricity in accordance with Article 6 of the Directive
Provided that such rights shall not be exercised until such
time that the derogation under paragraph 5 of Article 66 of the
Directive applies.
(4) The Regulator may issue authorisations to construct a
direct line, subject either to the refusal of system access on the basis,
as appropriate, of Article 6 of the Directive or to the opening of a
dispute settlement procedure under regulation 48
Provided that refusal of system access on the basis of
Article 6 shall not be exercised until such time that the derogations
under paragraph 3 of Article 66 of the Directive applies.
(5) The Regulator may refuse to authorise a direct line if the
granting of such an authorisation would obstruct the application of the
provisions on public service obligations in Article 9 of the Directive.
Duly substantiated reasons shall be given for such a refusal.
(1) The construction of new generation capacity shall
require an authorisation from the Regulator
Provided that no such authorisation shall be required for the
producers listed in Part A of the Third Schedule.
(2)
The authorisation procedure for the construction of new
generating capacity, shall be conducted in accordance with objective,
transparent and non-discriminatory criteria.
(3) (a) The Regulator, in the processing of applications for
authorisations, shall take into account the size and potential impact of
the generation plant which the application relates to. Specific,
simplified and streamlined authorisation procedures for small
decentralised and, or distributed generation, which take into account
their limited size and potential impact, shall be determined by the
Regulator.
(b) The Regulator when processing the applications for
authorisations referred to in paragraph (a) shall
(i) take into account the outcome of the
comprehensive assessment referred to in regulation 21(1)
and 21(2) of the Energy Efficiency Regulations;
L.N. 66 of 2021.
(ii) ensure that the requirements of regulation 21(1)
L.N. 66 of 2021.
of the Energy Efficiency Regulations are fulfilled; and
(iii) take into account the outcome of the cost-
benefit analysis referred to in regulation 21(2) of the L.N. 66 of 2021.
Energy Efficiency Regulations.
(4) The Regulator, in the processing of applications for
authorisations for the new construction or reconstruction of generating
capacity, shall request that the applicant has obtained any relevant
approvals and permits from other competent authorities.
(5) The permits and approvals referred to in sub-regulation (4)
shall consider the following criteria
(a) the safety and security of the electricity system,
installations and associated equipment;
(b)
the protection of public health and safety;
(c)
the protection of the environment;
(d)
land use and siting;
(e)
the use of public ground;
(f)
energy efficiency;
(g)
the nature of the primary sources;
(h)
the characteristics particular to the applicant, such as
technical, economic and financial capabilities;
(i) compliance with measures adopted pursuant to
Article 9 of the Directive;
(j) the contribution of generating capacity to meeting the
overall Union target of at least a thirty-two per cent (32%) share
of energy from renewable sources in the Union's gross final
consumption of energy in 2030 referred to in Article 3(1) of
Directive (EU) 2018/2001 of the European Parliament and of the
Council;
(k) the contribution of generating capacity to reducing
emissions;
(l) the alternatives to the construction of new generating
capacity, such as demand response solutions and energy storage;
(6) The Regulator shall publish the procedures relative to the
granting of an authorisation as in such manner as it shall determine so
as to bring it to the attention of those likely to be affected by it.
(7) An application for an authorisation under this regulation
shall be in writing and be in such form and contain such information as
the Regulator may reasonably request.
(8) An application for an authorisation shall be accompanied
by the following fees
(a) for a generating station with a capacity equal or
greater than 40kW and less than 5MW, a non-refundable fee of
two hundred euro (€200) shall apply;
(b) for a generating station with a capacity equal or
greater than 5MW, a non-refundable fee of five hundred (€500)
shall apply.
(9) An authorisation granted by the Regulator under this
regulation, shall be in writing and, unless previously revoked in
accordance with any term contained in the authorisation, shall
continue in force for such period as may be specified in the form
determined by or under the authorisation.
(10) Where the Regulator refuses to grant an authorisation
(a) the reasons for such refusal shall be objective, non-
discriminatory, well founded and duly substantiated,
(b) the applicant for the authorisation shall be notified, in
writing, by the Regulator of the reasons for the refusal, and
(c) the applicant shall have the right to appeal to the
Administrative Review Tribunal against a decision of the
Regulator in accordance with regulation 60.
(1) All final customers shall be entitled to have their Basic
electricity provided by a supplier, subject to the supplier's agreement, contractual
rights.
regardless of the Member State in which the supplier is registered,
provided that the supplier follows the applicable trading and balancing
rules
Provided that such rights shall not be exercised until such
time that the derogation under paragraph 5 of Article 66 of the
Directive applies.
(2) Final customers shall have the right to a contract with their
supplier that specifies
(a)
the identity and address of the supplier;
(b) the services provided, the service quality levels
offered, as well as the time for the initial connection;
(c)
the types of maintenance service offered;
(d) the means by which up-to-date information on all
applicable tariffs, maintenance charges and bundled products or
services may be obtained;
(e) the duration of the contract, the conditions for
renewal and termination of the contract and services, including
products or services that are bundled with those services, and
whether terminating the contract without charge is permitted;
(f) any compensation and the refund arrangements which
apply if contracted service quality levels are not met, including
inaccurate or delayed billing;
(g) the method of initiating an out-of-court dispute
settlement procedure in accordance with regulation 23;
(h) information relating to consumer rights, including
information on complaint handling and all of the information
referred to in this paragraph, that is clearly communicated on the
bill or the electricity undertaking's web site.
Conditions shall be fair and well known in advance. In any case,
this information shall be provided prior to the conclusion or
confirmation of the contract. Where contracts are concluded through
intermediaries, the information relating to the matters set out in this
sub-regulation shall also be provided prior to the conclusion of the
contract.
Final customers shall be provided with a summary of the key
contractual conditions in a prominent manner and in concise and
simple language.
(3)
Suppliers shall
(a) give final customers adequate notice of any intention
to modify contractual conditions and shall inform customers
about their right to terminate the contract when the notice is
given;
(b) notify their final customers, in a transparent and
comprehensible manner, directly of any adjustment in the supply
its scope, at an appropriate time no later than two weeks, or no
later than one (1) month in the case of household customers,
before the adjustment comes into effect
Provided that final customers shall be free to
terminate contracts if they do not accept the new contractual
conditions or adjustments in the supply price notified to them by
their supplier.
(4) Suppliers shall provide final customers with transparent
information on applicable prices and tariffs and on standard terms and
conditions, in respect of access to and use of electricity services.
(5) Suppliers shall offer final customers a wide choice of
payment methods. Such payment methods shall not unduly
discriminate between customers. Any difference in charges related to
payment methods or prepayment systems shall be objective, non-
discriminatory and proportionate and shall not exceed the direct costs
borne by the payee for the use of a specific payment method or a
prepayment system, in line with Article 62 of Directive (EU) 2015/
2366 of the European Parliament and of the Council.
(6) Pursuant to sub-regulation (5), household customers who
have access to prepayment systems shall not be placed at a
disadvantage by the prepayment systems
(7) Suppliers shall offer final customers fair and transparent
general terms and conditions, which shall be provided in plain and
unambiguous language and shall not include non-contractual barriers
to the exercise of customers’ rights, such as excessive contractual
documentation. Suppliers shall not use unfair or misleading selling
methods.
(8) Final customers shall have the right to a good standard of
service and complaint handling by their suppliers. Suppliers shall
handle complaints in a simple, fair and prompt manner.
(9) When accessing universal service under the provisions
adopted by pursuant to regulation 24, final customers shall be
informed about their rights regarding universal service.
(10) (a) Suppliers shall provide household customers with
adequate information on alternative measures to disconnection
sufficiently in advance of any planned disconnection. Such alternative
measures may refer to sources of support to avoid disconnection,
prepayment systems, energy audits, energy consultancy services,
alternative payment plans, debt management advice or disconnection
moratoria and not constitute an extra cost to the customers facing
disconnection;
(b) Suppliers shall at least establish the following alternative
measures to disconnection
(i)
alternative payment plans;
(ii)
debt management advice;
(iii)
disconnection moratoria.
(11) Suppliers shall provide final customers with a final closure
account after any switch of supplier no later than six (6) weeks after
such a switch has taken place.
(1) Final customers who have a smart meter installed can Entitlement to a
request to conclude a dynamic electricity price contract with at least dynamic
electricity price
one supplier and with every supplier that has more than two hundred contract.
thousand (200,000) final customers.
(2) Suppliers shall keep final customers fully informed of the
opportunities, costs and risks of such dynamic electricity price
contracts and shall provide information to the final customers,
accordingly, including with regard to the need to have an adequate
electricity meter installed.
The Regulator shall monitor the market developments and assess
the risks that the new products and services may entail and deal with
abusive practices.
(3) Suppliers shall obtain each final customer's consent before
that customer is switched to a dynamic electricity price contract.
(4) For at least a ten-year period after dynamic electricity price
contracts become available, the Regulator shall monitor, and shall
publish an annual report on the main developments of such contracts,
including market offers and the impact on consumers' bills, and
specifically the level of price volatility.
(5) This regulation shall not apply until such time that a spot or
intra-day market is developed in Malta.
(1) Switching supplier or market participant engaged in
aggregation shall be carried out within the shortest possible time.
A customer wishing to switch suppliers or market participants
engaged in aggregation, while respecting contractual conditions, is
entitled to such a switch within a maximum of three (3) weeks from
the date of the request. By no later than 2026, the technical process of
switching supplier shall take no longer than twenty-four (24) hours and
shall be possible on any working day
Provided that the right to switch supplier shall not be
exercised until such time that the derogation under paragraph 5 of
Article 66 of the Directive applies.
(2) Suppliers and market participant shall not charge any
switching-related fees to household customers and small enterprises;
(3) By way of derogation from sub-regulation (2), suppliers or
market participants engaged in aggregation may charge customers
contract termination fees where those customers voluntarily terminate
fixed-term, fixed-price electricity supply contracts before their
maturity
Provided that such fees are part of a contract that the
customer has voluntarily entered into and that such fees are clearly
communicated to the customer before the contract is entered into
Provided further that, such fees shall be proportionate and
shall not exceed the direct economic loss to the supplier or the market
participant engaged in aggregation resulting from the customer's
termination of the contract, including the costs of any bundled
investments or services that have already been provided to the
customer as part of the contract. The burden of proving the direct
economic loss shall be on the supplier or market participant engaged in
aggregation, and the permissibility of contract termination fees shall
be monitored by the Regulator.
(4) Customers shall have the right to switch supplier or market
participants engaged in aggregation in a non-discriminatory manner as
regards cost, effort and time
Provided that the right to switch supplier shall not be
exercised until such time that the derogation under paragraph 5 of
Article 66 of the Directive applies.
(5) Household customers shall be entitled to participate in
collective switching schemes
Provided that the right to switch supplier shall not be
exercised until such time that the derogation under paragraph 5 of
Article 66 of the Directive applies.
(1) All customers shall be free to purchase and sell Aggregation
electricity services, including aggregation, other than supply, contract.
independently from their electricity supply contract and from an
electricity undertaking of their choice
Provided that such rights shall not be exercised until such
time that the derogations from paragraphs 3 and 5 under Article 66 of
the Directive apply. This shall be without prejudice to the right of
customers to sell electricity services, including aggregation to the
DSO.
(2) Where a final customer wishes to conclude an aggregation
contract, the final customer is entitled to do so without the consent of
the final customer's electricity undertakings.
Market participants engaged in aggregation shall fully inform
customers of the terms and conditions of the contracts that they offer to
them.
(3) Final customers shall be entitled to receive all relevant
demand response data or data on supplied and sold electricity free of
charge at least once every billing period if requested by the customer.
(4) Final customers shall be able to exercise rights referred to
in sub-regulations (2) and (3) in a non-discriminatory manner as
regards cost, effort or time. In particular, customers shall not be
subject to discriminatory technical and administrative requirements,
procedures or charges by their supplier on the basis of whether they
have a contract with a market participant engaged in aggregation.
(1) Household customers, and microenterprises with an
expected yearly consumption of below 100,000 kWh, shall have
access, free of charge, to at least one tool comparing the offers of
suppliers, including offers for dynamic electricity price contracts.
Customers shall be informed of the availability of such tools in or
together with their bills or by other means.
The tools shall meet at least the following requirements
(a) they shall be independent from market participants
and ensure that electricity undertakings are given equal treatment
in search results;
(b) they shall clearly disclose their owners and the
natural or legal person operating and controlling the tools, as
well as information on how the tools are financed;
(c) they shall set out clear and objective criteria on which
the comparison is to be based, including services, and disclose
them;
(d)
they shall use plain and unambiguous language;
(e) they shall provide accurate and
up-to-date
information and state the time of the last update;
(f) they shall be accessible to persons with disabilities,
by being perceivable, operable, understandable and robust;
(g) they shall provide an effective procedure for
reporting incorrect information on published offers; and
(h) they shall perform comparisons, while limiting the
personal data requested to that strictly necessary for the
comparison.
The Regulator shall ensure that at least one tool covers the entire
market. Where multiple tools cover the market, those tools shall
include, as complete as practicable, a range of electricity offers
covering a significant part of the market and, where those tools do not
completely cover the market, a clear statement to that effect, before
displaying results.
(2) The tools referred to in sub-regulation (1) may be operated
by any entity, including private companies and public authorities or
bodies.
(3) The Regulator shall be responsible for issuing trust marks
for comparison tools that meet the requirements set out in sub-
regulation (1), and for ensuring that comparison tools bearing a trust
mark continue to meet the requirements set out in sub-regulation (1)
Provided that the issue of trust mark shall not be required
when the comparison tool is provided by a public authority or body
and when such comparison meets the requirements set out in sub-
regulation (1).
(4) Any tool comparing the offers of market participants shall
be eligible to apply for a trust mark in accordance with this regulation
on a voluntary and non-discriminatory basis.
(1) Final customers shall be entitled to act as active Active
customers without being subject to disproportionate or discriminatory customers.
technical requirements, administrative requirements, procedures and
charges, and to network charges that are not cost-reflective.
(2)
(a)
Active customers shall have the right to
(i)
operate either directly or through aggregation;
(ii) sell self-generated electricity, including through
power purchase agreements;
(iii) participate in flexibility schemes and energy
efficiency schemes;
(iv) delegate to a third party the management of the
installations required for their activities, including
installation, operation, data handling and maintenance,
without that third party being considered to be an active
customer;
(b)
Active customers shall be
(i) subject to cost-reflective, transparent and non-
discriminatory network charges that account separately for
the electricity fed into the grid and the electricity consumed
from the grid, in accordance with regulation 47(6) and
Article 18 of Regulation (EU) 2019/943, ensuring that they
contribute in an adequate and balanced way to the overall
cost sharing of the system;
(ii) financially responsible for the imbalances they
cause in the electricity system; to that extent they shall be
balance responsible parties or shall delegate their balancing
responsibility in accordance with Article 5 of Regulation
(EU) 2019/943
Provided that until such time that a liquid intraday market
is developed the DSO shall bear the balancing responsibility.
(3) Existing schemes that do not account separately for the
electricity fed into the grid and the electricity consumed from the grid,
shall not grant new rights under such schemes after 31 st December
2023. In any event, customers subject to existing schemes shall have
the possibility at any time to opt for a new scheme that accounts
separately for the electricity fed into the grid and the electricity
consumed from the grid as the basis for calculating network charges.
(4)
Active customers that own an energy storage facility
(a) shall have the right to a grid connection within a
reasonable time after the request, provided that all necessary
conditions, such as balancing responsibility and adequate
metering, are fulfilled;
(b) shall not be subject to any double charges, including
network charges, for stored electricity remaining within their
premises or when providing flexibility services to system
operators;
(c) are not subject
to
disproportionate
licensing
requirements or fees;
(d) may provide several services simultaneously, if
technically feasible.
(1) The Minister shall provide an enabling regulatory
framework for citizen energy communities ensuring that
(a) participation in a citizen energy community shall be
open and voluntary.
(b) members or shareholders of a citizen energy
community shall be entitled to leave the community, in which
case regulation 9 shall apply.
(c) members or shareholders of a citizen energy
community shall not lose their rights and obligations as
household customers or active customers.
(d) subject to fair compensation as assessed by the
Regulator, relevant distribution system operators shall cooperate
with citizen energy communities to facilitate electricity transfers
within citizen energy communities.
(e) citizen energy communities shall be subject to non-
discriminatory, fair, proportionate and transparent procedures
and charges, including with respect to registration and licensing,
and to transparent, non-discriminatory and cost- reflective
network charges in accordance with Article 18 of Regulation
(EU) 2019/943, ensuring that they contribute in an adequate and
balanced way to the overall cost sharing of the system.
(2) The Minister may provide in the enabling regulatory
framework that citizen energy communities
(a)
shall be open to cross-border participation;
(b) shall be entitled to own, establish, purchase or lease
distribution networks and to autonomously manage them subject
to conditions set out in sub-regulation (4);
(c) shall be subject to the exemptions provided for in
regulation 35(2).
(3)
Citizen energy communities shall be
(a) able to access all electricity markets, either directly or
through aggregation, in a non-discriminatory manner;
(b) treated in a non-discriminatory and proportionate
manner with regard to their activities, rights and obligations as
final customers, producers, suppliers, distribution system
operators or market participants engaged in aggregation;
(c) financially responsible for the imbalances they cause
in the electricity system, to that extent they shall be balance
responsible parties or shall delegate their balancing
responsibility in accordance with Article 5 of Regulation (EU)
2019/943
Provided that until such time that a liquid intraday
market is developed the DSO shall be delegated with the
balancing responsibility;
(d) with regard to consumption of self-generated
electricity, citizen energy communities shall be treated like
active customers in accordance with regulation 12(2)(b)(i);
(e)
may arrange within the citizen energy community the
sharing of electricity that is produced by the production units
owned by the community, subject to other requirements laid
down in this regulation and subject to the community members
retaining their rights and obligations as final customers.
For the purposes of paragraph (e), where electricity is shared, this
shall be without prejudice to applicable network charges, tariffs and
levies, in accordance with a transparent cost-benefit analysis of
distributed energy resources developed by the competent national
authority
Provided that the aforesaid sharing of electricity shall not
be carried out until such time that the derogation under paragraph 5 of
Article 66 of the Directive applies.
(4) The Minister may decide to grant citizen energy
communities the right to manage distribution networks in their area of
operation and establish the relevant procedures, without prejudice to
Chapter IV of the Directive or to other rules and regulations applying
to distribution system operators. If such a right is granted, citizen
energy communities shall
(a) be entitled to conclude an agreement on the operation
of their network with the relevant distribution system operator or
transmission system operator to which their network is
connected;
(b) be subject to appropriate network charges at the
connection points between their network and the distribution
network outside the citizen energy community and that such
network charges account separately for the electricity fed into
the distribution network and the electricity consumed from the
distribution network outside the citizen energy community in
accordance with regulation 47(4);
(c) not discriminate or harm customers who remain
connected to the distribution system.
(1) Final customers shall have the right to participate in
demand response through aggregation. Final customers, including
those offering demand response through aggregation, may participate
alongside producers in a non-discriminatory manner to provide
demand response services.
(2) Transmission system operators and distribution system
operators, when procuring ancillary services, shall treat market
participants engaged in the aggregation of demand response in a non-
discriminatory manner alongside producers on the basis of their
technical capabilities.
(3) (a) (i) Each market participant engaged in aggregation,
including independent aggregators, may enter electricity markets
without the consent of other market participants;
(ii) market participants engaged in aggregation
shall be financially responsible for the imbalances that they
cause in the electricity system; to that extent they shall be
balance responsible parties or shall delegate their balancing
responsibility in accordance with Article 5 of Regulation
(EU) 2019/943
Provided that until such time that a liquid
intraday market is developed the DSO shall be delegated
with the balancing responsibility.
(b) Final customers who have a contract with independent
aggregators shall not be subject to undue payments, penalties or other
undue contractual restrictions by their suppliers;
(c) The provisions of the Dispute Resolution (Procedures)
Regulations shall mutatis mutandis apply to disputes between market
participants engaged in aggregation and other market participants,
including responsibility for imbalances.
(4) (a) Transmission system operators and, or distribution
system operators, acting in close cooperation with market participants
and final customers, shall establish the technical requirements for
participation of demand response in all electricity markets on the basis
of the technical characteristics of those markets and the capabilities of
demand response. Such requirements shall cover participation
involving aggregated loads.
(b) The technical requirements referred to paragraph (a) shall
be subject to public consultation and thereafter to the approval of the
Regulator.
(5) The DSO shall make known the demand response services
that may be provided by final customers and all market participants.
(1) Bills and billing information shall be accurate, easy to Bills and billing
understand, clear, concise, user- friendly and presented in a manner information.
that facilitates comparison by final customers. On request, final
customers shall receive a clear and understandable explanation of how
their bill was derived, especially where bills are not based on actual
consumption.
(2) Final customers shall receive all their bills and billing
information free of charge.
(3) Final customers shall be offered the option of electronic
bills and billing information and shall be offered flexible arrangements
for the actual payment of the bills.
(4) If the contract provides for a future change of the product
or price, or a discount, this shall be indicated on the bill together with
the date on which the change takes place.
(5) Any changes to the requirements for the content of bills
shall be subject to consultation with consumer organisations.
(6) Bills and billing information shall fulfil the minimum
requirements set out in the First Schedule.
(1) The Minister shall assign responsibility for installing
smart meters to a distribution system operator. The distribution system
operator shall deploy smart metering systems that assist the active
participation of customers in the electricity market
Provided that such deployment may be subject to a cost-
benefit assessment, if the Minister so directs, which shall be
undertaken by the distribution system operator in accordance with the
principles laid down in the Second Schedule.
(2) The Regulator shall adopt and publish the minimum
functional and technical requirements for the smart metering systems
to be deployed, in accordance with regulation 17 and the Second
Schedule. In establishing such minimum requirements, the Regulator
shall ensure the interoperability of those smart metering systems, as
well as their ability to provide output for consumer energy
management systems. In that respect, the Regulator shall have due
regard to the use of the relevant available standards, including those
enabling interoperability, to best practices and to the importance of the
development of smart grids and the development of the internal market
for electricity.
(3) Final customers shall contribute to the associated costs of
the deployment of smart metering systems in a transparent and non-
discriminatory manner. The establishment of the contribution made by
customers should take into account the long-term benefits to the whole
value chain. The Regulator shall regularly monitor such deployment to
track the delivery of benefits to consumers.
(4) Where the deployment of smart metering systems has been
negatively assessed as a result of the cost-benefit assessment referred
to in sub-regulation (1), the distribution system operator shall revise
this assessment at least every four years, or more frequently, in
response to significant changes in the underlying assumptions and in
response to technological and market developments. The Minister
shall notify to the Commission the outcome of the updated cost-benefit
assessment as it becomes available.
(5) The provisions in these regulations concerning smart
metering systems shall apply to future installations and to installations
that replace older smart meters. Smart metering systems that have
already been installed, or for which the ‘start of works’ began, before
the 4 th July 2019, may remain in operation over their lifetime but, in
the case of smart metering systems that do not meet the requirements
of regulation 17 and the Second Schedule, shall not remain in
operation after the 5 th July 2031.
For the purpose of this sub-regulation, "start of works" means
either the start of construction works on the investment or the first firm
commitment to order equipment or other commitment that makes the
investment irreversible, whichever is the first in time. Buying of land
and preparatory works such as obtaining permits and conducting
preliminary feasibility studies are not considered as start of works. For
take-overs, ‘start of works’ means the moment of acquiring the assets
directly linked to the acquired establishment.
Where the deployment of smart metering systems is Functionalities
positively assessed as a result of the cost-benefit assessment referred of
metering
to in regulation 16(1), or where smart metering systems are systems.
systematically deployed after 4 th July 2019, smart metering systems
shall be deployed in accordance with European standards, the Second
Schedule and the following requirements
(a) the smart metering systems shall accurately measure
actual electricity consumption and shall be capable of providing
to final customers information on actual time of use. Validated
historical consumption data shall be made easily and securely
available and visualised to final customers on request and at no
additional cost. Non-validated near real-time consumption data
shall also be made easily and securely available to final
customers at no additional cost, through a standardised interface
or through remote access, in order to support automated energy
efficiency programmes, demand response and other services;
(b) the security of the smart metering systems and data
communication shall comply with relevant Union security rules,
having due regard of the best available techniques for ensuring
the highest level of cybersecurity protection while bearing in
mind the costs and the principle of proportionality;
(c) the privacy of final customers and the protection of
their data shall comply with relevant Union data protection and
privacy rules;
(d) meter operators shall ensure that the meters of active
customers who feed electricity into the grid can account for
electricity fed into the grid from the active customers' premises;
(e) if final customers request it, data on the electricity
they fed into the grid and their electricity consumption data shall
be made available to them, in accordance with the implementing
acts adopted pursuant to Article 24 of the Directive, through a
standardised communication interface or through remote access,
or to a third party acting on their behalf, in an easily
understandable format allowing them to compare offers on a
like-for-like basis;
(f) appropriate advice and information shall be given to
final customers prior to or at the time of installation of smart
meters, in particular concerning their full potential with regard to
the management of meter reading and the monitoring of energy
consumption, and concerning the collection and processing of
personal data in accordance with the applicable Union data
protection rules;
(g) smart metering systems shall enable final customers
to be metered and settled at the same time resolution as the
imbalance settlement period in the national market.
For the purposes of paragraph (e), it shall be possible for final
customers to retrieve their metering data or transmit them to another
party at no additional cost and in accordance with their right to data
portability under Union data protection rules.
(1) Where the deployment of smart metering systems has
been negatively assessed as a result of the cost-benefit assessment
referred to in regulation 16(1) and where smart metering systems are
not systematically deployed, every final customer shall be entitled on
request, while bearing the associated costs, to have installed or, where
applicable, to have upgraded, under fair, reasonable and cost-effective
conditions, a smart meter that
(a) is equipped, where technically feasible, with the
functionalities referred to in regulation 17, or with a minimum
set of functionalities to be defined and at national level in
accordance with the Second Schedule;
(b) is interoperable and able to deliver the desired
connectivity of the metering infrastructure with consumer energy
management systems in near real-time.
(2) In the context of a customer request for a smart meter
pursuant to sub-regulation (1), the distribution system operator shall
(a) ensure that the offer to the final customer requesting
the installation of a smart meter explicitly states and clearly
describes
(i) the functions and interoperability that can be
supported by the smart meter and the services that are
feasible as well as the benefits that can be realistically
attained by having that smart meter at that moment in time;
(ii) any associated costs to be borne by the final
customer.
(b) ensure that it is installed within a reasonable time, no
later than four (4) months after the customer's request;
(c) regularly, and at least every two (2) years, review and
make publicly available the associated costs, and trace the
evolution of those costs as a result of technology developments
and potential metering system upgrades.
(1) Where final customers do not have smart meters, Conventional
final customers shall be provided by the distribution system operator meters.
with individual conventional meters that accurately measure their
actual consumption.
(2) The distribution system operator shall ensure that final
customers are able to easily read their conventional meters, either
directly or indirectly through an online interface or through another
appropriate interface.
(1) When laying down the rules regarding the Data
management and exchange of data, the Regulator shall specify the management.
rules on the access to data of the final customer by eligible parties in
accordance with this regulation and the applicable Union legal
framework. For the purpose of these regulations, data shall be
understood to include metering and consumption data as well as data
required for customer switching, demand response and other services.
(2) The Regulator shall organise the management of data in
order to ensure efficient and secure data access and exchange, as well
as data protection and data security.
Independently of the data management model applied, the parties
responsible for data management shall provide access to the data of the
final customer to any eligible party, in accordance with sub-regulation
(1). Eligible parties shall have the requested data at their disposal in a
non-discriminatory manner and simultaneously. Access to data shall be
easy and the relevant procedures for obtaining access to data shall be
made publicly available.
(3) The rules on access to data and data storage for the purpose
of these regulations shall comply with the relevant Union law.
The processing of personal data within the framework of these
regulations shall be carried out in accordance with Regulation (EU)
2016/679.
(4) The Regulator shall authorise and certify or, where
applicable, supervise the parties responsible for the data management,
in order to ensure that they comply with the requirements of these
regulations.
Without prejudice to the tasks of the data protection officers
under Regulation (EU) 2016/679, parties responsible for data
management shall appoint compliance officers who are to be
responsible for monitoring the implementation of measures taken by
those parties to ensure non-discriminatory access to data and
compliance with the requirements of these regulations.
(5) No additional costs shall be charged to final customers for
access to their data or for a request to make their data available.
Parties responsible for data management shall be responsible for
setting the relevant charges for access to data by eligible parties.
The Regulator shall ensure that any charges imposed by
regulated entities that provide data services are reasonable and duly
justified.
Electricity undertakings shall apply the interoperability
requirements and procedures for access to data referred to in paragraph
2 of Article 24 of the Directive. Those requirements and procedures
shall be based on existing national practices.
The Regulator shall act as a single point of contact, to
provide customers with all necessary information concerning their
rights, the applicable law and dispute settlement mechanisms available
to them in the event of a dispute
Provided that this shall be without prejudice to the
establishment of other single points of contact which may be part of
general consumer information points.
(1) Final customers shall have access to simple, fair, Right to out-of-
transparent, independent, effective and efficient out-of-court court
settlement.
mechanisms for the settlement of disputes concerning rights and
obligations established under these regulations and provided by the
Regulator.
(2) Where the final customer referred to in sub-regulation (1) is
a consumer within the meaning of Directive 2013/11/EU of the
European Parliament and of the Council, the out-of-court dispute
settlement mechanisms shall comply with the quality requirements of
Directive 2013/11/EU.
(3) When settling a dispute in the cases referred to in sub-
regulation (2), the Regulator may, where warranted, decide for
reimbursement and compensation.
(4) Alternative dispute resolution entities shall cooperate to
provide simple, fair, transparent, independent, effective and efficient
out-of-court dispute settlement mechanisms for any dispute that arises
from products or services that are tied to, or bundled with, any product
or service falling under the scope of these regulations.
(5) Electricity undertakings shall participate mandatorily in the
out-of-court dispute settlement for household customers which is
provided by the Regulator.
(1) All household customer and small enterprises, shall Universal
enjoy universal service, namely the right to be supplied with electricity service.
of a specified quality within their territory at competitive, easily and
clearly comparable, transparent and non-discriminatory prices.
(2) Distribution system operators shall be obliged to connect
customers to their network under terms, conditions and tariffs set in
accordance with the procedure laid down in regulation 47(4).
(1) Vulnerable customer for the purposes of these Vulnerable
regulations means energy poor customers which includes customers customers.
with low income levels and for whom the share of energy expenditure
is a significant part of disposable income. Vulnerable customers shall
also be customers who are critically dependent on electrical equipment
for health reasons or other criteria determined by the Minister
responsible for social policy.
(2) The disconnection of electricity to vulnerable customers in
critical times is prohibited.
The Minister responsible for social policy shall establish
and publish a set of criteria for the assessment of the number of
households in energy poverty, which may include low income, high
expenditure of disposable income on energy and poor energy
efficiency.
Enemalta plc is designated the distribution system operator
in Malta.
(1) The distribution system operator shall be responsible
for ensuring the long-term ability of the system to meet reasonable
demands for the distribution of electricity, for operating, maintaining
and developing under economic conditions a secure, reliable and
efficient electricity distribution system in Malta with due regard for
the environment and energy efficiency.
(2) In any event, the distribution system operator shall not
discriminate between system users or classes of system users,
particularly in favour of its related undertakings.
(3) The distribution system operator shall provide system users
with the information they need for efficient access to, including use of,
the system.
(4) The distribution system operator, when dispatching
generating installations shall give priority to generating installations
using renewable sources or using high-efficiency cogeneration, in
accordance with Article 12 of Regulation (EU) 2019/943
Provided that priority dispatch shall continue to apply for
all intermittent renewable energy sources and high-efficiency
cogeneration until such time that a liquid intra-day wholesale market is
developed.
(5) Each distribution system operator shall act as a neutral
market facilitator in procuring the energy it uses to cover energy losses
in its system in accordance with transparent, non-discriminatory and
market-based procedures, whenever it has such a function.
(6) The distribution system operator shall be responsible for
the procurement of products and services necessary for the efficient,
reliable and secure operation of the distribution system. The rules
adopted by the distribution system operator for that purpose shall be
objective, transparent and non-discriminatory, and shall be developed
in coordination with transmission system operators and other relevant
market participants. The terms and conditions, including rules and
tariffs, where applicable, for the provision of such products and
services to distribution system operators shall be established in
accordance with regulation 47(4) in a non-discriminatory and cost-
reflective way and shall be published.
(7) In performing the tasks referred to in sub-regulation (6), the
distribution system operator shall procure the non- frequency ancillary
services needed for its system in accordance with transparent, non-
discriminatory and market-based procedures, unless the Regulator has
assessed that the market-based provision of non-frequency ancillary
services is economically not efficient and has granted a derogation.
The obligation to procure non-frequency ancillary services does not
apply to fully integrated network components.
(8) The procurement of the products and services referred to in
sub-regulation (6) shall ensure the effective participation of all
qualified market participants, including market participants offering
energy from renewable sources, market participants engaged in
demand response, operators of energy storage facilities and market
participants engaged in aggregation. In particular, the Regulator and
the distribution system operator, in close cooperation with all market
participants, as well as transmission system operators, shall establish
the technical requirements for participation in those markets on the
basis of the technical characteristics of those markets and the
capabilities of all market participants.
(9) The distribution system operator shall cooperate with
transmission system operators for the effective participation of market
participants connected to their grid in retail, wholesale and balancing
markets. Delivery of balancing services stemming from resources
located in the distribution system shall be agreed with the relevant
transmission system operator in accordance with Article 57 of
Regulation (EU) 2019/943 and Article 182 of Commission Regulation
(EU) 2017/1485.
(10) The distribution system operators may perform activities
other than those provided for in these regulations and in Regulation
(EU) 2019/943, where such activities are necessary for the distribution
system operators to fulfil their obligations under these regulations or
Regulation (EU) 2019/943, provided that the Regulator has assessed
the necessity of such a derogation. This sub-regulation shall be without
prejudice to the right of the distribution system operator to own,
develop, manage or operate networks other than electricity networks
where the distribution system operator has been granted such a right.
(1) Within such time specified by the Regulator and Technical rules.
following such consultation processes as the Regulator may direct to
be made, the distribution system operator shall prepare, keep updated
and publish a "network code", and subject to the approval of the
Regulator, defining the technical safety criteria and the technical rules
establishing the minimum technical design and operational
requirements for the connection to the system of
(a)
generating installations;
(b)
energy storage;
(c)
distribution systems;
(d)
directly connected consumers’ equipment;
(e)
interconnector circuits;
(f)
direct lines; and
(g)
renewable and citizen energy communities.
(2) The network code shall set the minimum operational rules
and obligations on network security and foreseeable circumstances in
which security shall be maintained. The network code shall ensure the
interoperability of systems and shall be objective and non-
discriminatory. The network code shall be notified in accordance with
the Notification Procedure Regulations. The Regulator may from time
to time give directions, which may include technical safety criteria, to
the distribution system operator in respect to the matters to be
specified in the network code and its review and revision by the
distribution system operator.
(1) The Minister shall provide the necessary regulatory
framework to allow and provide incentives to the distribution system
operators to procure flexibility services, including congestion
management in Malta, in order to improve efficiencies in the operation
and development of the distribution system. In particular, distribution
system operators may procure such services from providers of
distributed generation, demand response or energy storage and make
use of energy efficiency measures, where such services cost-
effectively alleviate the need to upgrade or replace electricity capacity
and support the efficient and secure operation of the distribution
system.
(2) Distribution system operators shall procure the services
referred to sub-regulation (1) in accordance with transparent, non-
discriminatory and market-based procedures unless the Regulator has
established that the procurement of such services is not economically
efficient or that such procurement would lead to severe market
distortions or to higher congestion
Provided that where market-based procedures are not
possible the distribution system operator may procure flexibility by
offering connection agreements to users of the network and/or propose
network tariffs designed to encourage network users to alter their
behaviour for a more efficient use of the distribution network.
(3) (a
The distribution system operator, subject to the
approval of the Regulator, shall, in a transparent and participatory
process that includes all relevant system users and transmission system
operators, establish the specifications for the flexibility services
procured and, where appropriate, standardised market products for
such services at least at national level;
(b) The specifications shall ensure the effective and non-
discriminatory participation of all market participants, including
market participants offering energy from renewable sources, market
participants engaged in demand response, operators of energy storage
facilities and market participants engaged in aggregation;
(c) Distribution system operators shall exchange all necessary
information and shall coordinate with transmission system operators in
order to ensure the optimal utilisation of resources, to ensure the
secure and efficient operation of the system and to facilitate market
development
Provided that the distribution system operator shall be
adequately remunerated for the procurement of such services to allow
it to recover at least its reasonable corresponding costs, including the
necessary information and communication technology expenses and
infrastructure costs.
(4) (a) The development of a distribution system shall be
based on a transparent network development plan that the distribution
system operator shall publish at least every two (2) years and shall
submit to the Regulator.
(b) The network development plan shall provide transparency
on the medium and long-term flexibility services needed, and shall set
out the planned investments for the next five-to-ten years, with
particular emphasis on the main distribution infrastructure which is
required in order to connect new generation capacity and new loads,
including recharging points for electric vehicles. The network
development plan shall also include the use of demand response,
energy efficiency, energy storage facilities or other resources that the
distribution system operator is to use as an alternative to system
expansion.
(5) (a) The distribution system operator shall consult all
relevant system users and the relevant transmission system operators
on the network development plan.
(b) The distribution system operator shall publish the results of
the consultation process along with the network development plan and
submit the results of the consultation and the network development
plan to the Regulator. The Regulator may request for amendments to
be made to the plan.
(1) The distribution system operator shall cooperate on a
non-discriminatory basis with any undertaking that owns, develops,
operates or manages recharging points for electric vehicles, including
with regard to connection to the grid.
(2) Distribution system operators shall not own, develop,
manage or operate recharging points for electric vehicles, except
where distribution system operators own private recharging points
solely for their own use.
(3) By way of derogation from sub-regulation (2), distribution
system operators shall be allowed to own, develop, manage or operate
recharging points for electric vehicles, provided that all of the
following conditions are fulfilled
(a) other parties, following an open transparent and non-
discriminatory tendering procedure that is subject to review and
approval by the Regulator, have not been awarded a right to own,
develop, manage or operate recharging points for electric
vehicles, or could not deliver those services at a reasonable cost
and in a timely manner;
(b) the Regulator has carried out an ex ante review of the
conditions of the tendering procedure under paragraph (a) and
has granted its approval;
(c) the distribution system operator operates the
recharging points on the basis of third-party access in accordance
with Article 6 and does not discriminate between system users or
classes of system users, and in particular in favour of its related
undertakings.
The Regulator may draw up guidelines or procurement clauses to
help distribution system operators ensure a fair tendering procedure.
(4) Where the conditions under sub-regulation (3) have been
implemented the designated competent authority in terms of the
Alternative Fuels Order shall perform, at regular intervals or at least
every five (5) years, a public consultation in order to re-assess the
potential interest of other parties in owning, developing, operating or
managing recharging points for electric vehicles. Where the public
consultation indicates that other parties are able to own, develop,
operate or manage such points, the distribution system operators'
activities in this regard shall be phased-out, subject to the successful
completion of the tendering procedure referred to in paragraph (a) of
sub-regulation (3). As part of the conditions of that procedure, the
Regulator may allow the distribution system operator to recover the
residual value of its investment in recharging infrastructure.
(1) The distribution system operator which is assigned Tasks of
the responsibility referred to under regulation 27 by the Minister shall distribution
system
give all eligible parties non-discriminatory access to data under clear operators
management.
and equal terms, in accordance with the relevant data protection rules.
(2) The distribution system operator when involved in the data
management in particular in relation to smart metering systems shall
not have privileged access to data for the conduct of its supply
activities which is not available to all eligible parties.
(3) Where smart metering systems have been deployed in
accordance with regulation 16 and where distribution system operator
is involved in data management, the compliance programmes referred
to in point (d) of Article 35(2) of the Directive shall include specific
measures in order to exclude discriminatory access to data from
eligible parties as provided for in regulation 20.
(4) Where distribution system operators are not subject to the
requirements of Article 35 of the Directive, vertically integrated
undertakings shall not have privileged access to data for the conduct of
their supply activities.
(1) Distribution system operators shall not own, develop, Ownership of
energy storage
manage or operate energy storage facilities.
facilities by
distribution
system
(2) By way of derogation from sub-regulation (1), distribution operators.
system operators may own, develop, manage or operate energy storage
facilities, where they are fully integrated network components and the
Regulator has granted its approval, or where all of the following
conditions are fulfilled
(a) other parties, following an open, transparent and non-
discriminatory tendering procedure that is subject to review and
approval by the Regulator, have not been awarded a right to own,
develop, manage or operate such facilities, or could not deliver
those services at a reasonable cost and in a timely manner;
(b) such facilities are necessary for the distribution
system operators to fulfil their obligations under these
regulations for the efficient, reliable and secure operation of the
distribution system and the facilities are not used to buy or sell
electricity in the electricity markets; and
(c) the Regulator has assessed the necessity of such a
derogation and has carried out an assessment of the tendering
procedure, including the conditions of the tendering procedure,
and has granted its approval.
The Regulator may draw up guidelines or procurement clauses to
help distribution system operators ensure a fair tendering procedure.
(3) The Regulator shall perform, at regular intervals or at least
every five (5) years, a public consultation on the existing energy
storage facilities in order to assess the potential availability and
interest in investing in such facilities. Where the public consultation,
as assessed by the Regulator, indicates that third parties are able to
own, develop, operate or manage such facilities in a cost-effective
manner, the Regulator, shall ensure that the distribution system
operators' activities in this regard are phased out within eighteen (18)
months. As part of the conditions of that procedure, the Regulator, may
allow the distribution system operators to receive reasonable
compensation, in particular to recover the residual value of their
investment in the energy storage facilities.
(4) Sub-regulation (3) shall not apply to fully integrated
network components or for the usual depreciation period of new
battery storage facilities with a final investment decision until 4 th July
2019, provided that such battery storage facilities are
(a) connected to the grid at the latest two (2) years
thereafter;
(b)
integrated into the distribution system;
(c) used only for the reactive instantaneous restoration of
network security in the case of network contingencies where
such restoration measure starts immediately and ends when
regular re-dispatch can solve the issue; and
(d) not used to buy or sell electricity in the electricity
markets, including balancing.
Without prejudice to regulation 44 or another legal Confidentiality
requirement to disclose information, the distribution system operator obligation
distribution
shall preserve the confidentiality of commercially sensitive system
operators.
information obtained in the course of carrying out its business, and
shall prevent information about its own activities which may be
commercially advantageous from being disclosed in a discriminatory
manner.
(1) The Regulator may classify a system which Closed
distributes electricity within a geographically confined industrial, distribution
systems.
commercial, residential or shared services site and does not, without
prejudice to sub-regulation (3), supply household customers, as a
closed distribution system if
(a) for specific technical or safety reasons, the operations
or the production process of the users of that system are
integrated; or
(b) that system distributes electricity primarily to the
owner or operator of the system or their related undertakings.
(2) Closed distribution systems shall be considered to be
distribution systems for the purposes of these regulations. The
Regulator may exempt the operator of a closed distribution system
from
(a) the requirement under sub-regulations (5) and (7) of
regulation 28 to procure the energy it uses to cover energy losses
and the non- frequency ancillary services in its system in
accordance with transparent, non-discriminatory and market-
based procedures;
(b) the requirement under Article 6(1) of the Directive
that tariffs, or the methodologies underlying their calculation, are
approved in accordance with regulation 47(4) prior to their entry
into force;
(c) the requirements under regulation 30(1) to procure
flexibility services and under regulation 30(3) to develop the
operator's system on the basis of network development plans;
(d) the requirement under regulation 31(2) not to own,
develop, manage or operate recharging points for electric
vehicles; and
(e) the requirement under regulation 33(1) not to own,
develop, manage or operate energy storage facilities.
(3) Where an exemption is granted under sub-regulation (2),
the applicable tariffs, or the methodologies underlying their
calculation, shall be reviewed and approved in accordance with
regulation 47(1) upon request by a user of the closed distribution
system.
(4) Incidental use by a small number of households with
employment or similar associations with the owner of the distribution
system and located within the area served by a closed distribution
system shall not preclude an exemption under sub-regulation (2) being
granted.
(1) Each
transmission
system
operator
shall
be
responsible for
(a) ensuring the long-term ability of the system to meet
reasonable demands for the transmission of electricity, operating,
maintaining and developing under economic conditions secure,
reliable and efficient transmission system with due regard to the
environment, in close cooperation with neighbouring
transmission system operators and distribution system operators;
(b)
ensuring adequate means to meet its obligations;
(c) contributing to security of supply through adequate
transmission capacity and system reliability;
(d) managing electricity flows on the system, taking into
account exchanges with other interconnected systems. To that
end, the transmission system operator shall be responsible for
ensuring a secure, reliable and efficient electricity system and, in
that context, for ensuring the availability of all necessary
ancillary services, including those provided by demand response
and energy storage facilities, insofar as such availability is
independent from any other transmission systems with which its
system is interconnected;
(e) providing to the operator of other systems with which
its system is interconnected sufficient information to ensure the
secure and efficient operation, coordinated development and
interoperability of the interconnected system;
(f) ensuring non-discrimination as between system users
or classes of system users, particularly in favour of its related
undertakings;
(g) providing system users with the information they
need for efficient access to the system;
(h) collecting congestion rents and payments under the
inter-transmission system operator compensation mechanism, in
accordance with Article 49 of Regulation (EU) 2019/943,
granting and managing third-party access and giving reasoned
explanations when it denies such access, which shall be
monitored by the regulatory authorities; in carrying out their
tasks under this regulation, transmission system operators shall
primarily facilitate market integration;
(i)
procuring ancillary services to ensure operational
security;
(j) adopting a framework for cooperation
and
coordination between the regional coordination centres;
(k) participating in the establishment of the European and
national resource adequacy assessments pursuant to Chapter IV
of Regulation (EU) 2019/943;
(l)
the digitalisation of transmission systems;
(m) data management, including the development of data
management systems, cybersecurity and data protection, subject
to the applicable rules, and without prejudice to the competence
of other authorities.
(2) In addition to the task in sub-regulation (1) the activity of
electricity transmission shall include at least the following tasks
(a) the representation of the transmission system operator
and contacts to third parties and the regulatory authorities;
(b) the representation of the transmission system operator
within the ENTSO for Electricity;
(c) granting and managing third-party access on a non-
discriminatory basis between system users or classes of system
users;
(d) the collection of all the transmission system related
charges including access charges, energy for losses and ancillary
services charges;
(e) the operation, maintenance and development of a
secure, efficient and economic transmission system;
(f) investment planning ensuring the long-term ability of
the system to meet reasonable demand and guaranteeing security
of supply;
(g) the setting up of appropriate joint ventures, including
with one or more transmission system operators, power
exchanges, and the other relevant actors pursuing the objectives
to develop the creation of regional markets or to facilitate the
liberalisation process; and
(h) all corporate services, including legal services,
accountancy and IT services.
(3) In performing the tasks referred to in sub-regulation (1),
transmission system operators shall take into account the
recommendations issued by the regional coordination centres.
(4) In performing the task referred to in paragraph (i) of sub-
regulation (1), transmission system operators shall procure balancing
services subject to the following
(a) transparent, non-discriminatory and market-based
procedures;
(b) the participation of all qualified electricity
undertakings and market participants, including market
participants offering energy from renewable sources, market
participants engaged in demand response, operators of energy
storage facilities and market participants engaged in aggregation.
For the purpose of paragraph (b) of sub-regulation (4), the
Regulator and transmission system operators shall, in close
cooperation with all market participants, establish technical
requirements for participation in those markets, on the basis of the
technical characteristics of those markets.
(5) Sub-regulation (4) shall apply to the provision of non-
frequency ancillary services by transmission system operators, unless
the Regulator has assessed that the market-based provision of non-
frequency ancillary services is economically not efficient and has
granted a derogation. In particular, the regulatory framework shall
ensure that transmission system operators are able to procure such
services from providers of demand response or energy storage and
shall promote the uptake of energy efficiency measures, where such
services cost-effectively alleviate the need to upgrade or replace
electricity capacity and support the efficient and secure operation of
the transmission system.
(6)
Transmission system operators, subject to approval by the
Regulator, or the Regulator itself, shall, in a transparent and
participatory process that includes all relevant system users and the
distribution system operators, establish the specifications for the non-
frequency ancillary services procured and, where appropriate,
standardised market products for such services at least at national
level. The specifications shall ensure the effective and non-
discriminatory participation of all market participants, including
market participants offering energy from renewable sources, market
participants engaged in demand response, operators of energy storage
facilities and market participants engaged in aggregation.
Transmission system operators shall exchange all necessary
information and shall coordinate with distribution system operators in
order to ensure the optimal utilisation of resources, to ensure the
secure and efficient operation of the system and to facilitate market
development. Transmission system operators shall be adequately
remunerated for the procurement of such services to allow them to
recover at least the reasonable corresponding costs, including the
necessary information and communication technology expenses and
infrastructure costs.
(7) The obligation to procure non-frequency ancillary services
referred to in sub-regulation (5) does not apply to fully integrated
network components.
(8) The Minister may allow transmission system operators to
perform activities other than those provided for under these
regulations and in Regulation (EU) 2019/943 where such activities are
necessary for the transmission system operators to fulfil their
obligations under these regulations or Regulation (EU) 2019/943,
provided that the Regulator has assessed the necessity of such a
derogation. This sub-regulation shall be without prejudice to the right
of the transmission system operators to own, develop, manage or
operate networks other than electricity networks where the
transmission system operators has been granted such a right.
(9) The Minister may assign one or more of the responsibilities
of transmission system operators as provided for in regulations 36, 38
and 40 to a distribution system operator.
(1) Without prejudice to regulation 44 or another legal Confidentiality
duty to disclose information, each transmission system operator and and
transparency
each transmission system owner shall preserve the confidentiality of requirements
transmission
commercially sensitive information obtained in the course of carrying system
out its activities, and shall prevent information about its own activities operators
transmission
which may be commercially advantageous from being disclosed in a system owners.
discriminatory manner. In particular it shall not disclose any
commercially sensitive information to the remaining parts of the
undertaking, unless such disclosure is necessary for carrying out a
business transaction.
(2) Transmission system operators shall not, in the context of
sales or purchases of electricity by related undertakings, misuse
commercially sensitive information obtained from third parties in the
context of providing or negotiating access to the system.
(3) Information necessary for effective competition and the
efficient functioning of the market shall be made public. That
obligation shall be without prejudice to preserving the confidentiality
of commercially sensitive information.
(1) The transmission system operator shall establish and
publish transparent and efficient procedures for non-discriminatory
connection of new generating installations and energy storage facilities
to the transmission system. Those procedures shall be subject to
approval by the Regulator.
(2) The transmission system operator shall not be entitled to
refuse the connection of a new generating installation or energy
storage facility on the grounds of possible future limitations to
available network capacities, such as congestion in distant parts of the
transmission system. The transmission system operator shall supply
necessary information
Provided that this shall be without prejudice to the
possibility for transmission system operators to limit the guaranteed
connection capacity or to offer connections subject to operational
limitations, in order to ensure economic efficiency regarding new
generating installations or energy storage facilities, provided that such
limitations have been approved by the Regulator.
Provided further that, the Regulator shall ensure that any
limitations in guaranteed connection capacity or operational
limitations are introduced on the basis of transparent and non-
discriminatory procedures and do not create undue barriers to market
entry.
(3) Where the generating installation or energy storage facility
bears the costs related to ensuring unlimited connection, no limitation
referred to in sub-regulation (2) shall apply.
(4) The transmission system operator shall not be entitled to
refuse a new connection point, on the ground that it would lead to
additional costs resulting from the necessary capacity increase of
system elements in the close-up range to the connection point.
(1) (a) Each undertaking that owns a transmission system Ownership
unbundling of
shall act as a transmission system operator.
transmission
systems and
transmission
(b)
The same person or persons shall not be entitled to either
system
operators.
(i) directly or indirectly to exercise control over an
undertaking performing any of the functions of generation
or supply, and directly or indirectly to exercise control or
exercise any right over a transmission system operator or
over a transmission system; or
(ii) directly or indirectly to exercise control over a
transmission system operator or over a transmission
system, and directly or indirectly to exercise control or
exercise any right over an undertaking performing any of
the functions of generation or supply;
(c) The same person or persons shall not be entitled to appoint
members of the supervisory board, the administrative board or bodies
legally representing the undertaking, of a transmission system operator
or a transmission system, and directly or indirectly to exercise control
or exercise any right over an undertaking performing any of the
functions of generation or supply; and
(d) The same person shall not be entitled to be a member of the
supervisory board, the administrative board or bodies legally
representing the undertaking, of both an undertaking performing any
of the functions of generation or supply and a transmission system
operator or a transmission system.
(2) The rights referred to in (b) and (c) of sub-regulation (1)
shall include, in particular
(a)
the power to exercise voting rights;
(b) the power to appoint members of the supervisory
board, the administrative board or bodies legally representing the
undertaking; or
(c)
the holding of a majority share.
(3) For the purpose of sub-regulation 1(b), the notion
"undertaking performing any of the functions of generation or supply"
shall include "undertaking performing any of the functions of
production and supply" within the meaning of Directive 2009/73/EC,
and the terms "transmission system operator" and "transmission
system" shall include "transmission system operator" and
"transmission system" within the meaning of that Directive.
(4) The obligation set out in sub-regulation 1(a) shall be
deemed to be fulfilled in a situation where two or more undertakings
which own transmission systems have created a joint venture which
acts as a transmission system operator in two or more Member States
for the transmission systems concerned.
No other undertaking may be part of the joint venture, unless it
has been approved under Article 44 of the Directive as an independent
system operator or as an independent transmission operator for the
purposes of Section 3 of the Directive.
(5) For the implementation of this regulation, where the person
referred to sub-regulation 1(b), (c) and (d) is a public body, two
separate public bodies exercising control over a transmission system
operator or over a transmission system on the one hand, and over an
undertaking performing any of the functions of generation or supply
on the other, shall be deemed not to be the same person or persons.
(6) Undertakings performing any of the functions of generation
or supply shall not in any event be able to directly or indirectly take
control over or exercise any right over unbundled transmission system
operators on whom paragraph 1 of Article 43 of the Directive is
applied.
(7) This regulation shall not apply to transmission system
operators in Malta until such date the derogation from Article 43 of the
Directive applies.
(1) At least every two (2) years, transmission system
operators shall submit to the Regulator a ten-year network
development plan based on existing and forecast supply and demand
after having consulted all the relevant stakeholders. That network
development plan shall contain efficient measures in order to
guarantee the adequacy of the system and the security of supply. The
transmission system operator shall publish the ten-year network
development plan on its website.
(2)
The ten-year network development plan shall in particular
(a) indicate to market participants the main transmission
infrastructure that needs to be built or upgraded over the next
ten(10) years;
(b) contain all the investments already decided and
identify new investments which have to be executed in the next
three (3) years; and
(c)
provide for a time frame for all investment projects.
(3) When elaborating the ten-year network development plan,
the transmission system operator shall fully take into account the
potential for the use of demand response, energy storage facilities or
other resources as alternatives to system expansion, as well as
expected consumption, trade with other countries and investment plans
for Union-wide and regional networks.
(4) The Regulator shall consult all actual or potential system
users on the ten-year network development plan in an open and
transparent manner. Persons or undertakings claiming to be potential
system users may be required to substantiate such claims. The
Regulator shall publish the result of the consultation process, in
particular possible needs for investments.
(5) (a) The Regulator shall examine whether the ten-year
network development plan covers all investment needs identified
during the consultation process, and whether it is consistent with the
non-binding Union-wide ten-year network development plan ("Union-
wide network development plan") referred to in point (b) of Article
30(1) of Regulation (EU) 2019/943. If any doubt arises as to the
consistency with the Union-wide network development plan, the
Regulator shall consult ACER. The Regulator may require the
transmission system operator to amend its ten-year network
development plan.
(b) The competent authority responsible for the national energy
and climate plan submitted in accordance with Regulation (EU) 2018/
1999 shall examine the consistency of the ten-year network
development plan with the national energy and climate plan.
(6) The Regulator shall monitor and evaluate
the
implementation of the ten-year network development plan.
(7) In circumstances where the transmission system operator,
other than for overriding reasons beyond its control, does not execute
an investment, which, under the ten-year network development plan,
was to be executed in the following three (3) years, the Regulator shall
take at least one of the following measures to ensure that the
investment in question is made if such investment is still relevant on
the basis of the most recent ten-year network development plan
(a) to require the transmission system operator to execute
the investments in question;
(b) to organise a tender procedure, open to any investors
for the investment in question; or
(c) to oblige the transmission system operator to accept a
capital increase to finance the necessary investments and allow
independent investors to participate in the capital.
(8) Where the Regulator has made use of its powers under
paragraph (b) of sub-regulation (7), it may oblige the transmission
system operator to agree to one or more of the following
(a)
financing by any third party;
(b)
construction by any third party;
(c)
building the new assets concerned itself;
(d)
operating the new asset concerned itself.
The transmission system operator shall provide the investors with
all information needed to realise the investment, shall connect new
assets to the transmission network and shall generally make its best
efforts to facilitate the implementation of the investment project. The
relevant financial arrangements shall be subject to approval by the
Regulator.
(9) Where the Regulator has made use of its powers under sub-
regulation (7), the relevant tariff regulations shall cover the costs of the
investments in question.
(1) Each transmission system operator shall prior to
commencing any transmission system operations, make an application
to the Regulator for certification in accordance with the procedure laid
down in sub-regulations (4), (5), (6) and in Article 51 of Regulation
(EU) 2019/943.
(2) The certification of a transmission system operator as
having complied with the requirements of regulation 39 pursuant to the
certification procedure in this regulation shall be deemed to be a
designation. Designation of transmission operators shall be notified by
the Regulator to the European Commission in writing.
(3) Transmission system operators shall notify the Regulator of
any planned transaction which may require a reassessment of their
compliance with applicable requirements of regulation 39.
(4) The Regulator shall monitor the continuing compliance of
transmission system operators with the requirements of regulation 39.
They shall open a certification procedure to ensure such compliance
(a)
upon notification by the transmission system operator
pursuant to sub-regulation (3);
(b) on their own initiative where they have knowledge
that a planned change in rights or influence over transmission
system owners or transmission system operators may lead to an
infringement of regulation 39, or where they have reason to
believe that such an infringement may have occurred; or
(c)
upon a reasoned request from the Commission.
(5) The Regulator shall adopt a decision on the certification of
a transmission system operator within four (4) months of the date of
the notification by the transmission system operator or from the date of
the Commission request. After expiry of that period, the certification
shall be deemed to be granted. The explicit or tacit decision of the
regulatory authority shall become effective only after conclusion of the
procedure set out in sub-regulation (6).
(6) The explicit or tacit decision on the certification of a
transmission system operator shall be notified without delay to the
Commission by the regulatory authority, together with all the relevant
information with respect to that decision. The Commission shall act in
accordance with the procedure laid down in Article 51 of Regulation
(EU) 2019/943.
(7) The Regulator and the Commission may request from
transmission system operators and undertakings performing any of the
functions of generation or supply any information relevant for the
fulfilment of their tasks under this regulation.
(8) The Regulator and the Commission shall preserve the
confidentiality of commercially sensitive information.
(1) (a) Where certification is requested by a transmission Certification in
system owner or a transmission system operator which is controlled by relation
countries.
a person or persons from a third country or third countries, the
Regulator shall notify the Commission.
(b) The Regulatory shall also notify to the Commission
without delay any circumstances that would result in a person or
persons from a third country or third countries acquiring control of a
transmission system or a transmission system operator.
(2) The transmission system operator shall notify to the
regulatory authority any circumstances that would result in a person or
persons from a third country or third countries acquiring control of the
transmission system or the transmission system operator.
(3) The Regulatory shall adopt a draft decision on the
certification of a transmission system operator within four (4) months
of the date of notification by the transmission system operator. It shall
refuse the certification if it has not been demonstrated
(a) that the entity concerned complies with the
requirements of regulation 39; and
(b) that granting certification will not put at risk the
security of energy supply in Malta and the Union.
In considering the security of supply issue the Regulator shall
take into account
(i) the rights and obligations of the Union with
respect to that third country arising under international law,
including any agreement concluded with one or more third
countries to which the Union is a party and which addresses
the issues of security of energy supply;
(ii) the rights and obligations of Malta with respect
to that third country arising under agreements concluded
with it, insofar as they comply with Union law; and
(iii) other specific facts and circumstances of the
case and the third country concerned.
(4) The Regulator shall notify the decision to the Commission
without delay, together with all the relevant information with respect
to that decision.
(5) The Regulator shall, before it adopts a decision on the
certification under this regulation, request an opinion from the
Commission on whether
(a) the entity concerned complies with the requirements
of regulation 39; and
(b) granting certification will not put at risk the security
of energy supply to the Union.
(6) (a) The Regulator shall, within two (2) months of
receiving an opinion of the European Commission with respect to its
draft decision on the certification pursuant to this regulation or if the
European Commission has not provided an opinion, within two (2)
months from the expiry of the time frame for an opinion, adopt its final
decision on the certification. In adopting its final decision, the
Regulator shall take utmost account of the Commission’s opinion (if
provided). The Regulator shall have the right to refuse certification
where granting certification puts at risk Malta’s security of energy
supply or the security of energy supply of another Member State.
(b) The Regulator’s final decision and the Commission’s
opinion shall be published together. Where the final decision diverges
from the Commission’s opinion, the Regulator shall provide and
publish, together with that decision, the reasoning underlying such
decision.
(7) Nothing in this regulation shall affect the right of the
Regulator or the Minister to exercise, in accordance with Union law,
national legal controls to protect legitimate public security interests.
(1) Transmission system operators shall not own, Ownership of
energy storage
develop, manage or operate energy storage facilities.
facilities by
transmission
system
(2) By way of derogation from sub-regulation (1), transmission operators
system operators may own, develop, manage or operate energy storage
facilities, where they are fully integrated network components and the
Regulator has granted its approval, or where all of the following
conditions are fulfilled
(a) other parties, following an open, transparent and non-
discriminatory tendering procedure that is subject to review and
approval by the Regulator, have not been awarded a right to own,
develop, manage or operate such facilities, or could not deliver
those services at a reasonable cost and in a timely manner;
(b) such facilities or non-frequency ancillary services are
necessary for the transmission system operators to fulfil their
obligations under these regulations for the efficient, reliable and
secure operation of the transmission system and they are not
used to buy or sell electricity in the electricity markets; and
(c) the Regulator has assessed the necessity of such a
derogation, has carried out an ex ante review of the applicability
of a tendering procedure, including the conditions of the
tendering procedure, and has granted its approval.
The Regulator may draw up guidelines or procurement clauses to
help transmission system operators ensure a fair tendering procedure.
(3) The decision to grant a derogation shall be notified to the
Commission and ACER together with relevant information about the
request and the reasons for granting the derogation.
(4)
The Regulator shall perform, at regular intervals or at least
every five (5) years, a public consultation on the existing energy
storage facilities in order to assess the potential availability and
interest of other parties in investing in such facilities. Where the public
consultation, as assessed by the Regulator, indicates that other parties
are able to own, develop, operate or manage such facilities in a cost-
effective manner, the Regulator shall ensure that transmission system
operators’ activities in this regard are phased-out within eighteen (18)
months. As part of the conditions of that procedure, the Regulator may
allow the transmission system operators to receive reasonable
compensation, in particular to recover the residual value of their
investment in the energy storage facilities.
(5) Sub-regulation (4) shall not apply to fully integrated
network components or for the usual depreciation period of new
battery storage facilities with a final investment decision until 2024,
provided that such battery storage facilities are
(a) connected to the grid at the latest two (2) years
thereafter;
(b)
integrated into the transmission system;
(c) used only for the reactive instantaneous restoration of
network security in the case of network contingencies where
such restoration measure starts immediately and ends when
regular re-dispatch can solve the issue; and
(d) not used to buy or sell electricity in the electricity
markets, including balancing.
(1) The Regulator shall, insofar as necessary to carry out
its functions, have right of access to the accounts of electricity
undertakings as set out in regulation 45.
(2) The Regulator shall preserve the confidentiality of
commercially sensitive information. The Regulator may disclose such
information where this is necessary in order for the Regulator to carry
out its functions.
(1) The Regulator shall take the necessary steps to ensure
that the accounts of electricity undertakings are kept in accordance
with sub-regulations (2) and (3).
(2) Electricity undertakings, whatever their system of
ownership or legal form, shall draw up, submit to audit and publish
their annual accounts in accordance with the rules of the Companies
Act or other applicable legislation concerning the annual accounts of
limited liability companies.
Undertakings which are not legally obliged to publish their
annual accounts shall keep a copy of these at the disposal of the public
in their head office.
(3) Electricity undertakings shall, in their internal accounting,
keep separate accounts for each of their generation, transmission,
distribution and supply activities as they would be required to do if the
activities in question were carried out by separate undertakings, with a
view to avoiding discrimination, cross-subsidisation and distortion of
competition. They shall also keep accounts, which may be
consolidated, for other electricity activities not relating to transmission
or distribution. Revenue from ownership of the transmission or
distribution system shall be specified in the accounts. Where
appropriate, they shall keep consolidated accounts for other, non-
electricity activities. The internal accounts shall include a balance
sheet and a profit and loss account for each activity and notes to the
separate internal accounts as detailed in sub-regulation (6).
(4) The audit referred to in sub-regulation (2) shall, in
particular, verify that the obligation to avoid discrimination and cross-
subsidisation referred to in sub-regulation (3) is respected.
(5) The annual accounts shall indicate in the notes any
transaction of a certain size conducted with related undertakings.
(6) (a) Electricity undertakings shall specify in the notes to
the separate accounts referred to in sub-regulation (3) the rules for the
allocation of assets and liabilities and expenditure and income which
they follow in drawing up the separate accounts required in sub-
regulation (3). Such rules shall be used only after the approval of the
Regulator;
(b) The rules referred to in paragraph (a) may be amended only
with the approval of the Regulator and such amendments shall be
mentioned in the notes and shall be duly substantiated;
(c) The electricity undertakings shall indicate in the notes to
the separate accounts the details of any transaction of a certain size
(being of a size which, in the opinion of the Regulator, would have a
commercial impact) conducted with any
(i)
related undertaking;
(ii) associated undertakings within the meaning
assigned by the Companies Act.
In carrying out the regulatory tasks specified in these General
regulations, the Regulator shall take all reasonable measures in pursuit objectives
Regulator.
of the following objectives within the framework of its duties and
powers as laid down in regulation 47 in close consultation with other
relevant national authorities, including competition authorities, as well
as authorities, including regulatory authorities, from neighbouring
Member States and neighbouring third countries, as appropriate, and
without prejudice to their competence
(a) promoting, in close cooperation with regulatory
authorities of other Member States, the Commission and ACER,
a competitive, flexible, secure and environmentally sustainable
internal market for electricity within the Union, and effective
market opening for all customers and suppliers in the Union, and
ensuring appropriate conditions for the effective and reliable
operation of electricity networks, taking into account long-term
objectives;
(b) developing competitive and properly functioning
regional cross-border markets within the Union with a view to
achieving the objectives referred to in paragraph (a);
(c) eliminating restrictions on trade in electricity
between Member States, including developing appropriate cross-
border transmission capacities to meet demand and enhancing
the integration of national markets which may facilitate
electricity flows across the Union;
(d) helping to achieve, in the most cost-effective way, the
development of secure, reliable and efficient non-discriminatory
systems that are consumer-oriented, and promoting system
adequacy and, in accordance with general energy policy
objectives, energy efficiency, as well as the integration of large
and small-scale production of electricity from renewable sources
and distributed generation in both transmission and distribution
networks, and facilitating their operation in relation to other
energy networks of gas or heat;
(e) facilitating access to the network for new generation
capacity and energy storage facilities, in particular removing
barriers that could prevent access for new market entrants and of
electricity from renewable sources;
(f) ensuring that system operators and system users are
granted appropriate incentives, in both the short and the long
term, to increase efficiencies, especially energy efficiency, in
system performance and to foster market integration;
(g)
ensuring that customers benefit through the efficient
functioning of their national market, promoting effective
competition and helping to ensure a high level of consumer
protection, in close cooperation with relevant consumer
protection authorities;
(h) helping to achieve high standards of universal service
and of public service in electricity supply, contributing to the
protection of vulnerable customers and contributing to the
compatibility of necessary data exchange processes for customer
switching.
(1)
The Regulator shall have the following duties
Duties and
powers of the
Regulator.
(a) fixing or approving, in accordance with transparent
criteria, transmission or distribution tariffs or their
methodologies, or both;
(b) ensuring the compliance of transmission system
operators and distribution system operators and, where relevant,
system owners, as well as the compliance of any electricity
undertakings and other market participants, with their
obligations under these regulations, Regulation (EU) 2019/943,
the network codes and the guidelines adopted pursuant to
Articles 59, 60 and 61 of Regulation (EU) 2019/943, and other
relevant Union law, including as regards cross-border issues, as
well as with ACER’s decisions;
(c) in close coordination with the other regulatory
authorities, ensuring the compliance of the ENTSO for
Electricity and the EU DSO entity with their obligations under
these regulations, Regulation (EU) 2019/943, the network codes
and guidelines adopted pursuant to Articles 59, 60 and 61 of
Regulation (EU) 2019/943, and other relevant Union law,
including as regards cross-border issues, as well as with ACER’s
decisions, and jointly identifying non-compliance of the ENTSO
for Electricity and the EU DSO entity with their respective
obligations; where the regulatory authorities have not been able
to reach an agreement within a period of four (4) months after
the start of consultations for the purpose of jointly identifying
non-compliance, the matter shall be referred to the ACER for a
decision, pursuant to Article 6(10) of Regulation (EU) 2019/942;
(d) approving products and procurement process for non-
frequency ancillary services;
(e) implementing the network codes and guidelines
adopted pursuant to Articles 59, 60 and 61 of Regulation (EU)
2019/943 through national measures or, where so required,
coordinated regional or Union-wide measures;
(f) cooperating in regard to cross-border issues with the
regulatory authority or authorities of the Member States
concerned and with ACER, in particular through participation in
the work of ACER’s Board of Regulators pursuant to Article 21
of Regulation (EU) 2019/942;
(g) complying with, and implementing, any relevant
legally binding decisions of the Commission and of ACER;
(h) ensuring that transmission system operators make
available interconnector capacities to the utmost extent pursuant
to Article 16 of Regulation (EU) 2019/943;
(i) reporting annually on its activity and the fulfilment of
its duties to the relevant national authorities, the Commission
and ACER, including on the steps taken and the results obtained
as regards each of the tasks listed in this regulation;
(j) ensuring that there is no cross-subsidisation between
transmission, distribution and supply activities or other
electricity or non-electricity activities;
(k) monitoring investment plans of the transmission
system operators and providing in its annual report an
assessment of the investment plans of the transmission system
operators as regards their consistency with the Union-wide
network development plan; such assessment may include
recommendations to amend those investment plans;
(l) monitoring and assessing the performance of
transmission system operators and distribution system operators
in relation to the development of a smart grid that promotes
energy efficiency and the integration of energy from renewable
sources, based on a limited set of indicators, and publish a
national report every two years, including recommendations;
(m) setting or approving standards and requirements for
quality of service and quality of supply or contributing thereto
together with other competent authorities and monitoring
compliance with and reviewing the past performance of network
security and reliability rules;
(n) monitoring the level of transparency, including of
wholesale prices, and ensuring compliance of electricity
undertakings with transparency obligations;
(o) monitoring the level and effectiveness of market
opening and competition at wholesale and retail levels, including
on electricity exchanges, prices for household customers
including prepayment systems, the impact of dynamic electricity
switching rates, disconnection rates, charges for maintenance
services, the execution of maintenance services, the relationship
between household and wholesale prices, the evolution of grid
tariffs and levies, and complaints by household customers, as
well as any distortion or restriction of competition, including by
providing any relevant information, and bringing any relevant
cases to the relevant competition authorities;
(p) monitoring the occurrence of restrictive contractual
practices, including exclusivity clauses which may prevent
customers from contracting simultaneously with more than one
supplier or restrict their choice to do so, and, where appropriate,
informing the national competition authorities of such practices;
(q) monitoring the time taken by transmission system
operators and distribution system operators to make connections
and repairs;
(r) helping to ensure, together with other relevant
authorities, that the consumer protection measures are effective
and enforced;
(s) publishing recommendations, at least annually, in
relation to compliance of supply prices with regulation 4, and
providing those recommendations to the competition authorities,
where appropriate;
(t) ensuring non-discriminatory access to customer
consumption data, the provision, for optional use, of an easily
understandable harmonised format at national level for
consumption data, and prompt access for all customers to such
data pursuant to regulation 20 and 21 of these regulations;
(u) monitoring the implementation of rules relating to the
roles and responsibilities of transmission system operators,
distribution system operators, suppliers, customers and other
market participants pursuant to Regulation (EU) 2019/943;
(v) monitoring investment in generation and storage
capacities in relation to security of supply;
(w) monitoring technical cooperation between Union and
third-country transmission system operators;
(x) contributing to the compatibility of data exchange
processes for the most important market processes at regional
level;
(y) monitoring the availability of comparison tools that
meet the requirements set out in regulation 11;
(z) monitoring the removal of unjustified obstacles to
and restrictions on the development of consumption of self-
generated electricity and citizen energy communities.
(2) While preserving its independence, without prejudice to the
Regulator’s specific competence and consistent with the principles of
better regulation, the Regulator shall, as appropriate, consult
transmission system operators and distribution system operators, as
appropriate, closely cooperate with other relevant national authorities
when carrying out the duties set out in sub-regulation (1).
Any approvals given by the Regulator under these regulations are
without prejudice to any duly justified future use of its powers by the
Regulator under these regulations or to any penalties imposed by other
relevant authorities or the Commission.
(3) For the purpose of carrying out the duties under these
regulations in an efficient and expeditious manner, the Regulator shall
have the following powers
(a)
to issue binding decisions on electricity undertakings;
(b) to require any information from electricity
undertakings relevant for the fulfilment of its tasks, including the
justification for any refusal to grant third-party access, and any
information on measures necessary to reinforce the network;
(c) appropriate rights of investigation and relevant
powers of instruction for dispute settlement under sub-regulation
(2) and (3) of regulation 48.
(4) The Regulator, except where ACER is competent to fix and
approve the terms and conditions or methodologies for the
implementation of network codes and guidelines under Chapter VII of
Regulation (EU) 2019/943 pursuant to Article 5(2) of Regulation (EU)
2019/942 because of their coordinated nature, shall be responsible for
fixing or approving sufficiently in advance of their entry into force at
least the national methodologies used to calculate or establish the
terms and conditions for
(a) connection and access to national networks, including
transmission and distribution tariffs or their methodologies,
those tariffs or methodologies shall allow the necessary
investments in the networks to be carried out in a manner
allowing those investments to ensure the viability of the
networks;
(b) the provision of ancillary services which shall be
performed in the most economic manner possible and provide
appropriate incentives for network users to balance their input
and off-takes, such ancillary services shall be provided in a fair
and non-discriminatory manner and be based on objective
criteria; and
(c) access to cross-border infrastructures, including the
procedures for the allocation of capacity and congestion
management.
(5) The methodologies or the terms and conditions referred to
in sub-regulation (4) shall be published.
(6) With a view to increasing transparency in the market and
providing all interested parties with all necessary information and
decisions or proposals for decisions concerning transmission and
distribution tariffs as referred in regulation 48(3), the Regulator shall
make publicly available the detailed methodology and underlying
costs used for the calculation of the relevant network tariffs, while
preserving the confidentiality of commercially sensitive information.
(7) The Regulator shall monitor congestion management of
national electricity systems including interconnectors, and the
implementation of congestion management rules. To that end,
transmission system operators or market operators shall submit their
congestion management rules, including capacity allocation, to the
Regulator. The Regulator may request amendments to those rules.
(1) The Regulator may require transmission system Decisions and
operators and distribution system operators, if necessary, to modify the complaints.
terms and conditions, including tariffs or methodologies referred to
regulation 47 of these regulations, to ensure that they are proportionate
and applied in a non-discriminatory manner, in accordance with
Article 18 of Regulation (EU) 2019/943. In the event of delay in the
fixing of transmission and distribution tariffs, the Regulator shall have
the power to fix or approve provisional transmission and distribution
tariffs or methodologies and to decide on the appropriate
compensatory measures if the final transmission and distribution
tariffs or methodologies deviate from those provisional tariffs or
methodologies.
(2) Any party having a complaint against a transmission or
distribution system operator in relation to that operator's obligations
under these regulations may refer the complaint to the Regulator
which, acting as dispute settlement authority, shall issue a decision
within two (2) months of receipt of the complaint. That period may be
extended by two (2) months where additional information is sought by
the Regulator. That extended period may be further extended with the
agreement of the complainant. The Regulator's decision shall have
binding effect unless and until overruled on appeal.
(3) Any party who is affected and who has a right to complain
concerning a decision on methodologies taken pursuant to regulation
47 or, where the Regulator has a duty to consult, concerning the
proposed tariffs or methodologies, may, within two (2) months, after
publication of the decision or proposal for a decision, submit a
complaint for review. Such a complaint shall not have suspensive
effect.
(4) The Regulator shall take the appropriate measures
including administrative action or criminal proceedings in conformity
with the law, against the natural or legal persons responsible where
confidentiality rules imposed by these regulations have not been
respected.
(5) Complaints referred to in sub-regulations (2) and (3) shall
be without prejudice to the exercise of rights of appeal under Union or
national law.
(6) Decisions taken by the Regulator shall be fully reasoned
and justified to allow for judicial review. The decisions shall be
available to the public while preserving the confidentiality of
commercially sensitive information.
(1) The Regulator shall closely consult and cooperate
with other regulatory authorities, in particular within ACER, and shall
provide each other and ACER with any information necessary for the
fulfilment of their tasks under the Directive. With respect to the
information exchanged, the Regulator shall ensure the same level of
confidentiality as that required of the originating authority.
(2)
The Regulator shall cooperate at least at a regional level to
(a) foster the creation of operational arrangements in
order to enable an optimal management of the network, promote
joint electricity exchanges and the allocation of cross-border
capacity, and to enable an adequate level of interconnection
capacity, including through new interconnection, within the
region and between regions to allow for development of effective
competition and improvement of security of supply, without
discriminating between suppliers in different Member States;
(b) coordinate the joint oversight of entities performing
functions at regional level;
(c) coordinate, in cooperation with other involved
authorities, the joint oversight of national, regional and European
resource adequacy assessments;
(d) coordinate the development of all network codes and
guidelines for the relevant transmission system operators and
other market actors; and
(e) coordinate the development of the rules governing the
management of congestion.
(3) The Regulator shall have the right to enter into cooperative
arrangements with other regulators to foster regulatory cooperation.
(4) The actions referred to in sub-regulation (2) shall be carried
out, as appropriate, in close consultation with other relevant national
authorities and without prejudice to their specific competence.
(1) The Regulator, when forming part of system Duties and
operation region in which a regional coordination centre is established powers
Regulator with
shall, in close coordination with other regional regulatory authorities: respect
regional
coordination
(a) approve the proposal for the establishment of regional centres.
coordination centres in accordance with Article 35(1) of
Regulation (EU) 2019/943;
(b) approve the costs related to the activities of the
regional coordination centres, which are to be borne by the
transmission system operators and to be taken into account in the
calculation of tariffs, provided that they are reasonable and
appropriate;
(c)
approve the cooperative decision-making process;
(d) ensure that the regional coordination centres are
equipped with all the necessary human, technical, physical and
financial resources for fulfilling their obligations under the
Directive and carrying out their tasks independently and
impartially;
(e) propose jointly with other regulatory authorities of a
system operation region possible additional tasks and additional
powers to be assigned to the regional coordination centres by the
Member States of the system operation region;
(f) ensure compliance with the obligations under these
regulations and other relevant Union law, in particular as regards
cross-border issues, and jointly identify non-compliance of the
regional coordination centres with their respective obligations;
where the regulatory authorities have not been able to reach an
agreement within a period of four (4) months after the start of
consultations for the purpose of jointly identifying non-
compliance, the matter shall be referred to ACER for a decision,
pursuant to Article 6(10) of Regulation (EU) 2019/942;
(g) monitor the performance of system coordination and
report annually to ACER in this respect in accordance with
Article 46 of Regulation (EU) 2019/943.
(2) For the purpose of carrying out the duties referred to in sub-
regulation (1) in an efficient and expeditious manner, the Regulator
shall have the following powers
(a)
to request information from the regional coordination
centres;
(b) to carry out inspections, including unannounced
inspections, at the premises of the regional coordination centres;
(c) to issue joint binding decisions on the regional
coordination centres.
(3) The Regulator, when a regional coordination centre has its
seat in Malta, may impose an administrative fine on the regional
coordination centre where it does not comply with its obligations
under these regulations, Regulation (EU) 2019/943 or any relevant
legally binding decisions of the Regulator or of ACER.
(1) The Regulator may request the opinion of ACER on
the compliance of a decision taken by a regulatory authority with the
network codes and guidelines referred to in the Directive or in Chapter
VII of Regulation (EU) 2019/943.
(2) The Regulator may inform the Commission where it
considers that a decision relevant for cross-border trade taken by
another regulatory authority does not comply with the network codes
and guidelines referred to in these regulations or in Chapter VII of
Regulation (EU) 2019/943 within two (2) months of the date of that
decision.
The Regulator shall comply with the Commission decision
requiring it to withdraw its decision within two (2) months and shall
inform the Commission accordingly.
(1) Suppliers shall keep at the disposal of the national Record keeping.
authorities including the Regulator, the national competition authority
and the Commission, for the fulfilment of their tasks, for at least five
(5) years, the relevant data relating to all transactions in electricity
supply contracts and electricity derivatives with wholesale customers
and transmission system operators.
(2) The data shall include details on the characteristics of the
relevant transactions such as duration, delivery and settlement rules,
the quantity, the dates and times of execution and the transaction prices
and means of identifying the wholesale customer concerned, as well as
specified details of all unsettled electricity supply contracts and
electricity derivatives.
(3) The Regulator may decide to make available to market
participants elements of that information
Provided that commercially sensitive information on
individual market players or individual transactions shall not be
released
Provided further that this sub-regulation shall not apply to
information about financial instruments falling within the scope of
Directive 2014/65/EU.
(4) This regulation shall not create additional obligations
towards the authorities referred to in sub-regulation (1) for entities
falling within the scope of Directive 2014/65/EU.
(5) In the event that the authorities referred to in sub-regulation
(1) need access to data kept by entities falling within the scope of
Directive 2014/65/EU, the authorities responsible under that Directive
shall provide them with the required data.
Any person who prior to the entry into force of these Former
regulations was licensed under, and any licence issued under the licensing.
Electricity Regulations, 2004 and the Electricity Market Regulations, L.N.
2004. shall be deemed to have been licensed or to have been issued under S.L. 545. 13.
these regulations, and the provisions of these regulations shall mutatis
mutandis apply to that person and licence
Provided that such person may continue to perform such
operations or activities as licensed under existing licence conditions,
unless required by the Regulator to apply for a new licence under these
regulations
Provided further that any such person shall comply with
such licence conditions as established in the new licence that maybe
issued by the Regulator with effect from such date that the Regulator
may establish.
(1) The following operations and activities shall require a
licence issued by the Regulator and in accordance with such terms and
conditions as may be specified in the licence
(a)
generation of electricity;
(b)
supply of electricity;
(c) carrying out of any of the functions of a distribution
system operator;
(d) carrying out the any of the functions of a transmission
system operator
Provided that, in view of the derogations from the
application of Articles 4 and 6 of the Directive granted to Malta
pursuant to Article 66 of the Directive and until such time as the
aforesaid derogations remain in force, the licence for the supply of
electricity shall be issued only to the distribution system operator,
designated in accordance with regulation 27.
(2) A licence shall not be required for the categories specified
in the Third Schedule for the carrying out of the operations or
activities mentioned therein, including energy storage facilities.
(3) Without prejudice to any other law, licences may be granted
or refused on the basis of the following criteria
(a) compliance by the applicant with all other relevant
permits and authorisations, however so described, including
those issued by any other public authority or Government
Department;
(b) the capability of the applicant to ensure safety
conditions, in the context of the licence being applied for;
(c)
private and professional integrity of the applicant;
(d)
protection of the health and safety of employees;
(e)
protection of the environment;
(f) record of compliance with these regulations and any
other relevant laws by the person or entity with regard to whom
the decision shall be made;
(g) compliance with safety, health, security, hazardous
substances, environment, land use and planning requirements.
(4) An application for a new licence or for its renewal under
these regulations shall be
(a) in writing and in such form and shall contain such
information as the Regulator may require;
(b) accompanied by such fees, bank guarantees and
insurance policies as the Regulator may determine and deem to
be appropriate. All fees shall be payable on application and any
bank guarantees and, or insurance policies shall be effective as
from the date of the issue of the licence and shall subsist
throughout its duration. Interests and penalties, as established by
the Regulator, shall be payable in the event of default in the due
payment of fees
Provided that a licence granted under these regulations
shall not relieve the licensee from the requirement of any other licence,
permit or other authorisation, or from an obligation arising from any
other law.
(5) A licence granted under these regulations may include such
conditions as appear to the Regulator to be requisite or expedient,
having regard to the duties of the Regulator.
(6) The Regulator shall communicate to the applicant in
writing within a reasonable time, which shall not be of more than six
(6) months from the date of receipt of a valid application, any decision
taken concerning an application for a licence or an application for the
renewal of a licence or any valid reason impeding the Regulator to
reach such a decision.
The Regulator may, at any time in the course of the period Suspension,
for which a licence is valid, order its suspension, revocation or revocation
cancellation of
cancellation where the Regulator is satisfied that
licence.
(a) the holder of the licence has failed or is failing to
comply with any condition of the licence or with these
regulations; or
(b) the licensee does not possess all other relevant
licences, permits and authorisations however so described that
are required by any other public authority or Government
department; or
(c) the holder of the licence is contravening any
requirement imposed by law; or
(d) the holder of the licence fails to comply with any
directive given by the Regulator; or
(e) any information submitted in the application for a
licence or the application for renewal of a licence and for which
the licence has been issued or renewed, as the case may be, is
determined to be false; or
(f) if the holder of the licence does not meet any criteria
in respect to one or more of the criteria referred to in regulation
53(3)
Provided that in exercising the powers for suspension,
revocation or cancellation of licences, the Regulator may take into
account the nature of the failure, or the fact that the holder of the
licence is taking the appropriate steps which the Regulator considers to
be necessary in order to comply with the conditions of the licence,
these regulations or any other requirement that the Regulator may
deem relevant.
(1) When the holder of a licence issued under these
regulations, decides either to suspend or terminate his licence, such
holder shall promptly notify the Regulator in the form prescribed by
the Authority, to notify such a termination or suspension.
(2) Upon acknowledgment by the Regulator to the holder of a
licence of the notification mentioned in sub-regulation (1), the licence
shall be considered to have ceased to be in force and with immediate
effect from the date of such acknowledgment such holder shall be
deemed to be unlicensed.
(3) Notwithstanding any notice for the termination or
suspension of a licence, the holder of the licence shall remain liable for
the payment of any fee due to the Regulator.
(1) A licence issued by the Regulator under these
regulations shall not be validly transferred inter vivos to any other
person unless
(a) the transferor informs in writing the Regulator in
such form and manner as the Regulator shall prescribe;
(b) the Regulator is satisfied that at least the same criteria
as listed in regulation 54(3) are complied with;
(c) the transfer is subject to the conditions prescribed in
the licence; and
(d)
the Regulator approves in writing the transfer of the
licence.
(2) A licence issued by the Regulator under these regulations
shall not be validly transmitted causa mortis to any other person
unless
(a) the transferor informs in writing the Regulator in
such form and manner as the Regulator shall prescribe;
(b) the Regulator is satisfied that at least the same criteria
as listed in regulation 53(3) are complied with;
(c) the transfer is subject to the conditions prescribed in
the licence; and
(d)
the Regulator approves in writing the transfer of the
licence
Provided that a licence issued in terms of these regulations
shall be an indivisible right
Provided further that in the event that the Regulator
approves the transfer of the licence as aforesaid, the transfer shall have
retrospective effect from the date of the death of the decujus.
(3) Where the licensee is a body corporate or any other body of
persons, a change in the control of the ownership or management of
that body shall be deemed to be equivalent to the transfer of the licence
and shall be subject to the approval of the Regulator. For the purpose
of this sub-regulation, a transfer in the control of the ownership of a
body corporate or other body of persons shall be deemed to occur in
any case where a transfer of the capital, shares, stocks or other rights
held in the body corporate or other body of persons leads to a change
in the person holding the controlling interest therein.
(1) The electricity supplier or the operator of any Recharging
recharging point accessible to the public shall provide for the points.
possibility for electric vehicle users to recharge on an ad hoc basis
without entering into a contract.
(2) The distribution system operator shall cooperate on a non-
discriminatory basis with any person establishing or operating
recharging points accessible to the public.
(1) Any person who contravenes any of the provisions of
these regulations or of a licence condition or of an authorisation or
approval issued thereunder, shall be guilty of an offence, and shall, on
conviction, be liable to a fine (multa) of not more than sixty-nine
thousand euro (€69,000) or for one thousand and three hundred euro
(€1,300) for each day during which the offence persists.
(2) Any person who, when information with respect to these
regulations is requested or required by the Regulator, knowingly or
negligently
(a)
gives any false, inaccurate or misleading information;
or
(b)
supplies incomplete information; or
(c) fails, without reasonable cause, to supply information
requested within the time given; or
(d)
prevents or hinders any investigation; or
(e) produces or furnishes, or causes or knowingly allows
to be produced or furnished, any document or information which
he knows to be false in any material respect,
shall be guilty of an offence, and shall, on conviction, be liable to
a fine (multa) of not less than one thousand euro (€1,000) and of not
more than sixty thousand euro (€60,000) for each day during which the
failure to comply subsists.
(3) Notwithstanding any other provision of these regulations,
where any person fails to comply with the provisions of these
regulations or of a licence or authorisation condition for a period not
exceeding three (3) months, the Regulator may revoke such licence or
authorisation.
(1) The Regulator may impose an administrative fine
upon any person who infringes any provision of these regulations or
who fails to comply with any directive or decision given by the
Regulator in ensuring compliance with these regulations.
(2)
An administrative fine imposed under sub-regulation (1)
shall not exceed one hundred thousand euro (€100,000) for each
contravention and, or six hundred euro (€600) for each day of non-
compliance, from the date of the decision given by the Regulator
Provided that, in the case of undertakings (including
vertically integrated undertakings) or a body corporate, a fine of up to
ten per cent (10%) of the total turnover concerned in the preceding
business year may be imposed even if such fine results in an amount
which exceeds the threshold provided in this sub-regulation.
The Administrative Review Tribunal established by article Administrative
5 of the Administrative Justice Act shall be competent to hear and Review
Tribunal.
determine appeals from decisions of the Regulator made under these Cap. 490.
regulations. Unless otherwise provided by law, an appeal from a
decision of the Regulator made under these regulations shall lie to the
Administrative Review Tribunal in accordance with article 32 of the
Act.
The Electricity Market Regulations are hereby being Repeals the
Electricity
repealed.
Market
Regulations.
S.L. 545. 13.