Installations (Capacity between 400kWp and less than 1000kWp)
Table of Provisions (17)
Statutory Text (17 Articles)
L.N. 212 of 2021
REGULATOR FOR ENERGY AND WATER SERVICES ACT
(CAP. 545)
PUBLIC FINANCE MANAGEMENT ACT
(CAP. 601)
Competitive Bidding Rules for Renewable Sources of Energy
Installations (Capacity between 400kWp and less than 1000kWp)
(Amendment) Regulations, 2021
IN EXERCISE of the powers conferred by article 37 of the
Regulator for Energy and Water Services Act and by article 4 of the
Public Finance Management Act, the Minister for Energy, Enterprise
and Sustainable Development, after consultation with the Regulator
for Energy and Water Services, and the Minister for Finance and
Employment have made the following regulations:-
The title of these regulations is the Competitive Bidding
Rules for Renewable Sources of Energy Installations (Capacity
between 400kWp and less than 1000kWp) (Amendment) Regulations,
2021 and these regulations shall be read and construed as one with the
Competitive Bidding Rules for Renewable Sources of Energy
Installations (Capacity between 400kWp and less than 1000kWp)
Regulations, hereinafter referred to as the "principal regulations".
In regulation 1 of the principal regulations, the words
"(Capacity between 400kWp and less than 1000kWp)" shall be
substituted by the words "(Capacity from 40kW up to less than
1000kW)".
Regulation 2 of the principal regulations shall be amended
as follows
(a) in the definition "approved renewable energy
installation", the words "with a capacity between 400kWp and
less than 1000kWp" shall be substituted by the words "with a
capacity from 40kWp up to less than 1000kWp";
(b) the definition "common point of connection to the
grid" shall be deleted;
(c) the definition "competitive bidding process" shall be
substituted by the following new definition
" "competitive bidding process" means a non-
discriminatory bidding process that provides for the
participation of a sufficient number of undertakings and
where the support is granted on the basis of the bid
submitted by the bidder. In addition, the volume related to
the bidding process is a binding constraint leading to a
situation where not all bidders can receive support;";
(d) in the definition "eligible renewable energy
installation", the words "with a capacity between 400kWp and
less than 1000kWp" shall be substituted by the words "with a
capacity from 40kW up to less than 1000kW" and immediately
thereafter there shall be added the following new definition
" "force majeure" means acts of God, strikes, lock-
outs or other industrial disturbances, acts of the public
enemy, wars, whether declared or not, blockades,
insurrection, riots, epidemics, landslides, earthquakes,
storms, direct lighting strikes, floods, washouts, civil
disorder, explosions and other similar unforeseeable events,
which by the exercise of due diligence cannot be overcome
and which, in the view of the Contracting Authority prevent
a successful bidder from adhering to obligations due to
causes beyond his reasonable control;";
(e) the definition "full load hours" shall be substituted by
the following new definition
" "full load hours" means the equivalent number of
hours in a calendar year during which the renewable energy
installation produces at its full nominal or kW capacity;";
(f) the definition "kW" shall be substituted by the
following new definition
" "kW" means kilo Watt and in the context of these
regulations shall be taken to refer to the nominal capacity of
the renewable energy installation, which in the case of a
solar photovoltaic installation is equal to the total DC peak
power at standard test conditions of the installation;";
(g)
the definition "kWp" shall be deleted; and
(h) the definition "renewable energy sources" shall be
substituted by the following new definition
" "renewable energy sources" means renewable non-
fossil energy sources, that is, wind, solar (solar thermal and
solar photovoltaic), and geothermal energy, ambient energy,
tide, wave and other ocean energy, hydropower, biomass,
landfill gas, sewage treatment plant gas and biogas;".
Regulation 3 of the principal regulations shall be amended
as follows
(a) sub-regulation (1) thereof shall be substituted by the
following new sub-regulation
"(1) The purpose of these regulations is to introduce
the competitive bidding process as the method to determine
the fixed price per kWh to be paid for electricity generated
and sold to the distribution system operator from approved
renewable energy installations with a capacity between
40kW and less than 1000kW and hence to promote and
support the generation of electricity from renewable energy
sources."; and
(b) sub-regulation (3) thereof shall be substituted by the
following new sub-regulation
"(3) These regulations shall not apply to
undertakings in difficulty as defined in Commission
Regulation (EU) No 651/2014 of 17 June 2014 declaring
certain categories of aid compatible with the internal
market in application of Articles 107 and 108 of the Treaty,
as amended by Commission Regulation (EU) No 2017/
1084 of 14 June 2017 amending Regulation (EU) No 651/
2014 as regards aid for port and airport infrastructure,
notification thresholds for aid for culture and heritage
conservation and for aid for sport and multifunctional
recreational infrastructures, and regional operating aid
schemes for outermost regions and amending Regulation
(EU) No 702/2014 as regards the calculation of eligible
costs, and by Commission Regulation (EU) 2020/972 of 2
July 2020 amending Regulation (EU) No 1407/2013 as
regards its prolongation and amending Regulation (EU) No
651/2014 as regards its prolongation and relevant
adjustments, and as may be subsequently amended.".
Regulation 5 of the principal regulations shall be amended
as follows
(a) sub-regulation (4) thereof shall be substituted by the
following new sub-regulation
"(4) The awarded bid price per kWh shall only be
applicable to a successful bidder and only in respect of the
renewable energy installation as described in the bid
including the capacity offered in the bid (in kW), as part of
the competitive bidding process. The capacity associated
with the bid price shall be deemed to be equal to
Offered kW x Full Load Hours
1600"; and
(b) in sub-regulation (6) thereof, the words "as offered
kWp x Full Load Hours:" shall be substituted by the words "as
offered kW x Full Load Hours:".
Regulation 7 of the principal regulations shall be Substitutes
substituted by the following new regulation
"7. (1) An
approved
renewable
energy
installation shall be fully commissioned as described in
the bid, including the capacity offered in the bid, and an
application to connect the installation to the distribution
system shall be submitted to the distribution system
operator within eighteen (18) months to be reckoned as
from the date of the letter of award issued by the
Contracting Authority to the successful bidder to secure
the eligibility of the awarded bid price per kWh.
(2) If the successful bidder fails to comply with
sub-regulation (1), the time to commission and apply to
connect said fully commissioned approved renewable
energy installation to the distribution system as indicated
in sub-regulation (1) may be extended once only by six(6)
months by means of a request in writing to the
Contracting Authority, which request shall be made in the
format required by the Contracting Authority
Provided that if an extension is availed of, the
generated and sold to the distribution system operator for
the particular approved renewable energy installation
shall be equivalent to the awarded bid price per kWh, less
€0.005/kWh for all electricity generated and sold to the
distribution system operator up to the amount indicated in
regulation 5(6), for the guaranteed period.
(3) The request in writing for an extension
indicated in sub-regulation (2) shall reach the Contracting
Authority no later than one (1) month before the lapse of
the eighteen (18) month deadline indicated in sub-
regulation (1)
Provided that should an extension be
requested but not availed of, the reduction in the bid price
established in the proviso to sub-regulation (2) shall not
be applicable.
(4) The time necessary for the successful bidders
to obtain the necessary authorisations, licences and
permits as applicable, shall not suspend the running of the
time periods established in sub-regulations (1) and (2),
being the maximum time within which an approved
renewable energy installation shall be fully
commissioned and an application to connect the
installation to the distribution system shall be submitted
to the distribution system operator, for the award pursuant
to the competitive bidding process to remain valid.
Failure to comply with sub-regulations (1) (2), when a
request for an extension has been made, shall lead to the
automatic withdrawal of the award and the forfeiture of
the performance bond
Provided that a verified event of force majeure
may be invoked by a successful bidder, in line with the
provisions related thereto included in the invitation for
bids of the relevant competitive bidding process, to
request a suspension of the time periods established in
sub-regulations (1) and (2), which request may be granted
at the Contracting Authority’s discretion.".
In regulation 8 of the principal regulations, the word "kWp"
shall be substituted by the word "kW".
In the proviso to sub-regulation (1) of regulation 9 of the
principal regulations, the words "Regulation (EU) No 702/2014 as
regards the calculation of eligible costs, and as may be subsequently
amended." shall be substituted by the words "Regulation (EU) No 702/
2014 as regards the calculation of eligible costs, and by Commission
Regulation (EU) 2020/972 of 2 July 2020 amending Regulation (EU)
No 1407/2013 as regards its prolongation and amending Regulation
(EU) No 651/2014 as regards its prolongation and relevant
adjustments, and as may be subsequently amended.".
Sub-regulation (1) of regulation 10 of the principal Amends
regulations shall be substituted by the following new sub-regulation: regulation
the principal
regulations.
"(1) The successful bidder shall be required to provide a
performance bond to the Contracting Authority. The value of the
performance bond and the deadline for its submission shall be
included in the invitation for bids of the relevant competitive
bidding process.".
In regulation 11 of the principal regulations, the words Amends
"The bid price per kWh and the corresponding eligible renewable regulation
the principal
energy installation kWp capacity shall be selected pursuant to the regulations.
competitive bidding process, starting from the lowest bid offered, and
provided that the kWp available for allocation in the particular
competitive bidding process is not exceeded." shall be substituted by
the words "The bid price per kWh and the corresponding eligible
renewable energy installation kW capacity shall be selected pursuant
to the competitive bidding process, starting from the lowest bid
offered, and provided that the kW available for allocation in the
particular competitive bidding process is not exceeded.".
In paragraph (c) of regulation 12 of the principal Amends
regulation 12 of
regulations, the word "kWp" shall be substituted by the word "kW".
the principal
regulations.
In regulation 13 of the principal regulations, the word Amends
regulation 13 of
"kWp" shall be substituted by the word "kW".
the principal
regulations.
In sub-regulation (1) of regulation 15 of the principal Amends
regulations, the words "The successful bidder shall be responsible to regulation
the principal
obtain any relevant permits, authorisations and licences within the regulations.
time-frames stated in regulation 7." shall be substituted by the words
"Excepting any permits which may be required by the provisions of the
invitation for bids of the relevant competitive bidding process, to have
already been issued at the time of bidding, the successful bidder shall
be responsible to obtain any relevant permits, authorisations and
licences within the time-frames established in regulation 7.".
In sub-regulation (2) of regulation 16 of the principal Amends
regulation 16 of
regulations, the word "kWp" shall be substituted by the word "kW".
the principal
regulations.
In regulation 17 of the principal regulations, the words Amends
"with a capacity between 400kWp and less than 1000kWp" shall be regulation
the principal
deleted and substituted by the words "with a capacity from 40kWp up regulations.
to less than 1000kWp".
Regulation 18 of the principal regulations shall be
renumbered as sub-regulation (1) and immediately thereafter there
shall be added the following new sub-regulation
"(2) The rules for determining the amount of the deposit
necessary for submitting a complaint as provided for in sub-
regulation (1) shall be stipulated in the rules applicable to the
invitation for bids of the relevant competitive bidding process.".
€0.63