Photovoltaic Installations) (Amendment) Regulations, 2019
Statutory Text (5 Articles)
L.N. 2 of 2019
REGULATOR FOR ENERGY AND WATER SERVICES ACT
(CAP. 545)
Feed-in Tariffs Scheme (Electricity Generated from Solar
Photovoltaic Installations) (Amendment) Regulations, 2019
IN EXERCISE of the powers conferred by article 37(1) of the
Regulator for Energy and Water Services Act, the Minister for Energy
and Water Management, after consultation with the Regulator for
Energy and Water Services, in agreement with the Minister for
Finance, has made the following regulations:-
The title of these regulations is the Feed-in Tariffs Scheme Citation.
(Electricity Generated from Solar Photovoltaic Installations)
(Amendment) Regulations, 2019 and these regulations shall be read
and construed as one with the Feed-in Tariffs Scheme (Electricity S.L. 545.27.
Generated from Solar Photovoltaic Installations) Regulations,
hereinafter referred to as "the principal regulations".
The Second Schedule to the principal regulations, shall be Amends the
Second Schedule
amended as follows
to the principal
regulations.
(a)
in item 1 thereof;
(i) Table A shall be substituted by the following
new Table
''
Table A: Caps and Feed in Tariffs applicable for solar photo-
voltaic installations approved under the FIT scheme
Capacity of
Feed-in Tariffs
Maximum units
scheme solar photo-
applicable
allocated per
voltaic instal- between the 2nd annum for FIT
lation installed January 2019 and payment to PV
in any location 30th December
systems
2019 in case of (a) approved under
and between the this FIT scheme
2nd January 2019 between the 2nd
and 30th Decem- January 2019
ber 2019 in case of and 30th Decem-
(b)
ber 2019 in case
of (a) and
between the 2nd
January 2019
and 30th Decem-
ber 2019 in case
of (b)
(a)
=>1kWp and
5 cents per kWh 12.8 GWh per
<40kWp
annum (8MWp)
(b)
=>40kWp and
14.0c per kWh
0 GWh per
<1MWp
annum
(25MWp)*
*Valid applications for a feed-in tariff received by the
30th November 2018 and accepted by the Regulator over
and above the available capacity until the 31st December
2018, shall be allocated support under this scheme but at
the feed in tariff rates applicable on the 30th November
2018.''; and
(ii) the words ''Applications received under
previous schemes are not eligible under the FIT scheme in
Table A. Such applications have to be re-submitted to the
Regulator for approval, if applicable.'' shall be deleted;
(b) paragraph (a) of item 4 thereof, shall be substituted
by the following
''(a) approved for the FIT scheme from the 2nd
January 2019 and the 30th December 2019; and''.
€0.18