Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

L.N. 47 of 2018

BUILDING REGULATION ACT

(CAP. 513)

Energy Performance of Buildings Regulations, 2018

IN exercise of the powers conferred by article 6(1) of the

Building Regulation Act, the Minister for Transport, Infrastructure

and Capital Projects, after consultation with the Building Regulation

Office, has made the following regulations:-

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The title of these regulations is the Energy Citation and

scope.

Performance of Buildings Regulations, 2018.

(2) The scope of these regulations is to transpose Directive

2010/31/EU of the European Parliament and of the Council on the

energy performance of buildings and to give effect to its provisions.

These regulations promote the improvement of the energy

performance of buildings within the territory of Malta, taking into

account outdoor climatic and local conditions, as well as indoor

climate requirements and cost-effectiveness.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) Unless otherwise stated in these regulations, the Interpretation.

definitions prescribed in the Act and in the Technical Document F

referred to in regulation 5, shall also apply.

(2) For the purpose of these regulations and unless the context

otherwise requires, the following definitions shall apply

"the Act" means Building Regulation Act;

"advisory report" means a report made by an energy

performance of building (EPB) assessor, accompanying an Energy

Performance Certificate (EPC), worked on the basis of an assessment

of the energy performance of a building or heating or cooling

installations, and containing recommendations on how the energy

performance of the building or heating or cooling installations may be

improved in a cost-effective manner;

"air-conditioning system" means a combination of the

components required to provide a form of indoor air treatment, by

which temperature is controlled or lowered;

"asset rating" means an energy performance rating based on

(a)

data for the building as actually constructed;

(b)

calculations of the energy used in a building for

heating, cooling, ventilation, hot water and lighting; and

(c)

standard input data in relation to internal and

external climates and building occupation, and representing the

intrinsic energy performance potential of the building under

standardised conditions of weather and building occupation;

"authorised officer" means a person authorised by the Head of

the Building Regulation Office to monitor and ensure compliance

with these regulations;

"body corporate" means a body or legal entity, such as an

association, company, person, the government, government agencies,

corporation, or institution, identified by a particular name and bearing

a distinct and separate legal personality or legal status from that of its

members, also known as corporate entity;

"boiler" means the combined boiler body-burner unit, designed

to transmit to fluids the heat released from burning;

"building" means a roofed construction having walls, for which

energy is used to condition the indoor climate, and which may refer to

the building as a whole or part thereof which has been designed or

altered to be used separately;

"building element" means a technical building system or an

element of the building envelope;

"building envelope" means the integrated elements of a building

which separate its interior from the outdoor environment;

"the Building Regulation Board" means the Board as

established by article 3 of the Act;

"the Building Regulation Office" shall have the same meaning

as assigned to it under article 2(1) of the Act;

"building unit" means a section, floor or apartment within a

building which is designed or altered to be used separately;

"cogeneration" means the simultaneous generation in one

process of thermal energy and electrical and, or mechanical energy;

"compliance certificate" means a certificate issued by a

competent person certifying that the completed building is compliant

with these regulations and associated Technical Document F (Parts 1

and 2) and any other instructions issued by the Building Regulations

Office;

"the Commission" means the European Commission as

established by the Treaty on the European Union as amended by the

Lisbon Treaty of 2009;

"cost-optimal level" means the energy performance level which

leads to the lowest cost during the estimated economic lifecycle,

where

(a) the lowest cost is determined taking into account

energy-related investment costs, maintenance and operating

costs including, where applicable, energy costs and savings, the

category of building concerned, earnings from energy produced,

throughout the estimated economic lifecycle together with any

disposal costs, if applicable; and

(b) the estimated economic lifecycle is determined

according to the remaining estimated economic lifecycle of a

building where energy performance requirements are set for the

building as a whole, or to the estimated economic lifecycle of a

building element where energy performance requirements are

set for building elements. The cost-optimal level shall be

deemed to be obtained where the cost benefit analysis within the

range of performance levels, calculated over the estimated

economic lifecycle, is positive;

"design rating" is an energy performance rating based on

(a) calculations, done at the design stage, of the energy

used in a building for heating, cooling, ventilation, hot water

and lighting;

(b) standard input data related to internal and external

climates and building occupancy; and

(c)

the design characteristics of the building as

complete with permanently installed finishes, fixtures, fittings

and mechanical and electrical installations to render that

building habitable and good for its intended use under

standardised conditions of weather and building occupancy;

"development permission application" means an application for

a development permit issued by the Planning Authority;

"district heating" or "district cooling" means the distribution of

thermal energy in the form of steam, hot water or chilled liquids or

other fluids, from a central source of production through a network to

multiple buildings or sites, for the use of space or process heating or

cooling;

"dwelling" means a building or building unit used or intended to

be used for domestic purposes and usually containing eating, living,

sleeping and sanitary facilities;

"effective rated output" means the maximum calorific output,

expressed in kW, specified and guaranteed by the manufacturer as

being deliverable during continuous operation while complying with

the useful efficiency indicated by the manufacturer;

"Enemalta" means the Enemalta plc as established by the

Enemalta (Transfer of Assets, Rights, Liabilities and Obligations)

Act;

"energy from renewable sources" means energy from renewable

non-fossil sources, namely wind, solar, aerothermal, geothermal,

hydrothermal and ocean energy, hydropower, biomass, landfill gas,

sewage treatment plant gas and biogases;

"energy performance assessment (EPA)" means an assessment

of the energy performance of a building carried out by an EPB

assessor for the purpose of assigning an EPC;

"energy performance certificate (EPC)" means a certificate

issued by an EPB assessor recognised by the Building Regulation

Office or by a person designated by it and authorised to act on its

behalf. The methodology used by the EPB assessor shall conform

with the methodology adopted in accordance with regulation 4;

"energy performance of a building (EPB)" means the calculated

or measured amount of energy, needed to meet the energy demand

associated with a typical use of the building, which includes, inter

alia, energy used for heating, cooling, ventilation, hot water and

lighting;

"EPB assessor" means a person who is duly registered with the

Building Regulation Office after it has taken into consideration that

such person is in possession of

(a) a warrant to practice the profession of architect and,

or civil/structural engineer, or the warrant to practice the

profession of mechanical or electrical engineer, and who has

also successfully undertaken a period of training on the

assessment of the energy performance of buildings built in

Malta, and such training is approved by the Building Regulation

Board; or

(b) in the case of an EU citizen, a registration certificate

as an EPB assessor in any other Member State, and a warrant to

practice the profession of architect and, or civil/structural

engineer, or the warrant to practice the profession of mechanical

or electrical engineer

Provided that in the case of a person who comes to Malta

to provide such services for the first time, the service provider or EPB

assessor shall, in terms of regulation 9(1) of the Recognition of S.L. 451.03.

Professional Qualifications Regulations, inform the Building

Regulation Office in a written declaration to be made at least two

weeks in advance. Such declaration shall be renewed each year if the

service provider intends to provide temporary or occasional services

during that year

Provided also that for the first provision of services

whether on a temporary or permanent basis, or if there is a material

change in the situation substantiated by the documents, the Building

Regulation Office may, in terms of regulation 9(2) of the Recognition S.L. 451.03.

of Professional Qualifications Regulations, require that the

declaration and the registered certificate be accompanied by the

following documents

(a)

proof of the nationality of the service provider;

(b) an attestation certifying that the holder is legally

established in a Member State for the purpose of pursuing the

activities concerned and that he is not prohibited, even

temporarily, from practising the relevant profession and that of

an EPB assessor;

(c)

evidence of professional qualifications;

"EPC data file" means an electronic file which contains a report

on the outcome of an EPA, which is completed by an EPB assessor

and provided to the Building Regulation Office for the purpose of

notifying it of the record to be made or updated on the EPC register in

respect of a particular building, and it shall be deemed to include any

calculations and related data or documents accompanying such

report;

"EPC record" means the current and any previous EPC, any

advisory report, any EPC data file and any related data or documents,

as the case may be, pertaining to a building;

"EPC register" means a database of EPC records and related

data or documents established, operated, and maintained by the

Building Regulation Office;

"EPC system" means the registers, procedures and rules

established, operated, and maintained by the Building Regulation

Office for the purpose of administering EPCs and related activities in

accordance with these regulations;

"European standard" means a standard adopted by the European

Committee for Standardisation, the European Committee for Electro-

technical Standardisation or the European Telecommunications

Standards Institute and made available for public use;

"existing building" means any building which

(a) is already constructed prior to the date of entry into

force of these regulations; or

(b) is in the course of construction or earmarked for

construction and has a valid development permit in terms of

these regulations prior to the date of entry into force of these

regulations;

"heat pump" means a machine, a device or installation that

transfers heat from natural surroundings such as air, water or ground

to buildings or industrial applications by reversing the natural flow of

heat, such that it flows from a lower to a higher temperature. In the

case of reversible heat pumps, it may also move heat from the

building to the natural surroundings;

"independent air-conditioning systems inspector" means a

registered air-conditioning systems inspector who is not the owner or

tenant of the air-conditioning system being inspected, or an employee

of the owner, or of any contractor responsible for the installation or

maintenance of an air-conditioning system for which an inspection is

made;

"independent energy performance assessor" means a registered

assessor of energy performance of building, who is not the owner or

tenant of the building being assessed, or an employee of the owner, or

of any contractor responsible for the construction, finishing and, or

installation of mechanical or electrical services of a building for

which an EPC is being requested or inspections of boilers, or lighting,

space heating or space cooling systems are made;

"independent heating systems inspector" means a registered

heating systems inspector who is not the owner or tenant of the

heating system being inspected, or an employee of the owner, or of

any contractor responsible for the installation or maintenance of a

heating system for which an inspection is made;

"installation" means a system providing artificial lighting, water

heating, space heating or space cooling or space ventilation in any

combination;

"major renovation or alteration" means a renovation or

alteration

(a)

which affects a building by 25% or more of its

volume before such an intervention; or

(b) where renovation of 25% or more of windows or

roofs or external walls is made; or

(c)

where renovation of 25% or more of any energy

consuming installations for artificial lighting, or heating or

cooling of air or water or space ventilation is made; or

(d) where a change-of-use development permission

application and, or notification concerning buildings, is

submitted to the Planning Authority;

"Member State" means a state which is a member of the

European Union;

"the Minister" means the Minister responsible for the building

industry and policy;

"nearly zero-energy building" means a building that has a very

high energy performance, as determined in accordance with Schedule

I. The nearly zero or very low amount of energy required shall be

covered to a very significant extent by energy from renewable

sources, including energy from renewable sources produced on-site or

nearby;

"new building" means any building which does not fall under

any of the categories of existing building;

"non-residential building or premises" means any building or

premises, or any part of a building or premises, which is not used or is

unsuitable for use as a residential building or habitation, and includes

industrial buildings, places of assembly, offices, schools and shops;

"owner" means

(a)

a person who has the exclusive and full ownership

of the building and who is acting in his own name, or as an

agent for or on behalf of another person, who is entitled or shall

be so entitled to receive the rent of the building;

(b) where the building is subject to usufruct, the bare

owner or the usufructuary;

(c)

an emphyteuta;

(d) any one of the spouses, where the building to which

the EPC relates forms part of the community of acquests;

"owner of an air-conditioning system" means a person acting in

his own name, or as an agent for or on behalf of another person, who

has the exclusive and full ownership of the air-conditioning system;

"owner of a heating system" means a person acting in his own

name, or as an agent for or on behalf of another person, who has the

exclusive and full ownership of the heating system;

"person" means any natural or legal person;

"Planning Authority" means the authority established under

article 5 of the Development Planning Act;

"primary energy" means energy from renewable and non-

renewable sources and which has not undergone any conversion or

transformation process;

"prospective buyer or tenant" means a person who

(a) is in the process of entering a sale agreement with

another person or with the agent of such other person for the

purpose of purchasing a building; or

(b) enters a promise of sale agreement with another

person or the agent of such other person for the purpose of

purchasing a building; or

(c)

enters a contract of letting and hiring, whether

verbally or written, to rent a building;

"register of EPB assessors" means a database containing a list of

EPB assessors registered with the Building Regulation Office and any

other related data established, operated, maintained and owned by the

Building Regulation Office;

"registered air-conditioning systems inspector" means a person

who is duly registered with the Building Regulation Office as an air-

conditioning systems inspector;

"registered heating systems inspector" means a person who is

duly registered with the Building Regulation Office as a heating

systems inspector;

"technical building system" means technical equipment for the

heating, cooling, ventilation, hot water, lighting or for a combination

thereof, of a building or building unit;

"unincorporated body" means a body or business which is

privately owned, often owned by one person having unlimited

liability owing to the non-registration of the business as a company

and which on the contrary of corporate bodies lacks legal personality;

"useful floor area" means the area of the building relevant to the

official calculation methodology relevant to that building category.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

These regulations provide for requirements as regards

Applicability.

(a) the common general framework for a methodology

for calculating the integrated energy performance of buildings

and building units;

(b) the application of minimum requirements for the

energy performance of new buildings and new building units;

(c)

the application of minimum requirements for the

energy performance of

(i) existing buildings, building units and

building elements which are subject to major renovation;

(ii) building elements which form part of the

building envelope and that have a significant impact on the

energy performance of the building envelope when they

are retrofitted or replaced; and

(iii) technical building systems whenever they are

installed, replaced or upgraded;

(d) national plans for increasing the number of nearly

zero-energy buildings;

(e)

energy certification of buildings or building units;

(f)

regular inspection of heating and air-conditioning

systems in buildings; and

(g) independent control systems for energy performance

certificates and inspection reports.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

The methodology for calculating the energy performance

of buildings shall be in accordance with the common general

framework set out in Schedule I as established and implemented

through the Energy Performance Rating of Dwellings in Malta

(EPRDM) and Simplified Building Energy Model (iSBEMmt),

supplemented by the User’s Guide to iSBEMmt and the Technical

Guide to iSBEM, as issued and updated from time to time and as

communicated in the Gazette.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Board shall take the

necessary measures to establish minimum energy performance

requirements for buildings or building units, with a view to achieving

cost-optimal levels. The energy performance shall be calculated in

accordance with the methodology referred to in regulation 4. Cost-

optimal levels shall be calculated in accordance with the comparative

methodology framework referred to in regulation 6. Building design

should be compliant with the Technical Document F on the EPB

published by the Conservation of Fuel, Energy and Natural Resources

(Minimum Requirements on the Energy Performance of Buildings)

Regulations, as may from time to time be amended, as the Building

Regulation Board shall determine.

(2) The Building Regulation Board shall take the necessary

measures to establish minimum energy performance requirements for

building elements that form part of the building envelope and which

have a significant impact on the energy performance of the building

envelope when they are replaced or retrofitted, with a view to

achieving cost-optimal levels.

(3) When setting requirements, the Building Regulation Board

shall differentiate between new and existing buildings and between

different categories of buildings. These requirements shall take into

account general indoor climate conditions, in order to avoid possible

negative effects such as inadequate ventilation, as well as local

conditions and the designated function and the age of the building.

(4) Minimum energy performance requirements shall be

reviewed at regular intervals which shall not be longer than five years

and, if necessary, shall be updated in order to reflect technical

progress in the building sector.

(5) The following categories of buildings shall be exempted

from the requirements of sub-regulations (1), (2), (3) and (4)

(a)

buildings classified as scheduled property (Grade 1

or 2) by the Planning Authority under article 57 of the

Development Planning Act and buildings officially protected as

part of a designated environment or because of their special

architectural or historical or contextual merit, in so far as

compliance with certain minimum energy performance

requirements would unacceptably alter their character or

appearance;

(b)

buildings used as places of worship;

(c)

temporary buildings with a time of use of two years

or less, industrial sites, workshops and non-residential

agricultural buildings with low energy demand, and non-

residential agricultural buildings which are in use by a sector

covered by a national sectoral agreement on energy

performance;

(d) stand-alone buildings with a total useful floor area

of less than 50m 2 ;

(e)

a building constructed for the Enemalta plc, the

Water Services Corporation or any other similar entity, and used

as a generation, transmission or distribution station.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Board shall establish Calculation of

standard cost-optimal levels based on macro-economic scale and cost-optimal

levels of

micro-economic scale of minimum energy performance requirements minimum

energy

using the comparative methodology framework established in performance

accordance with Schedule III and relevant parameters, such as requirements.

climatic conditions and the practical accessibility of energy

infrastructure, and compare the results of such standards with the

minimum energy performance requirements set out in the Technical

Document F.

(2) The Building Regulation Board shall report to the

Commission, at regular intervals, which shall not be longer than five

years, all input data and assumptions used for such standards and the

results thereof. The report may be included in the Energy Efficiency

Action Plans (EEAP) referred to in regulation 24(2) of the Energy S.L. 545.16.

Efficiency and Cogeneration Regulations.

(3) If the result of the comparison performed in accordance

with sub-regulation (2) shows that the minimum energy performance

requirements in force are significantly less energy efficient than cost-

optimal levels of minimum energy performance requirements, the

Building Regulation Board shall justify this difference in writing to

the Commission in the report referred to in sub-regulation (2). Such

report shall, to the extent that the difference cannot be justified, be

accompanied by a plan outlining appropriate steps to significantly

reduce the difference by the next review of the energy performance

requirements as referred to in regulation 5(1), (2), (3) and (4).

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Office shall take the

necessary measures to ensure that new buildings meet the minimum

energy performance requirements as currently set in Technical

Document F. As from 1st January 2016 all newly completed buildings

that are subject to these regulations are to be certified for compliance

with these regulations with regards to the applicable minimum energy

performance requirements as set in Technical Document F. The

compliance certificate drawn up by the responsible architect/engineer

has to be submitted by the owner to the Building Regulation Office

within one month of completion and before the use of the building.

(2) For new buildings, the designer shall ensure that before

construction starts, the technical, environmental and economic

feasibility of high-efficiency alternative systems such as those listed

below, if available, is considered and taken into account

(a)

decentralized energy supply systems based on

energy from renewable sources;

(b)

cogeneration;

(c)

district or block heating or cooling, if available,

particularly where it is based entirely or partially on energy

from renewable sources;

(d)

heat pumps.

(3) The analysis of alternative systems referred to in sub-

regulation (2) shall be documented and available for verification

purposes and presented to the Building Regulation Office prior to

construction

(a) for small developments, the architect will be

required to make a self declaration following the consideration

of the alternative systems;

(b) for major developments, an engineer’s report will be

submitted that shows the considerations taken with regard to the

alternative systems feasibility.

Such analysis of alternative systems may be carried out for

individual buildings or for groups of similar buildings or for common

typologies of buildings in the same area. As far as collective heating

and cooling systems are concerned, the analysis may be carried out

for all buildings connected to the system in the same area.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) When buildings undergo major renovation, in order

to ensure that the renovated part thereof is upgraded to meet the

minimum energy performance requirements in force at the time, the

owner has to provide to the Building Regulation Office a compliance

certificate drawn up by a warranted architect (perit) or engineer or

both, as the case may be, certifying such compliance, within one

month of completion of works and before the use of the building.

(2) Such requirements shall be applied to the renovated

building or building unit as a whole. Additionally or alternatively,

requirements may be applied to the renovated building elements.

(3) When a building element that forms part of the building

envelope which is -

(a)

greater than 10% of the whole building envelope

area in case of opaque elements; or

(b) greater than 5% of the whole building envelope area

in case of glazed elements,

and is retro-fitted or replaced, in order to ensure that it meets the

minimum energy performance requirements, the owner has to provide

to the Building Regulation Office a compliance certificate by a

warranted architect (perit) certifying such compliance within one

month of completion of works and before the use of the building.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) For the purpose of optimising the energy use of Technical

technical building systems, establish system requirements in respect building

systems.

of the overall energy performance, the proper installation, and the

appropriate dimensioning, adjustment and control of the technical

building systems which are installed in buildings, the system designer

is required to follow Technical Document F (Part 2) as updated and

approved from time to time by the Building Regulation Board.

(2) System requirements are established for new, replacement

and upgrading of technical building systems and shall be applied in so

far as they are technically, economically and functionally feasible, in

accordance with Technical Document F (Part 2).

(3) The system requirements shall cover at least the following

(a)

heating systems;

(b)

hot water systems;

(c)

air-conditioning systems;

(d)

large ventilation systems; or

(e)

a combination of such systems.

(4) Where the guidance contained in any technical document

issued in connection with these regulations relates only to the

particular requirements of these regulations, any construction works

and the installation of any permanent mechanical or electrical

services shall also comply with the requirements of any other laws

and regulations that are operative for the control of construction

works and installations.

(5) When new building services, in accordance with sub-

regulation (3), are installed in buildings, the owner has to provide the

Building Regulation Office with a certificate, issued by a warranted

engineer, declaring compliance with the applicable minimum energy

performance requirements as set in Technical Document F (Part 2).

(6) The Minister shall encourage the introduction of intelligent

metering systems whenever a building is constructed or undergoes

major renovation, whilst ensuring that this encouragement conforms

with paragraph 2 of the Second Schedule to the Electricity Market

Regulations, regarding measures on client protection.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Board shall establish a

system to monitor and enforce that

(a) by 31st December 2020 all new buildings are nearly

zero-energy buildings; and

(b) new buildings occupied and owned by public

authorities are nearly zero-energy buildings by 31st December

2018. (2) The Building Regulation Board, in collaboration, co-

ordination with, and the participation of, the Building Regulation

Office, shall draw up national plans for the purpose of increasing the

number of nearly zero-energy buildings. The national plans may

include targets differentiated according to the category of building.

(3) The Board shall also develop policies and take measures

such as the setting of targets in order to stimulate the transformation

of buildings that are refurbished into nearly zero-energy buildings,

and shall draw up reports including such measures and inform the

Building Regulation Office and the Commission about such reports.

Upon notification of the reports, the Building Regulation Office shall

include the mentioned targets in the national plans as set out in

regulation 24(2) of the Energy Efficiency and Cogeneration

Regulations and inform the Commission about such targets.

(4) The national plans shall include, inter alia, the following

elements

(a) the detailed application, in accordance with the

definition thereof, of nearly zero-energy buildings, reflecting

the national conditions, and including a numerical indicator of

primary energy use expressed in kWh/m 2 per year. Primary

energy factors used for the determination of the primary energy

use may be based on national yearly average values and may

take into account relevant European standards;

(b) intermediate targets for improving the energy

performance of new buildings, with a view to preparing the

implementation of sub-regulation (2);

(c)

information on the policies and financial or other

measures adopted in the context of sub-regulations (2) and (3)

for the promotion of nearly zero-energy buildings, including

details of national requirements and measures concerning the

use of energy from renewable sources in new buildings and

existing buildings undergoing major renovation in the context of

regulations 7, 8, 10, 11 and 17(5) of the Promotion of Energy S.L. 545.11.

from Renewable Sources Regulations.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) In view of the importance of providing appropriate Financial

financing and other instruments to catalyse the energy performance of incentives

market barriers.

buildings and the transition to nearly zero-energy buildings, the

Building Regulation Office shall take all appropriate steps to consider

the most relevant instruments in the light of national circumstances.

(2) The Building Regulation Office shall draw up a list of

existing and, if appropriate, proposed measures and instruments,

including those of a financial nature, other than those required by

these regulations, which promote the objectives of these regulations.

The Building Regulation Office shall update this list every three years

and communicate these lists to the EU Commission which may be

included in the Energy Efficiency Action Plans referred to in

Directive 2006/32/EC.

(3) The Building Regulation Office shall also take into

account the cost-optimal levels of energy performance when

providing incentives for the construction or major renovation of

buildings for such consumers who want to make the best use of

energy resources.

(4) The provisions of these regulations shall not prevent the

Building Regulation Office from providing incentives for new

buildings, renovations or building elements which go beyond the

cost-optimal levels.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Office shall provide all

necessary measures to establish and maintain a system of registration

of the EPC. The EPC shall include the EPB and reference values such

as minimum energy performance requirements, in order to make it

possible for owners or tenants of the building or building unit to

compare and assess its energy performance.

(2) The EPC may include additional information such as the

annual energy consumption for buildings and the percentage of

energy from renewable sources in the total energy consumption.

(3) The EPC shall include recommendations for the cost-

optimal or cost-effective improvement of the EPB or building unit,

unless there is no reasonable potential for such improvement

compared to the energy performance requirements in force. The

recommendations included in the EPC shall cover

(a)

measures to be carried out in connection with a

major renovation of the building envelope or technical building

system(s); and

(b) measures for individual building elements

independent of a major renovation of the building envelope or

technical building system(s).

(4) The recommendations included in the EPC shall be

technically feasible for the specific building and may provide an

estimate for the range of payback periods or cost-benefits over its

economic lifecycle.

(5) The EPC shall provide an indication as to where the owner

or tenant can receive more detailed information, including as regards

the cost-effectiveness of the recommendations made in the EPC. The

evaluation of cost effectiveness shall be based on a set of standard

conditions, such as the assessment of energy savings and underlying

energy prices and a preliminary cost forecast.

(6) In addition, the EPC shall contain information on the steps

to be taken to implement the recommendations. Other information,

such as energy audits or incentives of a financial or other nature and

financing possibilities, may also be provided to the owner or tenant.

(7) Certification for building units shall be based

(a)

on the assessment of an individual building unit

when it deals with residential buildings;

(b) for all other non-residential uses, delineation shall

be based on use factor or ownership.

(8) Certification for single-family houses may be based on the

assessment of another representative building of similar design and

size with a similar and actual energy performance quality if such

correspondence can be guaranteed by the expert issuing the EPC.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Office shall ensure that an Issue of energy

performance

EPC is issued for

certificates

(EPCs).

(a) buildings or building units which are constructed,

sold or rented out to a new tenant; and

(b) buildings where a total useful floor area over 250m 2

is occupied by a public authority and frequently visited by the

public.

(2) The requirement to issue an EPC does not apply where a

certificate, issued in accordance with these regulations, for the

building or building unit concerned, is available and valid.

(3) The owner of a building shall ensure that when buildings

or building units are constructed, sold or rented out, the EPC or a

copy thereof is shown to the prospective new tenant or buyer and

handed over to the buyer or new tenant, at the latest, before the date

of entering the promise of sale or rent agreement. As a derogation

from this same sub-regulation (3), if the new owner intends to make a

major renovation or demolish the building, the owner may request an

exemption to issue an EPC subject to the new owner making a

declaration to the Building Regulation Office that at no time will the

existing building be used until such renovation or new construction

would have taken place. A new EPC will be required in accordance

with such renovation or new built.

(4) Where a building is sold or rented out prior to

construction, the seller shall provide a design rating EPC for the

building, and which in such case shall be handed over to the buyer or

tenant, at the latest, before the date of entering the promise of sale,

deed or rent agreement. A copy of the design rating EPC shall also be

attached to the promise of sale/deed. If alterations which change the

energy performance characteristics of the building have been made

during construction, a new EPC has to be provided to the buyer or

tenant. These alterations can only be effected by mutual agreement

between the parties and have to be recorded by a notarial deed.

(5) The owner or his agent shall ensure that where buildings,

building units and building units in a building having an EPC are

offered for sale or for rent, the energy performance indicator of the

EPC of the building or the building unit, as the case may be, is stated

in the advertisements in commercial media in compliance with the

Advertising Requirements Guidelines published by the Building

Regulation Office and updated from time to time.

(6) The provisions of this regulation shall be implemented in

accordance with applicable national rules on joint ownership or

common property.

(7) The categories of buildings referred to in regulation 5(5)

shall be excluded from the application of sub-regulations (1), (3), (5)

and (6).

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) An owner or his agent shall obtain an EPC in the

form prescribed by these regulations when a building is constructed,

sold or rented.

(2) To be valid, the EPC shall be obtained from an

independent EPB assessor after it is registered with the Building

Regulation Office.

(3) As from the date indicated in this sub-regulation, a person

or agent acting on behalf of the owner who commissions the design of

a new building shall have in his possession an EPC based on the

design rating of the building and in the form prescribed by these

regulations just prior to obtaining a full development permit from the

Planning Authority

(a)

in relation to dwellings whose development permit

application was submitted after 2nd January 2009; and

(b) in relation to all other buildings whose development

permit application was submitted after 1st June 2009.

(4) As from the date indicated in this sub-regulation, a person

or agent acting on behalf of the owner who offers a building for sale

or letting, shall provide an EPC to the prospective buyer or tenant

prior to the promise of sale or at the time of signing of the rent

agreement. The EPC shall be in the form prescribed in these

regulations and shall be based on the design rating of the building if

the building is not yet constructed and finished, or on the asset rating,

if the building is already constructed and finished

(a)

as from 2nd January 2009, in relation to dwellings; and

(b) as from 1st June 2009, in relation to all other buildings.

(5) In the event that the person or agent indicated in sub-

regulation (4) does not provide the prospective buyer or the tenant

with an EPC within the period indicated in sub-regulation (4), the

buyer or the tenant shall have the right to engage an assessor to issue

the necessary certificate and, in all cases, the prospective buyer or

tenant shall have the right to deduct the expenses incurred for the

issue of the EPC from the amount of the sum agreed for the sale or the

payments of the rent due.

(6) Notwithstanding the provisions of sub-regulations (1), (2),

(3) and (4), the procurement of an EPC shall not apply to the

following categories of buildings

(a)

buildings classified as scheduled property (Grade 1

or 2) by the Planning Authority under article 57 of the

Development Planning Act and buildings officially protected as Cap. 552.

part of a designated environment or because of their special

architectural or historical or contextual merit, in so far as

compliance with certain minimum energy performance

requirements would unacceptably alter their character or

appearance;

(b)

buildings used as places of worship;

(c)

temporary buildings with a time of use of two years

or less, industrial sites, workshops and non-residential

agricultural buildings with low energy demand, and non-

residential agricultural buildings which are in use by a sector

covered by a national sectoral agreement on energy

performance;

(d) stand-alone buildings with a total useful floor area

of less than 50m 2 ;

(e)

a building constructed for the Enemalta plc, the

Water Services Corporation or any other similar entity, and used

as a generation, transmission or distribution station.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) An EPC issued in terms of these regulations shall be Provisions

valid for a period of ten years from the date of its first issue, provided relating

EPC.

that no major renovation or alteration occur in the building.

(2) The EPC shall include reference values and shall be

accompanied by a recommendation report. The recommendation

report shall indicate cost-effective measures for improving the EPB.

(3) Any report or data file in connection with the production of

an EPC shall conform to national data protection laws in force.

(4) If after the construction of the building or the installation

of mechanical and electrical services in new buildings it results that

such construction or installation of services is different from the

design on which a design rating EPC has been obtained, a new EPC

based on the asset rating of the building shall have to be secured by

the owner before the expiry of the periods indicated in regulation

14(4) or before the building is used. The provisions of regulation

14(5) shall also apply.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) Where a total useful floor area over 500m 2 of a

building for which an EPC has been issued in accordance with

regulation 13(1)(b) is occupied by public authorities and frequently

visited by the public, the EPC shall be displayed in a prominent place

clearly visible to the public. In such a case the threshold shall be

lowered to 250m 2 by 9 July, 2015.

(2) Where a total useful floor area over 250m 2 of a building,

for which an EPC has been issued in accordance with regulation

13(1)(b), is frequently visited by the public, the EPC shall also be

displayed in a prominent place clearly visible to the public.

(3) Public authorities are encouraged to take into account the

leading role which they should exercise in the field of EPB, inter alia,

by implementing the recommendations included in the EPC issued for

buildings occupied by them within its validity period.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Office shall provide all

necessary measures to establish and maintain a system for the

registration of reports in connection with the regular inspection of the

accessible parts of systems used for heating buildings, such as the

heat generator, control system and circulation pump(s), with boilers

of an effective rated output for space heating purposes of more than

20kW.

(2) Such inspection shall include an assessment of the boiler

efficiency and the boiler sizing compared with the heating

requirements of the building. The assessment of the boiler sizing does

not have to be repeated as long as no changes were made to the

heating system or as regards the heating requirements of the building

in the meantime.

(3) The Building Regulation Office shall set different

inspection frequencies depending on the type and effective rated

output of the heating system whilst taking into account the costs of

the inspection of the heating system and the estimated energy cost

savings that may result from the inspection. The Building Regulation

Office may also decrease or increase the frequency of such

inspections as appropriate, where an electronic monitoring and

control system is in place.

(4) The Building Regulation Office shall publish, and amend

from time to time, the Guide for Owners of Heating and Air-

Conditioning Systems in Malta hereinafter referred to as "the Guide",

as notified in the Gazette. The Guide shall establish which heating

systems are to be inspected according to the requirements of sub-

regulation (1) and the inspection frequencies of such systems

according to the requirements of sub-regulation (3).

(5) The owner of a heating system shall obtain an inspection

report by commissioning an independent heating systems inspector,

from the list of registered heating systems inspectors as published and

updated by the Building Regulation Office at the time of inspection.

(6) The Building Regulation Office shall establish the

methodology for the inspection of heating systems. The Building

Regulation Office shall also set up and approve training courses for

heating systems inspectors.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Office shall provide all Inspection of

necessary measures to establish and maintain a system for the air-conditioning

systems.

registration of reports in connection with the regular inspection of the

accessible parts of air-conditioning systems of an effective rated

output of more than 12kW.

(2) Such inspection shall include an assessment of the air-

conditioning efficiency and the sizing compared to the cooling

requirements of the building. The assessment of the sizing shall not

be repeated as long as no changes were made to this air-conditioning

system or as regards the cooling requirements of the building in the

meantime.

(3) In providing measures referred to in sub-regulations (1)

and (2), the Building Regulation Office shall, in so far as this is

economically and technically feasible, ensure that inspections are

carried out in accordance with the inspection of heating systems and

other technical systems referred to in regulation 17 and the inspection

of leakages referred to in Regulation (EC) No 842/2006 of the

European Parliament and of the Council on certain fluorinated

greenhouse gases.

(4) The Building Regulation Office shall set different

inspection frequencies depending on the type and effective rated

output of the air-conditioning system whilst taking into account the

costs of the inspection of the air-conditioning system and the

estimated energy cost savings that may result from the inspection.

The Building Regulation Office may also decrease or increase the

frequency of such inspections as appropriate, where an electronic

monitoring and control system is in place.

(5) The Building Regulation Office shall publish, and amend

from time to time, the Guide for Owners of Heating and Air-

Conditioning Systems in Malta, in accordance with regulation 17(4).

The Guide shall establish which air-conditioning systems are to be

inspected according to the requirements of sub-regulation (1) and the

inspection frequencies of such systems according to the requirements

of sub-regulation (4).

(6) The owner of an air-conditioning system shall obtain an

inspection report by commissioning an independent air-conditioning

systems inspector, from the list of registered air-conditioning system

inspectors as published and updated by the Building Regulation

Office at the time of inspection.

(7) The Building Regulation Office shall establish the

methodology for the inspection of air-conditioning systems. The

Building Regulation Office shall also set-up and approve training

courses for air-conditioning systems inspectors.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) Inspectors of heating or air-conditioning systems

shall issue an inspection report after each inspection of a heating or

air-conditioning system. The inspection report shall contain the result

of the inspection performed in accordance with regulations 17 and 18

and shall include recommendations for the cost-effective

improvement of the energy performance of the inspected system.

(2) The recommendations may be based on a comparison of

the energy performance of the system inspected with that of the best

available feasible system and a similar system for which all relevant

components achieve the level of energy performance required by

these regulations.

(3) Inspectors of heating or air-conditioning systems shall

register each inspection report with the Building Regulation Office

prior to handing over this inspection report to the owner of the

heating or air-conditioning system. Inspection reports will not be

considered valid unless this procedure is adhered to.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Office may demand, from

the owner of a building in terms of these regulations, or the agent of

such owner, the production of an EPC in respect of the building or an

inspection report with respect to the heating and, or air-conditioning

systems as required by these regulations, and if the building owner or

the agent of such owner, as the case may be, refuses or fails to

produce without reasonable cause the EPC or inspection report, such

person shall be guilty of an offence, unless such person provides the

requested EPC or inspection report within sixty days after the request

was made.

(2) Where a person produces an EPC or inspection report to an

authorised officer but refuses or fails to permit the said officer to read

and examine the EPC or the inspection report, such person or other

persons involved in such a case shall be guilty of an offence, and the

authorised officer may demand of the person or persons their name

and identification card number and official address.

21.(1) (a) The EPA and certification shall be carried out using Energy

procedures, including calculation methods and software approved by performance

assessment

the Building Regulation Office, as notified in the Gazette.

(EPA) and

certification

(EPC) /

(b) The inspection procedure and inspection report for Inspection

procedure and

heating or air-conditioning systems shall be carried out using inspection

procedures, approved by the Building Regulation Office, as notified report

heating or air-

in the Gazette.

conditioning

systems.

(2) (a) In carrying out the EPA of a building or installation,

an assessor shall comply with any direction given by the Building

Regulation Office in relation to the manner in which the assessment is

to be carried out.

(b) In carrying out the inspection of a heating or air-

conditioning system, an inspector shall comply with any direction

given by the Building Regulation Office in relation to the manner in

which this procedure is to be carried out.

(3) (a)

An EPB assessor may refuse to carry out an EPA of

a building or installation if in the opinion of the assessor any part of

the building or installation is in such a condition that it would not be

safe or practicable to carry out that assessment.

(b) An inspector of heating or air-conditioning systems

may refuse to carry out an inspection procedure if in the opinion of

the inspector any part of the building or installation is in such a

condition that it would not be safe or practicable to carry out that

inspection.

(4) (a)

An endorsed EPC shall not be issued by the assessor

to the building owner or his agent, as the case may be, unless and

until it is accepted in the register maintained by the Building

Regulation Office.

(b) Inspection reports of heating or air-conditioning

systems shall be handled in accordance with regulation 19(3).

22.(1) (a) The Building Regulation Office may revoke an EPC

and EPC data file compiled by an EPB assessor where it has

reasonable grounds for believing that the EPC or data file was not

completed or issued in accordance with these regulations, and shall

enter such revocation in the EPC record of that building and the

register maintained by the Building Regulation Office.

(b) Where an EPC or EPC data file is revoked, the

Building Regulation Office shall inform the EPB assessor, giving

reasons for the revocation, and shall also inform the person who

commissioned the EPC, the owner or tenant of the building, as the

case may be.

(c)

Where an EPC or EPC data file is revoked under this

sub-regulation

(i) a request for the reimbursement of the

administrative fee or part thereof may be made by the

person who paid an administrative fee or contributed in the

administrative fee for the relevant EPB assessment to the

EPB assessor who carried out the assessment; and

(ii) the EPB assessor shall be obliged to make the

reimbursement in whole or in part, as the case may be,

referred to in sub-paragraph (i), within twenty-eight days

of the receipt of the request, if such assessor is satisfied

that the fee or a contribution to the fee was paid by the

person making the request.

(2) (a)

The Building Regulation Office may revoke an

inspection report either during the registration procedure or during

the verification process in accordance with regulation 32. The

Building Regulation Office shall inform the respective heating or air-

conditioning systems inspector about this revocation.

(b) The inspection report will be reinstated only once

the requested corrections are carried out to the satisfaction of the

Building Regulation Office. All expenses related to these corrections

shall be borne by the respective heating or air-conditioning systems

inspector.

(c)

The requested corrections shall reach the Building

Regulation Office within fourteen days. After this period the

inspector shall be removed from the list of registered inspectors until

full compliance with this sub-regulation is achieved.

23.(1) (a) After an EPC has been registered with the Building Alteration,

Regulation Office and signed by the assessor, no person shall, either cancellation

addition to an

in writing, drawing or in any other manner alter, cancel, or add EPC

advisory report /

anything to the EPC or to any related report or to a printed copy of an Alteration

cancellation or

EPC or to any related report or entry made therein.

addition to an

inspection

report for

(b)

No person shall produce

heating or air-

conditioning

systems.

(i) a printed copy of any EPC and related

advisory report for any building or installation, which copy

has been altered or added contrary to paragraph (a), or

upon which the figures have become illegible or the colour

has become altered by fading or otherwise; or

(ii) an EPC and related advisory report save for

those provided in relation to the particular building for

which it was issued; or

(iii) an EPC and related advisory report which has

become void or the validity of which has expired; or

(iv) any imitation of a registered EPC and related

advisory report.

(c)

The Building Regulation Office may require the

owner of a building or, as the case may be, through his agent, to

surrender to it an EPC or report where the Building Regulation Office

has reason to believe that the EPC or report contains particulars

which are not correct and, upon being so required, the owner of the

building or, as the case may be, the owner’s agent, shall surrender the

relevant documents to the Building Regulation Office.

(2) (a)

After an inspection report for heating or air-

conditioning systems has been registered with the Building

Regulation Office and signed by the respective registered inspector,

no person shall

(i) either by writing, drawing or in any other

manner alter, cancel, or add anything to this inspection

report; or

(ii) produce and present copies of an inspection

report which was altered contrary to sub-paragraph (i).

(b) Inspection reports which are registered with the

Building Regulation Office may be replaced by an amended

inspection report, by the same heating or air-conditioning systems

inspector, within fourteen days after initial registration. Such

amended inspection report shall be submitted subject to prior

approval of the Building Regulation Office.

24.(1) (a) All data, documentation and records issued by an

EPB assessor and submitted to the Building Regulation Office, in

relation with the carrying out of an EPC under these regulations, shall

become the property of the Building Regulation Office, which has the

power to demand from the assessor any such data, documentation or

records as it considers appropriate.

(b) Every inspection report issued by an inspector of

heating or air-conditioning systems and submitted to the Building

Regulation Office, in relation to an inspection of heating or air-

conditioning systems under these regulations, shall become the

property of the Building Regulation Office, which has the power to

demand from the inspector of heating or air-conditioning systems any

additional data, documentation or records in relation to such

inspection report as it considers appropriate.

(2) The lawful EPC record in relation to a building and the

lawful inspection report in relation to an inspection of a heating or

air-conditioning system shall be that maintained on the respective

registers kept by the Building Regulation Office.

(3) (a)

The most recent EPC record entered in relation to a

building on the EPC register by the Building Regulation Office shall

be deemed to supersede any previous EPC record for that building.

(b) The most recent inspection report in relation to an

inspection of a heating or air-conditioning system entered on the

inspections’ register by the Building Regulation Office shall be

deemed to supersede any previous inspection reports for that system.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) Subject to the provisions of sub-regulations (3) and

(4), the Building Regulation Office is the only institution legally

empowered to register EPB assessors to assess the energy

performance of buildings, and as published from time to time in the

Gazette by the Building Regulation Office.

(2) In registering an EPB assessor, the Building Regulation

Office shall designate the type of energy performance certification

and also the category of buildings in respect of which the EPB

assessor is authorised to carry EPAs and certifications.

(3) The Building Regulation Office shall not consider a person

for registration as an EPB assessor unless

(a)

the person makes an application for registration to

the Building Regulation Office in the form specified by it for

such purpose;

(b) the application for registration is accompanied by

such fee as may be specified by the Building Regulation Office;

and

(c)

the person meets any other requirements specified

by the Building Regulation Office.

(4) In considering an application for registration as an EPB

assessor, the Building Regulation Office shall be satisfied that the

applicant meets the requirements as defined in the definition of EPB

assessor in these regulations.

(5) An EPB assessor who is registered by the Building

Regulation Office in respect of one type of certification or one

category of building may apply to the Building Regulation Office to

be registered in respect of another type or category of buildings, and

may be so registered, subject to compliance with the provisions set

out in sub-regulations (3) and (4) and the payment of such fee as may

be specified by the Building Regulation Office.

(6) An EPB assessor shall be required to renew his registration

at such reasonable frequency as may be determined by the Building

Regulation Office, subject to the payment of such registration

renewal fee as may be specified by the Building Regulation Board.

(7) The Building Regulation Office shall provide each EPB

assessor with a certificate of registration for the designated type and

category of buildings to which his registration pertains, and the

certificate, if requested by the owner of a building or the owner’s

agent, or authorised officer, shall be presented for inspection to the

person making such request.

(8) Where the Building Regulation Office suspends or

terminates the registration of a person as an EPB assessor, it shall

register the suspension or termination of the appointment and the date

on which the registration was suspended or revoked.

(9) The Building Regulation Office may, having regard to all

the circumstances of the case, suspend or terminate the registration of

an EPB assessor following

(a)

failure by the EPB assessor to attend a course of

periodic training if required by the Building Regulation Office

or to satisfactorily complete such a training course; or

(b) failure by an EPB assessor to comply with a

direction under these regulations; or

(c)

failure by an EPB assessor to carry out a building

EPA for EPC purposes in a fit and proper manner, or failure to

maintain or provide satisfactory data, documentation or records

of any such assessment; or

(d) the committing, or aiding or abetting the

committing, by the EPB assessor, of an offence under these

regulations; or

(e)

the forming of an opinion by the Building

Regulation Office that the EPB assessor has ceased to be

capable of performing his functions properly and efficiently

under these regulations.

(10) A suspension or termination of registration under sub-

regulation (9) shall be notified to the person concerned in writing

including reasons for the suspension or termination and the Building

Regulation Office shall inform the person of the appeal procedure

under sub-regulation (11).

(11) A person whose registration has been suspended or

terminated under sub-regulation (10) may, within fourteen days from

the said suspension or termination, appeal to the Building Regulation

Board or the Committee of Appeal against the decision regarding the

suspension or termination taken by the Building Regulation Office, as

established under the Act, in terms of the provisions relating to appeal

under articles 12 and 13 of the said Act, or the Court of Appeal, as the

case may be.

(12) A person whose registration as an EPB assessor has lapsed

or been suspended or terminated may be directed by the Building

Regulation Office to destroy any data or documentation provided by

building owners or their agents, and any copies thereof, in relation to

EPB assessments carried out by him in his capacity as an EPB

assessor. Alternatively, the Building Regulation Office may withdraw

such data or documentation.

(13) A person who purports to be a registered EPB assessor for

a designated category of buildings, or a registered inspector for air-

conditioning or heating systems or an authorised officer under these

regulations shall be guilty of an offence in terms of these regulations.

(14) A person who, purporting to give information to an EPB

assessor or inspector, to the Building Regulation Office, or to an

authorised officer for the performance of his functions under these

regulations, makes a statement that he knows to be false or

misleading in a material particular, or fails to disclose a material

particular shall be guilty of an offence in terms of these regulations.

(15) An EPB assessor who issues an EPC or a registered

inspector who makes a statement or report, which he knows to be

false or misleading in a material particular, shall be guilty of an

offence in terms of these regulations.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) Subject to the provisions of sub-regulation (3), the Registration of

Building Regulation Office is the only institution legally empowered inspectors

heating or air-

to register inspectors of heating or air-conditioning systems in conditioning

systems.

accordance with these regulations and as published from time to time

in the Gazette by the Building Regulation Office.

(2) In registering an inspector of heating or air-conditioning

systems, the Building Regulation Office shall designate the type of

system in respect of which the inspector is authorised to carry out

inspections and issue inspection reports.

(3) The Building Regulation Office shall not consider a person

for registration as an inspector of heating or air-conditioning systems

unless

(a) the person makes an application for registration to

the Building Regulation Office in the form and during the

period specified by it for such purpose;

(b) the application for registration is accompanied by

such fee as may be specified by the Building Regulation Office;

(c)

the person has the necessary qualifications to apply

for and successfully complete a training course provided by the

Building Regulation Office, or a training provider recognised by

the Building Regulation Office as suitable for providing such

training, on the inspection of heating or air-conditioning

systems installed in Malta;

(d) the person meets any other requirements specified

by the Building Regulation Office.

(4) An inspector of heating or air-conditioning systems may be

required to renew his registration at such reasonable frequency

subject to the payment of such registration renewal fee as may be

specified by the Building Regulation Board.

(5) The Building Regulation Office shall provide an inspector

of heating or air-conditioning systems with a certificate of

registration for the designated type of system to which his registration

pertains. This certificate of registration shall also include a unique

registration number of the inspector, date of registration and the

validity period of such registration.

(6) The Building Regulation Office may, having regard to all

the circumstances of the case, suspend or terminate the registration of

an inspector of heating or air-conditioning systems following

(a) failure by such inspector to comply with a direction

under this regulation and regulation 22(2); or

(b) failure by such inspector to attend a course of

periodic training if required by the Building Regulation Office

or to satisfactorily complete such a training course; or

(c)

failure by such inspector to carry out an inspection

in a fit and proper manner, or failure to maintain or provide

satisfactory data, documentation or records of any such

inspection; or

(d) the committing, or aiding or abetting the

committing, by such inspector, of an offence under these

regulations; or

(e)

the forming of an opinion by the Building

Regulation Office that such inspector has ceased to be capable

of performing his functions properly and efficiently under these

regulations.

(7) A person shall be guilty of an offence in terms of these

regulations if such person

(a) claims falsely to be an inspector of heating or air-

conditioning systems, or an authorised officer under these

regulations; or

(b) makes a statement that he knows to be false or

misleading in a material particular or fails to disclose a material

particular, when giving information to an inspector of heating or

air-conditioning systems, to the Building Regulation Office or

to an authorised officer for the performance of his functions

under these regulations; or

(c)

issues an inspection report for heating or air-

conditioning systems which he knows to be false or misleading

in a material particular.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Office shall, from time to Directions

time, issue directions to EPB assessors or inspectors of heating or air- issued

Building

conditioning systems, present or prospective, in relation to

Regulation

Office.

(a)

the manner in which the EPB assessments or

inspection procedures of heating or air-conditioning systems are

to be carried out;

(b) the manner in which an EPC and related advisory

reports are to be issued;

(c)

the manner in which inspection reports for heating

or air-conditioning systems are to be issued;

(d) the qualifications and training requirements to

maintain or achieve such roles;

(e)

the records, data bases and documentation to be

maintained;

(f)

codes of practice to be respected; and

(g) such other matters as are reasonably necessary for

the proper administration of these regulations.

(2) EPB assessors and inspectors of heating or air-

conditioning systems shall comply with any relevant direction given

under sub-regulation (1).

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

The Building Regulation Office may specify fees as are Registration and

reasonably necessary for the registration procedures and other other

administrative

administrative matters in relation to its obligations in these fees.

regulations. The Building Regulation Office shall be the sole user of

the revenue collected from these fees and such revenue shall be used

to defray costs incurred by it to properly establish, operate, maintain

and promote the various obligations of the Building Regulation

Office.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Office shall establish, Registers held

by the Building

operate and maintain

Regulation

Office.

(a)

a register of EPB assessors, an EPC register

comprising EPCs and related advisory reports, EPC data files

and related data or documents; and

(b) a register for inspectors of heating or air-

conditioning systems, a register of inspection reports for heating

or air-conditioning systems; and

(c)

any other register that the Building Regulation

Office considers relevant and necessary.

(2) Any register established under sub-regulation (1) may be

held in non-legible form provided it is capable of being reproduced in

legible form.

(3) Each register established under sub-regulation (1) shall be

a public record and shall be kept under the management of the

Building Regulation Office.

(4) In relation to the registers established under sub-regulation

(1), the following access rights shall apply

(a)

extracts from the register of the EPB assessors and

the register of inspectors of heating or air-conditioning systems,

comprising the name, contact details and the designated type,

shall be made available to the public;

(b) subject to compliance with the provisions of the

Data Protection Act, the Building Regulation Office may allow

publication or access, on a restricted or an open basis, to any

extract from any register maintained by the Building Regulation

Office under these regulations where the Building Regulation

Office is satisfied that such publication or access is in the public

interest;

(c)

other than as provided for in paragraphs (a) and (b),

a data file or other extract from a register relating to an EPC for

a particular building or an inspection report for a particular

heating or air-conditioning system, shall only be made available

to

(i) the relevant EPB assessor or the relevant

inspector of heating or air-conditioning systems; or

(ii) an EPB assessor having been appointed by

the building owner or the agent of the building owner to

undertake any subsequent EPB assessment of the relevant

building; or

(iii) the relevant building owner, or the agent of

that building owner.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) In any proceedings a certificate signed by an

authorised officer of the Building Regulation Office containing only

information stated in that certificate to be taken from a register

maintained by the Building Regulation Office shall be sufficient

evidence of the facts stated therein unless there is proof to the

contrary.

(2) In any proceedings a document purporting to be a

certificate under sub-regulation (1) shall be deemed to be a certificate

for all legal intents and purposes, and to have been signed by an

authorised officer of the Building Regulation Office, unless there is

proof to the contrary.

(3) A certificate under sub-regulations (1) and (2) that

purports to bear a facsimile signature of the authorised officer of the

Building Regulation Office or a copy of such signature applied by

means of a stamp or produced by a computer, shall be deemed to have

been signed by an authorised officer, unless there is proof to the

contrary.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Office shall ensure that the Independent

energy performance certification of buildings and the inspection of experts.

heating and air-conditioning systems be carried out in an independent

manner by a qualified duly registered EPB or registered inspector of

heating or air-conditioning systems.

(2) The Building Regulation Office shall make available to the

public information on training and accreditations. It shall ensure that

regularly updated lists of qualified and, or accredited experts are

made available to the public.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Office shall ensure that Independent

independent control systems for EPCs and reports on the inspection control system.

of heating or air-conditioning systems are established in accordance

with Schedule II. The Building Regulation Office may establish

separate systems for the control of EPCs and for the control of reports

on the inspection of heating and air-conditioning systems.

(2) The Building Regulation Office may delegate the

responsibilities for implementing the independent control systems.

Where the Building Regulation Office decides to do so, it shall ensure

that the independent control systems are implemented in compliance

with Schedule II.

(3) The Building Regulation Office shall ensure that the EPCs

and the inspection reports referred to in sub-regulation (1) are made

available to the competent authorities or bodies on request.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) Owners or tenants of buildings or building units Information.

shall be informed of the different methods and practices that serve to

enhance energy performance as stipulated in these regulations.

(2) The EPC assessor and the registered inspectors,

respectively, shall in particular provide information to the owners or

tenants of buildings on EPCs and inspection reports, their purpose

and objectives, on cost-effective ways to improve the EPB and, where

appropriate, on financial instruments available to improve the EPB.

(3) The Building Regulation Office shall ensure that guidance

and training are made available for those responsible for

implementing these regulations. Such guidance and training shall

address the importance of improving energy performance, and shall

enable consideration of the optimal combination of improvements in

energy efficiency, use of energy from renewable sources and use of

district heating and cooling when planning, designing, building and

renovating industrial or residential areas.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

In order to facilitate the effective implementation of these

regulations, the Building Regulation Board shall consult the

stakeholders involved, including local authorities, in accordance with

the relevant applicable national legislation. Such consultation is of

particular importance for the application of regulations 10 and 33.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

Any person who contravenes any of the requirements of

these regulations shall be guilty of an offence in terms of these

regulations.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Building Regulation Office may appoint

persons to be authorised officers for the purpose of enforcing these

regulations.

(2) An authorised officer shall be in possession of a warrant of

appointment and shall, upon request, produce the warrant of

appointment.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) An officer authorised by the Building Regulation

Office may enter, inspect and examine a building or any part of a

building or installation for the purpose of ensuring compliance to

these regulations.

(2) Such authorised officer may carry out such inspections and

examinations in relation to the building and installations, as are

reasonably necessary for the purpose of ensuring compliance to these

regulations.

(3) A person who -

(a)

fails to permit an inspection of a building, or

installation, under these regulations;

(b) without reasonable cause fails or refuses to comply

with any request or requirement made by an authorised officer

under these regulations;

(c)

obstructs, impedes, interferes with or assaults an

authorised officer in the exercise of a power under these

regulations;

(d) gives to an authorised officer information which is

false or misleading in a material respect; or

(e)

alters, suppresses, or destroys any EPC data file,

related calculation, EPC, advisory report, book, document or

record, including a printed copy thereof, and including

electronic data, which the person concerned has been requested

or required to produce, or may reasonably expect to be required

to produce,

shall be guilty of an offence in terms of these regulations.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) Criminal proceedings for an offence under these Criminal

regulations shall be heard either before the Court of Magistrates proceedings.

(Malta) or the Court of Magistrates (Gozo), both as a Court of

Criminal Judicature, and shall be in accordance with the provisions of

the Criminal Code regulating such procedure.

(2) Where any person, whether voluntarily or negligently, acts

or purports to act as a director, manager, secretary or other officer or

member of a body, whether corporate or unincorporate, and in so

doing contravenes any provision of these regulations, such person

shall be guilty of an offence, and shall, on conviction, be liable to the

penalties in terms of regulations 39 and 40.

(3) Notwithstanding the provisions of the Criminal Code, the Cap. 9.

Attorney General shall always have the right to appeal before the

Court of Criminal Appeal from any judgement given by the Court of

Magistrates (Malta) or the Court of Magistrates (Gozo), both as a

Court of Criminal Judicature, in respect of proceedings taken in

relation to any offence committed against these regulations.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

Any administrative penalty or sanction imposed by the Administrative

Building Regulation Office, in accordance with article 22 of the Act, penalties.

upon any person who infringes any provision of these regulations or

who fails to comply with any directive or decision given by the

Building Regulation Office in ensuring compliance with these

regulations shall be due to the Building Regulation Office as a civil

debt constituting an executive title for the purpose of Title VII of Part

I of Book Second of the Code of Organization and Civil Procedure as Cap. 12.

if the payment of the debt had been ordered by a judgement delivered

by the Civil Court.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

A person found guilty of an offence shall, on conviction,

be liable to

(a)

a fine (multa) of not less than five hundred euro

(€500) and not exceeding one thousand and five hundred euro

(€1,500), if contravening regulations 7(1), 8(1), 13(5), 14(1), (3)

and (4), 15(4), 16(1) and (2), 17 and 18 and other corresponding

clauses pertaining to heating and air-conditioning systems;

(b) a fine (multa) of not less than one thousand and five

hundred euro (€1,500) and not exceeding five thousand euro

(€5,000) if contravening regulations 20, 21(1), (2) and (4), 22,

23, 25(12), (13) and (14), 26(7) and other corresponding clauses

pertaining to heating and air-conditioning systems;

(c)

a fine (multa) of not less than one thousand and five

hundred euro (€1,500) and not exceeding five thousand euro

(€5,000), or to a term of imprisonment not exceeding three

months, or to both such fine and imprisonment, if contravening

regulation 37(3).

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) Any documents issued in relation to these

regulations may be issued either in the Maltese language or in the

English language, or in both languages.

(2) Any EPC or report issued in accordance with these

regulations shall be issued solely in the English language.

Malta Government Gazette — Legal Notice 2018 47 · Gazzetta tal-Gvern ta’ Malta Nru. 19,947 – 13.02.2018 — Energy Performance of Buildings Regulations, 2018

(1) The Energy Performance of Buildings Regulations,

2012, hereinafter referred to as "the revoked regulations" are hereby

revoked without prejudice to anything done or omitted to be done

thereunder.

2012. (2) Notwithstanding the provisions of sub-regulation (1), the

revoked regulations shall still apply for all buildings whose planning

permit application was submitted prior to the entry into force of these

regulations, as regards ongoing administrative procedures and

building performance so long as no alterations are made; the

provisions of these regulations shall apply for all buildings whose

planning permit application is submitted after the coming into force

of these regulations.

Schedule I

(Regulation 4)

Common general framework for the calculation of energy

performance of buildings

1. The energy performance of a building shall be determined

on the basis of the calculated or actual annual energy that is

consumed in order to meet the different needs associated with its

typical use and shall reflect the heating energy needs and cooling

energy needs (energy needed to avoid overheating) to maintain the

envisaged temperature conditions of the building, and domestic hot

water needs.

2. The energy performance of a building shall be expressed in

a transparent manner and shall include an energy performance

indicator and a numeric indicator of primary energy use, based on

primary energy factors per energy carrier, which may be based on

national or regional annual weighted averages or a specific value for

on-site production.

The methodology for calculating the energy performance of

buildings should take into account European standards and shall be

consistent with relevant EU legislation, including Directive 2009/28/

EC on the Promotion on the Use of Energy from Renewable Sources.

3. The methodology shall be laid down taking into

consideration at least the following aspects

(a)

the following actual thermal characteristics of the

building including its internal partitions

(i)

thermal capacity;

(ii) insulation;

(iii) passive heating;

(iv) cooling elements; and

(v)

thermal bridges;

(b) heating installation and hot water supply, including

their insulation characteristics;

(c)

air-conditioning installations;

(d) natural and mechanical ventilation which may

include air-tightness;

(e)

built-in lighting installation (mainly in the non-

residential sector);

(f)

the design, positioning and orientation of the

building, including outdoor climate;

(g)

passive solar systems and solar protection;

(h) indoor climatic conditions, including the designed

indoor climate;

(i)

internal loads.

4. The positive influence of the following aspects shall,

where relevant in the calculation, be taken into account

(a) local solar exposure conditions, active solar systems

and other heating and electricity systems based on energy from

renewable sources;

(b)

electricity produced by cogeneration;

(c)

district or block heating and cooling systems;

(d)

natural lighting.

5. For the purpose of the calculation, buildings should be

adequately classified into the following categories

(a)

single-family houses of different types;

(b)

apartment blocks;

(c)

offices;

(d)

educational buildings;

(e)

hospitals;

(f)

hotels and restaurants;

(g)

sports facilities;

(h)

wholesale and retail trade services buildings;

(i)

other types of energy-consuming buildings.

Schedule II

(Regulation 32)

Independent control systems for energy performance certificates and

inspection reports

1. The competent authorities or bodies to which the

competent authorities have delegated the responsibility for

implementing the independent control system shall make a random

selection of at least a statistically significant percentage of all the

energy performance certificates issued annually and subject those

certificates to verification.

The verification shall be based on the options indicated below or

on equivalent measures

(a) validity check of the input data of the building used

to issue the energy performance certificate and the results stated

in the certificate;

(b) check of the input data and verification of the results

of the energy performance certificate, including the

recommendations made;

(c)

full check of the input data of the building used to

issue the energy performance certificate, full verification of the

results stated in the certificate, including the recommendations

made, and on-site visit of the building, if possible, to check

correspondence between specifications given in the energy

performance certificate and the building certified.

2. The competent authorities or bodies to which the

competent authorities have delegated the responsibility for

implementing the independent control system shall make a random

selection of at least a statistically significant percentage of all the

inspection reports issued annually and subject those reports to

verification.

Schedule III

(Regulation 6)

Comparative methodology framework to identify cost-optimal levels

of energy performance requirements for buildings

and building elements

The comparative methodology framework shall enable Member

States to determine the energy performance of buildings and building

elements and the economic aspects of measures relating to the energy

performance, and to link them with a view to identifying the cost-

optimal level.

The comparative methodology framework shall be accompanied

by guidelines outlining how to apply this framework in the

calculation of cost-optimal performance levels. The comparative

methodology framework shall allow for taking into account use

patterns, outdoor climate conditions, investment costs, building

category, maintenance and operating costs (including energy costs

and savings), earnings from energy produced, where applicable, and

disposal costs, where applicable. It should be based on relevant

European standards relating to these regulations.

By calculating the costs of the energy efficiency measures

during the expected economic life-cycle, the cost-effectiveness of

different levels of minimum energy performance requirements is

assessed by the Member States. This will allow the determination of

cost-optimal levels of energy performance requirements.

€3.69

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →