New Roads and Road Works Regulations, 2018
Table of Provisions (53)
Statutory Text (53 Articles)
L.N. 291 of 2018
AUTHORITY FOR TRANSPORT IN MALTA ACT
(CAP. 499)
New Roads and Road Works Regulations, 2018
IN EXERCISE of the powers conferred by article 43 of the
Authority for Transport in Malta Act, the Minister for Infrastructure,
Transport and Communications has, after consultation with the
Authority for Transport in Malta, made the following regulations:-
The title of these regulations is the New Roads and Road
Works Regulations, 2018.
PART I
PRELIMINARY PROVISIONS
(Regulation 31)
The charges payable to the Authority for the grant of a permit shall be
as follows
Permit
Processing Fees
(a) Works, not exceeding 10 metres in length, to be
carried out in local/residential roads ...........................
€150
(b) Works, exceeding 10 metres in length, to be carried in
RWP1
local/residential roads ................................................
€250
Major Road Works
Permit
(c) Works to be carried out in distributor and arterial
roads ..........................................................................
€250
(d) Road construction works .............................................
€500
(a) For each RWP 2 permit issued ....................................
€50
RWP2
(b) For services rendered by the Authority official called
Emergency Road
on site, per hour or part thereof ...................................
€60
Works Permit
(c) Penalty where Authority official is called on false
emergencies ................................................................
€500
(a) Works [excluding those works referred to in
paragraph (b) of the definition of "minor works" in
regulation 2] in residential roads ................................
€10
RWP3
(b) Works [excluding those works referred to in
Minor Road Works,
paragraph (b) of the definition of "minor works" in
Maintenance and
regulation 2] in arterial or distributor roads ...............
€25
Repairs Permit
(c) Works on behalf of the Authority and those referred to
in paragraph (b) of the definition "minor works" in
regulation 2 .................................................................
Nil
In these regulations, unless the context otherwise requires,
the following expressions have the following meanings
"arterial and distributor roads" has the same meaning as is given
to it in the Agency for Infrastructure Malta Act;
"the Agency" shall mean the Agency for Infrastructure Malta as
established by and under the Agency for Infrastructure Malta Act;
"the Authority" means the Authority for Transport in Malta
established under the Authority for Transport in Malta Act;
"application" means an application for any road works permit;
"applicant" means the person commissioning the road works,
and includes the Agency for Infrastructure Malta;
"communications service provider" means an operator who
provides an electronic communications service using, for such
purpose, facilities placed in or under or on a public road;
"completion period" means the specified period in which all
works covered by the permit shall be completed;
"contractor" means an undertaking commissioned by an
applicant to undertake road works and which has the professional and
technical means to carry out any road works and which shall annually
provide the Authority with a bank guarantee for the amount of up to
fifteen thousand euro (€15,000);
"emergency works" means works which are required to be
executed following failure of underground utility or communications
services or works the carrying out of which is urgently required in
order to prevent or put an end to, or reduce the risk of loss, injury or
damage to persons or property;
"improvement" includes the widening, re-aligning and re-
shaping of roads;
"the European Union" has the same meaning as is given to it in
the European Union Act and includes Norway, Iceland and Cap. 460.
Liechtenstein;
"guidelines" means measures adopted by the Authority laying
down the steps to be followed and the elements to be considered in
applying the safety procedures set out in Part II;
"infrastructure project" means a project for the construction of
new road infrastructure or a substantial modification to the existing
network which affects the traffic flow, including, but not limited only
to, traffic management schemes;
"inhabited area" means any area in which there is an
aggregation of residential buildings inhabited or capable of being
inhabited by more than one hundred persons, or any other area
designated as such by the Minister in consultation with the Authority;
"Local Council" means a local government council established
in terms of the Local Councils Act;
"local plan" has the same meaning as is given to it in the
Development Planning Act;
"local road" has the same meaning as is given to it in the
Agency for Infrastructure Malta Act;
"maintenance" in relation to public roads includes improvement
and management;
"major works" means any road works which are neither minor
works nor emergency works;
"Planning Authority" means the Planning Authority as
established under the Development Planning Act;
"Member State" means a Member State of the European Union;
"the Minister" means the Minister responsible for infrastructure;
"minor works" shall include works consisting of -
(a)
the connection of a consumer to a service provided
by, or intended to be provided by, a utility service provider or a
communications service provider and which includes trenching
not exceeding a total area of three square metres;
(b)
using an access hole for the purpose of ducting,
assessing, repairing or maintaining infrastructure under a road
without effecting traffic flow not requiring excavation;
(c)
the excavation of trial pits to assess or detect buried
infrastructure;
(d)
the placing of any thing in any road that directly or
indirectly causes obstruction to the traffic flow;
(e)
the installation, repair or maintenance of traffic
control items and inhabited road furniture not requiring
excavations;
(f)
routine road maintenance in local roads, arterial
and distributor roads;
"network safety ranking" means a method of identifying,
analysing and classifying parts of the existing road network according
to their potential for safety development and accident cost savings;
"new road" includes the extension of an existing road;
"occupier" means any person who is lawfully in possession of or
exercising control over any land;
"owner", in relation to land or other immovable property, means
any person who owns the land or any person representing the owner
in the administration of the land concerned, or acting on behalf of the
owner or assuming the character of owner, according to
circumstances;
"permit" means a road works permit required from the Authority
under the provisions of these regulations;
"person" means any natural or legal person;
"project owner" means a person appointed by an applicant for
major road works permit, who shall be completely responsible for the
application and whose position within the applicant entity would
allow him to take decisions on his own in a reasonably short time and
give direction to his team;
"private road" has the same meaning as is given to it in the
Agency for Infrastructure Malta Act;
"public road" means any road not being a private road, which
includes both arterial and distributor roads and local roads;
"ranking of high accident concentration sections" means a
method to identify, analyse and rank sections of the road network
which have been in operation for more than three years and upon
which a large number of fatal accidents in proportion to the traffic
flow have occurred;
"residential building" means a structure used for the dwelling of
a person or persons and includes any house, mezzanine, garage, room,
store or other building;
"road" has the same meaning as is given to it in the Agency for
Infrastructure Malta Act;
"road safety audit" means an independent detailed systematic
and technical safety check relating to the design characteristics of a
road infrastructure project and covering all stages from planning to
early operation;
"road safety impact assessment" means a strategic comparative
analysis of the impact of a new road or a substantial modification to
the existing network on the safety performance of the road network;
"road works" means any intervention on existing roads,
including major road maintenance, the breaking up or opening of a
road, trenching works, the construction or reconstruction of footways
or carriageways, alterations in carriageways and footways, traffic
calming measures, the construction or removal of road humps, and
any intervention that alters or seeks to re-instate the surface of an
existing road;
"routine road maintenance" means actions performed on a
regular basis in order to keep a road safe and fit for travel, actions
performed to prevent deterioration where possible, and actions
performed to return the appearance of the road surface to good
condition; it includes, but is not limited to, patching pot holes, surface
patching, crack sealing and filling, cleaning of roads, drains and
culverts; installing traffic signs and signals; replacing damaged signs
and road markings, controlling roadside brush and vegetation;
"tenement" means any building or land separated from a road by
a wall;
"traffic management schemes" means schemes for the
management of traffic in various events with a combination of
network planning and engineering measures to enhance road safety,
with the aim to alleviate the adverse effects of motorized traffic
including traffic signal controlled junctions, parking regulation,
traffic calming, pedestrian and cycle route improvements and road
signing also for road works and temporary situations;
"trans-European road network" means the road network
identified in Section 2 of Annex I to Decision No 1692/96/EC of the
European Parliament and of the Council on Community guidelines
for the development of the trans - European transport network;
"trenching" means the construction of an excavation made
below the surface of the road for the purpose of accessing, installing,
repairing and maintaining of utilities under a road;
"underground utilities" means any electric, communications,
water, sewer or drainage service or means of transmission that is
installed beneath the surface of a road;
"undertaking" means any entity, including any person, engaged
in economic activity, regardless of its legal status and the way in
which it is financed;
"utility service provider" means an authority or an enterprise,
the primary business of which is to provide electricity or
communication or gas or water or sewage to the public. The utility
provider may be the Government or may be publicly or privately
owned.
PART II
CONSTRUCTION AND MAINTENANCE OF ROADS
(Regulations 32, 38)
TRAFFIC MANAGEMENT CLASSIFICATION DURING ROAD WORKS
Fine for
Item
Minimum Requirements
Standard Requirements
breach
TM A - Works on ALL roads not affecting traffic in any way
Works carried
1. Provide
temporary
1. Temporary
Traffic
€50
out on footpath
pedestrian access (Safe
Management Arrangements
route for pedestrians)
in line with: Safety at
Works carried
Inhabited Road Works and
out within the
2. Approval by Authority
Road Works - A Code of
parking bay
for Transport in Malta
Practice
area, not
for any obstruction to
affecting traffic
pedestrian crossing and
2. Traffic Signs Manual Chapter
pedestrian areas
8 Volume 1Traffic Safety
Measures and Signs for Road
Works
and
Temporary
Situations
3. Construction machinery not
obstructing carriageway
4. Programme of Works
TM B - Works on traffic carriageway on ALL roads partially obstructing traffic, however,
existing traffic flows retained
Works on traffic
1. Provide
temporary
1. Traffic Management Plan of
€100
carriageway
pedestrian access (Safe
works area
route for pedestrians)
2. Enforcement required
Temporary
Traffic
Works on
Management
centre- strips,
3. Programme of Works
Arrangements in line
side verges,
with Code
roundabouts
4. Construction machinery not
and any other
obstructing carriageway
2. Approval by Authority
road junctions
for Transport in Malta
etc.
for any obstruction to
pedestrian crossing and
pedestrian areas
TM C - Works on ALL roads affecting traffic, including partial and full obstruction, where traffic
diversions are required
Works on
1. Provide
temporary
1. Traffic Management Plan of
€300
carriageway
pedestrian access (Safe
works area
fully
route for pedestrians)
2. Traffic Management
Plan
obstructing
Temporary
Traffic
area-wide
traffic flow on
Management
arterial,
Arrangements in line
3. Enforcement required
distributor, link
with Code
roads and other
4. Programme of Works
2. Approval by Authority
roads (as
for Transport in Malta
required)
5. Construction machinery not
for any obstruction to
obstructing carriageway
pedestrian crossing and
pedestrian areas
TM D - Development Projects (Industrial, Residential, Commercial) which have an impact on
existing adjacent roads
4.1
Works on
1. Provide
temporary
1. Impact on change in traffic
€500
development
pedestrian access (Safe
volumes, traffic patterns,
projects which
route for pedestrians)
vehicle
mix,
road
have an impact
environment
Temporary
Traffic
on the
Management
2. Traffic Management Plan of
characteristics
Arrangements
in
line
development works area
of the existing
with Code
adjacent roads
3. Programme of Works
2. Approval by Authority
4. Construction machinery not
for Transport in Malta
obstructing carriageway
for any obstruction to
pedestrian crossing and
pedestrian areas
B B 2894
Whenever, in terms of the exercise of its functions under
article 6 of the Agency for Infrastructure Malta Act, a new road is
being constructed or re-constructed or an existing road is being
widened or deviated by the Agency, the Agency shall cause a notice,
accompanied by a plan showing the proposed new road or the portion
of the road intended to be widened or deviated, and the lands through
which it is to pass, to be published in the Gazette and in any
newspaper.
(Regulation 2)
The trans-European road network within the Authority’s jurisdiction
€2.43
The Authority may prepare and publish a Code of Practice
setting out best principles of good practice with respect to road works
applicable to any person conducting such roads works and in
particular to minimise disruption and inconvenience during road
works.
(1)
The designing, building, or the carrying out of Compliance
maintenance or other works on any road shall comply with the with standards.
following Design and Construction Standards for Road Works, which
shall be accessible to the public at the offices of the Authority, during
normal office hours or on any online medium
(i)
Volume 1- Specifications for Road Works;
(ii)
Volume 2 - Notes
for
Guidance
on
the
Specification for Road Works;
(iii)
Volume 3 - Road Construction Details;
(iv)
Volume 4 - Method of Measurement for Road
Works and Notes for Guidance of Measurement of Road Works;
(v)
Volume 5 - Design Manual for Roads and Bridges;
(vi)
Volume 6 - Guidelines for the Standard
Presentation of Design Documents for Road Construction;
(vii) Volume 7 - Directives for the Standardisation of
Pavements for Traffic Areas.
(2) Without prejudice to any action that may be exercisable
against any person who designs or builds any road in contravention of
this regulation, nothing in this regulation shall be construed as
granting a right to any person against the Authority or against the
Government or other public authority or Agency or against any
person acting in his or her official capacity as an officer or an
employee of Government or of any such aforesaid authority or agency
in respect of failure of any road to conform to the performance
associated with the Design and Construction Standards for Road
Works stipulated in this regulation.
(1)
A road safety impact assessment shall be Road safety
undertaken by the Agency at the initial planning stage of major impact
assessments.
infrastructural project on that part of the national road network
prescribed in the Third Schedule, to be submitted to the Authority.
(2) Such impact assessments may also be carried out at the
initial planning stage of any infrastructure project on the remaining
road network.
(3) The impact assessment shall be carried out during the
planning stage of a project before the completion of a definite design
and it shall as much as possible take into account the elements set out
in Annex I to Directive 2008/96/EC on road infrastructure safety
management.
(4) The results of the safety impact assessment shall be
considered by the Agency in the planning process of the project.
(5) Where changes are required to the planned infrastructure
project, the impact assessment shall indicate the road safety
considerations which contribute to the choice of the proposed
solution and shall further provide all relevant information necessary
for a cost-benefit analysis of the different options assessed.
(1)
Every infrastructure project on that part of the
national road network prescribed in the Third Schedule shall be
subject to a road safety audit which shall be carried out at the
following different stages of a project
(a)
the preliminary design phase,
(b)
the detailed design stage and during construction of
the project,
(c)
prior to being opened to traffic, and
(d)
approximately a year after being opened to traffic.
(2) Road safety audits in terms of sub-regulation (1) may also
be carried out on any infrastructure project on the remaining arterial
and distributor road network.
(3) Road safety audits shall conform to standards produced by
the Authority which shall as much as possible meet the criteria set out
in Annex II of Directive 2008/96/EC.
(4) A road safety audit may be undertaken in conjunction with
a road safety impact assessment as provided for under regulation 6.
(1)
Road safety audits shall be carried out by qualified
road safety auditors designated for the purpose by the Authority.
(2) The safety auditors referred to in sub-regulation (1) shall
not have been or are involved in the conception or operation of the
infrastructure project for which they have been engaged to carry out
the audit.
(3) Only persons who hold a certificate of professional
competence issued by the Authority or by a body approved by the
Authority or by any other competent authority following initial
training shall be considered to be qualified road safety auditors. An
auditor shall remain so qualified if he takes part in further training
courses at least once every five years.
(4) The Authority shall recognise certificates of professional
competence issued to road safety auditors before the coming into
force of these regulations.
(5) The Authority shall provide training curricula for road
safety auditors.
(1)
The road safety auditor appointed to carry out an Safety audit.
audit of an infrastructure project shall set out safety critical design
elements in an audit report for each stage of the project.
(2) Where unsafe features are identified in the course of the
audit, but the design is not rectified before the end of the appropriate
stage as referred to in Annex II to Directive 2008/96/ EC, the
Authority shall give the reasons thereof in an Annex to that report.
(3) The report referred to in sub-regulation (1) shall result in
relevant recommendations from a safety point of view.
(1)
At least every three years a ranking of high Safety ranking
accident concentration sections and a network safety ranking shall be of
network.
carried out by the Authority on the basis of reviews of the operation
of the arterial and distributor road network.
(2) For the purpose of the provisions of sub-regulation (1), the
Authority shall endeavour to meet the criteria set out in Annex III to
Directive 2008/96/EC and shall keep a data record of fatal accidents
occurring on the arterial and distributor road network.
(3) For the purpose of keeping a record of fatal accidents
occurring on the arterial and distributor road network, the Authority
shall draw up an accident report which shall include elements listed in
Annex IV to Directive 2008/96/EC.
(4) Road sections showing higher priority according to the
results of the ranking of high accident concentration sections and
from network safety ranking shall be evaluated by expert teams by
means of site visits guided by the elements referred to in item 3 of
Annex III to Directive 2008/96/EC. At least one member of the expert
team shall meet the requirements of regulation 8(2).
(5) Remedial treatment shall be targeted at road sections
referred to in sub-regulation (3) and priority shall be given to those
measures referred to in item 3(e) of Annex III to Directive 2008/96/
EC, giving close attention to those presenting the highest benefit-cost
ratio.
(6) The Authority shall calculate the average social cost of a
fatal accident and the average social cost of a severe accident
occurring on the national road network and may choose to further
differentiate the cost rates, in which case they shall be updated at least
every five years.
(1)
The Authority shall inform road users of the
existence of a high accident concentration section through the media
and by placing appropriate warning signs close to such sections.
(2) The Agency shall, in accordance with such directives as
the Authority may issue from time to time, put and keep in place
appropriate signs to warn road users of road infrastructure segments
that are undergoing repairs.
(3) The said signs shall include signs which shall be visible
during both day and night and they shall be set up at a safe distance
and shall comply with the provisions of the Vienna Convention on
Road Signs and Signals of 1968.
(1)
The Authority shall undertake, at least every three
to five years, safety inspections in respect of all arterial and
distributor roads in operations on the national road network in order
to identify the road safety related features and prevent accidents.
(2) Safety inspections shall also be carried out during road
works on the national road network.
(3) Such inspections shall comprise inspections of the road
network and surveys on the possible impact of road works on the
safety of the traffic flow and shall be based on guidelines adopted by
the Authority.
(4) The Authority shall adopt guidelines on temporary safety
measures applying to road works and shall also implement an
appropriate inspection scheme to ensure that those guidelines are
properly applied.
(5) The inspections are to be carried out by a team headed by a
trained safety expert who shall not have been or are involved in the
design or construction of any road for which a road inspection has to
be carried out in terms of this regulation.
(6) A road safety expert shall have the relevant experience or
training in road design, road safety, traffic engineering and accident
analyses.
(7) The safety expert shall prepare a formal report on the
detected safety issues and on general recommendations to eliminate
or mitigate problems.
PART III
ROADS IN INHABITED AREAS
(1)
Every new road in any inhabited area or any road Width of new
made with a view that it may form part of an inhabited area which roads
inhabited areas.
may hereafter be built up shall be at least eight metres wide
Provided that the Planning Authority, in consultation with
the Agency and the Authority, may require any such road to be of a
stated width exceeding eight metres but not exceeding eighteen
metres.
(2) Where an existing road in an inhabited area is extended,
the minimum width of the road may, with the permission of the
Planning Authority, in consultation with the Agency and the
Authority, be reduced to six metres.
No new road in an inhabited area, nor any road made with Course,
a view that it may form part of an inhabited area which may hereafter direction
position of new
be built up, shall be made without the sanction from the Planning roads
inhabited areas.
Authority, in consultation with the Agency and the Authority, as to its
course, direction and position, and as to the manner in which the
adjoining residential buildings are to be sewered and supplied with
water and the surface water is to flow off.
A new road in an inhabited area or an area which may Permission
hereafter be built up may only be opened with the permission of the required
opening of a
Planning Authority, in consultation with the Agency and the new
inhabited area.
Authority, and the Planning Authority may refuse permission for the
opening of such a new road
Provided that where such permission is refused, the party
aggrieved shall have the right to appeal from such a decision under
the provisions of the Development Planning Act.
No building abutting on a new road in an inhabited area Erection of
shall be erected before the road has been levelled to the proper line buildings
new roads.
fixed by the Planning Authority, in consultation with the Agency and
the Authority. The length of the road to be so levelled shall extend
from any existing inhabited road already opened to the public to the
extreme end of the frontage of the building to be erected.
(1) (a) Subject to the provisions of regulations 13, 14,
15 and 16, no person may commence the construction of any building
having access to, or having any window or other opening on to, any
road belonging to the Government, before paying to the Planning
Authority, in respect of the formation of the said road, a contribution
equal to the cost, as at the time of payment of the contribution, of the
formation of such road (such cost to include the value, as at the time
of payment of the contribution, of the land required for the formation
of the road) or before paying to the Planning Authority at least
twenty-five per cent of such contribution and at the same time
undertaking in writing to pay the balance within a period of not more
than twelve months by equal monthly instalments, commencing one
month from the date of such payment and undertaking
Provided that where the land on either side or on both sides
of the road belongs to different owners the total contribution shall be
apportioned among such owners in proportion to the frontage of the
land belonging to each owner on to such road, in such manner that the
whole cost of the road shall be distributed in proportion to such
frontage among the various owners.
(b) Where any monthly instalment referred to in
paragraph (a) is not paid within ten days from the date when the
payment of such instalment falls due, the whole amount of the
outstanding contribution shall become and be immediately due and
owing to the Planning Authority and the person who made the
undertaking referred to in the said paragraph shall be deemed to have
commenced the construction of the building in contravention of this
regulation.
(2) A contribution in respect of the cost of the widening of any
road, at whatever time carried out, may be claimed by the Planning
Authority as in the case of a new road and such contribution shall
only be levied from the owner who has or owners who have derived a
benefit from such widening and shall be apportioned in proportion to
the benefit so derived.
(3) Where any road to which this sub-regulation applies
exceeds eighteen metres in width, the cost of the formation or
widening of the road in excess of such width shall not be taken into
account in fixing the contribution payable to the Planning Authority.
(4) Any contribution payable under the provisions of this
regulation and any apportionment thereof among the owners shall, in
default of agreement, be fixed by the Planning Authority
Provided that any party interested may impugn the
assessment of the Planning Authority by an application before the
competent civil court.
(5) The rates of contributions which may be levied in respect
of any class or type of building and the manner of their collection
shall be those established under regulations made in terms of article Cap. 552
42 of the Development Planning Act.
(6) The said contributions shall be collected and levied by the
Planning Authority on account of the Government.
(1)
The rates to be charged by the Agency for the Rates for
levelling, metalling and asphalting of surface otherwise of roads in an levelling,
of roads.
inhabited area or an area which may hereafter be built up shall be Cap. 499.
those as prescribed by regulations under the Authority for Transport
in Malta Act.
(2) Where any person fails to form any road in an inhabited
area or an area which may hereafter be built up in accordance with the
provisions of these regulations, the Agency may itself proceed to
form such a road after giving notice of its intention to do so by means
of a notice in the Gazette, giving such person fifteen days within
which to comply. Such formation shall be at the expense of the person
who would otherwise have been obliged to form such inhabited road,
and the Agency shall have the right to recover any expense so made
from such person.
PART IV
PRIVATE ROADS
The Agency may, at any time, carry out or cause or allow Agency may
to be carried out in and under any private road any work whatsoever carry
in private roads.
which it considers necessary or useful on grounds of public utility.
Every new private road shall be properly levelled, metalled Levelling, etc.,
and put in a proper state as regards its drainage, by the person by of
by owner.
whom such road shall have been opened, in accordance with the
directives of the Authority to the satisfaction of the Agency. Every
such road shall, moreover, be provided by the said person with
footways with kerb and gutter made of hard stone or other suitable
material to the satisfaction of the Agency.
Every private road shall be kept in a proper state of repair Upkeep of
to the satisfaction of the Agency, by the person by whom such road private roads.
shall have been opened.
The owners of any property immediately abutting on any
private road or the persons holding such property on emphyteutical
lease shall, for the purpose of this Part, be deemed to be the persons
who opened such road and the owners thereof
Provided that any person who is bound to carry out any
work in any such road shall be entitled to bring against third parties
any civil action, admissible according to law, for the recovery of any
expenses incurred in the execution of the work
Provided further that no such civil action shall delay the
execution of the work by the person who is bound thereto.
(1)
Without prejudice to any other action available
according to law, the Agency shall be enabled to carry out or, as the
case may be, to continue the carrying out of all or any of the works
specified in regulations 20 and 21 after having given the owner notice
by registered letter of its decision so to do; any such works shall be
carried out at the expense of the person who has opened the road.
(2) Every private road, including the footway thereof, shall, on
notice by registered letter given by the Authority, be asphalted or
surfaced otherwise as indicated by the Authority, by the Agency, at
the owner’s expense.
(3) Each of the notices mentioned in the last two preceding
sub-regulations shall specify the amount payable by the owner as his
share of the expense in connection with the proposed works.
(4) The Agency shall give notice by registered letter of the
date of completion of the works referred to in sub-regulations (1) and
(2) to the owners, who shall effect payment, unless they have already
done so, of the amount due by them without interest, within a month
of the receipt of the notice of completion of the works.
(5) Every notice sent by registered post in terms of this
regulation shall be deemed to have reached the addressee in the
normal course of postal delivery.
(6) Private roads shall, when such roads are included in a
scheme or in a local plan -
(a)
on their asphalting or other surfacing; and
(b)
upon the publication in the Gazette of an Order by
the President to that effect,
become Government property and the owners shall thereafter be
relieved of any further obligation of maintaining the roads.
(7) Notwithstanding any other provision of law to the contrary,
the site of every road or part of a road transferred to the Government
in accordance with sub-regulation (6) shall, on the Order of the
President, be freed absolutely from every privilege and hypothec
theretofore affecting it, without prejudice to the entire credit secured
by that privilege or hypothec continuing to be a charge on the residue
of the property of which that site formed part and on all other affected
properties, if any, of the debtor. Any such liberation shall not be
subject to any requirement of reference or other entry in the Public
Registry.
(8) (a)
If the owner of the road shall fail to pay any
amount due by him under and within the period specified in sub-
regulation (4), he shall thereupon become liable to the payment over
and above the amount so due of interest at eight per centum thereon
as from the date of completion of the works to the date of payment,
and the expense incurred by the Agency together with that interest
thereon shall constitute a privileged claim in favour of the Agency on
that owner’s property immediately abutting on the inhabited road, and
such claim shall be paid in preference to all other claims, whether
privileged or hypothecary on such property, notwithstanding any
other provision of law to the contrary.
(b) Such right of priority may not be enforced unless the claim
is registered in the Public Registry within two months from the
completion of the works aforesaid. In default of evidence to the
contrary the date of the completion of the works shall be deemed to
be that indicated in the note for the registration of the privilege.
For the purpose of the registration and recovery of any Expenses
claim under regulation 23, the expense incurred by the Agency shall incurred
Agency to be
be apportioned by the Agency among the owners in proportion to the apportioned
among the
frontage of their respective land or buildings along the inhabited road: owners.
Provided that any owner may impugn the assessment made
by the Agency by an application before the competent civil court in
contestation with the said Agency.
PART V
ROAD NAMES
The Agency, the Authority, and to the extent of any Power in
responsibility of a Local Council in terms of the Local Councils Act, connection
painting of
a Local Council, in consultation with the Planning Authority, may names
etc.
cause the name by which any road is to be called, as well as the name Cap. 363.
of the town, suburb or village in which the road is situated, and any
other notice or mark which may be considered useful for directing
routes or giving warnings about dangerous corners, or for any other
public purpose, to be painted or affixed and maintained in a legible
state on the walls of any building other than a building destined for
divine worship.
Where a Local Council shall cause the name by which a
private road is to be called, that road shall remain a private road.
No person shall paint, mark, write or affix in any road open
to the public any name as that by which such road is to be called, or
any name of any town, suburb or village, or any notice or mark
similar to that painted or made in accordance with the provisions of
regulation 25 without the approval of the Authority, or of the Local
Council responsible for the locality in which such road is situated, as
the case may be, although such road is a private road.
(1)
It is forbidden to destroy, obliterate or deface the
name of any road, town, suburb or village or add any word or mark
thereto, or damage any slab bearing any such name.
(2) Where a person contravenes the provisions of sub-
regulation (1), such person shall be guilty of a contravention and
shall, on conviction, be liable to a fine (ammenda) of one hundred
euro (€100).
PART VI
ROAD WORKS
(1)
Without prejudice to the obligations relating to
road works under any other laws or regulations in force, no works
shall be executed in, or excavations made under a public road without
a permit from the Authority following consultation with the Agency
or Local Council, as the case may be, which may also impose
conditions as described hereinafter.
(2) The application for a permit shall be made to the Authority
by the applicant on the prescribed form and shall be accompanied by
any information and documents required by the Authority, and by the
appropriate fees as prescribed in the First Schedule.
(3) The permit shall be valid for the period indicated in it and
all work shall be fully completed within the completion period
specified in the permit.
(4) The Authority may renew any permit the validity of which
has expired upon the submission by the holder thereof of an
application for renewal.
(5) Road works may only be carried out by Local Councils,
the Agency for Infrastructure Malta, utility services providers, and
communications service providers, and all parties involved shall at all
stages follow the Code of Practice
Provided that no works shall commence by utility service
providers, communication service providers or any contractor thereof,
prior to the issuance of the necessary permit by the Authority, and a
licence from the Local Council concerned, as prescribed in the Local Cap. 363.
Council’s Act
Provided further that in the case of emergency works, the
Authority must following the approval and permit for said works and
prior to the commencement thereof immediately notify the Local
Council of the works to be carried out.
(6) Where works in contravention of any of the dispositions of
the provisions of sub-regulation (5) are undertaken, the contractor or
service provider as the case may be shall be liable to an
administrative fine (ammenda) imposed by the Authority of up to one
thousand (€1,000) euro for each contravention, which fine
(ammenda) may also be withdrawn from the bank guarantee.
(1)
There shall be three types of road works permits as Types of
permits.
follows
(a)
Major Road Works Permit - RWP 1,
(b)
Emergency Road Works Permit - RWP 2,
(c)
Minor Road Works, Maintenance and Repairs
Permit - RWP 3.
(2) A Major Road Works Permit shall cover major works
which involve any type of road works.
(3) An Emergency Road Works Permit shall cover any
emergency road works and it shall be valid for a period not exceeding
three days.
(4) A Minor Road Works Permit shall cover minor works.
(1)
An application for the granting or renewal of any of Processing of
the permits prescribed by these regulations shall not be processed by applications
road works
the Authority where the application -
permits.
(a)
is not submitted on the prescribed form,
(b)
is not accompanied by the prescribed fee, or
(c)
is not accompanied by the information and, or
documents requested by the Authority, including -
(i) a copy of an insurance certificate covering
such works,
(ii) a proper site plan (an A4 extract from the
1988 1.2500 scale survey sheet), endorsed by a qualified
civil engineer showing clearly the location of the proposed
works,
(iii) a written agreement to back fill and restore
the surface of the road to specifications set by the
Authority and in accordance with the conditions specified
in the permit, and
(iv) any other requirements as may be stipulated
by the Authority.
(2) Where an application is made for an Emergency Road
Works Permit, the permit shall be issued once the Authority confirms
the emergency of such works and issues the relative permit
Provided that the permit holder shall pay those fees for the
services rendered by the Authority official or the penalties as
prescribed in the First Schedule;
Where the Authority issues a permit under these
regulations, it may attach such conditions to the permit as seem to it
appropriate having regard to all the circumstances of the case.
(2) Without prejudice to the generality of sub-regulation (1),
the types of conditions which the Authority may attach to a permit
under the said sub-regulation include conditions relating but not
(a)
days on which works may not be carried out;
(b)
times of day during which works may not be
carried out;
(c)
the prohibition or restriction of traffic;
(d)
traffic management arrangements to be made in
connection with the works as prescribed in the Second
(e)
the manner in which the specified works are to be
carried out;
(f)
consultation and publicity in relation to the
specified works, including the display of information at the
location of those works;
(g)
full compliance with the guidelines and policies
published from time to time by the Authority; and
(h)
performance and, or defects liability conditions
Provided that the Authority may impose any other
conditions following consultation with the Agency or Local Council,
as the case may be.
(3) Where a contractor executes works in contravention of any
condition attached to the permit or in contravention to any other
direction which the Authority may give, the Authority, if it considers
it desirable to do so, may revoke or suspend the permit as the case
may be, and the contractor shall be liable to an administrative fine of
fifty euro (€50) for each contravention, which fine may be withdrawn
from the bank guarantee
Provided that where the breach is in contravention of any
of the traffic management conditions, the administrative fine shall be
in accordance with any of those provided in the Second Schedule.
(1)
Meta l-Awtorità toħroġ permess taħt dawn ir-
regolamenti, hija tista’ tehmeż mal-permess dawk il-kondizzjonijiet li
taħseb li jkunu xierqa b’konjizzjoni għaċ-ċirkostanzi kollha tal-każ.
(2) Mingħajr preġudizzju għall-ġeneralità tas-subregolament
(1), it-tipi ta’ kondizzjonijiet li l-Awtorità tista’ tehmeż mal-permess
taħt l-imsemmi subregolament jinkludi kondizzjonijiet li għandhom
x’jaqsmu ma’, iżda mhux limitatament għal -
(a)
ġranet li fihom ma jkunux jistgħu jsiru x-xogħlijiet;
(b) ħinijiet tal-ġurnata li fihom ma jkunux jistgħu jsiru x-
xogħlijiet;
(ċ)
il-projbizzjoni jew restrizzjoni tat-traffiku;
(d) arranġamenti li jkollhom isiru għall-maniġġar tat-
traffiku b’rabta max-xogħlijiet kif imsemmi fit-Tieni Skeda;
(e)
il-mod li fih ix-xogħlijiet imsemmija għandhom isiru;
(f) konsultazzjoni u pubbliċità dwar ix-xogħlijiet
imsemmija, kompriż il-wiri ta’ informazzjoni fil-post fejn ikunu
qegħdin isiru x-xogħlijiet;
(g) konformità sħiħa mal-linji gwida u l-linji ta’ politika
pubblikati minn żmien għal żmien mill-Awtorità; u
(h) il-kondizzjonijiet dwar kif għandhom isiru x-
xogħlijiet u, jew dwar ir-responsabbiltà ta’ difetti
Iżda l-Awtorità tista’ timponi kull kundizzjoni oħra wara
konsultazzjoni mal-Aġenzija jew il-Kunsill Lokali, skont il-każ.
(3) Meta kuntrattur jagħmel xogħlijiet bi ksur ta’ xi waħda
mill-kundizzjonijiet li jkunu ġew mehmuża mal-permess jew bi ksur
ta’ xi ordni li l-Awtorità tista’ tagħti, l-Awtorità, jekk tħoss li jkun
xieraq li tagħmel hekk, tista’ tirrevoka jew tissospendi l-permess skont
ma jkun il-każ, u l-kuntrattur jeħel multa amministrattiva ta’ ħamsin
euro (€50) għal kull kontravvenzjoni, u dik il-multa tista’ tinġibed
mill-garanzija bankarja
Iżda fejn il-kontravvenzjoni tkun bi ksur ta’ xi kondizzjoni
dwar il-maniġġar tat-traffiku, il-multa amministrattiva għandha tkun
skont dawk li hemm fit-Tieni Skeda.
(1)
Where the Authority refuses to issue a permit, it Refusal to grant
shall by notice in writing, within seven days, inform the applicant of an
or a permit.
its decision and the reasons therefore.
(2) Where the issue of such a permit is refused, the applicant
may, within twenty-one days starting on the date of such notice,
appeal before the Administrative Review Tribunal provided for under Cap. 490.
the Administrative Justice Act.
(1)
The Agency shall have the power to contract major The Agency
road works where such works are to be commissioned by a utility may
major works.
services provider which is Government owned.
(2) Where such works are contracted by the Agency, this shall
be done on behalf and at the expense of the utility service provider
concerned.
(1)
The Authority shall, prior to the granting of a Protection of
permit for road works, approve a suitable and safe traffic traffic
commuters.
management plan prepared by the applicant in respect of those works
and ensure the putting into effect and maintenance of the said plan,
which plan shall include but not limited to lighted barricades, warning
lights, or warnings devices, and signage as needed in order to prevent
damage or injury to persons, vehicles and property and to minimise
the inconvenience and danger to the public by the said road works.
(2) The said traffic management plan and the required
measures shall be carried out at the expense of the applicant.
(3) The applicant shall ensure that the contractor shall
maintain the traffic management plan throughout all the works
execution period. Failure to do so shall make the applicant and, or the
contractor liable to an administrative fine as provided for in the
Second Schedule, which fine may also be withdrawn from the bank
guarantee, without prejudice to any further action that may be taken
by the Authority, including the withdrawal of the bank guarantee and
suspension of authorization for future road works.
A contractor executing road works shall compensate third
parties in respect of any damages or loss suffered by third parties as a
result of the execution of those road works
Provided that the said liability does not extend to damage
or loss which is attributable to negligence or misconduct on the part
of the person suffering the damage or loss.
(1)
Where trenching works are executed in a road, the
contractor shall be required to reinstate the road in accordance with
the conditions stipulated in the permit.
(2) Where the contractor fails to reinstate the road as required
in sub-regulation (1), the contractor or service provider as the case
may be shall be liable to an administrative fine (ammenda) imposed
by the Authority of up to fifteen thousand (€15,000) euro, which fine
(ammenda) may also be withdrawn from the bank guarantee.
(1)
A contractor which undertakes road works shall,
upon completion of such works, submit a works compliance report to
the Authority within fifteen days from completion prior to which the
no objection of the contracting authority must be obtained.
(2) The Authority shall then inform the Agency of the issuance
of the compliance certificate.
(3) Major and emergency road works shall, upon completion,
be tested by an independent and accredited laboratory recognised by
the Authority.
(4) In addition to the test carried out as provided for in sub-
regulation (2), and on the basis of the same tests where applicable,
major and emergency road works shall be certified by a warranted
architect and civil engineer (Perit) in terms of compliance with
standards and specifications set by the Authority in respect of all
aspects including but not exclusively, material used, workmanship,
and any performance requirements stipulated in applicable standards.
Only upon such positive certification shall the Authority issue a
certificate confirming that those works had been carried out to its
satisfaction.
(5) Reinstatement works shall be subject to a two-year
guarantee, unless otherwise stated.
(6) Where the Authority is not satisfied with the restoration
and resurfacing of the road, the contractor shall redo the said works to
the satisfaction of the Authority, and where the contractor fails to
comply, the Authority may ask the Agency to carry out the works
itself at the expense of the contractor concerned.
(7) The Authority may exclude from road works, for pre-
established period of times of no less than six consecutive months,
contractors who consistently fail from such compliance.
Contractors shall be required to pay a charge of between Charges for
fifty euro (€50) and five hundred euro (€500) for each day, or part prolonged
works.
thereof, where the duration of road works carried out by that
contractor exceeds the prescribed completion period without a
justifiable reason. The said charges shall be those prescribed in the
Second Schedule.
(1)
It is an offence for a person to execute, or cause or Prohibitions of
unauthorised
suffer to be executed, any unauthorised road works.
works.
(2) In the case of an offence under sub-regulation (1) hereof
the Authority shall, by the issue of a stop notice, direct that person to
stop the works immediately and to take such steps as appear to it
necessary to reinstate, within a period not exceeding twenty-four
hours, the road, failing which the Authority shall carry out the works
itself at the expense of the person concerned.
(3) Any delays in the reinstatement of the works beyond the
time limit imposed under sub-regulation (2) shall bear an
administrative penalty of five hundred euro (€500) per day to be
charged to the person who had executed the unauthorised works and
to the person on whose behalf or at whose request the works have
been carried out.
(4) The Authority shall not entertain any other application by
the same person or persons to undertake any other works until such
time the road is reinstated by the person or persons concerned or,
where the reinstatement works are carried out by the Agency, until
such time as all expenses and penalties have been settled.
(5) The Authority shall not enter into negotiations with the
person or persons concerned until such time as that person or persons
comply with the direction given under sub-regulation (2).
PART VII
OTHER PROVISIONS
The Authority may give orders and take the requisite steps
for closing any road and stopping the thoroughfare thereof during the
construction, alteration, repair or demolition of such road, or of a
conduit, sewer or other public work in such road.
It shall not be lawful, without a permit from the Authority,
the obtaining of the necessary licence from the appropriate Local
Council, to construct any work or make any thing in any road, which
may cause obstruction or create danger or inconvenience to the
public, or, in spite of an intimation by the Police or by a local warden,
to leave any building or work which is ruinous or dangerous to
persons or to the property of others.
Any person intending to take down, construct, alter, or
repair any building in such a manner as will necessitate the deposit of
building materials in the road, or may be a source of injury, danger, or
inconvenience, shall, before beginning the same, cause sufficient
fences to be put up in order to separate the building where the works
are to be carried out from the road with a convenient space for the
thoroughfare, and shall keep such fences and such space in good
condition during such time as the public safety or convenience
requires; and shall, in all cases in which it is necessary in order to
prevent accidents, cause the same to be sufficiently lighted during the
night.
A sufficient light shall also be placed, during the night, on
or near the materials lying in the road, by the person who shall have
laid there such materials on the occasion of any building, repair or
excavation.
It shall not be lawful to leave in any road building
materials or other obstructions longer than necessary; and in any such
case, the proof that the necessary time has not been exceeded shall lie
on the person so causing such materials or other obstructions to be
laid.
(1)
Any opening in the surface or footway of any road, Openings in
leading to a vault, cellar, or other place underground, shall be covered surface
footway leading
by a door or other proper covering, and such door or covering shall be to
to be covered.
kept in repair by the owner.
(2) Nevertheless, where such vault, cellar, or place
underground is intended for habitation, it shall suffice to make on the
edge of the opening a sufficient fence for the safety of the public,
where this is practicable without causing considerable obstruction in
the road.
The occupier of any tenement shall rebuild, without delay, Rebuilding of
any wall of such tenement which shall have fallen on the road, or walls
the road.
which, being a party-wall between a tenement and a road, shall
require, in the opinion of the Authority, to be rebuilt.
(1)
A person committing an offence under regulation Penalties.
39(1) or regulation 41 is liable to a fine (ammenda) of one thousand
five hundred euro (€1,500).
(2) If on completion of the work for which a permit has been
issued the contractor does not carry out the re-instatement within
forty-eight hours of completion, or within such longer period as may
be allowed in the permit, or the re-instatement is not properly carried
out, the Authority may ask the Agency to carry out the re-instatement
at the expense of the grantee. Such reinstatement expense may be
withdrawn from the bank guarantee.
(3) Where reinstatement is effected or remedied by the
Authority, the contractor is still responsible for such reinstatement.
(4) The applicant shall be liable in solidum with the contractor
which carried out the works to carry out the reinstatement works.
(5) Throughout the carrying out of works, the Authority may
give further instructions to the contractor pertaining to any of the
conditions in the permit through an addendum to the permit. Failure
to immediately comply with the Authority’s instructions shall make
the contractor liable to an administrative penalty of fifty euro (€50)
per day, without prejudice to any further action that may be taken by
the Authority, including the withdrawal of the bank guarantee and
suspension of authorization for future road works.
(6) Where a person contravenes any other provision under
these regulations he shall be liable to a fine (ammenda) of not less
than twenty euro (€20) but not exceeding one thousand five hundred
euro (€1,500).
The New Roads and Road Works Regulations are hereby
repealed without prejudice to anything done or omitted to be done
thereunder.