76 tal-2017
Table of Provisions (20)
Statutory Text (20 Articles)
L.N. 76 of 2017
FINANCIAL ADMINISTRATION AND AUDIT ACT
(CAP. 174)
REGULATOR FOR ENERGY AND WATER SERVICES ACT
(CAP. 545)
Competitive Bidding Rules for Renewable Sources
of Energy Installations Regulations, 2017
BY VIRTUE of the powers conferred by article 4 of the
Financial Administration and Audit Act, and in exercise of the
powers conferred by article 37(1) of the Regulator for Energy and
Water Services Act, the Minister of Finance and the Prime Minister,
after consultation with the Regulator for Energy and Water Services,
have made the following regulations:-
The title of these regulations is the Competitive Bidding Citation.
Rules for Renewable Sources of Energy Installations Regulations,
2017.
(1) Unless otherwise stated in these regulations, the Interpretation.
definitions in the Financial Administration and Audit Act shall apply. Cap. 174.
(2) In these regulations, unless the context otherwise requires
"annual threshold" means the cap in kWh for the payment of the
awarded bid price per kWh for the period of time commencing on the
1st January and ending on the 31st December of each year;
"approved renewable energy installation" means a new solar
photovoltaic installation or new wind energy installation with a
capacity of 1000kWp or more and granted financial support for the
first time pursuant to a competitive bidding process, and excludes
solar photovoltaic installations and new wind energy installations that
benefit or have benefited from any other support including support on
the initial capital investment;
"awarded bid price per kWh" means the bid price per kWh
offered by a successful bidder whose offer is selected pursuant to a
competitive bidding process;
"bid price per kWh" means price per kWh offered by a bidder in
a competitive bidding process;
"common point of connection to the grid" means the point on
the electricity distribution network where the Distribution System
Operator and customer/generator assets are connected and coincides
with the location of the meter;
"commissioned" means the first time a renewable energy
installation is put into operation, following the establishment of
operational readiness by the warranted electrical engineer certifying
the installation;
"competitive bidding process" means a non-discriminatory
bidding process that provides for the participation of a sufficient
number of undertakings and where the aid is granted on the basis of
the initial bid submitted by the bidder. In addition, the volume related
to the bidding process is a binding constraint leading to a situation
where not all bidders can receive aid;
"Contracting Authority" means the entity
issuing
and
administering the competitive bidding process;
"DC" means direct current;
"distribution" means the transport of electricity on high voltage,
medium voltage and low voltage distribution systems with a view to
its delivery to consumers, but not including supply;
"distribution system" means all the interconnected technical
facilities used for conveying electricity to final customers;
"distribution system operator" shall have the same meaning as
under the Electricity Market Regulations;
"eligible renewable energy installation" means a new solar
photovoltaic installation or new wind energy installation with a
capacity of 1000kWp or more applying to be granted financial
support for the first time pursuant to a competitive bidding process,
and excludes solar photovoltaic installations and new wind energy
installations that benefit or have benefited from any other support
including support on the initial capital investment;
"full load hours" means the equivalent number of hours in a year
during which the renewable energy installation produce at its full
nominal or kWp capacity;
"generation" means the production of electricity;
"guaranteed period" means the period of time indicated in the
relevant competitive bidding process during which the awarded bid
system operator from a qualifying renewable energy installation is
guaranteed;
"kW" means kilo Watt;
"kWh" means kilo Watt hour(s);
"kWp" means the nominal capacity of the renewable energy
installation, which in the case of a solar photovoltaic installation is
equal to the total DC peak power of a solar photovoltaic installation;
"metering equipment" means the electricity meters provided by
the distribution system operator including smart meters, any voltage
and current transformers and any other associated equipment and
wiring required to measure the quantity of electricity supplied or
exported;
"Minister" means the Minister responsible for Energy;
"new solar photovoltaic installation" means a solar photovoltaic
installation which has never been used for the generation of
electricity in whole or in part and which is installed by a successful
bidder after the conclusion of a competitive bidding process;
"new wind energy installation" means a wind energy installation
which has never been used for the generation of electricity in whole
or in part and which is installed by a successful bidder after the
conclusion of a competitive bidding process;
"performance bond" means the performance bond to be
provided by a successful bidder to the Contracting Authority pursuant
to regulation 10;
"premium" means the difference between the awarded bid price
per kWh and the proxy for the market price per kWh and is payable
only when the awarded bid price per kWh is higher than the proxy for
the market price per kWh and the proxy for the market price per kWh
is not negative;
"proxy for the market price" means the average of the estimated
variable cost of meeting the demand forecast for a given year from
locally generated conventional and imported electricity, with the
demand assumption excluding that portion of the forecast demand
which is not expected to be met by conventional and imported
electricity;
"renewable energy sources" means renewable non-fossil energy
sources, that is, wind, solar, geothermal, wave, tidal, hydropower,
biomass, landfill gas, sewage treatment plant gas and biogases;
"smart meters" shall have the same meaning as in the Electricity
Supply Regulations;
"solar photovoltaic installation" means a solar photovoltaic
system that generates electricity exclusively from solar radiation and
consisting of all accessories including
(a)
an array or arrays of photovoltaic modules that
collect and absorb sunlight for conversion into electricity;
(b)
an inverter or inverters;
(c)
associated balance of system components, including
wiring, conduits, switchgear, protection equipment, ancillary
equipment and any other part of the installation necessary for
the production and conveyance of electricity up to the metering
equipment supplied by the distribution system operator;
"successful bidder" means a bidder whose offer is selected
pursuant to a competitive bidding process;
"supply" means the sale or retail, including resale, of electricity
to customers;
"wind energy installation" means an installation that converts
wind energy into electricity and shall include the tower on which the
wind turbine is mounted, a rotor and the nacelle which houses the
equipment, including the generator, that converts the mechanical
energy in the spinning rotor into electricity and any other ancillary
equipment necessary to connect to the grid.
(1) The purpose of these regulations is to introduce the
competitive bidding process as the method to determine the fixed
distribution system operator from approved renewable energy
installations and hence to promote and support the generation of
electricity from renewable energy sources. The method and amount of
support for solar photovoltaic installations with a kWp capacity lower
than 1000kWp shall continue to be determined administratively. For
the purpose of calculating the 1000kWp threshold, renewable energy
installations with a common point of connection to the electricity grid
shall be considered as one installation.
(2) These regulations shall apply only to renewable energy
produced from renewable energy installations installed in Malta,
Gozo and other islands of the Maltese Archipelago, including the
territorial waters thereof.
(3) These regulations shall not apply to firms in difficulty as
defined by the Guidelines on State aid for Rescuing and Restructuring
non-financial Undertakings in difficulty (2014/C 249/01).
The price per kWh to be paid for electricity generated and Competitive
sold to the distribution system operator from eligible renewable bidding process.
energy installations shall be determined through a competitive
bidding process
Provided that any award and, or payment of any amounts
to an undertaking that has benefited from earlier unlawful aid
declared incompatible by a Decision of the European Commission
shall be suspended until such time as that undertaking has reimbursed
the total amount of unlawful and incompatible aid and the
corresponding recovery interest.
(1) The awarded bid price per kWh resulting pursuant to Determination
a competitive bidding process shall be paid in each calendar year up of
kWh.
to a capped amount of units of electricity generated and sold to the
distribution system operator and payable for the guaranteed period.
(2) The awarded bid price per kWh shall be determined by
"pay-as-bid" such that the successful bidders shall be paid, for the
electricity generated and sold to the distribution system operator from
an approved renewable energy installation, the awarded bid price per
kWh based on their actual bid.
(3) The bidder shall submit the bid price per kWh for each
eligible renewable energy installation as required in the competitive
bidding process.
(4) The awarded bid price per kWh shall only be applicable to
a successful bidder and only in respect of the renewable energy
installation as described in the bid including the capacity offered in
the bid (in kWp), as part of the competitive bidding process. The
capacity associated with the bid price shall be deemed to be equal to
Offered kWp x Full Load Hours
(5) Without prejudice to sub-regulation (4), the ownership of
an approved renewable energy installation selected pursuant to a
competitive bidding process may be transferred to a third party and
subject to the third party obtaining the necessary permits,
authorisation and licences, as may be applicable.
(6) The awarded bid price per kWh with respect to an
approved renewable energy installation shall be payable for the actual
number of units of electricity generated by such installation and sold
to the distribution system operator, up to the annual threshold
calculated as offered kWp x Full Load Hours
Provided that the number of assumed full load hours in the
case of a solar photovoltaic installation shall be equal to 1600 hours
Provided further that in the case of other types of
renewable energy installations, such as wind energy, the number of
full load hours which shall determine the annual threshold for the
payment of the awarded price per kWh, shall be specified in the terms
and conditions applicable in the relevant competitive bidding process.
(7) Any units generated above the amount calculated in sub-
regulation (6) of this regulation in any calendar year shall be
purchased by the distribution system operator and paid at the proxy
for the market price per kWh only, without the payment of the
premium.
(8) The successful bidders shall not be entitled to tradeable
guarantees of origin or other tradeable certificates for the electricity
sold to the distribution system operator.
(9) Without prejudice to sub-regulations (4) and (5), an
approved renewable energy installation may be relocated to an
alternative site subject to obtaining the necessary permits,
authorisations and licenses as may be applicable, and subject to the
conditions laid down in the competitive bidding procedure
(1) The competitive bidding process shall include an
administratively established cap on the maximum bid price per kWh
that bidders may offer. The cap may consist of one maximum bid
categories.
(2) The bid prices per kWh shall be submitted in steps of
€0.005/kWh and shall not exceed the cap referred to in sub-regulation
(1).
(1) An approved renewable energy installation shall be
commissioned and an application to connect the installation to the
distribution system has been submitted to the distribution system
operator within eighteen (18) months to be reckoned as from the date
of the letter of award issued by the Contracting Authority to the
successful bidder to secure the eligibility of the awarded bid price per
kWh.
(2) If the successful bidder fails to comply with sub-regulation
(1), the time to commission and apply to connect the approved
renewable energy installation to the distribution system as indicated
in sub-regulation (1) may be extended once only by six months by
means of a request in writing to the Contracting Authority and made
in the format required by the Contracting Authority
Provided that the price payable to the successful bidder for
electricity generated and sold to the distribution system operator for
the particular approved renewable energy installation shall be
equivalent to the awarded bid price per kWh, less €0.005/kWh for all
electricity generated and sold to the distribution system operator up to
the amount indicated in regulation 5(6), for the guaranteed period.
(3) The time necessary for the successful bidders to obtain the
necessary authorisations, licences and permits as applicable, shall not
suspend the running of the time periods indicated in sub-regulations
(1) and (2), being the maximum time within which an approved
renewable energy installation must be commissioned and an
application to connect the installation to the distribution system has
been submitted to the distribution system operator, for the award
pursuant to the competitive bidding process to remain valid. Failure
to comply with sub-regulation (1) and sub-regulation (2) (when an
application for an extensions has been made), shall lead to the
automatic withdrawal of the award and the forfeiture of the
performance bond.
The launch of each competitive bidding process, as well as Publication of
the maximum capacity in kWp as determined by the Minister for each launch
bidding process
competitive bidding process, shall be made public by means of a and
kWp capacity.
Government Notice published in the Gazette.
(1) The process shall be carried out through a Process.
competitive bidding process
Provided that the competitive bidding process shall be
compliant with the fundamental rules and principles of the Treaty on
the Functioning of the European Union regarding equality,
transparency, proportionality and prohibiting discrimination on
grounds of nationality and the European Commission’s Guidelines on
State Aid for environmental protection and energy 2014-2020.
(2) The invitation for bids shall also include terms and
conditions which shall constitute an integral part of the contract with
the successful bidder. The form of contract to be entered into shall
also be specified in the invitation for bids.
(1) The successful bidder shall be required to provide a Performance
performance bond to the Contracting Authority within one week from Bond.
the date of the Letter of Award. The value of the performance bond
shall be included in the invitation for bids of the relevant competitive
bidding process.
(2) Without prejudice to the terms and conditions applicable to
the relevant competitive bidding process, the performance bond shall
be forfeited by a bidder, inter alia, if the bidder fails to satisfy the
conditions in regulation 7.
(3) In the case when the capacity of an approved renewable
energy installation as installed and connected to the grid is lower than
the capacity allocated during the bidding process, the forfeiture of the
performance bond shall be in accordance with the terms and
conditions established for such purpose by the relevant competitive
bidding process.
Bids which are deemed as being administratively
compliant shall be ranked according to the bid price per kWh with the
lowest bid price per kWh being given the first preference. The bid
installation kWp capacity shall be selected pursuant to the
competitive bidding process, starting from the lowest bid offered, and
provided that the kWp available for allocation in the particular
competitive bidding process is not exceeded.
The letter of award to the successful bidder shall include,
but not be limited to, the following
(a)
details of the bidder;
(b)
awarded bid price per kWh;
(c)
capacity in kW and threshold on the units of
electricity for which the bid price per kWh may be paid in each
calendar year for the guaranteed period.
The Contracting Authority shall publish on its website the
results of each competitive bidding process, including the awarded
bid price per kWh for each successful bidder for each approved
renewable energy installation and the corresponding capacity in kWp,
as established in the competitive bidding process.
The successful bidder shall bear the costs of connection of
the approved renewable energy installation to the nearest suitable
point of connection to the distribution system. The costs for
connection to the distribution system shall be determined by the
distribution system operator in accordance with the Electricity Supply
Regulations.
(1) The letter of award issued to a successful bidder Permits.
pursuant to a competitive bidding process shall only grant to that
successful bidder the right to be paid the price per kWh and shall not
be, nor shall it be deemed to grant or constitute, an automatic
authorisation to construct an approved renewable energy installation
or give any right for the issue of any authorisation, licence or permit
which may be required. The successful bidder shall be responsible to
obtain any relevant permits, authorisations and licences within the
timeframes indicated in regulation 7. The successful bidder shall
submit applications for permits, authorisations and licences in
accordance with the applicable laws and procedures with a view to
obtaining such permits, authorisations and licences. Any cost related
to obtaining the required permits, authorisations, license shall be
borne by the successful bidder.
(2) The issue of the letter of award shall not grant the
successful bidder any right to damages or compensation if any of the
permits, authorisations and licences required are not issued for any
reason whatsoever. The performance bond shall be forfeited in favour
of the Contracting Authority in any such cases.
(1) The awarded bid price per kWh shall become Payment of bid
applicable as from the date of installation of the metering equipment price
awarded.
by the distribution system operator and shall continue to be applicable
for the duration of the guaranteed period.
(2) Payment of the awarded bid price per kWh shall be based
on actual meter readings obtained from the metering equipment
referred to in sub-regulation (1) and capped to a maximum kWp and
units of electricity according to the letter of award.
A competitive bidding process for the award of support for Frequency of
eligible renewable energy installations with capacity of 1000kWp or competitive
bidding process.
more shall be launched as a minimum on a yearly basis for such
capacity as indicated in the relevant competitive bidding process.
Without prejudice to the generality of the foregoing, the Wind
terms and conditions of a competitive bidding process made public installations.
and published in the Gazette, and applicable to wind installations
shall require as a pre-requisite in any such competitive bidding
process the issue of the applicable Planning Permit as may be
required by law.
The Public Contracts Review Board established by Appeals.
regulation 80 of the Public Procurement Regulations shall have S.L.174.04
jurisdiction to hear and determine complaints submitted by any
person having or having had an interest in competitive bidding
process made under these regulations and in accordance with the
B
procedures laid down in those regulations.
€0.90