Photovoltaic Installations) (Amendment No. 3) Regulations, 2017
Table of Provisions (9)
Statutory Text (9 Articles)
L.N. 120 of 2017
REGULATOR FOR ENERGY AND WATER SERVICES ACT
(CAP. 545)
Feed-in Tariffs Scheme (Electricity Generated from Solar
Photovoltaic Installations) (Amendment No. 3) Regulations, 2017
IN exercise of the powers conferred by article 37(1) of the
Regulator for Energy and Water Services Act, the Prime Minister,
after consultation with the Regulator for Energy and Water Services,
has made the following regulations
The title of these regulations is the Feed-in Tariffs Scheme
(Electricity Generated from Solar Photovoltaic Installations)
(Amendment No. 3) Regulations, 2017, and these regulations shall be
read and construed as one with the Feed-in Tariffs Scheme
(Electricity Generated from Solar Photovoltaic Installations)
Regulations, hereinafter referred to as "the principal regulations".
Regulation 2 of the principal regulations shall be amended
as follows
(a)
the definition "marginal cost per unit" shall be
deleted;
(b)
immediately after the definition of "premises
code", there shall be added the following new definition
" "proxy for the market price" means the average of
the estimated variable cost of meeting the demand forecast
for a given year from locally generated conventional and
imported electricity, with the demand assumption
excluding that portion of the forecast demand which is not
expected to be met by conventional and imported
electricity;".
In paragraphs (b) and (c) of sub-regulation (6) of
regulation 4 of the principal regulations, the words "marginal cost"
shall be substituted wherever they occur by the words "proxy for the
market price established under the Fourth Schedule".
Regulation 4A of the principal regulations shall be
amended as follows
(a)
the words "marginal cost of electricity" shall be
substituted by the words "proxy for the market price
established";
(b)
in the English version of the principal regulations,
in paragraph (b) thereof the words "marginal cost" shall be
deleted and substituted by the words "proxy for the market price
established"; and
(c)
in paragraph (d) (i) and (ii) thereof, the words
"marginal cost" shall be substituted by the words "proxy for the
market price established under the Fourth Schedule".
In regulation 6 of the principal regulations, the words Amends
"marginal cost per unit incurred by the distribution system operator as regulation
the principal
established in the Fourth Schedule" shall be substituted by the words regulations.
"proxy for the market price established under the Fourth Schedule".
In sub-regulation (2) of regulation 12 of the principal Amends
regulations, the words "marginal cost" shall be substituted by the regulation
the principal
words "proxy for the market price established under the Fourth regulations.
Schedule".
Immediately after regulation 4A of the principal Adds new
regulation 4B to
regulations there shall be added the following new regulation
the principal
regulations.
4B. Any installation operator, who in force
"Transitory
provision.
of the Feed-In Tariffs (Electricity Generated
From
Solar
Photovoltaic
Installations)
Regulations, or in force of these regulations, is
being paid or may be paid the marginal cost,
however so described, shall as from the entry into
force of this regulation, be paid the proxy for the
market price.".
The Fourth Schedule to the principal regulations shall be Substitutes the
Fourth Schedule
substituted by the following new Schedule
to the principal
regulations.
"FOURTH SCHEDULE
(Regulations 4, 4A, 6, 9, 12)
Electricity rate per kWh applicable for electricity generated and
exported to the distribution system
(a)
in the case referred to in regulation 4(6)(b) and 4
(6) (c); or
(b)
in the case referred to in regulation 4A; or
(c)
after the expiry of the period of guaranteed
payment of the feed in tariff; or
(d)
where the thresholds established in the Second
Schedule for the eligibility of the FIT are exceeded the rate shall
be determined to be the proxy for the market price for electricity
to be incurred by the distribution system operator for the
particular year as approved by the Regulator.
The Regulator may define which cost items may be
considered in the determination of the proxy for the market
The rate determined to be the proxy for the market price
for the year 2017 shall be of seven cents and twenty-five mils
(€0.07,25) per kWh.".
€0.27