211 tal-2016 - Ordni tal-2016 dwar in-Notifikazzjoni dwar Żvilupp
Table of Provisions (8)
Statutory Text (8 Articles)
L.N. 211 of 2016
DEVELOPMENT PLANNING ACT
(CAP. 552)
Development Notification Order, 2016
BY VIRTUE of the powers conferred by article 55 of the
Development Planning Act, the Planning Authority, with the
concurrence of the Parliamentary Secretary for Planning and
Simplification of Administrative Processes, has made the following
Order:-
The title of this Order is the Development Notification
Order, 2016
CLASSES OF PERMITTED DEVELOPMENT
(Regulation 3)
INDEX TO SCHEDULE I
Class 1 Alterations to existing buildings and development
within the curtilage of buildings
(i)
Internal alterations
(ii)
Alteration or replacement of apertures
(iii)
Water tanks and associated apparatus
(iv)
Solar panels and photovoltaic panels
(v)
Roof Structures
Class 2
Minor works
(i)
Front garden walls and similar walls around
gardens and recreational areas
(ii)
Boundary walls around undeveloped land abutting
a street
(iii)
Timber gates in existing openings
(iv) Erection or alteration of random dry-stone rubble
walls on existing agricultural land
(v)
Repair of existing boundary walls
(vi)
Repair of buildings or other structures
(vii) Surveillance and security equipment, and similar
small equipment
(viii) Painting of the exterior of a building
(ix)
Air conditioning units
(x)
Replacement or reconstruction of roofs
Class 3 Formation, laying out, alteration or improvement of
roads by Government agencies, Local Councils and other entities
appointed thereby
(i)
Roads and pavements within a planning scheme
(ii)
Widening, improvement or maintenance of existing
roads
(iii)
Improvement or alteration of junctions
(iv)
Traffic lights
(v) Embellishment or enhancement of roundabouts,
traffic islands and centre strips
Class 4
Minor infrastructural development
(i)
Lamp standards, public seats, litter bins, bollards,
barriers and similar structures
(ii) Posting boxes, automated teller machines and
vending machines
(iii)
Telephone boxes or booths
(iv)
Monuments and art installations
Class 5
Development related to public utility services
(i)
Repairs to services
(ii) Development below ground level for water supply,
sewerage, and laying of pipes and cables
(iii)
Installation of service lines to individual customers
(iv) Installation of booster stations, valve houses, meter
houses and switchgear houses
(v)
Sewage inspection chambers above ground level
(vi)
Storm water culverts
(vii) Infrastructural service ducts
(viii) Feeder or service pillars
Class 6
Development related to public transport
(i)
Signs for operation of route buses
(ii)
Passenger shelters and barriers
Class 7
Development related to telecommunications
(i)
Installation, maintenance
or
alterations
of
telecommunications apparatus
(ii)
Satellite antennas
Class 8
Development related to agriculture and fisheries
(i)
Maintenance of existing farm roads by the
Department of Agriculture
(ii) Placing of plant and machinery for the operation of
a fishing port
Class 9
Placing of machinery and structures for operations
(i)
Placing of
machinery
and
structures
for
development operations
Class 10 Temporary use of land
(i)
Temporary reversible use of land
(ii) The reversible use of land, by Government entities,
Local Councils and other public entities appointed thereby
Development related to aviation
(i)
Change of use of buildings within the perimeter of
Class 12 Lighting of buildings, structures and roads
(i)
The external lighting of buildings, structures and
Class 13 Mineral and geological exploration and surveying,
and environmental monitoring
(i)
Drilling of
boreholes,
seismic
surveys
and
archaeological surveys
(ii)
Temporary environmental monitoring stations
Class 14 Tented structures and Awnings
(i)
Installation of an awning
(ii)
Placing of small tents, tarpaulins or similar
Class 15 Beach management facilities
(i)
Hiring of beach furniture
Class 16 Development in Malta Industrial Parks and Malta
Enterprise Zones
(i)
The construction, re-development, alteration or
extension of an industrial unit
(ii) The construction, re-development, alteration or
extension of a unit
Class 17 Development by the Armed Forces of Malta
(i)
Development by the Armed Forces of Malta
Class 18 Development relating to Migration Matters
(i)
Development carried out by an entity responsible
for the provision of reception services
Class 19 Filming and Activities
(i)
Filming operations
(ii)
Occasional activities
(iii)
Offroading events
CLASS 1 - Alterations to existing buildings and development
within the curtilage of buildings
(i)
Internal alterations, excluding all works that would
(a)
increase the number of dwellings;
(b) increase the number of commercial outlets and floor
space;
(c)
increase the non-residential units;
(d)
change the use of buildings; and
(e)
require an increase in parking provisions
(ii) (a)
The replacement of apertures and security elements
relative to windows, doors, balconies (including timber balconies),
gates and other similar elements, including in scheduled buildings or
buildings which the Authority deems to have conservation value.
(b)
The provision of security bars, projecting wrought
iron windows or security windows.
(c)
The replacement of apertures and security elements
in scheduled buildings or buildings which the Authority deems to
have conservation value
Provided that such works in sub-paragraphs (a) and (b) do not
materially alter the character and, or context of the building and its
surroundings and for sub-paragraph (c) original wooden apertures and
balconies and wrought iron elements in scheduled buildings or
buildings which the Authority deems to have conservation value shall
be retained and restored and shall not be replaced if these are
considered to form part of the historic character and fabric of the
building and, or streetscape and are in a sufficiently good condition
that they can be restored.
(iii) Water tanks, with associated apparatus and the necessary
screening.
(iv) Solar panels and associated apparatus, and photovoltaic
panels and associated apparatus
Provided that for paragraphs (iii) and (iv) when located on
scheduled buildings or buildings older than seventy five years which
the Authority deems to have conservation value, the permitted
development shall be located within the envelope of the building or at
roof level, not exceeding the height of the parapet wall, but not on top
of a roof structure.
(v) Roof Structures which are setback six metres from the
front elevation and do not exceed thirty six square metres when
measured externally, in UCAs but not in ODZ nor on scheduled
buildings.
Only development under paragraphs (i), and (ii) and (v) shall be
subject to the notification procedure established in regulation 5(1)
and (3).
CLASS 2 - Minor Works
(i) The construction, reconstruction, maintenance, or
demolition, of front garden walls, or walls around gardens, or
recreational areas, excluding walls which are constructed in random
dry-stone rubble walls (sejjiegħ). Works shall be limited to the wall
itself without any substantial modification to a front garden, other
garden, vehicular parking or driveway.
(ii) Boundary walls around undeveloped land abutting a street.
(iii) Timber gates in existing legal openings located in ODZ.
(iv) The construction, alteration, or maintenance, of random
dry-stone rubble walls (sejjiegħ) on existing agricultural land, or
along a legally existing street, in accordance with the Rubble Walls
and Rural Structures (Conservation and Maintenance) Regulations
(S.L.552.01), subject to the following conditions
(a)
the wall shall not be higher than one metre twenty
centimetres above soil level on both sides;
(b)
in case of different levels between terraced land,
the wall shall not be higher than one metre twenty centimetres
above the higher soil level, and two metres forty centimetres
above the lower soil level;
(c)
the total demolition and reconstruction of existing
random dry-stone rubble walls (sejjiegħ) is not permitted and, in
the case of partial demolition and reconstruction, the area to be
replaced should be declared as unsafe by the perit;
(d)
for the construction of new walls, a single access
opening of not more than one metre twenty centimetres wide,
with a gate constructed in timber and not exceeding the height
of wall, is permitted;
(e)
new access openings on existing walls are not
permitted;
(f)
the construction of new walls shall not entail the
sub-division of agriculture land.
(v) The repair of existing boundary walls provided that such
works do not affect the height and character of the existing wall.
(vi) The repair of buildings or other structures, subject that
such works do not
(a)
constitute the complete or substantial demolition
and re-construction, or replacement, of buildings or structures;
(b)
materially alter the character and, or context of the
building or structures, and its surroundings.
(vii) The fixing of surveillance cameras, security equipment,
and other similar small-scale equipment, even on scheduled property.
(viii) The painting of the exterior of a building or work,
provided that
(a)
it is not for
purpose
of
advertisement,
announcement or direction;
(b)
it is in congruence with the streetscape.
(ix) Air conditioning units, unless located on any façade that
faces a road, or visible from a road.
(x) Replacement or reconstruction of roofs with no substantial
rebuilding of walls and not on scheduled property.
Only development under paragraph (vi), when located within
Scheduled Property, UCA, or ODZ, and development under
paragraphs (i), (iii) and (x) shall be subject to the notification
procedure established in article 5(1) and (3).
CLASS 3 - Formation, laying out, alteration or improvement of
roads by Government agencies, Local Councils and other entities
appointed thereby
(i) The formation or laying out of roads and pavements as
indicated in a planning scheme, and the alteration or creation of
pavements within a development boundary.
(ii) The widening, improvement or maintenance of an existing
road within the highway boundary.
(iii) The improvement or alteration of junctions, unless it
involves the alteration of a grade separated junction or a significant
alteration in the traffic direction.
(iv) The installation, modification or removal of traffic lights
and any other similar traffic management systems.
(v) The embellishment or enhancement of existing
roundabouts, existing traffic islands and, or existing centre strips,
provided that such embellishment or enhancement would not create
an obstruction to the view of, or a distraction to, persons using any
road used by vehicular traffic, so as to be likely to cause danger to
such persons
Provided that
(a)
it does not entail additional undeveloped land
outside the planned or existing highway boundary;
(b)
it does not affect the planning scheme boundary or
entails departure from the official alignment;
(c)
it does not entail direct or indirect damage to
existing historical buildings or monuments, archaeological
features including underground shelters, cisterns or water
galleries, rubble walls and natural stone paving; and
(d)
it includes all the necessary measures so that,
wherever possible
(i)
infrastructural
services
are
installed
underground without any introduction, installation or
attachment of overhead wiring on the site or its
surroundings; and
(ii)
existing overhead wiring and other
infrastructural services currently above ground are
relocated underground;
(e)
it is subject to prior written authorisation by
Transport Malta;
(f)
within Valletta, Floriana, Cottonera and areas
scheduled for their archaeological importance, excavation
works shall be carried out under the supervision of an
archaeologist appointed by the Superintendent of Cultural
Heritage.
Only development under paragraph (ii) where the existing road
and, or pavement are constructed in natural stone paving and
paragraph (iv) where works are on or attached to a building which in
itself is a scheduled property shall be subject to the notification
procedure established in regulation 5(1) and (3).
CLASS 4 - Minor infrastructural development
(i) The erection or construction, and the maintenance,
alteration or other improvement, of lamp standards, public seats,
small-scale litter bins or similar baskets serving public recreational
areas or walkways, bollards, barriers and similar works or structures
not in ODZ.
(ii) The installation or placing of posting boxes, self-service
machines or Automated Teller Machines, or vending machines that
are in line with approved policies and guidelines not in ODZ.
(iii) The erection of telephone boxes or booths, provided that
the structure shall not exceed one meter squared in area measured
externally and a height of two metres and forty centimetres measured
externally not in ODZ.
(iv) The erection, construction, or installation of monuments
and art installations within public open spaces, excluding dismantling
or relocation, not in ODZ and provided that where the highway
boundary or a pavement are affected the development is subject to
prior written authorisation by Transport Malta and in all
circumstances subject to prior authorisation by the Malta Council for
Culture and the Arts.
Only development under paragraphs (i), (ii) and (iii) shall be
subject to the notification procedure established in regulation 5(1)
and (3).
CLASS 5 - Development related to public utility services
(i) The carrying out of any works for the purpose of
inspecting, maintaining, repairing or renewing any existing sewer,
main, pipe, cable or other apparatus, including the breaking open of
any made-up ground or soil for that purpose, provided that the land is
immediately and completely returned to its original condition once
the works have been completed.
(ii) Any development below ground
level,
including
excavation, which is required in connection with
(a)
the supply of water or for conserving, monitoring,
redistributing or augmenting water resources;
(b)
the provision, improvement, maintenance or repair
of a sewer or sewerage connection or associated apparatus; or
(c)
the maintenance or repair of an outfall pipe, or of a
sewage treatment plant, or of an ancillary reservoir; or
(d)
the laying underground of pipes, cables or any
other apparatus.
The land surface must be immediately and completely returned
to its original condition once the works have been completed.
(iii) The installation of service lines to individual customers
from a service line, including any excavations for such purpose,
provided that the land is immediately and completely returned to its
original condition once the works have been completed.
(iv) The installation, in a public infrastructural network, of a
booster station, valve house, meter house or switchgear house, unless
it involves any development above ground level in an UCA or ODZ.
(v) The construction, provision or improvement of sewage
inspection chambers above ground level unless such chamber
exceeds
(a)
one square metre in area measured externally; or
(b)
one metre in height measured externally above
ground level. If located ODZ, structures above ground level are
to be suitably designed to mitigate their visual impact on the
surrounding environment.
(vi) The provision, construction and renewing of any storm
water culvert or water channel, storm water drain, rainwater spout or
overflow pipe, or storm water reservoir that is altogether located
under an existing road carriageway or pavement or similar paved
area. The development must not involve channelisation of natural
watercourses or valley beds.
(vii) The provision, excavation, extension or enlargement of
service ducts for the improvement, rationalisation, management or
inspection of underground services, provided that the roof of the duct
is in keeping with the surrounding land surface and, if the site lies
ODZ, it shall be suitably finished to compliment the surrounding
environment.
(viii) The installation of feeder or service pillars, but not poles
or masts, provided that where located on a pavement, these shall
allow at least one metre of unobstructed pavement width
Provided that
(a)
it does not entail additional undeveloped land
outside the planned or existing highway boundary;
(b)
it does not entail direct or indirect damage to
existing historical buildings or monuments, archaeological
features including underground shelters, cisterns or water
galleries, rubble walls and natural stone paving; and
(c)
it includes all the necessary measures so that,
wherever possible
(aa) infrastructural
services
are
installed
underground without any introduction, installation or
attachment of overhead wiring on the site or its
surroundings; and
(bb) existing overhead wiring and other
infrastructural services currently above ground are
relocated underground;
(d)
within Valletta, Floriana, Cottonera and areas
scheduled for their archaeological importance, excavation
works shall be carried out under the supervision of an
archaeologist appointed by the Superintendent of Cultural
Heritage.
Development under this Class, when it is located in a UCA,
ODZ and in scheduled property or within thirty metres from a
scheduled property or in a designated area, shall be subject to the
notification procedure established in article 5(1) and (3).
CLASS 6 – Development related to public transport
(i) The installation of signs which do not exceed fifty square
centimetres in area, in connection with the operation of route buses.
(ii) The construction or replacement of existing passenger
shelters including advertisement as part of the passenger shelter, or
barriers for the control of people waiting to enter a route bus, except
where the development involves any road widening or any
encroachment onto land that is not a road carriageway, pavement or
similar paved area.
CLASS 7 - Development related to telecommunications
(i) The installation, maintenance or alteration of any
telecommunications apparatus unless such development is located
ODZ or on scheduled property.
Provided that the development does not involve
(a)
the erection or alteration of buildings; or
(b)
the introduction of poles and masts to support
overhead wiring and or structures with a height exceeding 10
metres to support the permitted apparatus;
(c)
direct or indirect damage to existing scheduled
buildings or monuments, archaeological features including
underground shelters, cisterns or water galleries, rubble walls
and natural stone paving.
(ii) A satellite antenna, unless in ODZ or on scheduled
property and provided that it is not visible from a public road.
CLASS 8 - Development related to agriculture and fisheries
(i) The maintenance of existing farm roads carried out by or
on behalf of the Department of Agriculture: Provided that such works
do not
(a)
involve encroachment beyond the pre-existing road
carriageway, or deposition of material beyond the road
carriageway, or levelling or reclamation of land; or
(b)
involve the expansion or extension or leveling or
widening or re-engineering or surfacing with concrete.
(ii) Placing of permanent plant and machinery required for the
operation of a designated fishing port subject to the prior approval of
the Fisheries Department.
Only development under paragraph (ii) shall be subject to the
notification procedure established in article 5(1) and (3).
CLASS 9 - Placing of machinery and structures for the duration
of construction works
(i) The placing on land of a building, moveable structure,
works, plant or machinery required temporarily required in
connection with, and for the duration of, operations on, in, under or
over that land or on land immediately adjoining it, in connection with
or for the purpose of development permitted by a development
permission, or by any other permission by the Authority, or by this
Order, including temporary batching plants, subject that such works
shall
(a)
not apply to mining or quarrying operations; and
(b)
in the case where such works would create an
obstruction to an existing pedestrian passage way, all the
necessary measures shall be taken to provide for a safe
alternative passage way as directed by the competent authority;
and
(c)
after completion of works, such temporary
installation shall be completely removed and the land shall be
completely restored to its pristine condition;
(d)
such use does not entail direct or indirect damage
to existing historical buildings or monuments, archaeological
features including underground shelters, cisterns or water
galleries, rubble walls and natural stone paving.
Development under this Class, where the operations are going to
take place within the confines of a site which is a scheduled property,
or in a designated area, or on land that is located ODZ and, or when
the operations are going to take place beyond the confines of the site
covered the development permission shall be subject to the
notification procedure established in article 5(1) and 3).
CLASS 10 - Temporary use of Land
(i) The reversible use of land, as well as any temporary
structures required for such use, for not more than thirty days in any
one calendar year, whether the permitted use is requested or applied
for by the same person or by different persons, provided that the
proposed use does not have any negative impacts on the relative site
and its surroundings and the land is fully restored to its pristine
condition and any structure removed within ten days from the expiry
of such thirty-day period.
For any land located within a distance of 100 meters from the
same land originally permitted for a specific temporary use in terms
of this sub-paragraph, the permission shall be automatically renewed
for the same or similar use as originally permitted provided that
(a)
any extension may not be granted for a period of
more than thirty days and no more than three extensions may be
granted in any given calendar year. The extended period need
not necessarily refer to the thirty day period immediately
following the previous period; and
(b)
the Authority is satisfied that the extension relates
to a site which lies within a development zone; and the proposed
use does not have any negative impacts on the relative site or its
surroundings and any structure used on the relative site is easily
demountable; and
(c)
any land in relation to which an extension has been
permitted in terms of this sub-paragraph shall be fully restored
to its pristine condition and any structure removed within ten
days from the expiry of each permitted period unless the
extended period immediately follows the previous period, in
which case the relative restoration and removal of any structure
shall be carried out within ten days from the last permitted
period.
(ii) The reversible use of land by Government entities, Local
Councils and other public entities appointed thereby, for the
temporary use of land for cultural and social purposes as well as any
temporary structures required for such use for not more than four
calendar months yearly, provided that the land used is fully restored
to its pristine condition and any structures are removed within ten
days from the expiry of such period, except for sites located in
scheduled property
Provided that the use of land is not permitted if such use is for a
caravan site or for camping, or for off-road vehicle, motor car and
motorcycle racing or rallying, or for practising for these events and
activities
Provided further that the development described shall only be
permitted if
(a)
any temporary structure required for such use
would not impair visibility at a road junction or otherwise pose
a threat to the safety of pedestrians or vehicular traffic;
(b)
such use does not entail direct or indirect damage
to existing historical buildings or monuments, archaeological or
natural features including underground shelters, cisterns or
water galleries, rubble walls and natural stone paving;
(c)
waste collection, waste disposal facilities, and any
necessary mobile sanitary facilities, as required by law and
which do not involve any non-reversible interventions, are
available on site prior to the commencement of use;
Development under this Class shall be subject to the notification
procedure established in article 5(1) and (3). For development under
paragraph (i), the first notification shall be automatically renewed
provided the site remains unchanged, unless the Authority decides
that the temporary use should cease prior to the expiry period and
notifies the applicant accordingly. The commencement date and the
expiry date shall be stated in the applicant’s request and the
confirmation by the Authority, and the limited time is not
automatically renewed annually nor extended in perpetuity.
CLASS 11 - Development related to aviation
(i)
Changes to the use of buildings within the perimeter of an
airport, for purposes connected with air transport services or other
flying activities at that airport.
CLASS 12 - Lighting of buildings, structures and roads
(i) the external lighting of buildings, structures and roads
provided that the development is not permitted where
(a)
it is incompatible with the character of the location
and/or create unacceptable light pollution; or
(b)
in the case of street lighting ODZ, involves lighting
beyond the street itself and/or cause unacceptable light pollution
in an area that should be kept free from artificial nocturnal
lighting or compromise the conservation of important flora,
fauna or ecosystems;
(c)
it involves the illumination of any sign or
advertisement, or such illumination constitutes its primary
purpose; or
(d)
it involves an area larger than a building or
structure;
(e)
it involves a scheduled property.
For the purposes of this Class, temporary lighting of buildings
and structures, for festivities and similar events, shall not be deemed
to constitute development.
Development under this Class, where the site or lighting
equipment of buildings and structures lies in a UCA or ODZ or in a
designated area or in or within 30 metres of a scheduled property,
shall be subject to the notification procedure established in article
5(1) and (3).
CLASS 13 - Mineral and geological exploration and surveying,
and environmental monitoring
(i)
Development on any land consisting of
(a)
the drilling of boreholes other than for groundwater
abstraction; or
(b)
the carrying out of seismic surveys;
(c)
the carrying out of archaeological surveys under
the supervision of the Superintendent of Cultural Heritage
Provided that the land is immediately and completely restored to
its original state once the works have been completed.
(ii) The placing of equipment or temporary stations for
environmental, atmospheric or marine study and monitoring, even if
in or within 30 metres of a scheduled property or in a designated area,
for not more than one calendar year, and on condition that
(a)
no damage or other significant disturbance to the
site or the surrounding environment is entailed;
(b)
no material is placed of on garigue or on exposed
rockfaces in a manner that could foreseeably result in damage
to, or scarring of, the land surface; and
(c)
the equipment or station is completely removed
and the land is fully returned to its pristine condition once the
station ceases to operate.
Within Valletta, Floriana, Cottonera and areas scheduled for
their archaeological importance, excavation works shall be carried
out under the supervision of an archaeologist appointed by the
Superintendent of Cultural Heritage.
CLASS 14 - Tented Structures and Awnings
(i) the installation of an awning fixed on the exterior of a
building, not being a Scheduled Property, located within Town
Centre, Local Centre, Commercial Area, Entertainment Priority Area,
or Tourism Zone as indicated in the respective Local Plan or the
Interim Retail Planning Guidance (2004) but outside Mdina and
Cittadella (Rabat, Gozo).
(ii) The placement of small tents, tarpaulins, or similar
structures to provide environmental control or privacy, not being a
scheduled property provided that such works are not visible from
outside the building.
Development under paragraph (i) where the site lies within
UCA, ODZ, or a designated area, shall be subject to the notification
procedure established in article 5(1) and (3).
CLASS 15 - Beach management facilities
(i) The temporary use of land for the hiring of beach furniture
(a)
the land to be occupied as the fixed point for hiring
of beach furniture shall not exceed an area of 9m 2 ;
(b)
no structures, whether permanent or temporary, are
to be placed or erected on the site;
(c)
the land shall be fully restored to its original state
between sunset and sunrise; and
(d)
no land, on which the beach furniture is placed or
erected, is occupied, designated, or in any manner delineated for
the exclusive use of an operator
Provided that the development shall only be permitted if
(a)
the site is located on a designated beach as
determined by the Malta Tourism Authority;
(b)
specific authorisation by the Malta Tourism
Authority is submitted, by the applicant to the Authority, as part
of the notification procedure.
Development under this Class shall be subject to the notification
procedure established in article 5(1) and (3).
CLASS 16 - Development in Malta Industrial Parks and Malta
Enterprise Zones
(i) The construction, re-development, alteration or extension
of an industrial unit or a unit for any purposes ancillary to the main
industrial unit within Malta Industrial Parks and Malta Enterprise
Zones, including associated signs and adverts, provided that
(a)
the predominant use of the industrial unit falls
within one of the industrial, storage and distribution use Classes
of the Use Classes Order, and includes any other use which is
ancillary to the predominant use;
(b)
the proposed development does not result in an
industrial unit higher than fifteen metres measured from the
highest street level along the external perimeter of the unit;
(c)
the unit does not replace communal landscaped
areas or communal car parking spaces;
(d)
the proposed development, including the creation
or formation of a new vehicular access or any changes to the
highway boundary, shall have the prior approval of the Malta
Industrial Parks or Malta Enterprise, where relevant;
(e)
the height of the industrial unit and the materials
shall have the prior approval of the authority responsible for
Civil Aviation, where deemed relevant by the Authority.
(ii) The construction, re-development, alteration or extension
of a unit for any purpose ancillary to the main industrial use within
Malta Industrial Parks and Malta Enterprise Zones, including
associated signs and adverts, provided that paragraphs (a) to (e) under
Class (i) of this Class shall mutatis mutandis apply.
Development under this Class shall be subject to the notification
procedure established in article 5(1) and (3).
Class 17 - Development by the Armed Forces of Malta
(i) Development carried out by the Armed Forces of Malta on
land under the operational control of the same Armed Forces of
Malta, provided that
(a)
when the development is located in designated
areas or scheduled property, it shall be subject to prior clearance
by the Superintendent of Cultural Heritage and by the
competent authority responsible for the protection of the natural
environment;
(b)
the development is recommended by the
Consultative Committee on the Development by the Armed
Forces of Malta set up by the Minister to provide advice on the
acceptability or otherwise of development proposals by the
Armed Forces of Malta. If, for any reason, the Consultative
Committee is not constituted, the proposed development is
recommended by the Minister responsible for the Armed Forces
of Malta.
Development under this Class shall be subject to the notification
procedure set out in article 5(1) and (3). However such notification
procedure is not required where in the opinion of the Minister
responsible for the Armed Forces, the development is urgently
required for national security reasons and the Authority is informed
accordingly.
Class 18 - Development relating to Migration Matters
(i) Development carried out by an entity responsible for the
provision of reception services including in particular for
beneficiaries of international protection and asylum seekers provided
that if the development is located in designated areas or scheduled
property, it shall be subject to prior clearance by the Superintendent
of Cultural Heritage and by the competent authority responsible for
the protection of the natural environment.
Development under this Class shall be subject to the notification
procedure set out in article 5(1) and (3). However such notification
procedure is not required where in the opinion of the Minister
responsible for Immigration, the development is urgently required for
humanitarian, security or other relevant reasons and the Authority is
informed accordingly.
Class 19 - Filming and Activities
(i) Filming operations including the construction or
installation of any ancillary, temporary structures and/or equipment
on the site, provided that all constructions and installations are
completely removed from the site, and the site is fully reinstated to its
pristine condition, prior to the expiry of the time period allowed for
the operations.
(ii) Occasional activities, excluding scientific research and
occasional activities which are not considered as development in
terms of the Act, for not more than one calendar week by the same
person, company or organisation including the construction or
installation of any ancillary structures and/or equipment on the site
provided that these are completely removed from the site by the
permitted time of cessation of the activity.
(iii) Offroading events in a locality which is marked as an
offroading site by means of signs approved under the Traffic Signs
and Carriageway Markings Regulations
Provided that
(a)
the Environment and Resources Authority shall be
consulted by the Authority upon receipt of the notification
request and the Environment and Resources Authority shall
reply within the period specified in the consultation notice
which shall in no case be less than 7 days and in case of no
reply, the Environment and Resources Authority shall be
deemed as having no objection to the proposal;
(b)
when an authorisation or an appropriate assessment
is required under the Flora, Fauna and Natural Habitats
Protection Regulations (S.L. 549.44) the provisions of article
5(3) which require the Authority to respond in writing to a
notification within thirty days from the validation of the
notification shall not apply;
(c)
the Authority may impose conditions, including
Bank Guarantees and Planning Contributions as set out in the
Act, it deems appropriate in its decision notice to safeguard any
interest of acknowledged importance.
Development under this Class shall be subject to the notification
procedure established in article 5(1) and (3).
(1)
In this Order, unless the context otherwise requires
"the Act" means the Development Planning Act;
"the Authority" means the Planning Board of the Planning
Authority;
"balconies improvement scheme" means a scheme with this
name, or any such scheme, for the financial support of the repair and
replacement of timber balconies in specific localities;
"calendar year" means a period of twelve months beginning
with the day on which the development or use or any intervention
connected therewith is first begun, according to whichever is the
earliest;
"designated areas" means sites and areas identified by the
Strategic Plan for the Environment and Development or Local Plan
policies, or other planning policies, for protection, conservation or
preservation, including areas of archaeological, ecological,
geological, geomorphological, hydrological, palaeontological,
architectural, historic, artistic, or antiquarian importance, or of natural
beauty, or scientific interest, together with any specific areas
designated under the Act. Urban Conservation Areas are excluded
from this definition, without prejudice to any designated areas
overlapping onto such Urban Conservation Areas;
"Development Control Design Policy, Guidance and Standards"
means Development Control Design Policy, Guidance and Standards
2015, without prejudice to any subsequent amendments or revisions
thereto as may be approved by the Authority;
"development plan" means and includes the Strategic Plan for
Environment and Development, subject plans, local plans, action
plans and development briefs;
"dwelling" means a single family dwelling unit including, but
not limited to, a terraced house, villa, bungalow, flat, a receded
dwelling, penthouse, maisonette or basement permitted to be used for
residential purposes in terms of currently approved Development
Control Design Policy, Guidance and Standards;
"environmental impact assessment" means an environmental
planning statement carried out in accordance with the Environment Cap. 549.
Protection Act;
"environmental planning statement" means an environmental
planning statement carried out in accordance with the Environment
Protection Act;
"existing agricultural holding" means land currently and
lawfully used for cultivation at the time the reservoir or pump
chamber is constructed;
"footprint" means the space contained within the external walls
of a building at ground floor level, including internal yards, shafts,
terraces or courtyards totally enclosed or surrounded by the building,
but excluding terraces, backyards, yards and pool decks not totally
enclosed or surrounded by the building;
"grade separated junction" means a junction where two or more
roads cross over each other at more than one level;
"highway boundary" means land which consists of an existing
road, street, square, court, alley, lane, bridge or footway;
"listed building" means a building which is itself a designated
area;
"material" includes waste, refuse, rubble and any soil imported
onto, or deposited on, the land;
"offroading" means any type of driving, manoeuvring or
parking with a motor vehicle not on a road, except for the purpose of
agriculture, maintenance of services and, or public works, or of law
enforcement and the keeping of good order;
"offroading" event" means any kind of training, racing or
rallying of an "offroading" type by a motor vehicle which are
organized by any person, or by a society or body of persons;
"operational land" or "operational building" means land or a
building used or required in connection with the movement or
maintenance of aircraft, or with the embarking, disembarking,
loading, discharge or transport of passengers, goods or livestock at an
airport, and is land or a building owned by or under the control of the
relevant airport operator;
"Outside Development Zone", hereinafter referred to as ODZ,
means land outside the boundary for development as approved by
Parliament in 2006;
"planning scheme" means a planning scheme made and
approved in accordance with the Building Permits (Temporary
Provisions) Act, 1988;
"public utility services" means and includes works related to
water distribution, sewerage and storm water undertakings and
electricity and telecommunications undertakings;
"ridge" means the edge of a hill or plateau, where relatively flat
or gently sloping land gives way to a valley side, hillside, escarpment,
cliff or other comparably distinct slope;
"route bus" means a vehicle constructed principally for the
carriage of seated passengers and with areas for standing passengers
to allow frequent passenger movement, licensed to carry passengers
for hire or reward and which is registered to perform scheduled trips
with the Central Office for Scheduled Bus Transport Services;
"same style, design, and materials" means the style and design,
and the type, form and colour of the materials, used in the works
which are to be replaced and "same style" or "different style" shall be
construed accordingly;
"scheduled property" means every area, building, structure,
remains, rock formation or other geological feature, excavation or
cavity, individual tree or group of trees or woodland scheduled in
terms of articles 57 and 58 of the Act. For the purposes of this Order,
any land designated or declared as a Special Area of Conservation or
otherwise declared as protected under the Environment Protection
Act shall be treated in the same manner as scheduled property;
"scheme for traffic management" means a scheme including any
works or operations for the purpose of controlling, affecting or
altering, the direction, rate of flow, and means of movement, of
vehicular and pedestrian traffic, and includes, but is not limited to, the
alteration of road junctions or kerblines, the parking of vehicles,
restrictions on parking, loading and unloading, pedestrianisation, and
the installation of traffic lights and pedestrian crossings and any other
electronic traffic control devices;
"temporary" means any non-permanent structure or use lasting
for a limited time not exceeding thirty days, unless otherwise stated in
this Order, and which does not involve any non-reversible
intervention;
"Urban Conservation Area", hereinafter referred to as UCA,
means a historic area (village core) as identified in a planning scheme
or local plan or other currently approved planning policies.
(2) In this Order, words and expressions that are not otherwise
defined in this Order and are defined in the Act shall have the same
meaning as they have in the Act.
(3) (a)
In this Order, wherever reference is made to a
period of thirty days, such period shall be deemed as excluding the
period of shutdown of the Planning Authority offices.
(b)
For the purposes of this Order, the period of S.L. 552.13
shutdown of the Authority offices shall be that period established by
Schedule 4 of the Development Planning (Procedure for Applications
and their Determination) Regulations.
(4) (a)
With reference to any scheduled property that
already incorporates a protective buffer zone, and Areas of High
Landscape Value, any buffer distance of thirty metres mentioned in
the Schedules to this Order shall not apply.
(b)
In the case of an already existing building on
property that is not ODZ and that is scheduled or designated solely on
the basis of features located underground, and if the new development
is located entirely above ground, the notification procedure
established in article 5(1) and (3) shall replace any restriction that
would otherwise be entailed by such scheduling or designation, and
the provisions of article 5(5) shall not apply.
(c)
In the case of property that is not ODZ and that is
scheduled or designated solely on the basis of landscape value, any
restriction on permitted development that is entailed by such
scheduling or designation shall not apply in respect of -
(i) trenching operations or other underground
works which do not permanently affect the land surface,
provided that the land is completely and immediately
returned to its original condition once the works have been
completed; and
(ii) internal alterations that do not affect the
external appearance of the building. The notification
procedure established in article 5(1) and (3) shall apply,
and the provisions of article 5(5) shall not apply.
(d)
Wherever there is a difference in opinion between
the Authority and any other party, or any need for interpretation, as to
whether a development -
(i)
is aesthetically or otherwise compatible with its
location; or
(ii)
affects or alters materially the character and, or
Permitted development and, or the context of the building or site
and its surroundings; or
(iii)
meets any requirement of this Order, whether
explicit or implied,
the opinion of the Authority shall prevail.
Malta Airport Boundary
€2.88
(1)
Development permission is hereby granted for the
Classes of development described in Schedule I, subject to the
Sanitary Regulations, the relevant provisions of the Development
Control Design Policy, Guidance and Standards, the Rural Policy and
Design Guidance and all other relevant approved plans and policies
under the Act, exceptions, conditions, restrictions, rules, limitations
and exclusions. The notification procedure in article 5(1) and (3) shall
be required for the Classes of development described in Schedule I
only where so provided in the same Schedule I.
(2) The granting of such a permission shall not imply, whether
directly or indirectly, permission for any other development, ancillary
to or even indispensable or inevitable for the proper execution of the
permitted development, nor does such a permission exempt from any
other requirement according to law or consent from third parties, nor
exempt from liability or responsibility any person contravening any
provision of law, whether applicable during the execution of the
permission or subsequent thereto or as consequential, involuntary
damage caused.
(3) The permission under sub-article (1) shall not dispense
from the requirement of any other permission, licenses or consent as
required by law and is without prejudice to any conditions, limitations
and exclusions which may be imposed by the public health authorities
and other competent entities.
Nothing in this Order shall permit development
that is contrary to, or would in any way prejudice -
(i) any condition or limitation imposed by any
development permission granted on an application made in
accordance with Part VII of the Act, unless such
development is permitted through a change in policy and
does not prejudice any site specific safeguard for which
such conditions or limitations were imposed; or
(ii) any condition or limitation imposed by a
clearance or license issued in accordance with the Act; or
(iii) a decision taken on any application or request
for such permit, clearance or licence.
(b)
Nothing in this Order shall permit development
(i) is already proposed in an application made in
accordance with Part VII of the Act, which is still being
processed, amended, reconsidered or appealed in
accordance with the Act; or
(ii) would prejudice the merits
of
such
processing, reconsideration or appeal, or
(iii) would prejudice the merits of a request for any
clearance or license required by the Act, or would
prejudice the merits of an appeal from a decision thereon.
(5) The permission granted by sub-regulation (1) shall not
authorize any development which -
(a)
requires or involves the formation, laying out,
material widening, expansion, extension or re-engineering of a
means of access to an existing road. This exclusion does not
apply with regard to development permitted by Class 3 and
Class 16 of Schedule I; or
(b)
creates an obstruction to the view of, or a
distraction to, persons using any road used by vehicular traffic,
so as to be likely to cause danger to such persons; or
(c)
requires an environmental impact assessment, an
appropriate assessment, a traffic impact statement, or any other
assessment or report required by the Act or any other
legislation;
(d)
in the case of any works connected with the
development, involve or entail the demolition of, or could
foreseeably cause direct or indirect damage to -
(i) any wall constructed in random rubble
(sejjiegħ) or random uniform rubble (laqx); or
(ii) any dry-stone huts (giren and similar
structures) or any other structures protected under the Act;
or
(iii) underground infrastructure; or
(iv) caves; or
(v)
fossiliferous or infilled fissures (dagħbien);
or
(vi) archaeological features; or
(vii) existing historical buildings or monuments, or
archaeological features and natural stone paving; or
(viii) cisterns or water galleries;
(e)
entails the destruction, uprooting or damage to
existing trees, unless such works have been approved by the
competent authorities;
(f)
involves the hacking, or drastic cleaning of
stonework by means of grit-blasting, high-pressure water jets,
compressed air, extensive sanding or abrasion, or other similar
interventions that would adversely affect any building (or
structure) of historic value or cultural heritage value.
(6) Any works permitted by sub-article (1) on scheduled
buildings or buildings which the Authority deems to have
conservation value shall be carried out strictly in accordance with
conservation and restoration methodologies established by the
Authority in official guiding documents and under the supervision of
a restoration architect.
If the Authority is of the opinion that development
described in Schedule I should not be carried out unless permission is
granted for it on an application, the Authority may by notice in the
Gazette direct that the permission granted by article 3 shall cease to
apply to the development.
(1)
Where provided in this Order, development shall Notification
be notified to the Authority prior to the commencement of any work, procedure.
on the form provided by the Authority. The Authority may require
different forms for different classes of permitted development and
different forms may not require all the information listed under
paragraphs (a) to (h). This form shall be accompanied by: three copies
of all the necessary plans and elevations; two good-quality colour
photographs properly representative of the site; and other relevant
documentation as provided in this Order or as the Authority may
deem necessary, so that the details submitted to the Authority shall
clearly and correctly identify
(a)
the perit in charge;
(b)
the applicant;
(c)
the precise location and full extent of the
applicant’s property, and the applicant’s title over the property.
Where considered necessary by the Authority, these shall be
confirmed by a copy of the deed showing the respective title;
(d)
the full nature and full extent of the works;
(e)
the
Class
of
Schedule
I
permitting
such
development;
(f)
all previous permits, applications and notifications
affecting the applicant’s property;
(g)
any required approval by other relevant public
authorities, as specified in this Order. This shall include an
authorisation by the competent authority, accompanied by a
clear site plan (and any other relevant documents) also stamped
and endorsed by the competent authority and cross-referred to
the authorisation; and
(h)
access to the site, indicated on a location map, if
the site does not abut on a public street.
(2) A notification may cover works which fall into more than
one Class or paragraph within a Class, where these are to be carried
out on the same site, except where otherwise provided in this Order.
(3) Where a notification is required under sub-article (1) and
without prejudice to any applicable provisions of this Order, the
applicant shall comply with the notification procedure established in
sub-article (1) and the Authority shall respond by an electronic means
of communication in writing to the notification within thirty days
from the validation of the notification.
(4) The Authority shall return one endorsed copy of all the
plans submitted, endorsed clearly indicating whether or not the works
are permitted. In the event of any discrepancy between any approved
drawings and the relevant provisions of this Order as communicated
in the Authority’s response, the latter shall prevail.
(5) If the works are permitted, such confirmation by the
Authority shall be valid for a period of one calendar year
commencing on the date on which the official notice by the Authority
is issued or, in the absence of such notice, on the date of expiry of the
aforesaid thirty days. If the works are not permitted, the Authority
shall give detailed reasons for such a decision.
(6) Where development has been carried out without the
notification required in accordance with sub-article (1), and that
development complies fully with the relevant exceptions, limitations
and conditions of this Order, the notification of that development
shall be treated as though it were a prior notification in accordance
with sub-article (1), except where otherwise provided in this Order.
(7) Where development has been carried out without the
notification required in accordance with sub-article (1), or a
notification has been made and the Authority has not responded to the
notification within thirty days from the validation of the notification,
and that development -
(a)
runs counter to policies or plans or legislation
approved according to the Act or the Environment Protection
Act: or
(b)
is not correctly, completely and unequivocally
reflected in the notification,
the Authority shall still have the right to stop works and, or to take
enforcement or other action, in accordance with the Act.
(8) Where development is carried out after the permit validity
stipulated in this regulation has expired, or after the Development
Order under which it is permitted has been repealed, the Authority
shall still have the right to stop works and, or to take enforcement or
other action, in accordance with the Act.
(9) In the case of development that involves or entails
trenching operations, the applicant or his appointed contractor shall
apply for trenching permission as the Authority may from time to
time establish. This provision shall also cover interventions for the
provision, repair, replacement or maintenance of an individual
domestic or similar connection to existing public infrastructure
services. An application for trenching permission shall be considered
as if it were a notification in accordance with sub-article (1) if
(a)
it is submitted to the Authority and satisfies the
conditions established in sub-article (1)(b), (d) and (g); and
(b)
the works are located altogether under a legally
existing road or legally existing pavement. The Authority’s
electronic reply to such application shall be treated as a written
reply to the notification according to sub-article (3), and all the
other provisions of this regulation shall apply.