Regulations, 2015
Table of Provisions (16)
Statutory Text (16 Articles)
L.N. 170 of 2015
MALTA RESOURCES AUTHORITY ACT
(CAP. 423)
Sale of Electricity generated from Cogeneration Units
Regulations, 2015
IN exercise of the powers conferred by article 28(1) of the Malta
Resources Authority Act, the Minister for Energy and Health, after
consultation with the Malta Resources Authority, has made the
following regulations:-
(1)
The title of these regulations is the Sale of Citation and
purpose.
Electricity Generated from Cogeneration Units Regulations, 2015.
(2) The purpose of these regulations is to regulate the sale of
electricity generated from cogeneration units and supplied to the
distribution system operator.
(Regulation 7)
Total maximum cogeneration unit electricity capacity MWe that
may be approved for the payment of the marginal cost per annum for
any electricity generated and sold to the distribution system operator
from such cogeneration unit capacity shall be 3MWe each year.
(1)
Unless otherwise stated in these regulations, Interpretation.
the definitions in the Act shall apply.
(2) In these regulations, unless the context otherwise requires
"the Act" means the Malta Resources Authority Act;
"annual", "annum" or "year" means the period of time
commencing on the 1st January and ending on the 31st December of
each year as prescribed in the Second Schedule;
"the Authority" means the Malta Resources Authority as
established by the Act;
"change of use of premises" means the change in the
classification of a premises in terms of these regulations whether
domestic or residential or non-residential or institutional household;
"co-generation" means the simultaneous generation in one
process of thermal energy and electrical or mechanical energy;
"cogeneration unit" means a unit that is able to operate in
cogeneration mode;
"commissioned" means the first time a cogeneration unit is put
into operation, following the establishment of operational readiness;
"consumed on site" means consumed on the same premises
where the cogeneration unit is installed;
"distribution" means the transport of electricity on high voltage,
medium voltage and low voltage distribution systems with a view to
its delivery to consumers, but not including supply;
"distribution system" means all the interconnected technical
facilities used for conveying electricity to final customers;
"distribution system operator" means a person responsible for
operating, ensuring the maintenance of and, if necessary, developing
the distribution system in a given area and, where applicable, its
interconnections with other systems and for ensuring the long-term
ability of the system to meet reasonable demands for the distribution
of electricity;
"domestic premises" means premises which include private
dwellings with no persons registered with the distribution system
operator as residing in them such as second homes, or private garages
and common areas including roofs, stairs, terraces, gardens to
buildings which are used solely for private dwellings;
"electricity from cogeneration" means electricity generated in a
process linked to the production of useful heat and calculated in
accordance with the methodology laid down in the First Schedule of
the Energy Efficiency and Cogeneration Regulations;
"installation operator" means the holder of the licence to
generate electricity from the cogeneration unit;
"institutional households" shall include the following premises
(a)
healthcare institutions such as premises used as a
hospital, nursing home or as any institution providing medical
or nursing care;
(b)
institutions for retired, elderly or disabled persons,
including premises used as a home for the retired or elderly
persons or persons with any disability;
(c)
educational institutions including premises used as
a boarding school or for similar purposes;
(d)
care institutions including premises used as
orphanages, shelter homes, open centres for refugees or for
similar purposes;
(e)
religious institutions including premises used
as convents, retreat houses, or for similar purposes;
(f)
military institutions such as military barracks;
(g)
other institutions including premises used as
boarding houses, penal or correctional facilities or for similar
purposes;
"kVAh" means kilo Volt Ampere hour;
"kW" means kilo Watt;
"kWh" means kilo Watt hours;
"marginal cost per KWh" means the additional cost of
producing one more unit as prescribed in the Second Schedule;
"metering equipment" means the electricity meters provided by
the distribution system operator including smart meters, any voltage
and current transformers and any other associated equipment and
wiring required to measure the quantity of electricity supplied or
exported;
"the Minister" means the Minister responsible for resources;
"MWe" means the electricity capacity rating of a cogeneration
unit;
"nominal installed capacity" means the nominal electricity
rating MWe as defined on the rating plate of the cogeneration unit;
"non-residential premises" means a building or plot of land
which is used wholly or mainly for the purpose of conducting an
economic activity, but does not include any building such as private
garages or common areas to buildings which are used solely as
private dwellings;
"operational readiness" means the capability to function in
accordance with design and specifications;
"premises code" means a unique number assigned by the
distribution system operator identifying a particular premises with its
individual service address and served with electricity and, or water;
"renewable energy sources" means renewable non-fossil energy
sources, that is, wind, solar, geothermal, wave, tidal, hydropower,
biomass, landfill gas, sewage treatment unit gas and biogases;
"residential premises" means any premises used solely and
regularly as a private dwelling where at least one person resides but
does not include institutional households;
"scheduled" means in accordance with the scheduled
programme of ARMS Limited for the taking of periodic electricity
meter readings;
"smart meters" shall have the same meaning as in the Electricity
Supply Regulations.
(Regulations 4, 5, 6 and 7)
Marginal cost per kWh applicable for electricity generated by the
cogeneration units and exported to the distribution system
The marginal cost per kWh referred to in regulations 4, 5, 6 and
7 shall amount to the marginal cost per kWh as approved by the
Authority from time to time.
The Authority may define which cost items may be considered
in the determination of the marginal cost per kWh of electricity
incurred by the distribution system operator.
The marginal cost per kWh for the year 2015 shall be of ten
cents and five mils (€0.10,5) per kWh.
B
€0.90
These regulations shall apply to electricity exported to the
distribution system from any cogeneration unit equipped for the
recuperation and utilization of the thermal energy produced and
producing electricity from fossil fuel or renewable energy, installed
either in a residential or domestic premises or non-residential or
institutional household and connected to the distribution system
either directly or indirectly with the appropriate protection and
metering equipment provided by the distribution system operator.
(1)
In the case of any cogeneration unit commissioned
and connected to the distribution system in terms of regulation 3, the
installation operator may
(a)
either sell all the electricity generated by the
cogeneration unit to the distribution system operator and be paid
by the distribution system operator the marginal cost per kWh
under the Second Schedule; or
(b)
generate electricity primarily for own consumption
and be paid by the distribution system operator the marginal
cost per kWh under the Second Schedule for any excess
electricity generated and exported to the distribution system
Provided that the consumption of the electricity
generated, in accordance with this paragraph, may only be done
by the installation operator who is a registered consumer with
the distribution system operator with respect to the same
premises code where the cogeneration unit is installed.
(2) The electricity generated -
(a)
from cogeneration units separately installed shall
be separately metered; and
(b)
from solar photovoltaic installations or other
renewable energy sources connected with the same premises
code as cogeneration units installed in terms of sub-regulation
(1) shall also be separately metered.
(3) In the case where the installation operator takes the option
available in terms of sub-regulation (1)(b), the distribution system
operator shall install metering equipment to measure all the electricity
generated by the cogeneration unit in addition to the import/export
metering equipment.
Without prejudice to the generality of the foregoing, subject to
the obtainment of the consent of the distribution system operator, the
installation operator may install metering equipment to measure all
the electricity generated by the cogeneration unit as an alternative to
the installation of metering equipment by the distribution system
operator for the purpose of measuring all the electricity generated by
the cogeneration unit.
(4) An installation operator who generates electricity from a
cogeneration unit connected with the same premises code as solar
photovoltaic installations installed primarily for own consumption
and exporting any excess electricity to the distribution system and, or
other installations generating electricity from renewable energy other
than solar photovoltaic installations, being all installed with the
option to generate primarily for own consumption, shall for any
excess electricity generated and exported to the distribution system be
paid by the distribution system operator at the marginal cost per kWh.
(1)
The payment for the electricity produced from the Commencement
cogeneration unit and sold to the distribution system operator shall be and
payment.
due from the date when the cogeneration unit is first connected to the
distribution system as provided in regulation 3.
(2) The payment of the marginal cost per kWh shall be subject
to the approval of the cogeneration capacity as required in these
regulations.
(3) The payment effected by the distribution system operator
to installation operators for electricity generated by cogeneration
units in accordance with regulation 3 shall be deemed to be inclusive
of any compensation for loss of revenue arising from any planned and
unplanned interruption which impedes the export of electricity from
the cogeneration unit to the distribution system.
(1)
The eligibility for the payment for any electricity Eligibility for
generated by the co-generation unit and sold to the distribution payment
electricity sold
system operator is subject to
to the
distribution
system operator.
(a)
the cogeneration unit obtaining all the necessary
authorisations, licences or permits from the relevant competent
authorities and the distribution system operator;
(b)
the cogeneration unit is equipped with metering
equipment that measures all the electricity generated by the
cogeneration unit in addition to the import/export metering
equipment;
(c)
the installation operator’s compliance at all times
with the obligations established in these regulations, the
Network Code and all other applicable legislation.
(2) The payment of the marginal cost per kWh shall only be
applicable up to the total amount of electricity sold to the distribution
system as measured by the metering equipment provided by the
distribution system operator and to the extent of the cogeneration unit
MWe capacity approved by the Authority
Provided that the approval of cogeneration MWe capacity
by the Authority shall be subject to the overall cap for the MWe
capacity that may be approved in any year as established by the
Second Schedule.
The total maximum cogeneration electricity capacity MWe
that shall be eligible for the sale of electricity to the distribution
system operator and the payment of the marginal cost per kWh by the
distribution system operator for exported electricity from such
cogeneration unit after the entry into force of these regulations shall
be that established in the First Schedule.
(1)
The distribution system operator may set off
amounts due by an installation operator for the supply of electricity
against amounts due to the installation operator for the exporting of
electricity under these regulations
Provided that such setting off shall only be permissible
where the claims are undisputed or are certain, liquidated and due.
(2) Where a set-off arrangement between the installation
operator and the distribution system operator is in place and the
amounts due to the installation operator for the exporting of
electricity referred to in sub-regulation (1) are in excess of the
amounts due by an installation operator for the supply of electricity
by the distribution system operator, the distribution system operator
shall credit the installation operator the balance due by means of a
credit note
Provided that the installation operator may request to be
paid the balance due by means of such credit note, after four
consecutive scheduled billing periods for the supply of electricity by
the distribution system operator to the installation operator, have
elapsed.
(3) Where no set-off agreement exists between the installation
operator and the distribution system operator and the amounts due to
the installation operator for the exporting of electricity are in excess
of the amounts due by an installation operator for the supply of
electricity by the distribution system operator, the distribution system
operator shall credit the installation operator the balance due, which
shall be paid to the installation operator within sixty days from the
scheduled reading of the metering equipment
Provided that the distribution system operator shall carry
out the reading of the metering equipment within intervals of at least
two months, to be reckoned as from the date of the first reading of the
metering equipment.
Installation operators shall
Obligations of
the installation
operator.
(a)
submit such
information
as
the
Authority
may reasonably require;
(b)
inform the Authority and the distribution system
operator, in the form and manner they may reasonable require, if
the cogeneration units have been disconnected or transferred,
sold or in any form modified in such a way as to change their
performance;
(c)
comply at all times with the provisions of
the applicable legislation, notification, authorisation, licence
conditions and Network Code as approved by the Authority;
(d)
make available to the distribution system operator
and to the Authority data required to be recorded for the
purposes of these regulations.
Where an installation operator is deceased, or by reason of Succession of
any other act or event, permanently ceases to be the installation obligations
benefits.
operator, payment for electricity generated by the cogeneration unit
and exported to the distribution system under these regulations may
be transferred to the new installation owner
Provided that
(a)
the new installation operator informs the
distribution system operator and the Authority of such change in
ownership in such form and manner as they may establish,
together with any documentary proof and information that they
may establish for such purposes;
(b)
the new installation operator takes over all
obligations held by the previous installation operator;
(c)
such person shall not be considered by the
distribution system operator and, or the Authority as a new
installation operator if such installation operator is not in
compliance with any other law, permit or any requirement in
relation to the cogeneration unit.
(1)
Modifications relevant to the cogeneration unit
installation arising from -
(a)
change of use of the premises where the
cogeneration unit is located;
(b)
change of account holder;
(c)
transfer of the cogeneration unit to another
different premises with same use;
(d)
transfer of cogeneration unit to another different
premises with different use;
(e)
change of the option from "sell all the electricity
generated" to "generate electricity primarily for own
consumption" or vice versa,
shall only be made after obtaining the necessary permits and
clearance from the Authority and the distribution system operator.
(2) In the case where an installation operator increases the
generation capacity of a cogeneration unit which is connected to the
distribution system, the payment of the marginal cost shall apply for
the whole unit as extended, provided that the installation operator
obtains all the necessary authorisations, licences and permits.
(3) The changes listed in sub-regulations (1) and (2) shall
become applicable for the payment of the marginal cost from the date
of the first meter reading taken after the date of submission of an
application to the distribution system operator to approve and take the
necessary action.
Installation operators shall not be entitled to any tradable
certificates including tradable guarantees of origin for electricity
generated from the cogeneration unit.
The provisions dealing with access, inspection, Access,
modification or tampering of meters found in the Electricity Supply inspection,
of metering
Regulations shall mutatis mutandis apply to installation operators equipment.
under these regulations in the same manner as provided for in those
regulations.