Avoidance of Damage to Third Party Property Regulations, 2013
Table of Provisions (29)
Statutory Text (29 Articles)
L.N. 72 of 2013
BUILDING REGULATION ACT
(CAP. 513)
Avoidance of Damage to Third Party Property Regulations, 2013
IN exercise of the powers conferred by articles 6, 11 and 24 of
the Building (Regulation) Act, the Minister for Resources and Rural
Affairs, has made the following regulations:-
(1)
The title of these regulations is the Avoidance of Citation and
commencement.
Damage to Third Party Property Regulations, 2013.
(2) These regulations shall come into force on the 1st May,
2013.
(Regulation 3)
1. Public footpaths and pavements.
2. Services underlying public footpaths and pavements,
within the immediate vicinity of the frontage of the construction site.
€1.89
(1)
The objective of these regulations is to ensure that Objective and
before any demolition, excavation and, or construction works are scope.
taken in hand, methodologies that are technically sound are prepared
by a perit, in collaboration with the site manager and the contractor,
to minimise the risk of damages to third party property or injury to
persons that may result through the proposed works.
(2) The provisions of these regulations shall in no way be
construed as having any bearing on the responsibilities related to the
design of buildings and construction activity emanating from other
legislative instruments.
In these regulations, unless the context otherwise requires
Interpretation.
"the Act" means Building Regulation Act;
"Building Regulation Office" has the meaning as defined in the
Act;
"construction work" includes all construction work carried out
on the fabric of a building or civil engineering structure, or
demolition or excavation activities taking place on a development
site, streets, open spaces and shall also include tunnelling works;
"contiguous property" means immediately adjacent to third
party property, including any building sharing a party wall with the
site, whether on the side or back of the site, or overlying or
underlying third party property, excluding those listed in the
Schedule;
"demolition" means the pulling down or removal of any of the
structural elements which form the building, such as the roof, internal
or external load-bearing walls and other load-bearing elements;
"developer" means the person on whose behalf the development
application in terms of the Environment and Development Planning
Act, or in terms of other regulations made thereunder, for the works
on site is submitted or, for construction activities which do not require
a development permit, any person, entity or company on whose
behalf the construction activity is undertaken;
"Director" means the Director responsible for the Building
Regulation Office or any public officer duly delegated by the Director
to act on his behalf;
"enforcement notice" shall have the same meaning assigned to it
in article 14 of the Act;
"excavation" means the cutting of rock or the removal of any
consolidated material, except that the removal of topsoil up to 600mm
in depth is not considered excavation;
"method statement" means a report prepared by a perit and shall
have the meaning assigned to it in these regulations;
"Malta Environment and Planning Authority" means the
Authority as established under article 6 of the Environment and
Development Planning Act;
"Minister" means the Minister responsible for the regulation of
the building industry;
"particulars of a person" includea the name and surname,
Identity Card number, address and contact number of a person;
"perit" means that person who is duly warranted in terms of the
Periti Act to exercise the profession assuming the responsibility for
the design, and, or the construction of building works, under the
generic title of perit;
"perit in charge of the project" means the perit who applies for
the development application or is in any other way legally responsible
for a project in terms of the Civil Code and the Environment and
Development Planning Act or regulations made thereunder, or such a
perit who takes over the works following a change of perit in terms of
the Environment and Development Planning Act or regulations made
thereunder;
"pneumatic drill" means equipment driven by compressed air or
other means, used for drilling or breaking into hard materials such as
rock or concrete;
"registered contractors" means contractors who are duly
registered in accordance with the Act;
"site manager" means a person carrying out the duty or duties
derived from the provisions of these regulations. Such person shall be
nominated by, and be responsible on behalf of, the developer for
ensuring the correct implementation of these regulations;
"third party" means a person having a legal title over property or
making use of the property by other lawful means, contiguous to a
construction site, excluding those properties listed in the Schedule.
These regulations shall be applicable to any construction Applicability.
work which involve
(a)
excavation which is underlying, or contiguous to or
within a distance of 2.5 metres to any existing building, earth-
retaining or water-retaining structure belonging to or occupied
by third parties; or
(b)
the demolition or removal of any existing wall, or
roof or structure abutting with, or immediately adjacent to, or
underlying or overlying any property belonging to or occupied
by third parties; or
(c)
the building of additional storeys or load-bearing
walls or structures over any property belonging to or occupied
by third parties; or
(d)
the construction of new buildings or additional
storeys adjacent to existing third party property
Provided that the Director may decide that, notwithstanding that
a construction activity does not fall within any one of the parameters
listed in this regulation, it shall still be required to comply with all the
requirements of these regulations. Such a decision shall be taken
following a request made by a third party whose property may be
affected by such construction activity. The decision of the Director is
to be communicated to the developer and to the third party making
the request, by registered mail.
(1)
The developer shall nominate a site manager who Responsibilities
shall be responsible to ensure that the development site and the of
site manager.
construction activities carried within it are in conformity with all the
provisions of these regulations.
(2) Unless otherwise stated in these regulations, responsibility
for adherence to these regulations shall rest solely with the site
manager.
(3) As soon as is practicable, but no later than the submission
of the method statement in accordance with regulation 7, the
developer shall nominate a site manager and submit such a person’s
particulars to the Director. The developer shall also submit a
declaration of acceptance, duly signed by the site manager, that he has
undertaken to accept this role and that he shall abide by the provisions
of these regulations.
(4) In the absence of a nomination of a site manager and
declaration in accordance with sub-regulations (1) and (3), the
developer shall ipso facto be deemed to be the site manager for the
purpose of these regulations.
(5) If the developer has changed because the development site
is sold, or for any other reason, when construction works are still to
be carried out or are being carried out, the original developer shall be
bound to inform the Director in writing submitting the details of the
new developer. Such new developer shall abide by these regulations
and shall have the duty to inform the Director whether he intends to
retain the same site manager or to nominate a new one, in which case
the provisions of the other sub-regulations to this regulation shall still
apply
Provided that nothing in these regulations shall exempt the perit
in charge of the project from the responsibilities which by reason of
the Periti Act or other relevant regulations, pertain solely to the perit
in charge of the project
Provided further that decisions relating to the applicability of
these regulations shall rest with the Director.
(6) The developer shall take all reasonable precautions to
ensure that the construction activity will not result in any damage to
contiguous properties, including damage that may result from the
infiltration of water.
(1)
The developer shall ensure that demolition,
excavation and construction works which fall under the provisions of
these regulations are appropriately and adequately insured to cover
any single occurrence or recurrence of damages sustained by third
party property, disability to persons or death as a result of the
construction works or activity being undertaken by the developer and
the contractors working on the site
Provided that the insurance cover shall not be less than five
hundred thousand euro (€500,000)
Provided also that the insurer shall carry out an appropriate and
adequate assessment of the risks involved in each particular case and
issue an appropriately valued insurance cover.
(2) The developer shall submit to the Director a copy of the
insurance cover, in accordance with sub-regulation (1), together with
a letter from the insurer -
(a)
confirming that the works are duly covered by an
insurance policy; and
(b)
stating the value of the excess of the relevant
insurance policy.
The copy of the insurance and the statement from the insurer
regarding the insurance cover and the amount of the excess shall be
submitted to the Director with the method statement indicated in
regulations 7 and 8.
(3) In addition to the provisions of sub-regulations (1) and (2),
the developer shall submit a bank guarantee to the Director, for all
construction activities, other than those listed in regulation 8. The
value of the bank guarantee shall be of three thousand euro (€3,000)
for each storey of developed third party property or properties which
is or are contiguous to a development site, for the first five properties
and a further one thousand euro (€1,000) for each additional
contiguous property, up to a maximum of forty thousand euro
(€40,000)
Provided that the Director shall exempt the developer from the
submission of a bank guarantee, as provided for in this sub-
regulation, if the developer submits to the Director a certified
statement issued by an insurance company attesting that the developer
is insured in such a manner as to cover indemnity for damages to third
party property, including damages of a minor nature
Provided further that, notwithstanding the provisions of this
sub-regulation and following a request made by the developer to the
Director, the value of the bank guarantee shall be equivalent to twice
the excess of the relevant insurance policy that has been issued to the
developer.
(4) Any third party having a claim for damages against the
developer shall immediately inform the Director. The Director shall
retain either the full bank guarantee up to the maximum of forty
thousand euro (€40,000) calculated according to sub-regulation (3),
or a part thereof equivalent to the amount being claimed by third
parties until such time that a court of law or arbitral award decides on
the matter, by means of a judgement or award, which is final
Provided that in the case where an amicable settlement is
reached with respect to such claim for damages, the parties shall
submit to the Director the settlement agreement, which shall also
make a clear provision for the bank guarantee withheld by the
Director and its release.
(5) Should a court of law or arbitral award liquidate damages
against the developer, the bank guarantee shall be forfeited in favour
of the Director, who will in turn, under the order of the Court or in
terms of the arbitration award, effect payment to any party awarded
damages, in accordance with the judgement of the court or the award
of the arbitration.
(6) On completion of the project, the developer shall, within
two weeks, submit a certification issued by the perit in charge of the
project that the works have been completed. For the purpose of this
sub-regulation project completion shall mean the completion of all
structural and other works including the roof screed of roofs, terraces
and yards, the closure of apertures and other works to render the
building sealed against the ingress of water.
(7) The Director shall, as soon as he is in receipt of the
certification from the perit in charge of the project, mentioned in sub-
regulation (6), immediately place in a prominent location upon the
website of the Building Regulation Office, a notice giving the date of
notification of project completion. The Director shall also within two
weeks, notify in writing all the owners and occupiers of those
properties, for which a condition report had been submitted by the
developer’s perit, with the details of such certification regarding
project completion.
(8) Following a request made by the owner of a contiguous
property, the Director shall retain the bank guarantee in those cases
where such owner submits proof that judicial or arbitral proceedings
for compensation of damages caused to the property have been
initiated.
(9) Unless such a request from the owner is received by the
Director within three months from the date of notification of project
completion, the Director shall release the bank guarantee.
(1)
No later than eight weeks before the Submission of a
commencement of any works that fall under these regulations, the site method
statement.
manager shall submit a method statement in the form of two hard
copies and one digital copy to the Director.
(2) The Director shall place the digital copy of the method
statement on the website of the Building Regulation Office and also
make available for the scrutiny of the public the hard copy of such
method statement. The Director shall also forward a hard copy of
each method statement it receives to the Malta Environment and
Planning Authority, so that it may be made available for the scrutiny
of members of the public at the offices of such Authority, except that
the condition reports of contiguous properties mentioned in these
regulations shall not be placed on the website nor be made accessible
to members of the public in any way. Method statement information
which is submitted separately and at a later date in accordance with
regulation 9(2) and (4) shall also be made accessible to the public in
accordance with this regulation.
(3) Any interested third party may request the Director to
review any method statement that is submitted provided the third
party submits a detailed report drawn up by a perit indicating the
technical reasons which may be of concern to the safety of such third
party or his property.
(4) Following a written request by a third party owner or
occupant of any property abutting, underlying or overlying any site,
on which construction works are to be undertaken, the Director may
request from the developer the submission of a partial method
statement at any stage during the processing of the application by the
Malta Environment and Planning Authority. Such method statement
shall be submitted within three weeks from the date when the
developer receives the request. In his request, the Director shall
indicate the details that are to be included in the partial method
statement to be submitted.
(5) The developer shall also be required to submit to the
Director, as well as to the respective owner or occupant of third party
property, the condition report of such third party property which is
contiguous to any development site, together with the method
statement. The condition report shall be prepared by a perit and
submitted to the Director and to the respective owner or occupant of
such third party property by registered mail.
(6) If the owner or occupant of such third party property does
not agree with the condition report of the property, he shall give
notice to the Director within three weeks and shall submit corrections
to the condition report or another condition report drawn up by his
own perit, to the developer and to the Director within a further three
weeks. If no corrections or no other condition report are submitted to
the Director within six weeks from receipt by the owner or occupant
of third party property, it shall be understood that the owner or
occupant of such property agrees with the condition report submitted
by the developer.
(7) In the eventuality of corrections, or another condition
report being submitted by third parties, the Director may, at his
discretion, ask the perit of the developer to consult with the perit of
the owner or occupant of third party property to review the condition
report and, should parties reach agreement, resubmit to the Director a
new report signed by both periti.
(8) Should the developer and the owner of third party property
fail to reach an agreement as described in sub-regulation (7), the
Director shall commission an inspection to be carried out by the
Building Regulation Office, to issue a final report. The costs of such
an inspection report shall be shared equally by the developer and by
the third party owner or occupant.
(9) Where a third party owner or occupant refuses entry to the
developer’s perit, or where the developer’s perit is unable to obtain
access to contiguous property, or where the identity of the owner or
occupant of contiguous property is unknown or cannot be traced, for
the purpose of preparing the condition report, such perit shall make a
written declaration giving details of his attempts to be allowed access
to the neighbour’s property, including the notification or attempts of
notification by registered mail, for the purpose of preparing the
condition report and include such details in the method statement.
(10) Where the occupant of a residence for which a condition
report is required is not the owner, the occupant shall
(a)
inform the owner that a perit, acting on behalf of
the developer of a contiguous development site, has requested
access to the property for purposes of preparing a condition
report; and
(b)
forward the condition report to the owner upon its
receipt from the developer.
Notwithstanding the provisions of regulations 4, 5, 6 and 7,
the following construction works are exempt from the submission of
the method statement and a copy of third-party insurance
(a)
excavations, including trenching works, which are
less than 1.5 metres deep;
(b)
internal and external structural alterations of a
building, including removal of walls, building of walls or
replacement of roofs where the total cost of the structural
alteration works does not exceed thirty thousand euro
(€30,000)
Provided that the developer shall submit the method statement
and a copy of a third party insurance to the Director if requested to do
so by the Director in accordance with regulations 6 and 7, in which
case all the relevant provisions of regulations 5, 6 and 7 shall become
applicable
Provided further that for the purposes of paragraph (b), the
Director may request the developer for the submission of detailed
costings of the works, which costings shall be prepared by a
competent person.
(1)
The method statement shall be prepared by a perit Form and
content of the
in collaboration with the site manager and the contractor.
method
statement.
(2) The method statement shall indicate
(a)
the commencement date of the works;
(b)
the particulars of the person who is commissioning
the works;
(c)
the
particulars
of
the
contractor
and
any
subcontractors;
(d)
the development permit number or any other
authorisations by public authorities, where necessary;
(e)
a site location plan and photograph of the site;
(f)
a condition report incorporating photographs of the
properties which are contiguous to the site of construction
works;
(g)
excavation, demolition or construction procedures
being adopted, including information which is relevant to
safeguarding the stability of the works being undertaken, and
the stability of contiguous structures or terrain as the case may
be;
(h)
plans and sections of the envisaged works, access
to site and any other information which the Director may from
time to time request;
(i)
the type of crane to be used, the location where this
is to be set-up, the methodology for setting up the crane, ground
condition information, and other information relating to the
crane that may be relevant. Inspection certificates for the crane
are also to be submitted
Provided that information relating to paragraphs (c), (g) and (i)
may be submitted to the Director separately and at a later date,
however no later than one month from commencement of related
works. The developer shall give a justification why this information
cannot be provided with the submission of the method statement in
accordance with regulation 7. Information submitted to the Director
at a later date shall be made accessible to the public in accordance
with regulation 7(2).
(3) In the case of demolition works, the method statement
shall take account of the structural condition of the construction itself
and of contiguous structures, the sequence of work, the type of tools
equipment and plant to be used, and the precautions to be taken at
each stage to cater for safeguards to be adopted
(a)
against instability of the structure;
(b)
for parts thereof being demolished;
(c)
for any contiguous structures;
(d)
for the safety of workers; and
(e)
for the safety of third parties.
(4) For excavations exceeding 3 metres in depth, prior to the
commencement of any excavation on the development site, the
developer shall carry out an appropriate geological investigation of
the area to be excavated. The geological investigation may be carried
out following the demolition of a building overlying the area to be
excavated. Prior to commencement of excavation works, the
developer shall submit to the Director the results of the investigation
and, if necessary, an amended method statement based on the results
of the investigation.
(5) For excavations in areas which are within a distance of 5
metres from the boundary of a contiguous site and which involve the
use of -
(a)
a mechanical excavator with a hydraulic hammer
attachment; or
(b)
a pneumatic drill;
the contractor shall excavate a trench by means of a trencher to a
depth of at least 1.5 metres. The location of the trench shall be such
that the vibration from the excavation equipment that will reach the
site boundary will be kept to a minimum. For this purpose, the trench
shall be between the excavator and that part of the site boundary
which is within 5 metres from the excavator.
(6) It shall not be lawful to make use of -
(a)
a mechanical excavator with a hydraulic hammer
attachment; or
(b)
a pneumatic drill,
either before 8 o’clock in the morning, or between 2 o’clock and 4 in
the afternoon or after 8 o’clock in the evening and all day on Sundays
and public holidays
Provided that the Director may, at his own discretion, either
waive the condition set out in this sub-regulation, following a request
in writing from the site manager, or impose further restrictions on the
time at which this equipment can be used, with respect to specific
sites
Provided further that the Director may exempt certain works
from the provisions of this sub-regulation, such as in the case of
quarries operating with a valid permit, certain emergency works of an
infrastructural nature, including drainage works and works
undertaken to eliminate danger to the public, such as where there is an
imminent danger of collapse of buildings or structures.
Professional responsibility for the method statement Professional
remains with the perit who prepares it, whilst ultimate responsibility responsibility
for the method
for adhering to the method statement rests with the site manager and statement.
the contractor.
(1)
The site manager, the contractor and any Compliance
subcontractors shall ensure that the works are carried out in with
statement or
accordance with the provisions indicated in the method statement.
enforcement
notice.
(2) Upon being served with an enforcement notice issued by
the Director, the site manager and the contractor shall immediately
comply with the notice and, if requested to do so in the notice, cease
construction activity.
These regulations do not exempt the developer, perit, site
manager and contractor from observing other obligations and
provisions of the law that are regulated by the Code of Police Laws,
the Civil Code, Health and Safety legislation and other regulations,
relating to excavation, demolition or construction works.
The Director shall, for construction jobs which fall within
any one category of the works listed in regulation 4
(a)
verify that the method statement has been
submitted in accordance with these regulations;
(b)
review the method statement, if a submission is
received from a third party claiming that the method statement
does not provide for adequate safety and, or is not in accordance
with these regulations;
(c)
verify that demolition, excavation and, or
construction works are covered by a third party insurance
policy, in accordance with regulation 6; and
(d)
monitor methodologies being carried out on site
and see that they are in line with the method statement
submitted and in accordance with these regulations
Provided that the Director, delegated perit, or other official of
the Buildings Regulation Office so authorised, may at any reasonable
time and if so required by the Director, with the assistance of the
Police Force, enter upon any development site in order to execute his
responsibilities as specified in this regulation.
(1)
The Director shall have the power to issue an
enforcement notice in any of the following circumstances
(a)
if the method statement has not been submitted in
accordance with these regulations; or
(b)
if no third party insurance is submitted for the
construction works in accordance with these regulations; or
(c)
if the demolition, excavation or construction works
are not being carried out in accordance with the method
statement or in accordance with regulations; or
(d)
if, irrespective of the adherence or otherwise to the
method statement and relevant regulations, the Director is of the
opinion that the demolition, excavation or construction works
are likely to cause material damage to third party property or
will result in danger to workers or to third parties.
(2) The Director may delegate to officers of the Building
Regulation Office and any perit duly appointed by him the power to
issue on his behalf an enforcement notice.
(3) Should any person who is served with an enforcement
notice fail to abide by the provisions of that notice or cease operations
as requested in the notice, the Director or his delegated representative
shall call for the presence of the Police Force who shall for such
purpose exercise such powers as are vested in them at law to assist the
server of the enforcement notice in ensuring that the said notice is
complied with
Provided that should the Director or his delegated representative
decide not to issue an enforcement notice, this shall not be construed
as a form of endorsement of the method statement, nor shall it be
construed as an endorsement of the work methodology being carried
out on site.
(4) All expenses reasonably incurred by the Director in the
exercise of his power under this regulation shall be recoverable as a
civil debt by the Director from the person or persons to whom the
enforcement notice is issued, subject to any right of recovery such
person or persons may have against any other person.
(5) The Director or any delegated official or perit shall not be
liable for any damages as a result of the exercise of one’s powers
under this regulation, unless it is proved that such damage resulted
from gross negligence on the part of the Director, his delegated
official or perit.
(1)
Notwithstanding the provisions of regulations 22, Interim
23, 24 and 25, where the Director holds that an infringement of these measures.
regulations represents a serious threat to the safety of third parties or
to the safety of third party property, he may take urgent interim
measures which may include requesting the developer to remedy the
situation in advance of reaching a final decision, or the imposition of
administrative fines, or both.
(2) If any steps or other action, including discontinuance or
stoppage required by an enforcement notice issued, to stop any
construction activity from being started or to cease all or part of a
construction activity, have not been taken within the time specified
therein, the Director may enter the development site and take such
steps or other action he deems necessary, including the disabling or
removal of any equipment, machinery, tools, belongings, vehicles or
other objects that may be on the site and the carrying out of any works
that may be necessary to comply with what is requested in the
enforcement notice and may for such purpose request the assistance
of the Police Force, and the Police Force shall for such purpose
exercise such powers as are vested in them at law.
(3) All expenses reasonably incurred by the Director in the
exercise of his powers under this regulation shall be recoverable as a
civil debt by the Director from the developer subject to such right of
recovery which the developer may have against any other person.
(4) The Director shall not be liable for any damages as a result
of the exercise of his powers under this regulation unless it is proved
that such damage resulted from gross negligence on the part of the
Director, his delegate or other official of the Building Regulation
Office.
(1)
The Director shall, before proceeding to take any
of the measures envisaged under regulation 15, write a letter to the
developer and send a copy of the said letter to the site manager and to
the person carrying out the construction works, warning them of the
measure that may be taken and the specific reason why it may be
taken. The Director may require the developer to cease or to rectify
any act or omission and, or to make submissions thereto within such
period of time not being less than seven days, which period may be
abridged if the Director considers that the continuance of the
infringement represents an immediate and serious threat to public
safety, public security or public health, and, or warrants the
immediate intervention of the Building Regulation Office
Provided that where the measure is or includes an administrative
fine the person concerned shall also be informed of the amount of the
fine
Provided further that when issuing a warning under this sub-
regulation, the Director may impose such conditions as he may
consider reasonable in the circumstances.
(2) If the developer remedies the infringement within the
period established by the Director in accordance with sub-regulation
(1), and agrees in writing to abide with any condition that the Director
may impose, the Director may desist from proceeding any further,
without prejudice to any regulatory measures that may have already
been imposed.
(3) If, after the lapse of the period mentioned in sub-regulation
(1), the Director considers that the developer has not given any valid
reasons to demonstrate why no measure should be taken against him,
the Director shall notify the developer in writing, specifying the
nature of the infringement, stating the measure being taken and, if the
measure is or includes an administrative fine, stating the amount of
the fine being imposed
Provided that the notification mentioned in this sub-regulation
shall be in the form of a judicial act and the fines provided for in these
regulations shall be due to the Government as a civil debt and
following the service of a judicial act, in terms of article 466 of the Cap. 12.
Code of Organization and Civil Procedure, which is either not
opposed or the opposition of which is denied, according to the
provisions of the said article, the same administrative fine shall
constitute an executive title for all the effects and purposes of Title
VII of Part I of Book Second of the Code of Organization and Civil
Procedure.
(1)
The Director may delegate to an official of the Responsibility
Building Regulation Office or to any perit in private practice, any or of
official or perit.
all of the responsibilities pertaining to the Director in regulations 13
and 14, and the person thus delegated shall be responsible for such
delegated matters.
(2) The Director or any delegated official or perit shall only
issue an enforcement notice to stop the construction works after
verifying and taking into consideration the provisions of regulation
14. (3) Where an enforcement notice is issued by the delegated
official or perit, a copy of the enforcement notice shall be submitted
to the Director as soon as possible, after the serving of the notice, but
no later than close of business of the first full working day after the
serving of the notice.
(1)
An enforcement notice shall include
Form and
content of
enforcement
(a)
an instruction to the developer, site manager and
notices.
the contractor not to initiate any construction activity or to cease
all or part of a construction activity;
(b)
the reasons as to why the notice is being issued,
including where necessary for technical reasons, a technical
report supported by photos of the construction activity which is
deemed to be unsafe, or not in accordance with the method
statement, or not in accordance with these regulations, and
which technical report is to be signed by a perit;
(c)
instructions (if any) to prevent further damage or
danger to the public or to third parties.
(2) Where the Director or his delegated representative deems
that the cessation of construction activity is to be immediate because
of imminent severe damage to contiguous properties or danger to the
public, or third parties, the enforcement notice and the required
preventive measures may be issued on site in a verbal manner and
later confirmed in writing within twenty-four hours of the issuance of
the said notice.
An enforcement notice may only be withdrawn by the
Director, provided that a new method statement indicating all
necessary remedial works and precautionary measures is submitted to
replace the original method statement.
Members of the public or their appointed perit or lawyer
may submit to the Director contestations on any method statement, or
complaints relating to the lack of safety of a construction activity
Provided that the Director may decide not to consider
complaints or contestations which do not provide a technical
justification for the contestation or concern.
(1)
Should any damage result to third party property or
should there be any injury or death resulting from a construction
activity, the onus of proof that the method statement was adhered to,
or that the regulations were complied with, rests with the developer,
the site manager and the contractor.
(2) Any dispute regarding building construction, not being one
in connection with a claim for personal injuries, but being a dispute
arising from damage to third party property resulting from
construction activity on a contiguous site shall be referred to
arbitration. The rules contained in the Arbitration Act or made
thereunder relating to mandatory arbitration shall apply
Provided that -
(a)
the damage incurred by the third party does not
impair the stability of his property nor endangers its users; or
(b)
the cost of damages being claimed by the third
party does not exceed one million euro (€1,000,000).
(1)
Any person who acts in contravention of the
provisions of regulations 6 or 7 shall be guilty of an offence in terms
of these regulations and shall be liable on conviction to a fine (multa)
not exceeding five hundred euro (€500) and in the case of a
continuing offence, to a further fine (multa) of one hundred euro
(€100) for each day the offence continues.
(2) The submission of a method statement which, in the
opinion of the Director, is significantly lacking when compared to the
requirements as set out in regulation 9 shall also be considered as an
offence in terms of sub-regulation (1) and shall be liable to the fines
set out in the said sub-regulation.
(3) Any person who fails to comply with a method statement
in terms of regulation 11(1) shall be guilty of an offence and shall be
liable, on conviction, to a fine (multa) not exceeding five hundred
euro (€500) and in the case of a continuing offence, to a further fine
(multa) of one hundred euro (€100) for each day the offence
continues.
(4) Any person who fails to abide by the provisions of an
enforcement notice in terms of regulation 11(2) or to cease operations
as requested in the notice or to adopt any urgent interim measures or
in any other manner acts in contravention of regulations 14 and 15,
shall be guilty of an offence in terms of these regulations and shall be
liable, on conviction, to a fine (multa) not exceeding one thousand
two hundred euro (€1,200) and in the case of a continuing offence, to
a further fine (multa) of one hundred euro (€100) for each day the
offence continues.
(5) Any person who makes a false declaration for the purposes
of these regulations shall be guilty of an offence and shall be liable,
on conviction, to a fine (multa) not exceeding one thousand five
hundred euro (€1,500), without prejudice to any other punishment for
which the applicant may have become liable under any other law.
(6) Notwithstanding the provisions of the Criminal Code, Cap. 9.
proceedings for an offence against these regulations shall be taken
before the Court of Magistrates (Malta) or the Court of Magistrates
(Gozo), as the case may be, sitting as courts of criminal judicature.
(7) Notwithstanding the provisions of the Criminal Code, the Cap. 9.
Attorney General shall always have a right of appeal from any
judgement given by the Courts of Magistrates (Malta) or the Court of
Magistrates (Gozo), in respect of proceedings for any offence against
these regulations.
(1)
Without prejudice to regulation 16 and any other Administrative
provisions under these regulations which the Director is entitled to penalties.
enforce, the Director may impose an administrative penalty in
accordance with the provisions of this regulation, in respect of any
person who infringes any provision of these regulations, or who fails
to comply with any directive or decision given by the Director.
(2) Any person who fails to comply with the provisions of
regulations 6, 7 and 9 or refuses to comply with an enforcement
notice issued under regulation 14 and any person who fails or refuses
to adopt urgent interim measures in terms of regulations 15 and 16
shall commit an infringement of these regulations and shall be liable
to the imposition of an administrative fine.
(3) An administrative penalty imposed under this regulation
shall not exceed one-half of the maximum fine (multa) which the
offender may be liable to, for the corresponding offence, in
accordance with the provisions of regulation 22
Provided that it shall always be at the Director’s sole discretion
as to whether to offer the offender the payment of the administrative
penalty or to commence proceedings for the commission of the
offence.
(4) In all cases where the Director imposes an administrative
penalty in respect of anything done or omitted to be done by any
person and such act or omission also constitutes a criminal offence,
no proceedings may be taken or continued against the said person in
respect of such criminal offence
Provided that all the fines provided for in this regulation shall be
due to the Government as a civil debt and following the service of a
judicial act, in terms of article 466 of the Code of Organization and
Civil Procedure, which is either not opposed or the opposition of
which is denied, according to the provisions of the said article, shall
constitute an executive title for all the effects and purposes of the
Code of Organization and Civil Procedure, Book Second, Part I, Title
VII.
(5) The payment of an administrative fine as a penalty shall
not prejudice the duty of a person to undertake any measure which
may be requested of him, whether such duty arises out of these
regulations, or out of an order issued by the Director through an
enforcement notice or to adopt an urgent interim measure in terms of
these regulations.
Where, following the payment of a penalty, the violation of
any provision of these regulations persists, regardless of any
instructions the Director may have given for the redress of same, the
Director may refer the matter to the police to institute proceedings
referred to in regulation 22 for such continuing violation.
Without prejudice to the provisions of regulations 15, 16 Appeal
and 23, any decision taken by the Director in terms of these procedure.
regulations shall be subject to the right of appeal before the Building
Regulation Board, in terms of articles 12 and 13 of the Act.
(1)
Construction works which have been taken in hand Transitory
and completed within a calendar month from the date of the coming provision.
into force of these regulations shall not fall within the provisions of
these regulations.
(2) With reference to construction works which have been
commenced but not completed within a calendar month from the date
of coming into force of these regulations, those construction works
which are still to be taken in hand shall fall within the provisions of
these regulations
Provided that the Director shall exempt the developer from the
submission of the bank guarantee following a request made by the
developer in writing within one calendar month from the coming into
force of these regulations, in which case the developer shall complete
the works within four months of the coming into force of these
regulations.
These regulations have been notified in terms of Directive Notification.
98/34/EC, as amended by Directive 98/48/EC, as transposed by the
Notification Procedure Regulations.