Stationary Installations Regulations, 2013
Table of Provisions (27)
Statutory Text (27 Articles)
L.N. 434 of 2013
ENVIRONMENT AND DEVELOPMENT PLANNING ACT
(CAP. 504)
MALTA RESOURCES AUTHORITY ACT
(CAP. 423)
European Union Greenhouse Gas Emissions Trading Scheme for
Stationary Installations Regulations, 2013
IN exercise of the powers conferred by article 61 of the
Environment and Development Planning Act and by article 28 of the
Malta Resources Authority Act, the Minister for Sustainable
Development, the Environment and Climate Change and the Minister
for Energy and the Conservation of Water, after consultation with the
Malta Environment and Planning Authority and the Malta Resources
Authority, have made the following regulations:-
(1)
The title of these regulations is the European Union
Greenhouse Gas Emissions Trading Scheme for Stationary
Installations Regulations, 2013.
(2) These regulations provide for the implementation in Malta
of the European Union scheme for greenhouse gas emissions
allowance trading for activities listed in Schedule 1 to these
regulations, for the period commencing 1st January, 2013 and any
subsequent periods. These regulations also transpose Directive 2009/
29/EC amending Directive 2003/87/EC so as to improve and extend
the greenhouse gas emission allowance trading scheme of the
Community in so far as it relates to stationary installations.
(3) These regulations shall be deemed to have come into force
on the 1st January, 2013.
For the purposes of these regulations and unless the
context otherwise requires, the following definitions shall apply
"account holder" means a natural or legal person that holds an
account in the Union registry;
"the Act" means the Malta Resources Authority Act;
"allowance" means an allowance to emit one tonne of carbon
dioxide equivalent during a specific period, which shall be valid for
the purposes of meeting the requirements of these regulations and
shall be transferable in accordance with the provisions of these
regulations;
"auctioneer" means the Debt Management Office within the
Treasury Department appointed by the Government to auction
allowances on its behalf;
"authorised representatives" means the representatives,
nominated by an account holder in respect of an account in the Union
registry, to have access to that account and undertake processes
relating to that account on behalf of the account holder;
"the Authority" means the Malta Resources Authority
established by article 3 of the Act;
"cancellation" means the definitive disposal of an allowance by
its holder or by the national registry administrator as may be
applicable;
"certified emissions reduction" or "CER" means a unit issued
pursuant to Article 12 of the Kyoto Protocol and the decisions
adopted pursuant to the UNFCCC or the Kyoto Protocol;
"Chapter II allowance" means an allowance allocated and issued
in respect of aviation activities listed in Annex I to Directive 2003/87/
EC, in accordance with Chapter II of Directive 2003/87/EC;
"Chapter III allowance" means an allowance allocated and
issued in respect of activities listed in Annex I to Directive 2003/87/
EC other than aviation activities, in accordance with Chapter III of
Directive 2003/87/EC;
"combustion" means any oxidation of fuels, regardless of the
way the heat, electrical or mechanical energy produced by this
process is used, and any other directly associated activities, including
waste gas scrubbing;
"the Commission" means the European Commission;
"confidential information" means any non-public information
deemed to be sensitive by the operator and, or, any privileged
information falling within the scope of these regulations, disclosed
only for promoting and elaborating certain purposes. It shall include,
inter alia
(a)
trade secrets;
(b)
any other information having a commercial value
that would be, or could reasonably be expected to be, destroyed
or diminished if the information were disclosed; or
(c)
information other than trade secrets or information
under paragraph (b) concerning a person, organisation or
undertaking in respect of their business, professional,
commercial or financial affairs;
"deviation" means, in respect of monitoring of annual
emissions, the use of a monitoring approach that is different, in full or
in part, from the approved monitoring and reporting plan, which use
is of a temporary nature;
"Directive 2003/87/EC" means Directive 2003/87/EC of the
European Parliament and of the Council of 13 October 2003
establishing a scheme for greenhouse gas emission allowance trading
within the Community and amending Council Directive 96/61/EC;
"Directive 2009/29/EC" means Directive 2009/29/EC of the
European Parliament and of the Council of 23 April 2009 amending
Directive 2003/87/EC so as to improve and extend the greenhouse gas
emission allowance trading scheme of the Community;
"Directive 2009/31/EC" means Directive 2009/31/EC of the
European Parliament and of the Council of 23 April 2009 on the
geological storage of carbon dioxide and amending Council Directive
85/337/EEC of the European Parliament and Council Directives
2000/60/EC, 2001/80/EC, 2004/35/EC, 2006/12/EC, 2008/1/EC and
Regulation (EC) No 1013/2006;
"economically justifiable demand" means the demand that does
not exceed the needs for heat or cooling and which would otherwise
be satisfied at market conditions by energy generation processes other
than cogeneration;
"electricity generator" means an installation that, on or after the
1st January, 2005, has produced electricity for sale to third parties,
and in which no activity listed in Schedule 1 is carried out other than
the combustion of fuels;
"emissions" means the release into the atmosphere of
greenhouse gases specified in respect of an activity listed in Schedule
1, from sources in an installation performing that activity;
"emission reduction unit" or "ERU" means a unit issued
pursuant to Article 6 of the Kyoto Protocol and the decisions adopted
pursuant to the United Nations Framework Convention on Climate
Change or the Kyoto Protocol;
"greenhouse gases" means the gases listed in Schedule 2;
"greenhouse gas emissions permit" means the permit issued
pursuant to regulation 6;
"high efficiency cogeneration" means cogeneration meeting the
criteria for high efficiency cogeneration set out in the Cogeneration S.L. 423.27.
Regulations;
"installation" means a stationary technical unit where one or
more activities listed in Schedule 1 are carried out and any other
directly associated activities which have a technical connection with
the activities carried out on that site and which could have an effect
on emissions and pollution;
"Joint Implementation project activity" or "JI project activity"
means a project activity undertaken in accordance with Article 12 of
the Kyoto Protocol and decisions adopted pursuant to the United
Nations Framework Convention on Climate Change or the Kyoto
Protocol;
"Kyoto Protocol" means the Kyoto Protocol to the United
Nations Framework Convention on Climate Change;
"least developed countries" means those countries included in
the list of Least Developed Countries as defined by the Committee for
Development Policy and endorsed by the Economic and Social
Council of the United Nations;
"Member State" means a state which is a member of the
European Union and which, for the purpose of these regulations,
includes Iceland, Liechtenstein and Norway;
"the Minister" means the Minister responsible for climate
change policy;
"modification" means, in respect of monitoring of annual
emissions, a permanent change in an approved monitoring plan, in
full or in part, and, where it is deemed to be of a significant nature,
shall require the approval of the Authority to become valid;
"National Accreditation Board - Malta" means the National
Accreditation Board established by the National Accreditation Board S.L. 419.07.
(Malta) (Establishment) Regulations;
"national registry administrator" means the entity responsible
for the administering of operator holding accounts on behalf of the
Government, which operator holding accounts are under the
jurisdiction of the Government in the Union registry, and designated
in accordance with relevant decisions and regulations adopted by the
Commission pursuant to Directive 2003/87/EC;
"new entrant" means
(a)
any installation carrying out one or more of the
activities listed in Schedule 1, which has obtained a greenhouse
gas emissions permit for the first time after the 30th June, 2011;
or
(b)
any installation carrying out an activity which is
included in the Union greenhouse gas emissions trading scheme
for the first time after the commencement of the period starting
the 1st January, 2013 or any subsequent period in accordance
with any decisions or regulations adopted by the Commission
pursuant to Directive 2003/87/EC; or
(c)
any installation carrying out one or more of the
activities listed in Schedule 1, which has had a significant
capacity extension after the 30th June, 2011, only in so far as
this extension is concerned;
(d)
any installation carrying out an activity which is
included in the Union greenhouse gas emissions trading scheme
after the commencement of the period starting the 1st January,
2013 or after the commencement of any subsequent period in
accordance with any decisions or regulations adopted by the
Commission pursuant to Directive 2003/87/EC, which has had a
significant capacity extension after the 30th June, 2011, only in
so far as this extension is concerned;
"operator" means any person who operates or controls an
installation;
"person" means any natural or legal person;
"proposed transferee" means a person who receives from
another person the greenhouse gas emissions permit, in whole or in
part, issued for the installation;
"proposed transferor" means an operator of an installation who
transfers to another person the greenhouse gas emissions permit, in
whole or in part, issued for the installation;
"the public" means one or more persons, associations,
organisations or groups of persons;
"Regulation (EC) No 765/2008" means Regulation (EC) No
765/2008 of the European Parliament and of the Council of 9 July
2008 setting out the requirements for accreditation and market
surveillance relating to the marketing of products and repealing
Regulation (EEC) No 339/93;
"surrender" means the accounting of an allowance by an
operator of an installation against the verified emissions of the
installation;
"tonne of carbon dioxide equivalent" means one metric tonne of
carbon dioxide (CO 2 ) or an amount of any other greenhouse gas listed
in Schedule 2 with an equivalent global-warming potential;
"the Union" or the "European Union" means the European
Union as established by the Treaty on the European Union as
amended by the Lisbon Treaty of 2009, as may be subject to
subsequent amendments;
"Union registry" means the registry established and maintained
in accordance with Article 19 of Directive 2003/87/EC as amended
by Directive 2009/29/EC for the execution of processes pertaining to
the maintenance of holding accounts and the allocation, surrender and
cancellation of allowances;
"UNFCCC" means the United Nations Framework Convention
on Climate Change which entered into force on the 21st March, 1994;
"verifier" means a legal person or another legal entity carrying
out verification activities pursuant to these regulations and accredited
by a national accreditation body pursuant to Regulation (EC) No 765/
2008 and relevant decisions and regulations adopted by the
Commission pursuant to Directive 2003/87/EC, or a natural person
otherwise authorised, without prejudice to Article 5(2) of Regulation
(EC) 765/2008, at the time a verification report is issued.
These regulations shall apply to operators of installations Applicability.
situated in the territory of Malta and carrying out one or more
activities listed in Schedule 1 resulting in emissions of the greenhouse
gases specified in respect of those activities in Schedule 1.
(1)
No operator of an installation shall carry out any Greenhouse gas
activity listed in Schedule 1 resulting in emissions specified in emissions
permits.
relation to that activity unless such operator holds a permit issued by
the Authority in accordance with regulation 6.
(2) Where an operator of an installation carries out any
activity listed in Schedule 1 without holding a permit in accordance
with sub-regulation (1), the operator of that installation shall be liable
to the imposition of an administrative fine
(a)
where emissions of an installation during that year
are equal to or less than fifty thousand (50,000) tonnes carbon
dioxide equivalents, of ten thousand euro (€10,000), and one
hundred euro (€100) for each day of non-compliance from the
date of a notice given by the Authority to the operator;
(b)
where emissions of an installation during that year
are more than fifty thousand (50,000) tonnes of carbon dioxide
equivalents and equal to or less than five hundred thousand
(500,000) tonnes of carbon dioxide equivalent, of fifty thousand
euro (€50,000), and three hundred euro (€300) for each day of
non-compliance from the date of a notice given by the Authority
to the operator;
(c)
where emissions of an installation during that year
are more than five hundred thousand (500,000) tonnes of carbon
dioxide equivalents, of one hundred thousand euro (€100,000),
and six hundred euro (€600) for each day of non-compliance
from the date of a notice given by the Authority to the operator.
(3) For the purposes of determining the administrative fine
under sub-regulation (2), where the emissions of the installation are
not known or are not reported or where the Authority is satisfied that
there is no reasonable possibility that the quantity of emissions will
be reported by the operator of the installation, the Authority may
itself determine the emissions from the activities performed in that
installation. The Authority shall use best available data and ensure
that a conservative estimate is made that does not underestimate
emissions. The operator of the installation shall be liable to the
imposition of an administrative fine equal to the amounts established
in sub-regulation (2) in respect of the quantity of emissions estimated
in terms of this sub-regulation.
(4) A permit issued by the Authority in accordance with sub-
regulation (1) shall be valid for the duration of the performance of the
activity or activities listed in Schedule 1 in respect of which the
permit is issued, unless the permit is surrendered in accordance with
regulation 9 or revoked in accordance with regulation 10.
(5) The Authority shall ensure that permits issued by it in
accordance with sub-regulation (1) shall be made publicly available.
An operator of an installation carrying out an Applications for
activity listed in Schedule 1 shall apply to the Authority for a greenhouse
emissions
greenhouse gas emissions permit.
permits.
(2) An operator of an installation shall submit an application
for a greenhouse gas emissions permit. The application shall be
submitted at least one hundred and twenty days before the
commencement of activities listed in Schedule 1 in respect of which
the application for a permit is to be submitted, unless otherwise
agreed in writing between the applicant and the Authority.
(3) An application made to the Authority for a greenhouse gas
emissions permit shall include, inter alia, the following
(a)
information as may be requested by the Authority
about the operator of the installation;
(b)
information as may be requested by the Authority
about the applicant, if different from the operator of the
installation;
(c)
a description of the installation and activities listed
in Schedule 1 to be carried out in the installation, including the
technology used;
(d)
the raw and auxiliary materials, the use of which is
likely to lead to emissions of gases specified in Schedule 1 in
respect of the activities to be carried in the installation;
(e)
the sources of emissions of gases listed in Schedule
1 from the installation;
(f)
a description of the measures planned to monitor
and report emissions in accordance with regulations 15 and 16;
(g)
any other appropriate information requested by the
(h)
any other information that the applicant wishes the
Authority to take into account when considering the application;
(i)
a non-technical summary of the details referred to
in paragraphs (c) to (f).
(4) Any operator who prior to the entry into force of these
regulations is in possession of a valid greenhouse gas emissions
permit issued under the European Community Greenhouse Gas L.N.
2005. Emissions Trading Scheme Regulations, 2005, shall continue to hold
such permit under existing conditions until such conditions are
revised by the Authority
Provided that any such operator shall comply with such
revised conditions which may be issued by the Authority and with
effect from such date as the Authority shall establish.
(1)
Operatur ta’ installazzjoni li tkun qegħda twettaq xi
attività elenkata fl-iSkeda 1 għandu japplika għand l-Awtorità għal
permess għal emissjonijiet tal-gassijiet serra.
(2) Operatur
ta’
installazzjoni
għandu
jippreżenta
applikazzjoni għal permess għal emissjonijiet tal-gassijiet serra. L-
applikazzjoni għandha tiġi ppreżentata mill-inqas mija u għoxrin
ġurnata qabel il-bidu fis-seħħ tal-attivitajiet elenkati fl-iSkeda 1 li
dwarhom għandha tiġi ppreżentata l-applikazzjoni għal permess,
kemm-il darba ma jiġix miftiehem xort’oħra bil-miktub bejn l-
applikant u l-Awtorità.
(3) Applikazzjoni li ssir lill-Awtorità għal permess għal
emissjonijiet tal-gassijiet serra għandha fost l-oħrajn tkun tinkludi
dan li ġej
(a)
dik l-informazzjoni li tista’ tintalab mill-Awtorità
dwar l-operatur tal-installazzjoni;
(b)
dik l-informazzjoni li tista’ tintalab mill-Awtorità
dwar l-applikant, jekk dan ma jkunx l-istess operatur tal-
installazzjoni;
(ċ)
deskrizzjoni tal-installazzjoni u attivitajiet elenkati
fl-iSkeda 1 li għandhom jitwettqu fl-installazzjoni, inkluża t-
teknoloġija użata;
(d)
xi jkun il-materjal grezz u awżiljari, li meta jintuża
x’aktarx iwassal għal emissjonijiet ta’ gassijiet speċifikati fl-
iSkeda 1 dwar l-attivitajiet li għandhom jitqwettqu fl-
installazzjoni;
(e)
is-sorsi ta’ emissjonijiet ta’ gassijiet elenkati fl-
iSkeda 1 mill-installazzjoni;
(f)
deskrizzjoni tal-miżuri ppjanati għall-monitoraġġ u
rappurtar ta’ emissjonijiet kif previst fir-regolamenti 15 u 16;
(g)
kull informazzjoni adatta oħra li tintalab mill-
Awtorità;
(h)
kull informazzjoni oħra li l-applikant ikun irid lill-
Awtorità tqis meta din tkun qegħda tifli l-applikazzjoni tiegħu;
(i)
sommarju mhux ta’ xorta teknika tad-dettalji
msemmija fil-paragrafi (ċ) sa (f).
(4) Kull operatur li qabel id-dħul fis-seħħ ta’ dawn ir-
regolamenti jkollu fil-pussess tiegħu permess validu għal
emissjonijiet tal-gassijiet serra maħruġin taħt ir-Regolamenti dwar A.L. 140 tal-
2005. Skema Kummerċjali tal-Komunità Ewropea dwar l-Emissjonijiet ta’
Gassijiet Serra, għandu jibqa’ jżomm dak il-permess taħt il-
kondizzjonijiet li jkunu jeżistu sakemm dawk il-kondizzjonijiet ma
jiġux riveduti mill-Awtorità
Iżda kull operatur bħal dak għandu jikkonforma ruħu ma’
dawk il-kondizzjonijiet riveduti li jistgħu jinħarġu mill-Awtorità u
b’seħħ minn dik id-data li l-Awtorità għandha tistabbilixxi.
(1)
The Authority shall issue a greenhouse gas
emissions permit granting authorisation to emit greenhouse gases
from all or part of an installation for which the application for a
permit is made, if it is satisfied that the operator of the installation is
capable of complying with the requirements of these regulations and
the conditions of the permit. A permit shall be issued within a period
of ninety days from the date on which the Authority receives the
application for a permit, unless otherwise agreed in writing between
the operator and the Authority.
(2) A greenhouse gas emissions permit issued by the Authority
may cover one or more installations on the same site operated by the
same operator. A greenhouse gas emissions permit may not cover two
or more installations situated on different sites. A greenhouse gas
emissions permit may not cover two or more installations on the same
site operated by different operators.
(3) The Authority shall, when issuing a greenhouse gas
emissions permit, ensure that the permit includes, inter alia, the
following
(a)
the name and address of the operator;
(b)
the name and address of the installation;
(c)
a description of the activities and emissions
covered by the permit;
(d)
a reference to monitoring, reporting and
verification requirements including the requirement to have a
monitoring plan approved by the Authority;
(e)
an obligation to report verified emissions of
greenhouse gases specified for the activity or activities listed in
Schedule 1 for each calendar year, within three months
following the end of that year;
(f)
an obligation to surrender allowances equal to the
total emissions of the installation in each calendar year within
four months following the end of that year;
(g)
requirements for any notifications to be made to the
Authority;
(h)
a requirement to pay penalties for non-compliance
with paragraph (f);
(i)
any other conditions that the Authority considers
appropriate to ensure compliance with the requirements of these
regulations.
(4) The Authority shall review a greenhouse gas emissions
permit issued to an operator of an installation at least every five years
and make amendments to the permit as appropriate.
(5) The Authority may, at any time, vary the conditions of a
permit in such a manner as it may deem fit, and issue an updated
permit
Provided that it shall inform the operator covered by the
permit of such variations by not later than thirty days prior to the
issuance of an updated permit.
(1)
The operator of an installation for which a Changes
greenhouse gas emissions permit has been issued shall notify the relating
installations.
Authority of
(a)
any changes planned in the nature or functioning of
the installation; or
(b)
any extension or reduction of the capacity of the
installation, which may require the updating of the greenhouse
gas emissions permit; or
(c)
in the case of a permit covering more than one
installation on the same site operated by the same operator, any
instance where one or more installations cease carrying out all
of the activities listed in Schedule 1 covered by the permit but
the operator continues to carry out at least one activity in one
installation under that permit
Provided that any such notification must be made in
writing at least one hundred and twenty days prior to such change,
extension or reduction of capacity is effectively to take place.
(2) The Authority shall, where appropriate, update the
greenhouse gas emissions permit accordingly, within a period of
ninety days from the date on which the Authority receives a
notification pursuant to sub-regulation (1), unless otherwise agreed in
writing between the operator and the Authority.
(3) Where there is a change in the name of the operator of an
installation, the Authority shall update the permit to include the name
and address of the new operator
Provided that the Authority shall be notified by the
operator, in writing, of the change in the name of the operator of the
installation at least sixty days before such a change is effectively to
take place.
(4) An operator that allows the coming into effect of changes
listed under sub-regulation (1) without notifying the Authority of
such changes in accordance with this regulation shall be liable to the
imposition of an administrative fine of five thousand euro (€5,000).
(5) Where a change in the name of the operator of an
installation comes into effect without such a change having been
notified to the Authority in accordance with sub-regulation (3), the
operator of the installation shall be liable to the imposition of an
administrative fine of one thousand euro (€1,000).
(6) The Authority shall notify the national registry
administrator of any changes made to a permit pursuant to this
regulation. The national registry administrator shall ensure that any
changes required are made to the account or accounts relating to the
installation or installations for which the changes to the permit relate,
so as to reflect such changes.
(1)
An operator of an installation ("proposed
transferor") may transfer to another person ("proposed transferee"), in
whole or in part, the greenhouse gas emissions permit issued to the
installation.
(2) An application for the transfer of a permit shall be
submitted to the Authority, in writing, jointly by the proposed
transferor and the proposed transferee.
(3) An application under sub-regulation (2) shall include the
following information
(a)
the name and address of the proposed transferor;
(b)
the name and address of the proposed transferee;
(c)
the name and address of the installation to which
the greenhouse gas emissions permit relates;
(d)
in the case of a request to transfer a permit in part,
information identifying the activity or activities or part of an
activity or activities to which the transfer of permit applies.
The Authority may request any additional information it
deems necessary to process an application for the transfer of a permit.
(4) The Authority shall carry out a transfer of a greenhouse
gas emissions permit, if it satisfied that the proposed transferee is
capable of complying with the requirements of these regulations and
the conditions of the permit. The transfer shall be carried out
(a)
in the case of a transfer of a permit in whole, by
transferring the permit for the installation to the proposed
transferee, updated to include the name and address of the
proposed transferee as the operator of the installation;
(b)
in the case of a transfer of a permit in part, by
(i) issuing a new greenhouse gas emissions
permit to the proposed transferee, recording the transfer,
identifying the activity or activities or part of an activity or
activities to be transferred and identifying the proposed
transferee as the operator in respect of the activity or
activities covered by the new permit;
(ii) revising and reissuing the greenhouse gas
emission permit to the proposed transferor, recording the
transfer, and the permit shall be updated so as to identify
the activity or activities to be carried out in the installation
operated by the proposed transferor.
(5) The transfer of a permit shall come into effect at a time
agreed between the proposed transferor, proposed transferee and the
Authority, as shall be recorded in the permit.
(6) The Authority shall notify the national registry
administrator of any application for the transfer of a permit made to it
and the coming into effect of such a transfer. The national registry
administrator shall ensure that any changes required are made to the
account or accounts relating to the installation or installations to
which the transfer of a permit relates so as to reflect the transfer of the
permit.
(1)
An operator who ceases to carry out all of the Surrender of
activities listed in Schedule 1 in all of the installations covered by a greenhouse
emissions
greenhouse gas emissions permit shall surrender the permit.
permits.
(2) An application for the surrender of a permit shall be
submitted to the Authority, in writing, by not later than thirty days
from the date on which the operator has ceased to carry out the
activity or activities in the installation to which the greenhouse gas
emissions permit relates.
(3) An application for the surrender of a permit shall include
the following
(a)
the name and address of the applicant;
(b)
the name and address of the installation to which
the greenhouse gas emissions permit relates;
(c)
the date on which the activity or activities have
ceased being carried out.
(4) The Authority shall process an application for the
surrender of a permit submitted in accordance with this regulation
within thirty days from the receipt of the application. The Authority
shall issue a notice of surrender of a permit, which shall include the
following conditions
(a)
a requirement to monitor, and report by the date
that may be specified in the notice of surrender of a permit, and
in accordance with these regulations, verified emissions for the
year during which the notice becomes effective up to the date on
which the notice becomes effective;
(b)
a requirement to surrender, by the date that may be
specified in the notice of surrender of a permit, and in
accordance with these regulations, a quantity of allowances
equal to the verified emissions reported under paragraph (a);
(c)
a requirement to surrender, by the date that may be
specified in the notice of surrender of a permit, and in
accordance with these regulations, a quantity of allowances
equal to verified emissions not covered by surrendered
allowances in respect of years previous to the year when the
notice of surrender of a permit becomes effective.
Monitoring, reporting and verification of emissions
referred to in paragraph (a) shall be carried out in accordance with
monitoring, reporting and verification requirements in the greenhouse
gas emissions permit to which the application to surrender a permit
relates.
(5) The permit shall cease to have effect from the date on
which the notice for surrender of a permit becomes effective in so far
as it authorises the carrying out of an activity or activities in the
installation or installations covered by the permit
Provided that any conditions in the permit shall remain in
effect until the Authority is satisfied that the requirements under sub-
regulation (4) have been complied with or that there is no reasonable
possibility of further allowances being surrendered by the operator of
the installation or installations to which the notice for surrender of a
permit relates.
(6) The Authority shall notify the national registry
administrator of any application for the surrender of a permit made to
it and the coming into effect of such surrender. The national registry
administrator shall ensure that any changes required are made to the
account or accounts relating to the installation or installations to
which the surrender of a permit relates so as to reflect the surrender of
the permit.
(7) When a permit for an installation is surrendered without
sufficient allowances having been surrendered in accordance with
regulation 19 to cover all emissions reported in respect of that
installation, the operator of that installation shall be liable to the
imposition of an administrative fine of one hundred euro (€100) for
each tonne of carbon dioxide equivalent emitted for which the
operator has not surrendered allowances.
(8) From the 1st January, 2013, where, for the year in which an
operator surrendering a permit does not surrender sufficient
allowances, the annual average Harmonised European Index of
Consumer Prices published shows a percentage increase as compared
to the latest Harmonised European Index of Consumer Prices
published for the previous year, the administrative fine shall be
increased by the same percentage. The administrative fine as revised
pursuant to this sub-regulation shall apply to subsequent years unless
further increased in accordance with the Harmonized European Index
of Consumer Prices. For the purposes of this sub-regulation, each
allowance not surrendered by the operator for a tonne of carbon
dioxide equivalent emitted shall be considered as a separate
contravention.
(9) For the purposes of determining the total administrative
fine under sub-regulation (7), where the emissions of the installation
or installations are not known, or are not reported, or where the
Authority is satisfied that there is no reasonable possibility that a
verified quantity of emissions will be reported by the operator of the
installation or installations covered by the permit to be surrendered,
the Authority may itself determine the emissions from the activities
performed in the installation or installations. The Authority shall use
best available data and ensure that a conservative estimate is made
that does not underestimate emissions. The operator shall be liable to
the imposition of an administrative fine equal to the amount
established in sub-regulation (7) in respect of the quantity of
emissions estimated in terms of this sub-regulation.
(1)
The Authority may, at any time, revoke a
greenhouse gas emissions permit issued to an operator of an
installation.
(2) The Authority may revoke a permit in accordance with
sub-regulation (1) by issuing a notice of revocation of a permit to the
operator, which shall include the following
(a)
information clearly identifying the operator and the
installation or installations covered by the notice;
(b)
the reasons for the revocation of the greenhouse
gas emissions permit;
(c)
the date on which the notice takes effect, which
shall not be earlier than fifteen days from the date of the notice;
(d)
the requirement for the operator to monitor and
report, by the date that may be specified in the notice of
revocation of a permit, and in accordance with these
regulations, verified emissions for any years in which the
operator performed the activity or activities covered by the
permit and for which he did not submit a verified emissions
report;
(e)
the requirement for the operator to surrender, by
the date that may be specified in the notice of revocation of a
permit, and in accordance with these regulations, a quantity of
allowances equal to the amount of emissions reported, for any
years in which the operator performed the activity or activities
covered by the permit and in respect of which he did not
surrender allowances.
(3) The permit shall cease to have effect from the date on
which the notice for revocation of a permit becomes effective in so far
as it authorises the carrying out of an activity or activities in the
installations or installations covered by the permit
Provided that any conditions in the permit shall remain in
effect until the Authority is satisfied that the requirements under sub-
regulation (2) have been complied with or that there is no reasonable
possibility of further allowances being surrendered by the operator of
the installation to which the notice for revocation of a permit relates.
(4) The Authority shall notify the national registry
administrator of any revocation of a permit and the coming into effect
of such revocation. The national registry administrator shall ensure
that any changes required are made to the account or accounts
relating to the installation or installations to which the revocation of a
permit relates so as to reflect the revocation of the permit.
(5) When a permit for an installation is revoked without
sufficient allowances having been surrendered to cover all emissions
reported in respect of that installation in accordance with regulation
19, the operator of that installation shall be liable to the imposition of
an administrative fine of one hundred euro (€100) for each tonne of
carbon dioxide equivalent emitted for which the operator has not
surrendered allowances.
(6) From the 1st January, 2013, where, for the year in which an
operator surrendering a permit does not surrender sufficient
allowances, the annual average Harmonised European Index of
Consumer Prices published shows a percentage increase as compared
to the latest Harmonised European Index of Consumer Prices
published for the previous year, the administrative fine shall be
increased by the same percentage. The administrative fine as revised
pursuant to this sub-regulation shall apply to subsequent years unless
further increased in accordance with the Harmonized European Index
of Consumer Prices. For the purposes of this sub-regulation, each
allowance not surrendered by the operator for a tonne of carbon
dioxide equivalent emitted shall be considered as a separate
contravention.
(7) For the purposes of determining the total administrative
fine under sub-regulation (5), where the emissions of the installation
or installations are not known, or are not reported, or where the
Authority is satisfied that there is no reasonable possibility that a
verified quantity of emissions will be reported by the operator of the
installation or installations covered by the permit to be surrendered,
the Authority may itself determine the emissions from the activities
performed in the installation or installations. The Authority shall use
best available data and ensure that a conservative estimate is made
that does not underestimate emissions. The operator shall be liable to
the imposition of an administrative fine equal to the amount
established in sub-regulation (5) in respect of the quantity of
emissions estimated in terms of this sub-regulation.
(1)
The Authority shall allocate free Chapter III
allowances to an operator of an installation eligible to a free
allocation of Chapter III allowances pursuant to Directive 2003/87/
EC. Such an allocation shall be made in accordance with Directive
2003/87/EC and relevant decisions and regulations adopted by the
Commission pursuant to Directive 2003/87/EC.
(2) No free allocation shall be made in respect of any
electricity production, except for electricity produced from waste
gases.
(3) No free allocation shall be given to
(a)
electricity generators;
(b)
installations for the capture of carbon dioxide;
(c)
pipelines for transport of carbon dioxide; or
(d)
carbon dioxide storage sites.
(4) No free allocation shall be made in respect of any
electricity production by new entrants.
(5) District heating and high efficiency cogeneration for
economically justifiable demand shall be eligible for free allocation,
in respect of the production of heating or cooling, in accordance with
Directive 2003/87/EC and relevant decisions and regulations adopted
by the Commission pursuant to Directive 2003/87/EC.
(6) No free allocation shall be given to an installation that has
ceased its operations, unless the operator demonstrates to the
Authority that this installation will resume production within a
specified and reasonable time. An installation for which the
greenhouse gas emissions permit has been surrendered or has been
revoked shall be considered to have ceased its operations. An
installation for which the operation or resumption of operation is
technically impossible shall be considered to have ceased operations.
(7) For the eight-year period beginning the 1st January, 2013,
and any subsequent period, the Authority shall ensure that a list of
installations covered by these regulations in Malta, and any free
allocation to each installation to be given in accordance with this
regulation, are published.
(1)
The quantity of Chapter III allowances that will not
be allocated free of charge, as determined for Malta in accordance
with Directive 2003/87/EC, shall be auctioned by the auctioneer in
accordance with the relevant decisions and regulations adopted by the
Commission pursuant to Directive 2003/87/EC.
(2) The auctioneer shall act in accordance with the relevant
decisions and regulations adopted by the Commission pursuant to
Directive 2003/87/EC.
(1)
Allowances issued to operators of installations in Union registry.
terms of these regulations shall be held in the Union registry. An
operator of an installation shall have an operator holding account in
respect of that installation in the Union registry.
(2) The national registry administrator shall perform its
functions in accordance with the relevant decisions and regulations
adopted by the Commission pursuant to Directive 2003/87/EC
Provided that, in respect of operator holding accounts of
operators of installations to which these regulations apply, the
Authority shall act as the national registry administrator
Provided also that, where the Authority acts as the national
registry administrator there shall be no conflict of interest between
the Authority and holders of operator holding accounts.
(3) A request to open an operator holding account shall be
made by the Authority or the operator of the installation to the
national registry administrator.
(4) A request for the opening of an operator holding account
shall include all information required by the national registry
administrator in accordance with the relevant decisions and
regulations adopted by the Commission pursuant to Directive 2003/
87/EC and any requirements and terms and conditions made by the
national registry administrator.
(5) The national registry administrator shall open and
administer an operator holding account for an operator of an
installation in accordance with the relevant decisions and regulations
adopted by the Commission pursuant to Directive 2003/87/EC and
any terms and conditions it may make. The national registry
administrator shall not open an account unless it is satisfied that the
request is in accordance with the requirements of this regulation.
(6) An operator holding account holder and its nominated
authorised representatives shall act in accordance with the relevant
decisions and regulations adopted by the Commission pursuant to
Directive 2003/87/EC and any terms and conditions made by the
national registry administrator.
(7) Where an operator of an installation fails to comply with
any requirements of decisions and regulations adopted by the
Commission in respect of registries or terms and conditions made by
the national registry administrator in respect of registries, the national
registry administrator may prevent the transfer of allowances or other
accounting units into or out of any operator holding account held by
that operator until any non-compliance is rectified
Provided that the national registry administrator shall not
prevent the surrender or cancellation of allowances in accordance
with regulation 22.
(1)
The Authority shall, by the 28th February of each
year, issue the quantity of Chapter III allowances that are to be
allocated for that year to an installation as determined in accordance
with regulation 11.
(2) Issuance of allowances shall be carried out in accordance
with the relevant decisions and regulations adopted by the European
Commission pursuant to Directive 2003/87/EC.
(3) Where -
(a)
a permit has been changed, in accordance with
regulation 7, in such a way that it no longer applies to an
installation; or
(b)
a permit has been surrendered in accordance with
regulation 9; or
(c)
a permit has been revoked in accordance with
regulation 10,
the Authority shall inform the national registry administrator. The
Authority shall ensure that no further allowances are issued to the
operator in respect of an installation subject to any of the conditions
under this sub-regulation, for the first year after the year when the
change in the permit, the surrender of the permit or the revocation of
the permit has come into effect, and for subsequent years.
(4) Chapter III allowances issued in accordance with sub-
regulation (1) in respect of the period beginning the 1st January, 2013
and subsequent periods shall be valid for emissions during the period
for which they are issued.
(5) Four months after the beginning of the period commencing
the 1st January, 2013 and subsequent periods, the Authority shall
cancel allowances that are no longer valid for that period and have not
been surrendered and cancelled in accordance with regulation 19.
(6) For each period referred to in sub-regulation (4), the
Authority shall issue allowances to operators for the current period to
replace any allowances held by them which are cancelled in
accordance with sub-regulation (5).
(1)
The operator of an installation shall submit to the Monitoring of
Authority a monitoring plan setting out measures to monitor and annual
emissions.
report emissions of greenhouse gases specified in respect of the
activities carried out in that installation as listed in Schedule 1. These
measures shall be in accordance with
(a)
the principles set out in Schedule 3;
(b)
relevant decisions and regulations adopted by the
Commission pursuant to Directive 2003/87/EC; and
(c)
any other requirements made by the Authority in
respect of monitoring and reporting of emissions of greenhouse
gases from activities listed in Schedule 1.
(2) The operator of an installation shall submit a monitoring
and reporting plan for the first time to the Authority at the same time
as an application is made for a greenhouse gas emissions permit in
accordance with regulation 4.
(3) The monitoring plan submitted by an operator of an
installation pursuant to sub-regulation (1) shall be approved by the
Authority if it is satisfied that the plan is in accordance with the
requirements set out under this regulation. The Authority may request
from the operator of the installation any additional information it
deems appropriate for the approval of the plan.
(4) An operator of an installation shall notify the Authority of
any deviations from the monitoring plan that may occur at any time
after the approval of the plan by the Authority
Provided that the Authority shall be notified of any
deviation from the plan
(a)
as early as possible before the deviation occurs, if
the deviation is known to the operator or is made known to the
operator prior to its occurrence; or
(b)
immediately after the deviation occurs if the
occurrence of the deviation is not known to the operator or is
not made known to the operator before or at the time of its
occurrence.
(5) An operator of an installation shall maintain a documented
record, which shall include information in accordance with
requirements that may be established by the Authority, of any
deviations that occur during a monitoring year and shall submit such
record to the Authority together with the annual emissions report
submitted pursuant to regulation 16.
(6) The operator of an installation shall regularly check if the
approved monitoring plan reflects the nature and function of the
installation. An operator may at any time after the approval of the
monitoring plan of an installation, submit to the Authority proposed
modifications that have to be made to the plan, in accordance with the
relevant decisions and regulations adopted by the Commission
pursuant to Directive 2003/87/EC. The operator shall maintain a
documented record of all modifications to the monitoring plan. No
proposed significant modifications to an approved plan shall be valid
without the approval of the Authority.
(7) Where it deems appropriate, the Authority may request the
submission of a revised plan.
(8) An operator of an installation shall monitor emissions from
that installation during each monitoring year.
(9) Without prejudice to sub-regulation (4), an operator of an
installation shall monitor annual emissions in accordance with the
monitoring plan approved by the Authority in accordance with this
regulation. The Authority may take any action it deems necessary
under these regulations to ensure that an operator is monitoring and
reporting annual emissions in accordance with the approved
monitoring plan.
(1)
An operator of an installation shall report annual
emissions, monitored in accordance with regulation 15, for each
monitoring year in accordance with
(a)
the principles set out in Schedule 3; and
(b)
relevant decisions and regulations adopted by the
Commission pursuant to Directive 2003/87/EC; and
(c)
any other requirements made by the Authority in
respect of reporting of emissions of greenhouse gases from
activities listed in Schedule 1.
(2) An operator of an installation shall submit to the Authority
a report on the emissions from that installation for a monitoring year
by not later than the 31st March of the subsequent year.
(3) The report submitted by an operator of an installation
pursuant to sub-regulation (2) shall be verified by a verifier in
accordance with
(a)
the principles set out in Schedule 4; and
(b)
relevant decisions and regulations adopted by the
Commission pursuant to Directive 2003/87/EC; and
(c)
any other requirements made by the Authority in
respect of verification of reports of emissions of greenhouse
gases from activities listed in Schedule 1.
(4) A verification report shall be submitted by the operator of
an installation with the emission report submitted.
(5) Where an operator of an installation fails to submit an
annual emissions report for a monitoring year that has been verified
as satisfactory by the 31st March of the subsequent year, the national
registry administrator shall not allow the transfer of allowances or
any other accounting units out of the operator holding account until a
report from the operator in respect of that installation has been
verified as satisfactory
Provided that the national registry administrator shall not
prevent the surrender or cancellation of allowances in accordance
with regulation 19, or the issuance of allowances in exchange for
CERs or ERUs in accordance with regulation 20.
(6) A verifier performing verification of an annual emissions
report of an installation shall notify the Authority and the National
Accreditation Board - Malta of the planned time and place of the
verification and the identity of the installation whose annual
emissions report is subject to its verification by not later than thirty
days prior to the date when the verification is to be performed.
(1)
The Authority may perform any checks it deems Competent
necessary to ensure that a report submitted by an operator is in authority
acceptance of
accordance with regulation 16.
verified annual
emissions
reports and
(2) The Authority shall, on the basis of the information determination
emissions in
included in the submitted report, the verification report submitted in case of non-
accordance with regulation 16 and its own checks, and by not later reporting
non-
than thirty days after the date of submission of the report, determine verification.
whether it can accept the submitted report. The Authority shall not
accept a report of annual emissions for which the verification report
has not been submitted. The Authority shall inform the operator, in
writing or through other documented means, of its decision. Where it
deems necessary, the Authority may require the submission of a
revised annual emissions report. The revised annual emissions report
shall be verified in accordance with regulation 16.
(3) Where, in respect of any monitoring year, an operator of an
installation does not submit a verified emission report in accordance
with regulation 16, or where it is deemed that the operator has not
submitted an emissions report which is in accordance with the
requirements set out in regulation 16, the Authority may, unless there
is written agreement between the Authority and the operator
providing otherwise, itself determine the emissions for activities
performed in that installation for that year. The Authority shall use
best available data and ensure that a conservative estimate is made
that does not underestimate emissions. When annual emissions are
determined under this sub-regulation, the Authority shall consider the
requirements set out in Schedules 3 and 4
Provided that the Authority shall notify the operator of the
installation of the emissions as determined and the methodology used
to determine such emissions.
(1)
An operator of an installation who fails to submit a
monitoring plan in accordance with regulation 15 in respect of the
period beginning the 1st January, 2013 or a subsequent period, shall
be liable to the imposition
(a)
for an operator of an installation for which
emissions for the first calendar year of the period for which the
plan relates or for the first year of performing an activity
covered by these regulations during the period for which the
plan relates are equal to or less than fifty thousand (50,000)
tonnes carbon dioxide equivalents, of an administrative fine of
five thousand euro (€5,000) and, or, one hundred euro (€100)
for each day of non-compliance, from the date of a notice given
by the Authority to the operator;
(b)
for an operator of an installation for which
emissions for the first calendar year of the period for which the
plan relates or for the first year of performing an activity
covered by these regulations during the period for which the
plan relates are more than fifty thousand (50,000) tonnes of
carbon dioxide equivalents and equal to or less than five
hundred thousand (500,000) tonnes of carbon dioxide
equivalent, of an administrative fine of ten thousand euro
(€10,000) and, or, three hundred euro (€300) for each day of
non-compliance, from the date of a notice given by the
Authority to the operator;
(c)
for an operator of an installation for which
emissions for the first calendar year of the period for which the
plan relates or for the first year of performing an activity
covered by these regulations during the period for which the
plan relates are more than five hundred thousand (500,000)
tonnes of carbon dioxide equivalents, of an administrative fine
of fifty thousand euro (€50,000) and, or, six hundred euro
(€600) for each day of non-compliance, from the date of a
notice given by the Authority to the operator.
(2) An operator of an installation who fails to monitor annual
emissions during a year in accordance with regulation 15 or fails to
submit a verified annual emissions report in respect of a year in
accordance with regulation 16, shall be liable to the imposition
(a)
for an operator of an installation for which
emissions for that year are equal to or less than fifty thousand
(50,000) tonnes carbon dioxide equivalents, of an
administrative fine of five thousand euro (€5,000) and, or, one
hundred euro (€100) for each day of non-compliance, from the
date of a notice given by the Authority to the operator;
(b)
for an operator of an installation for which
emissions for that year are more than fifty thousand (50,000)
tonnes of carbon dioxide equivalents and equal to or less than
five hundred thousand (500,000) tonnes carbon dioxide
equivalents, of an administrative fine of ten thousand euro
(€10,000) and, or, three hundred euro (€300) for each day of
non-compliance, from the date of a notice given by the
Authority to the operator;
(c)
for an operator of an installation for which
emissions for that year are more than five hundred thousand
(500,000) tonnes carbon dioxide equivalents, of an
administrative fine of fifty thousand euro (€50,000) and, or, six
hundred euro (€600) for each day of non-compliance, from the
date of a notice given by the Authority to the operator.
(3) For the purposes of determining the administrative fine
under this regulation, where the emissions of the installation are not
known or where the Authority is satisfied that there is no reasonable
possibility that a verified quantity of emissions will be reported by the
operator of the installation, the Authority may itself determine the
emissions from the activities performed in that installation. The
Authority shall use best available data and ensure that a conservative
estimate is made that does not underestimate emissions. The operator
of the installation shall be liable to the imposition of an administrative
fine equal to the amounts established in sub-regulations (1) and (2) in
respect of the quantity of emissions estimated by the Authority in
terms of this sub-regulation.
(1)
By the 30th April each year, an operator of an
installation shall surrender a number of allowances, other than
Chapter II allowances, equal to the total emissions from that
installation during the preceding calendar year as reported and
verified in accordance with regulation 16, or as determined by the
Authority in accordance with regulation 17. An operator of an
installation may not surrender Chapter II allowances.
(2) The national registry administrator shall cancel allowances
surrendered in accordance with sub-regulation (1).
(3) The national registry administrator shall cancel allowances
at any time at the request of an operator of an installation holding
those allowances.
(4) An obligation to surrender allowances shall not arise in
respect of emissions verified as captured and transported for
permanent storage to a facility for which a permit is in force in
accordance with Directive 2009/31/EC.
(5) Surrender and cancellation of allowances shall be carried
out in accordance with the relevant decisions and regulations adopted
by the Commission pursuant to Directive 2003/87/EC.
(6) The Authority shall publish the name of any operator who
is in breach of the requirement to surrender sufficient allowances
under sub-regulation (1).
(7) An operator who does not surrender sufficient allowances
by the 30th April of each year as required under sub-regulation (1) to
cover its emissions during the preceding year shall be liable to the
imposition of an administrative fine of one hundred euro (€100) for
each tonne of carbon dioxide equivalent emitted for which the
operator has not surrendered allowances.
(8) From the 1st January, 2013, where, for the year in which an
operator of an installation does not surrender sufficient allowances to
cover emissions during that year in accordance with sub-regulation
(1), the annual average Harmonized European Index of Consumer
Prices published shows a percentage increase as compared to the
latest Harmonized European Index of Consumer Prices published for
the previous year, the administrative fine shall be increased by the
same percentage. The administrative fine as revised pursuant to this
sub-regulation shall apply to subsequent years unless further
increased in accordance with the Harmonized European Index of
Consumer Prices. For the purposes of this sub-regulation, each
allowance not surrendered by the operator for a tonne of carbon
dioxide equivalent emitted shall be considered as a separate
contravention.
(9) The imposition of an administrative fine as prescribed in
sub-regulation (7) shall not release the operator from the obligation to
surrender an amount of allowances equal to those excess emissions in
respect of which the administrative fine is paid when surrendering
allowances in relation to the following calendar year.
(10) Where an operator of an installation fails to surrender
allowances in accordance with sub-regulation (1), the national
registry administrator shall not allow the transfer of allowances or
any other accounting units out of the operator holding account opened
in respect of that installation until the operator complies with the
requirement to surrender allowances
Provided that the national registry administrator shall not
prevent the surrender of allowances in accordance with sub-
regulation (1) or the cancellation of allowances in accordance with
sub-regulation (4), or the issuance of allowances in exchange for
CERs or ERUs in accordance with regulation 20.
(1)
To the extent that the levels of CER and ERU use, Use of CERs
allowed to an operator of an installation for the period from 2008 to and
project activities
2012, have not been used up, or where an entitlement to use credits is in
emissions
granted under sub-regulation (5), the operator may request to be trading scheme
issued allowances valid from 2013 onwards in exchange for CERs for
1st January
and ERUs issued in respect of emission reductions up until 2012 from 2013 to 31st
December 2020.
project types which were eligible for use in the Union scheme during
the period from 2008 to 2012. Until the 31st March, 2015, the
Authority shall make such an exchange on request.
(2) To the extent that the levels of CER and ERU use, allowed
to an operator of an installation for the period 2008 to 2012, have not
been used up, or where an entitlement to use credits is granted under
sub-regulation (5), the operator may exchange CERs and ERUs
issued in respect of emission reductions from 2013 onwards from
project types that were registered before 2013 and which were
eligible for use in the Union scheme during the period from 2008 to
2012, for allowances valid from 2013 onwards.
(3) To the extent that the levels of CER and ERU use, allowed
to an operator of an installation for the period from 2008 to 2012,
have not been used up, or where an entitlement to use credits is
granted under sub-regulation (5), the operator may exchange CERs
issued in respect of emission reductions from 2013 onwards from
project types started from 2013 onwards in least developed countries
and which were eligible for use in the Union scheme during the
period from 2008 to 2012, for allowances valid from 2013 onwards.
This sub-regulation shall apply until such countries have ratified a
relevant agreement with the Union or until 2020, whichever is the
earlier.
(4) To the extent that the levels of CER and ERU use, allowed
to an operator of an installation for the period from 2008 to 2012,
have not been used up, or where an entitlement to use credits is
granted under sub-regulation (5), the operator may use credits from
projects or other emission reducing activities in accordance with any
agreements that may be concluded by the Union with third countries,
up to levels of use as specified in such agreements, to comply with
obligations under these regulations.
(5) For the period from 2013 to 2020 an operator of an
installation shall be entitled to use an additional quantity of CERs and
ERUs up to an amount corresponding to a percentage of its verified
emissions during the period from the 1st January, 2013 to the 31st
December, 2020, as may be established by the Commission pursuant
to Directive 2003/87/EC.
(6) For the purposes of this regulation, operators shall not use
CERs or ERUs for which restrictions on use apply in accordance with
relevant decisions and regulations adopted by the Commission
pursuant to Directive 2003/87/EC.
No CERs or ERUs shall be issued for reductions or
limitations of greenhouse gas emissions with respect to activities that
fall within the scope of these regulations.
Decisions related to the allocation of allowances to
operators of installations and reports of emissions submitted in
accordance with regulation 17 shall be made available to the public in
accordance with the Freedom of Access to Information on the
Environment Regulations
Provided that any access to personal data shall be made in
accordance with the Data Protection Act and that information covered
by professional secrecy may not be disclosed to any other person or
authority except by virtue of the applicable laws, regulations,
administrative provisions and, or, the provisions of the Professional
Secrecy Act
Provided also that without prejudice to this regulation and
to the obligation which may be imposed on the Authority to disclose
any information, the Authority shall not disclose any confidential
information or any parts thereof or any other information which
should be treated as commercially confidential
Provided further that any information which shall be
treated as commercially confidential shall be made known at all times
to the Authority.
The Authority may require that submissions of Submission of
applications, monitoring and reporting plans and reports under these applications,
monitoring
regulations are made in the form and manner and by means of the plans
reports.
medium as specified by it.
The revenue from the auctioning of allowances, after Revenue from
deducting the audited costs to administer the scheme agreed to auctioning
allowances.
between the Ministry responsible for finance and the Malta Resources
Authority, shall accrue to the consolidated fund.
The Administrative Review Tribunal shall have Administrative
Review
jurisdiction to hear and determine appeals from decisions of the Tribunal.
Authority made under these regulations.
The European Community Greenhouse Gas Emissions Revokes Legal
Notice 140 of
Trading Scheme Regulations, 2005, are hereby revoked.
2005. Schedule 1
Regulations 1(2), 2, 3, 4(1), 4(2), 4(4), 5(1), 5(2), 5(3)(c), 5(3)(d),
5(3)(e), 6(3)(e), 7(1)(c), 9(1), 15(1), 15(1)(c), 16(1)(a), 16(1)(c) and 16(3)(c)
Categories of Activities for which these Regulations apply
1. Installations or parts of installations used for research, development and
testing of new products and processes and installations exclusively using biomass
are not covered by these Regulations.
2. The threshold values given below generally refer to production
capacities or outputs. Where several activities falling under the same category are
carried out in the same installation, the capacities of such activities are added
together.
3. When the total rated thermal input of an installation is calculated in
order to decide upon its inclusion in the Community scheme, the rated thermal
inputs of all technical units which are part of it, in which fuels are combusted
within the installation, are added together. These units could include all types of
boilers, burners, turbines, heaters, furnaces, incinerators, calciners, kilns, ovens,
dryers, engines, fuel cells, chemical looping combustion units, flares, and thermal
and catalytic post-combustion units. Units with a rated thermal input below 3MW
and units which use exclusively biomass shall not be taken into account for the
purposes of this calculation. ‘Units using exclusively biomass’ includes units
which use fossil fuels only during start-up or shut-down of the unit.
4. If a unit serves an activity for which the threshold is not expressed as
total rated thermal input, the threshold of this activity shall take precedence for the
decision about the inclusion in the Community scheme.
5. When the capacity threshold of any activity in this Schedule is found to
be exceeded in an installation, all units in which fuels are combusted, other than
units for the incineration of hazardous or municipal waste, shall be included in the
greenhouse gas emission permit.
Activities
Greenhouse gases
Combustion of fuels in installations with a total rated thermal input Carbon dioxide
exceeding 20MW (except in installations for the incineration of
hazardous or municipal waste)
Refining of mineral oil
Carbon dioxide
Production of coke
Carbon dioxide
Metal ore (including sulphide ore) roasting or sintering, including Carbon dioxide
pelletisation
Production of pig iron or steel (primary or secondary fusion) including Carbon dioxide
continuous casting, with a capacity exceeding 2.5 tonnes per hour
Production or processing of ferrous metals (including ferro-alloys) Carbon dioxide
where combustion units with a total rated thermal input exceeding
20MW are operated. Processing includes, inter alia, rolling mills, re-
heaters, annealing furnaces, smitheries, foundries, coating and pickling
Production of primary aluminium
Carbon dioxide
perfluorocarbons
Production of secondary aluminium where combustion units with a total Carbon dioxide
rated thermal input exceeding 20MW are operated
Production or processing of non-ferrous metals, including production of Carbon dioxide
alloys, refining, foundry casting, etc., where combustion units with a
total rated thermal input (including fuels used as reducing agents)
exceeding 20MW are operated
Production of cement clinker in rotary kilns with a production capacity Carbon dioxide
exceeding 500 tonnes per day or in other furnaces with a production
capacity exceeding 50 tonnes per day
Production of lime or calcinations of dolomite or magnesite in rotary Carbon dioxide
kilns or in other furnaces with a production capacity exceeding 50 tonnes
per day
Manufacture of glass including glass fibre with a melting capacity Carbon dioxide
exceeding 20 tonnes per day
Manufacture of ceramic products by firing, in particular roofing tiles, Carbon dioxide
bricks, refractory bricks, tiles, stoneware or porcelain, with a production
capacity exceeding 75 tonnes per day
Manufacture of mineral wool insulation material using glass, rock or slag Carbon dioxide
with a melting capacity exceeding 20 tonnes per day
Drying or calcinations of gypsum or production of plaster boards and Carbon dioxide
other gypsum products, where combustion units with a total rated
thermal input exceeding 20MW are operated
Production of pulp from timber or other fibrous materials
Carbon dioxide
Production of paper or cardboard with a production capacity exceeding Carbon dioxide
20 tonnes per day
Production of carbon black involving the carbonisation of organic Carbon dioxide
substances such as oils, tars, cracker and distillation residues, where
combustion units with a total rated thermal input exceeding 20MW are
operated
Production of nitric acid
Carbon dioxide
nitrous oxide
Production of adipic acid
Carbon dioxide
nitrous oxide
Production of glyoxal and glyoxylic acid
Carbon dioxide
nitrous oxide
Production of ammonia
Carbon dioxide
Production of bulk organic chemicals by cracking, reforming, partial or Carbon dioxide
full oxidation or by similar processes, with a production capacity
exceeding 100 tonnes per day
Production of hydrogen (H 2 ) and synthesis gas by reforming or partial Carbon dioxide
oxidation with a production capacity exceeding 25 tonnes per day
Production of soda ash (Na 2 CO 3 ) and sodium bicarbonate (NaHCO 3 )
Carbon dioxide
Capture of greenhouse gases from installations covered by the Directive Carbon dioxide
for the purpose of transport and geological storage in a storage site
permitted under Directive 2009/31/EC
Transport of greenhouse gases by pipelines for geological storage in a Carbon dioxide
storage site permitted under Directive 2009/31/EC
Geological storage of greenhouse gases in a storage site permitted under Carbon dioxide
Directive 2009/31/EC
Schedule 2
Regulation 2
Greenhouse gases
Carbon dioxide (CO 2 )
Methane (CH 4 )
Nitrous Oxide (N 2 O)
Hydrofluorocarbons (HFCs)
Perfluorocarbons (PFCs)
Sulphur Hexafluoride (SF 6 )
Schedule 3
Regulations 15(1)(a), 16(1)(a)
Principles for Monitoring and Reporting of annual emissions
Monitoring of carbon dioxide emissions
Emissions shall be monitored either by calculation or on the basis of
measurement.
Calculation
Calculations of emissions shall be performed using the formula
Activity data x Emission factor x Oxidation factor
Activity data (fuel used, production rate etc.) shall be monitored on the basis
of supply data or measurement.
Accepted emission factors shall be used. Activity-specific emission factors
are acceptable for all fuels. Default factors are acceptable for all fuels except non-
commercial ones (waste fuels such as tyres and industrial process gases). Seam-
specific defaults for coal, and EU-specific or producer country-specific defaults
for natural gas shall be further elaborated. IPCC default values are acceptable for
refinery products. The emission factor for biomass shall be zero.
If the emission factor does not account of the fact that some of the carbon is
not oxidized, then an additional oxidation factor shall be used. If activity-specific
emission factors have been calculated and already take oxidation into account,
then an oxidation factor need not be applied.
Default oxidation factors developed pursuant to Directive 96/61/EC * shall be
used, unless the operator can demonstrate that activity-specific factors are more
accurate.
A separate calculation shall be made for each activity, installation and for
each fuel.
Measurement
Measurement of emissions shall use standardized or accepted methods, and
shall be corroborated by a supporting calculation of emissions.
Monitoring of emissions of other greenhouse gases
Standardised or accepted methods shall be used, as developed and adopted by
the Commission in collaboration with all relevant stakeholders.
Reporting of emissions
Each operator shall include the following information in the report for an
installation
A.
Data identifying the installation, including
-
Name of the installation;
-
Its address, including postcode and country;
-
Type and number of activities listed in Schedule 1 carried
out in the installation;
-
Address, telephone, fax and email details for a contact
person; and
-
Name of the owner of the installation, and of any parent
company.
B.
For each activity listed in Schedule 1 to these regulations carried
out on the site for which emissions are calculated
-
Activity data;
-
Emission factors;
* Directive 96/61/EC: Council Directive 96/61/EC of 24 September 1996 concerning integrated pollution prevention and control.
-
Oxidation factors;
-
Total emissions; and
-
Uncertainty.
For each activity listed in Schedule 1 to these regulations carried
out on the site for which emissions are measured
-
Total emissions;
-
Information on the reliability of measurement methods; and
-
Uncertainty.
For emissions from combustion, the report shall also include the
oxidation factor, unless oxidation has already been taken into account in the
development of an activity-specific emission factor.
Schedule 4
Regulation 16(3)(a)
Criteria for Verification
General Principles
1. Emissions from each activity listed in Schedule 1 to these regulations
shall be subject to verification
2. The verification process shall include consideration of the report
submitted pursuant to regulation 16 and of monitoring during the preceding year. It
shall address the reliability, credibility and accuracy of monitoring systems and the
reported data and information relating to emissions, in particular
(a)
the reported activity data and related measurements and
calculations;
(b)
the choice and the employment of emission factors;
(c)
the calculations leading to the determination of the overall
emissions; and
(d)
if measurement is used, the appropriateness of the choice and
the employment of measuring methods.
3. Reported emissions may only be validated if reliable and credible data
and information allow the emissions to be determined with a high degree of
certainty. A high degree of certainty would require the operator to show that
(a)
the reported data is free of inconsistencies;
(b)
the collection of data has been carried out in accordance with the
applicable scientific standards; and
(c)
the relevant records of the installation are complete and
consistent.
4. The verifier shall be given access to all sites and information in relation
to the subject of the verification.
5. The verifier shall take into account whether the installation is registered
under the Community eco-management and audit scheme (EMAS).
Methodology
Strategic analysis
6. The verification shall be based on a strategic analysis of all the activities
carried out in the installation. This requires the verifier to have an overview of all
the activities and their significance for emissions.
Process analysis
7. The verification of the information submitted shall, where appropriate,
be carried out on the site of the installation. The verifier shall use spot-checks to
determine the reliability of the reported data and information.
Risk analysis
8. The verifier shall submit all the sources of emissions in the installation
to an evaluation with regard to the reliability of the data of each source
contributing to the overall emissions of the installation.
9. On the basis of this analysis the verifier shall explicitly identify those
sources with a high risk of error and other aspects of the monitoring and reporting
procedure which are likely to contribute to errors in the determination of the
overall emissions. This especially involves the choice of the emission factors and
the calculations necessary to determine the level of the emissions from individual
sources. Particular attention shall be given to those sources with a high risk of
error and the abovementioned aspects of the monitoring procedure.
10. The verifier shall take into consideration any effective risk control
methods applied by the operator with a view to minimizing the degree of
uncertainty.
Report
11. The verifier shall prepare a report on the validation process stating
whether the report submitted pursuant to regulation 16 of these regulations is
satisfactory. This report shall specify all issues relevant to the work carried out. A
statement that the report submitted pursuant to regulation 16 of these regulations is
satisfactory may be made if, in the opinion of the verifier, the total emissions are
not materially misstated.
Minimum competency requirements for the verifier
12. The verifier shall be independent of the operator, carry out his activities
in a sound and objective professional manner, and understand
(a)
the provisions of these regulations, as well as relevant standards
and guidance adopted by the Authority pursuant to these regulations;
(b)
the legislative, regulatory, and administrative requirements
relevant to the activities being verified; and
(c)
the generation of all information related to each source of
emissions in the installation, in particular, relating to the collection,
measurement, calculation and reporting of data.