Management of Radioactive Waste Regulations, 2013
Table of Provisions (16)
Statutory Text (16 Articles)
L.N. 186 of 2013
NATIONAL INTEREST (ENABLING POWERS) ACT
(CAP. 365)
Management of Radioactive Waste Regulations, 2013
IN exercise of the powers conferred by article 3 of the National
Interest (Enabling Powers) Act, the Prime Minister has made the
following regulations:-
(1)
The title of these regulations is the Management of
Radioactive Waste Regulations, 2013.
(2) These regulations shall come into force on the 23rd August
2013.
The aim of these regulations is to ensure that radioactive
waste is managed in a manner that protects human health and the
environment now and in the future without imposing undue burdens
on future generations.
(1)
These regulations provide the arrangements for
safety in radioactive waste management to protect workers and the
general public against the dangers arising from ionising radiation.
(2) These regulations shall apply to all stages of radioactive
waste management, from generation to disposal, when the radioactive
waste results from civilian activities.
(3) These regulations provide for the necessary public
information and participation in relation to radioactive waste
management while having due regard to security and proprietary
information issues.
(4) These regulations bring into effect the provisions of
Council Directive 2011/70/Euratom of 19 July 2011 establishing a
Community framework for the responsible and safe management of
spent fuel and radioactive waste and the International Atomic Energy
Agency’s Joint Convention on the Safety of Spent Fuel Management
and on the Safety of Radioactive Waste Management.
(5) These regulations provide additional measures, procedures
and guidance to those mentioned in the Nuclear Safety and Radiation
Protection Regulations.
(1)
These regulations shall apply to all radioactive Applicability.
waste with the exception of
(a)
releases authorised by virtue of regulation 19(4) of
the Nuclear Safety and Radiation Protection Regulations; and
(b)
waste which may be radioactive which falls within
the scope of the Waste Management (Management of Waste S.L. 504.87
from Extractive Industries and Backfilling) Regulations.
(2) Regulation 10 shall not apply to repatriation of disused
sealed sources to a supplier or manufacturer.
(3) These regulations allow for the return of radioactive waste
after processing in Malta to its country of origin where
(a)
the radioactive waste is to be shipped to that
Member State or undertaking for processing; or
(b)
other material is to be shipped to that Member State
or undertaking with the purpose of recovering the radioactive
waste.
For the purpose of these regulations, the following Interpretation.
definitions shall apply
"closure" means the completion of all operations at some time
after the emplacement of radioactive waste in a disposal facility,
including the final engineering or other work required to bring the
facility to a condition that will be safe in the long term;
"disposal" means the emplacement of radioactive waste in a
facility without the intention of retrieval;
"disposal facility" means any facility or installation the primary
purpose of which is radioactive waste disposal;
"licence" means a legal document issued by the Radiation
Protection Board related to the management of radioactive waste, or
to confer responsibility for siting, design, construction,
commissioning, operation, decommissioning or closure of a
radioactive waste management facility;
"licence holder" means a legal or natural person having overall
responsibility for any activity or facility related to the management of
radioactive waste as specified in a licence;
"Radiation Protection Board" means the Radiation Protection
Board established by virtue of regulation 9 of the Nuclear Safety and S.L. 365.15
Radiation Protection Regulations;
"radioactive waste" means radioactive material in gaseous,
liquid or solid form for which no further use is foreseen or considered
by the Radiation Protection Board;
"radioactive waste management" means all activities that relate
to handling, pre-treatment, treatment, conditioning, storage, or
disposal of radioactive waste, excluding off-site transportation;
"radioactive waste management facility" means any facility or
installation the primary purpose of which is radioactive waste
management;
"storage" means the holding of radioactive waste in a facility
with the intention of retrieval.
(1)
The objective of the radioactive waste management
programme is to enable radioactive waste to be treated in a manner
that protects human health and the environment now and in the future
without imposing undue burdens on future generations.
(2) The Radiation Protection Board has the responsibility for
the management of radioactive waste through the actions of its
member entities and through the radioactive waste national
programme. This programme includes a national policy and strategy
for the management of radioactive waste. The policy reflects the
Maltese priorities, circumstances, structures, and available human
and financial resources whilst the strategy shall implement the policy.
(3) The national programme shall consider all stages of
radioactive waste management, from generation to disposal.
(4) The responsibility of the coordination of the
implementation of the national programme rests with the Radiation
Protection Board (RPB).
(5) In connection with radioactive waste management
facilities due consideration will be given, but will not be limited to
(a)
the siting of the facility;
(b)
design and construction aspects of the facility;
(c)
safety and environmental assessments;
(d)
operational aspects; and
(e)
post-closure aspects.
(6) In the event that radioactive waste is sent overseas for
processing, the ultimate responsibility for the safe and responsible
disposal of those materials will remain in Malta or the other country
from which the radioactive material was shipped.
(7) The policy and strategy shall specify
(a)
the requirement for the minimisation of radioactive
waste; generation of radioactive waste shall be kept to the
minimum which is reasonably practicable, both in terms of
activity and volume, by means of appropriate design measures
and of operating and decommissioning practices, including the
recycling and reuse of materials;
(b)
the interdependencies between all steps in
radioactive waste generation and management shall be taken
into account;
(c)
the use of passive safety features for the long term
management of radioactive waste;
(d)
the need for the implementation of measures to
follow a graded approach;
(e)
the requirements for on-site and off-site emergency
plans;
(f)
financing systems for the management of waste
including the polluter pays principle;
(g)
the need for evidence-based and documented
decision-making process shall be applied with regard to all
stages of the management of radioactive waste;
(h)
that radioactive waste shall be disposed of in the
Member State in which it was generated, unless at the time of
shipment an agreement, taking into account the Waste S.L. 504.38
Management (Supervision and Control of Shipments of
Radioactive Waste and Spent Fuel) Regulations, has entered
into force between Malta and another country to use a disposal
facility in one of them;
(i)
that radioactive waste (stipulated in regulation 4)
shall be centrally managed waste in the long term;
(j)
the significant milestones to achieve the permanent
solution (including central storage and disposal) and timeframes
for the achievement of those milestones. These milestones will
include
(i)
the setting up of a central storage facility;
(ii)
disposal of radioactive waste;
(k)
the concepts or plans for the post-closure period of
a disposal facility’s lifetime, including the period during which
appropriate controls are retained and the means to be employed
to preserve knowledge of that facility in the longer term;
(l)
the assignment of responsibilities to the various
stakeholders;
(m)
research, development and demonstration activities
that are needed in order to implement solutions for the
management of radioactive waste;
(n)
an assessment of the national programme costs and
the underlying basis and hypotheses for that assessment, which
must include a profile over time;
(o)
financing schemes;
(p)
public information, involvement and transparency
policy or process
(i) necessary information on the management of
radioactive waste be made available to workers and the
general public. Information shall be made available to the
public in accordance with national legislation and
international obligations, provided that this does not
jeopardise other interests such as, inter alia, security,
recognised in national legislation or international
obligations;
(ii) to ensure that the public be given the
necessary opportunities to participate effectively in the
decision-making process regarding radioactive waste
management in accordance with national legislation and
international obligations;
(q)
gaining control over sources that are out of
regulatory control;
(r)
source recovery plan;
(s)
if there is no licence holder for a source or other
responsible party, the responsibility for the source rests with the
Government of Malta;
(t)
requirements for waste conditioning;
(u)
return of new sealed sources;
(v)
discharges from nuclear medicine departments;
(w)
require all parties to make arrangements for
education and training for their staff, as well as research and
development activities to cover the needs of the national
programme for radioactive waste management in order to
obtain, maintain and to further develop necessary expertise and
skills.
(1)
The competent authority that shall have overall Competent
responsibility for the implementation of these regulations is the authority.
Radiation Protection Board, established under regulation 9 of the S.L. 365.15
Nuclear Safety and Radiation Protection Regulations.
(2) It shall be the joint duty of the member agencies
constituting the Board to ensure matters pertaining to these
regulations are carried out in close collaboration and as efficiently as
possible, and the Occupational Health and Safety Authority shall take
the lead in co-ordinating the administrative actions.
The functions of the Board with respect to these Functions of the
Board.
regulations shall be to
(a)
be responsible for the establishment and
implementation of the national programme and the key
performance indicators to monitor progress towards
implementation;
(b)
to assess the national programme costs and the
underlying basis and hypotheses for that assessment, which
must include a profile over time;
(c)
advise the Prime Minister pursuant to regulation
9(3)(b) of the Nuclear Safety and Radiation Protection S.L. 365.15
Regulations, on the allocation of responsibility to the bodies
involved in the different steps of radioactive waste
management; in particular, the national framework shall give
primary responsibility for radioactive waste to their generators
or, under specific circumstances, to a licence holder to whom
this responsibility has been entrusted by competent bodies;
(d)
advise the Prime Minister pursuant to regulation
9(3)(b) of the Nuclear Safety and Radiation Protection
Regulations on the finance required for the national programme;
(e)
maintain an inventory of all radioactive waste and
estimates for future quantities, indicating the location and
amount of the radioactive waste in accordance with appropriate
classification of the radioactive waste;
(f)
licence of radioactive waste management activities,
facilities or both, including the prohibition of radioactive waste
management activities, of the operation of a radioactive waste
management facility without a licence or both and, if
appropriate, prescribing conditions for further management of
the activity, facility or both;
(g)
provide a system of appropriate control, a
management system, regulatory inspections, documentation and
reporting obligations for radioactive waste management
activities, facilities or both, including appropriate measures for
the post-closure periods of disposal facilities;
(h)
perform enforcement actions, including the
suspension of activities and the modification, expiration or
revocation of a licence together with requirements, if
appropriate, for alternative solutions that lead to improved
safety;
(i)
seek to improve the national framework, taking
into account operating experience, insights gained from the
decision-making process referred to in regulation 6(7)(g), and
the development of relevant technology and research;
(j)
perform reviews and update as required its national
programme, taking into account technical and scientific
progress as appropriate as well as recommendations, lessons
learned and good practices from peer reviews;
(k)
notify the national programme and any subsequent
significant changes to the Commission;
(l)
report to the Commission on the implementation of
Council Directive 2011/70/Euratom of 19 July 2011
establishing a Community framework for the responsible and
safe management of spent fuel and radioactive waste, for the
first time by 23 August 2015, and every three years thereafter,
taking advantage of the review and reporting under the Joint
Convention;
(m)
respond to any request from the Commission for
any clarification made in connection with the national
programme;
(n)
at least every ten years, arrange for self-
assessments of the national framework, Radiation Protection
Board, national programme and its implementation, and invite
international peer review of the national framework, Radiation
Protection Board and/or national programme with the aim of
ensuring that high safety standards are achieved in the safe
management of radioactive waste. The outcomes of any peer
review shall be reported to the Commission and the other
Member States, and may be made available to the public where
there is no conflict with security and proprietary information;
(o)
meet the Maltese reporting requirements and attend
meetings under the Joint Convention on the Safety of Spent
Fuel Management and on the Safety of Radioactive Waste
Management;
(p)
require that licence holders establish and
implement integrated management systems, including quality
assurance, which give due priority for overall management of
radioactive waste to safety and are regularly verified by the
Radiation Protection Board.
(1)
The prime responsibility for the safety of Licence holders.
radioactive waste management facilities and, or activities rest with
the licence holder.
(2) Licence holders shall regularly assess, verify and
continuously improve, as far as is reasonably achievable, the safety of
the radioactive waste management facility or activity in a systematic
and verifiable manner. This shall be achieved through an appropriate
safety assessment, other arguments and evidence.
(3) (a)
As part of the licensing of a facility or activity, the
safety demonstration shall cover the development and operation of an
activity and the development, operation and decommissioning of a
facility or closure of a disposal facility as well as the post-closure
phase of a disposal facility. The extent of the safety demonstration
shall be commensurate with the complexity of the operation and the
magnitude of the hazards associated with the radioactive waste, and
the facility or activity.
(b)
The licensing process shall contribute to safety in
the facility or activity during normal operating conditions, anticipated
operational occurrences and design basis accidents. It shall provide
the required assurance of safety in the facility or activity. Measures
shall be in place to prevent accidents and mitigate the consequences
of accidents, including verification of physical barriers and the
licence holder’s administrative protection procedures that would have
to fail before workers and the general public would be significantly
affected by ionising radiation. That approach shall identify and
reduce uncertainties.
(4) Licence holders shall establish and implement integrated
management systems, including quality assurance, which give due
priority for overall management of radioactive waste to safety.
(5) Licence holders shall provide for and maintain adequate
financial and human resources to fulfil their obligations with respect
to the safety of radioactive waste management as laid down in sub-
regulations (1) to (4).
Prior to a shipment to a third country, the Radiation
Protection Board shall inform the Commission of the content of any
such agreement and take reasonable measures to be assured that
(a)
the country of destination has concluded an
agreement with the Community covering radioactive waste
management or is a party to the Joint Convention on the Safety
of Spent Fuel Management and on the Safety of Radioactive
Waste Management ("the Joint Convention");
(b)
the country of destination has radioactive waste
management and disposal programmes with objectives
representing a high level of safety equivalent to those
established by these regulations;
(c)
the disposal facility in the country of destination is
authorised for the radioactive waste to be shipped, is operating
prior to the shipment, and is managed in accordance with the
requirements set down in the radioactive waste management and
disposal programme of that country of destination.
Licence holders are responsible for their Radioactive waste
and through the polluter pays principle and are responsible for all
financing of the management of their waste.
(1)
The member agencies of the Radiation Protection
Board shall enforce their respective regulatory functions within their
remit of matters pertaining to these regulations through their
respective powers.
(2) In any proceedings for an offence under these regulations
consisting of a failure to comply with a duty or requirement to do
something, it shall be for the accused to prove, as the case may be,
that it was not practicable to do more than was in fact done to satisfy
the requirement or duty, or that there was no better practicable means
than was in fact used to satisfy the duty or requirement.
Any person who commits an offence against these Offences and
regulations shall, on conviction, be liable to imprisonment for a penalties.
period of not more than five years or to a fine (multa) not exceeding
one hundred and sixteen thousand four hundred and sixty-eight euro
(€116,468), or to both such imprisonment and fine.
The Court of Magistrates (Malta) and the Court of Procedures
Magistrates (Gozo) as courts of criminal judicature, shall, before
and Gozo
notwithstanding the provisions of article 370 of the Criminal Code, be Courts.
competent to try all offences against these regulations.
Where the facts constituting a breach of any of the above Proceedings in
provisions also constitute a breach of any other law prohibited by the respect
other law.
particular regulations, proceedings shall not be taken in respect of the
breach of these regulations, but only in respect of the breach of the
other law.