10 tal-2013
Table of Provisions (36)
Statutory Text (36 Articles)
L.N. 10 of 2013
ENVIRONMENT AND DEVELOPMENT PLANNING ACT
(CAP. 504)
Industrial Emissions (Integrated Pollution Prevention
and Control) Regulations, 2013
BY VIRTUE of the powers conferred by articles 2, 61, 64 and
66 of the Environment and Development Planning Act, the Minister
for Tourism, Culture and the Environment, in consultation with the
Malta Environment and Planning Authority, has made the following
regulations:-
(1) The title of these regulations is the Industrial Citation and
Emissions (Integrated Pollution Prevention and Control) Regulations, commencement.
2013. (2) These regulations shall be deemed to have come into force
on the 7th January, 2013.
Categories of activities referred to in regulation 3
The threshold values given below generally refer to production capacities or
outputs. Where several activities falling under the same activity description
containing a threshold are operated in the same installation, the capacities of such
activities are added together. For waste management activities, this calculation
shall apply at the level of activities 5.1, 5.3(a) and 5.3(b).
In the application of this Schedule, the competent authority shall take into
account any guidance published by the European Commission on
(a)
the relationship between waste management activities described
in this Schedule and those described in Annexes I and II to Directive 2008/
98/EC; and
(b) the interpretation of the term "industrial scale" regarding the
description of chemical industry activities described in this Schedule.
1. Energy industries
1.1. Combustion of fuels in installations with a total rated thermal input of
50 MW or more
1.2. Refining of mineral oil and gas
1.3. Production of coke
1.4. Gasification or liquefaction of
(a)
coal;
(b) other fuels in installations with a total rated thermal input of 20
MW or more.
2. Production and processing of metals
2.1. Metal ore (including sulphide ore) roasting or sintering
2.2. Production of pig iron or steel (primary or secondary fusion) including
continuous casting, with a capacity exceeding 2.5 tonnes per hour
2.3. Processing of ferrous metals
(a)
operation of hot-rolling mills with a capacity exceeding 20 tonnes
of crude steel per hour;
(b)
operation of smitheries with hammers the energy of which
exceeds 50 kilojoule per hammer, where the calorific power used exceeds 20
MW;
(c)
application of protective fused metal coats with an input
exceeding 2 tonnes of crude steel per hour.
2.4. Operation of ferrous metal foundries with a production capacity
exceeding 20 tonnes per day
2.5. Processing of non-ferrous metals
(a)
production of non-ferrous crude metals from ore, concentrates or
secondary raw materials by metallurgical, chemical or electrolytic processes;
(b) melting, including the alloyage, of non-ferrous metals, including
recovered products and operation of non-ferrous metal foundries, with a
melting capacity exceeding 4 tonnes per day for lead and cadmium or 20
tonnes per day for all other metals.
2.6. Surface treatment of metals or plastic materials using an electrolytic or
chemical process where the volume of the treatment vats exceeds 30 m 3
3. Mineral industry
3.1. Production of cement, lime and magnesium oxide
(a)
production of cement clinker in rotary kilns with a production
capacity exceeding 500 tonnes per day or in other kilns with a production
capacity exceeding 50 tonnes per day;
(b) production of lime in kilns with a production capacity exceeding
50 tonnes per day;
(c)
production of magnesium oxide in kilns with a production
capacity exceeding 50 tonnes per day.
3.2. Production of asbestos or the manufacture of asbestos-based products
3.3. Manufacture of glass including glass fibre with a melting capacity
exceeding 20 tonnes per day
3.4. Melting mineral substances including the production of mineral fibres
with a melting capacity exceeding 20 tonnes per day
3.5. Manufacture of ceramic products by firing, in particular roofing tiles,
bricks, refractory bricks, tiles, stoneware or porcelain with a production capacity
exceeding 75 tonnes per day and/or with a kiln capacity exceeding 4 m 3 and with a
setting density per kiln exceeding 300 kg/m 3
4. Chemical industry
For the purpose of this section, production within the meaning of the
categories of activities contained in this section means the production on an
industrial scale by chemical or biological processing of substances or groups of
substances listed in points 4.1 to 4.6
4.1. Production of organic chemicals, such as
(a)
simple hydrocarbons (linear or cyclic, saturated or unsaturated,
aliphatic or aromatic);
(b) oxygen-containing hydrocarbons such as alcohols, aldehydes,
ketones, carboxylic acids, esters and mixtures of esters, acetates, ethers,
peroxides and epoxy resins;
(c)
sulphurous hydrocarbons;
(d) nitrogenous hydrocarbons such as amines, amides, nitrous
compounds, nitro compounds or nitrate compounds, nitriles, cyanates,
isocyanates;
(e)
phosphorus-containing hydrocarbons;
(f)
halogenic hydrocarbons;
(g)
organometallic compounds;
(h)
plastic materials (polymers, synthetic fibres and cellulose-based
fibres);
(i)
synthetic rubbers;
(j)
dyes and pigments;
(k)
surface-active agents and surfactants.
4.2. Production of inorganic chemicals, such as
(a)
gases, such as ammonia, chlorine or hydrogen chloride, fluorine
or hydrogen fluoride, carbon oxides, sulphur compounds, nitrogen oxides,
hydrogen, sulphur dioxide, carbonyl chloride;
(b) acids, such as chromic acid, hydrofluoric acid, phosphoric acid,
nitric acid, hydrochloric acid, sulphuric acid, oleum, sulphurous acids;
(c)
bases, such as ammonium hydroxide, potassium hydroxide,
sodium hydroxide;
(d) salts, such as ammonium chloride, potassium chlorate, potassium
carbonate, sodium carbonate, perborate, silver nitrate;
(e)
non-metals, metal oxides or other inorganic compounds such as
calcium carbide, silicon, silicon carbide.
4.3. Production of phosphorous-, nitrogen- or potassium-based fertilisers
(simple or compound fertilisers)
4.4. Production of plant protection products or of biocides
4.5. Production of pharmaceutical products including intermediates
4.6. Production of explosives
5. Waste management
5.1. Disposal or recovery of hazardous waste with a capacity exceeding 10
tonnes per day involving one or more of the following activities
(a)
biological treatment;
(b)
physico-chemical treatment;
(c)
blending or mixing prior to submission to any of the other
activities listed in points 5.1 and 5.2;
(d) repackaging prior to submission to any of the other activities
listed in points 5.1 and 5.2;
(e)
solvent reclamation/regeneration;
(f)
recycling/reclamation of inorganic materials other than metals or
metal compounds;
(g)
regeneration of acids or bases;
(h)
recovery of components used for pollution abatement;
(i)
recovery of components from catalysts;
(j)
oil re-refining or other reuses of oil;
(k)
surface impoundment.
5.2. Disposal or recovery of waste in waste incineration plants or in waste
coincineration plants
(a)
for non-hazardous waste with a capacity exceeding 3 tonnes per
hour;
(b)
for hazardous waste with a capacity exceeding 10 tonnes per day.
5.3. (a)
Disposal of non-hazardous waste with a capacity exceeding 50
tonnes per day involving one or more of the following activities, and excluding
activities covered by the Urban Waste Water Treatment Regulations (S.L. 504.40)
(i)
biological treatment;
(ii)
physico-chemical treatment;
(iii)
pre-treatment of waste for incineration or co-incineration;
(iv)
treatment of slags and ashes;
(v) treatment in shredders of metal waste, including waste electrical
and electronic equipment and end-of-life vehicles and their components.
(b) Recovery, or a mix of recovery and disposal, of non-hazardous waste
with a capacity exceeding 75 tonnes per day involving one or more of the
following activities, and excluding activities covered by the Urban Waste Water
Treatment Regulations (S.L. 504.40)
(i)
biological treatment;
(ii)
pre-treatment of waste for incineration or co-incineration;
(iii)
treatment of slags and ashes;
(iv) treatment in shredders of metal waste, including waste electrical
and electronic equipment and end-of-life vehicles and their components.
When the only waste treatment activity carried out is anaerobic digestion, the
capacity threshold for this activity shall be 100 tonnes per day.
5.4. Landfills, as defined in the Waste Management (Landfill) Regulations
(S.L. 504.53) receiving more than 10 tonnes of waste per day or with a total
capacity exceeding 25,000 tonnes, excluding landfills of inert waste
5.5. Temporary storage of hazardous waste not covered under point 5.4
pending any of the activities listed in points 5.1, 5.2, 5.4 and 5.6 with a total
capacity exceeding 50 tonnes, excluding temporary storage, pending collection, on
the site where the waste is generated
5.6. Underground storage of hazardous waste with a total capacity exceeding
50 tonnes
6. Other activities
6.1. Production in industrial installations of
(a)
pulp from timber or other fibrous materials;
(b) paper or card board with a production capacity exceeding 20
tonnes per day;
(c)
one or more of the following wood-based panels: oriented strand
board, particleboard or fibreboard with a production capacity exceeding 600
m 3 per day.
6.2. Pre-treatment (operations such as washing, bleaching, mercerisation) or
dyeing of textile fibres or textiles where the treatment capacity exceeds 10 tonnes
per day
6.3. Tanning of hides and skins where the treatment capacity exceeds 12
tonnes of finished products per day
6.4. (a)
Operating slaughterhouses with a carcass production capacity
greater than 50 tonnes per day
(b) Treatment and processing, other than exclusively packaging, of the
following raw materials, whether previously processed or unprocessed, intended
for the production of food or feed from
(i)
only animal raw materials (other than exclusively milk) with a
finished product production capacity greater than 75 tonnes per day;
(ii) only vegetable raw materials with a finished product production
capacity greater than 300 tonnes per day or 600 tonnes per day where the
installation operates for a period of no more than 90 consecutive days in any
year;
(iii) animal and vegetable raw materials, both in combined and
separate products, with a finished product production capacity in tonnes per
day greater than
-
75 if A is equal to 10 or more; or
-
[300- (22.5 x A)] in any other case
where "A" is the portion of animal material (in percent of weight) of the
finished product production capacity.
Packaging shall not be included in the final weight of the product.
This subsection shall not apply where the raw material is milk only.
(c) Treatment and processing of milk only, the quantity of milk received
being greater than 200 tonnes per day (average value on an annual basis).
6.5. Disposal or recycling of animal carcases or animal waste with a
treatment capacity exceeding 10 tonnes per day
6.6. Intensive rearing of poultry or pigs
(a)
with more than 40 000 places for poultry;
(b)
with more than 2 000 places for production pigs (over 30 kg), or
(c)
with more than 750 places for sows.
6.7. Surface treatment of substances, objects or products using organic
solvents, in particular for dressing, printing, coating, degreasing, waterproofing,
sizing, painting, cleaning or impregnating, with an organic solvent consumption
capacity of more than 150 kg per hour or more than 200 tonnes per year
6.8. Production of carbon (hard-burnt coal) or electrographite by means of
incineration or graphitisation
6.9. Capture of CO 2 streams from installations covered by this Schedule or
other regulations implementing the Industrial Emissions (Framework)
Regulations, for the purposes of geological storage pursuant to Directive 2009/31/
6.10. Preservation of wood and wood products with chemicals with a
production capacity exceeding 75 m 3 per day other than exclusively treating
against sapstain
6.11. Independently operated treatment of waste water not covered by Urban
Waste Water Treatment Regulations (S.L. 504.40) and discharged by an
installation listed in this Schedule.
(1) These regulations provide for the implementation in Scope.
part of Directive 2010/75/EU of the European Parliament and of the
Council of 24 November 2010 on Industrial Emissions (Integrated
Pollution Prevention and Control) (Recast).
(2) These regulations also provide for the implementation of L.N. 9 of 2013.
the Industrial Emissions (Framework) Regulations, 2013.
(3) These regulations lay down rules for the integrated
prevention and control of pollution arising from certain industrial
activities. They also lay down rules designed to prevent or, where that
is not practicable, to reduce emissions into air, water and land and to
prevent the generation of waste, in order to achieve a high level of
protection of the environment taken as a whole.
List of polluting substances
Air
1. Sulphur dioxide and other sulphur compounds
2. Oxides of nitrogen and other nitrogen compounds
3. Carbon monoxide
4. Volatile organic compounds
5. Metals and their compounds
6. Dust including fine particulate matter
7. Asbestos (suspended particulates, fibres)
8. Chlorine and its compounds
9. Fluorine and its compounds
10. Arsenic and its compounds
11. Cyanides
12. Substances and mixtures which have been proved to possess
carcinogenic or mutagenic properties or properties which may affect reproduction
via the air
13. Polychlorinated dibenzodioxins and polychlorinated dibenzofurans
Water
1. Organohalogen compounds and substances which may form such
compounds in the aquatic environment
2. Organophosphorus compounds
3. Organotin compounds
4. Substances and mixtures which have been proved to possess
carcinogenic or mutagenic properties or properties which may affect reproduction
in or via the aquatic environment
5. Persistent hydrocarbons and persistent and bioaccumulable organic
toxic substances
6. Cyanides
7. Metals and their compounds
8. Arsenic and its compounds
9. Biocides and plant protection products
10. Materials in suspension
11. Substances which contribute to eutrophication (in particular, nitrates
and phosphates)
12. Substances which have an unfavourable influence on the oxygen
balance (and can be measured using parameters such as BOD, COD, etc.)
13. Substances listed in Schedule X of the Water Policy Framework
Regulations (S.L. 423.20).
These regulations shall apply to the industrial activities set Industrial
out in Schedule 1 and, where applicable, reaching the capacity activities.
thresholds set out in that Schedule.
Criteria for determining best available techniques
1. The use of low-waste technology;
2. The use of less hazardous substances;
3. The furthering of recovery and recycling of substances generated and
used in the process and of waste, where appropriate;
4. Comparable processes, facilities or methods of operation which have
been tried with success on an industrial scale;
5. Technological advances and changes in scientific knowledge and
understanding;
6. The nature, effects and volume of the emissions concerned;
7. The commissioning dates for new or existing installations;
8. The length of time needed to introduce the best available technique;
9. The consumption and nature of raw materials (including water) used in
the process and energy efficiency;
10. The need to prevent or reduce to a minimum the overall impact of the
emissions on the environment and the risks to it;
11. The need to prevent accidents and to minimise the consequences for the
environment;
12. Information published by public international organisations.
The operator shall take all appropriate measures to operate General
principles
an installation in accordance with the following principles
governing the
basic
obligations of
(a)
all the appropriate preventive measures are taken
the operator.
against pollution;
(b)
the best available techniques are applied;
(c)
no significant pollution is caused;
(d) the generation of waste is prevented in accordance
with the Waste Regulations;
(e)
where waste is generated, it is, in order of priority
and in accordance with the Waste Regulations, prepared for re-
use, recycled, recovered or, where that is technically and
economically impossible, it is disposed of while avoiding or
reducing any impact on the environment;
(f)
energy is used efficiently;
(g) the necessary measures are taken to prevent
accidents and limit their consequences;
(h) the necessary measures are taken upon definitive
cessation of activities to avoid any risk of pollution and return
the site of operation to the satisfactory state defined in
accordance with regulation 16 of these regulations.
Public participation in decision making
1. The public shall be informed (by public notices or other appropriate
means such as electronic media where available) of the following matters early in
the procedure for the taking of a decision or, at the latest, as soon as the
information can reasonably be provided
(a)
the application for a permit or, as the case may be, the proposal
for the updating of a permit or of permit conditions in accordance with
regulation 13, including the description of the elements listed in regulation
5(1);
(b) where applicable, the fact that a decision is subject to a national
or transboundary environmental impact assessment or to consultations
between Member States in accordance with regulation 21;
(c)
details of the competent authorities responsible for taking the
decision, those from which relevant information can be obtained, those to
which comments or questions can be submitted, and details of the time
schedule for transmitting comments or questions;
(d)
the nature of possible decisions or, where there is one, the draft
decision;
(e)
where applicable, the details relating to a proposal for the
updating of a permit or of permit conditions;
(f)
an indication of the times and places where, or means by which,
the relevant information will be made available;
(g) details of the arrangements for public participation and
consultation made pursuant to point 5.
2. The competent authority shall ensure that, within appropriate time
frames, the following is made available to the public concerned
(a)
in accordance with national law, the main reports and advice
issued to the competent authority or authorities at the time when the public
concerned were informed in accordance with point 1;
(b) in accordance with the Freedom of Access to Information on the
Environment Regulations (S.L. 504.65), information other than that referred
to in point 1 which is relevant for the decision in accordance with regulation
7 of the Industrial Emissions (Framework) Regulations and which only
becomes available after the time the public concerned was informed in
accordance with point 1.
3. The public concerned shall be entitled to express comments and
opinions to the competent authority before a decision is taken.
4. The results of the consultations held pursuant to this Schedule must be
taken into due account in the taking of a decision.
5. The arrangements for public consultation shall be as follows
(a)
The public consultation process shall be initiated through a notice
in at least one local newspaper and on the competent authority’s website.
(b) The timeframe for public consultation shall be thirty days for the
procedures described in regulation 18(1)(a) to (d) and shall be fifteen days in
all other cases where the competent authority deems consultation necessary,
provided that where the application for reconsideration of a permit in
accordance with regulation 18(1)(e) includes a request for a substantial
change, the timeframe for public consultation shall be thirty days.
(c)
During this period, the competent authority shall make available
to the public any relevant documentation, including any application and
supporting documentation submitted by the operator, on the competent
authority’s website and at the premises of the Local Council within which the
installation is located, to enable the public to comment on them.
(d) Any objections or representations by the public shall be made in
writing to the competent authority at the address indicated in the notice
initiating the public consultation.
(e)
The competent authority may also require the operator to
organise one or more public meetings as part of the public consultation
process.
(1) An application for a permit shall include a
description of the following
(a)
the installation and its activities;
(b) the raw and auxiliary materials, other substances
and the energy used in or generated by the installation;
(c)
the sources of emissions from the installation;
(d)
the conditions of the site of the installation;
(e)
where applicable, a baseline report in accordance
with regulation 16(2);
(f)
the nature and quantities of foreseeable emissions
from the installation into each medium as well as identification
of significant effects of the emissions on the environment;
(g) the proposed technology and other techniques for
preventing or, where this is not possible, reducing emissions
from the installation;
(h) measures for the prevention, preparation for reuse,
recycling and recovery of waste generated by the installation;
(i)
further measures planned to comply with the general
principles of the basic obligations of the operator as provided
for in regulation 4;
(j)
measures planned to monitor emissions into the
environment;
(k) the main alternatives to the proposed technology,
techniques and measures studied by the applicant in outline;
(l)
any other information required by the competent
authority.
(2) An application for a permit shall also include a non-
technical summary of the details referred to in sub-regulation (1).
(3) When submitting an application, the operator shall follow
the format prescribed by any application forms published by the
competent authority on its website, and shall comply with any
guidance documents published by the competent authority on its
website.
(4) Where information supplied in accordance with the
requirements provided for in the Environmental Impact Assessment S.L. 504.79
Regulations, or a safety report prepared in accordance with Control of S.L. 424.19
Major Accident Hazards Regulations, or other information produced
in response to other legislation fulfils any of the requirements of sub-
regulation (1), that information may be included in, or attached to, the
application.
Schedule of fees for new permits
Category of activity as per Schedule 1
Fee for new permit
1. Energy
industries,
excluding
combustion installations (1.1 below)
€35,000
1.1 Combustion installations
€5,500 with an addition of €550 for
every 10 MW (rated thermal input)
or part thereof
2. Production and processing of metals, €35,000 with an addition of €350
excluding installations for surface treatment for every tonne per day or part
of metals and plastic materials (2.6 below) thereof of processed material
2.6 Installations for surface treatment of €5,000 with €500 for every 10m 3
metals and plastic materials
treatment vat capacity or part
thereof
3. Mineral industry
€25,000 with an addition of €250
for every tonne per day or part
thereof of processed material
4. Chemical
industry,
excluding €5,000 with €500 for every ton per
installations for the production of day plant production capacity or
pharmaceutical products (4.5 below)
part thereof, capped at €20,000
4.5 Installations using a chemical or
biological process for the production of
pharmaceutical
products
including
intermediates
€15,000
5. Waste management installations
5.1 Disposal or recovery of hazardous €20,000 for disposal operations
waste
€10,000 for recovery operations
5.2 Disposal or recovery of waste in waste €10,000 for incineration of only
incineration
plants
or
in
waste non-hazardous waste
coincineration plants
€20,000 in all other cases
5.3 Disposal or recovery of non-hazardous
waste, excluding point (b)(i)(iv) below
€10,000
5.3 (b)(i)(iv) Recovery or a mix of recovery
and disposal of non-hazardous waste
involving treatment in shredders of metal
waste, including waste electrical and
electronic equipment and end-of-life
vehicles and their components
€5,000
€20,000 for every 500,000 m 3
5.4 Landfills
capacity or part thereof
5.5 Temporary storage of hazardous waste €10,000
Category of activity as per Schedule 1
Fee for new permit
5.6 Underground storage of hazardous
waste
€10,000
6. Other activities, excluding intensive
rearing of poultry or pigs (6.6 below)
€15,000
6.6 Intensive rearing of poultry or pigs
€230
€3.24
In determining whether to grant or refuse the permit to an Criteria for
applicant, the competent authority shall take into account the assessing
applicant’s
applicant’s suitability to undertake the proposed activity, having suitability.
regard to, as the case may be
(a)
his record of compliance with these regulations and
with the Industrial Emissions (Framework) Regulations, 2013; L.N. 9 of 2013.
(b) his financial capacity to comply with all obligations
and liabilities that will or may arise from the proposed activity
under these regulations, or his ability to offer such financial
security as the competent authority may require;
(c)
his qualifications, experience and technical
competence, as well as those of his employees, to carry out the
proposed activity safely and with minimum risk to human
health and the environment, and to abide by any conditions set
in relation thereto by the competent authority.
(1)
The competent authority shall ensure that the permit Permit
conditions.
includes all measures necessary for compliance with the requirements
of regulations 4 and 11. Those measures shall include at least the
following
(a)
emission limit values for polluting substances listed
in Schedule 2, and for other polluting substances, which are
likely to be emitted from the installation concerned in
significant quantities, having regard to their nature and their
potential to transfer pollution from one medium to another;
(b) appropriate requirements ensuring protection of the
soil and groundwater and measures concerning the monitoring
and management of waste generated by the installation;
(c)
suitable
emission
monitoring
requirements
specifying
(i) measurement methodology, frequency and
evaluation procedure; and
(ii) where the provisions of regulation 8(3)(b) are
applicable, that results of emission monitoring are
available for the same periods of time and reference
conditions as for the emission levels associated with the
best available techniques;
(d) an obligation to supply the competent authority
regularly, and at least annually, with
(i) information on the basis of results of
emission monitoring referred to in paragraph (c) and other
required data that enables the competent authority to verify
compliance with the permit conditions; and
(ii) where the provisions of regulation 8(3)(b) are
applicable, a summary of the results of emission
monitoring which allows a comparison with the emission
levels associated with the best available techniques
Provided that the competent authority may specify the
format of this reporting and timeframes for its submission;
(e)
appropriate
requirements
for
the
regular
maintenance and surveillance of measures taken to prevent
emissions to soil and groundwater pursuant to paragraph (b) and
appropriate requirements concerning the periodic monitoring of
soil and groundwater in relation to relevant hazardous
substances likely to be found on site and having regard to the
possibility of soil and groundwater contamination at the site of
the installation;
(f)
measures relating to conditions other than normal
operating conditions such as start-up and shut-down operations,
leaks, malfunctions, momentary stoppages and definitive
cessation of operations;
(g) provisions on the minimisation of long-distance or
transboundary pollution;
(h) conditions for assessing compliance with the
emission limit values or a reference to the applicable
requirements specified elsewhere.
(2) For the purpose of sub-regulation (1)(a), emission limit
values may be supplemented or replaced by equivalent parameters or
technical measures ensuring an equivalent level of environmental
protection.
(3) BAT conclusions shall be the reference for setting the
permit conditions.
(4) Without prejudice to regulation 11, the competent
authority may set stricter permit conditions than those achievable by
the use of the best available techniques as described in the BAT
conclusions. The competent authority may establish guidance under
which it may set such stricter conditions.
(5) Where the competent authority sets permit conditions on
the basis of a best available technique not described in any of the
relevant BAT conclusions, it shall ensure that
(a)
that technique is determined by giving special
consideration to the criteria listed in Schedule 3; and
(b)
the requirements of regulation 8 are complied with.
Where the BAT conclusions referred to in paragraph (a) do not
contain emission levels associated with the best available techniques,
the competent authority shall ensure that the technique referred to in
paragraph (a) ensures a level of environmental protection equivalent
to the best available techniques described in the BAT conclusions.
(6) Where an activity or a type of production process carried
out within an installation is not covered by any of the BAT
conclusions or where those conclusions do not address all the
potential environmental effects of the activity or process, the
competent authority shall, after prior consultations with the operator,
set the permit conditions on the basis of the best available techniques
that it has determined for the activities or processes concerned, by
giving special consideration to the criteria listed in Schedule 3.
(7) For installations referred to in point 6.6 of Schedule 1, sub-
regulations (1) to (6) shall apply without prejudice to the legislation
relating to animal welfare.
(1) The emission limit values for polluting substances
shall apply at the point where the emissions leave the installation, and
any dilution prior to that point shall be disregarded when determining
those values.
With regard to indirect releases of polluting substances into
water, the effect of a water treatment plant may be taken into account
when determining the emission limit values of the installation
concerned, provided that an equivalent level of protection of the
environment as a whole is guaranteed and provided this does not lead
to higher levels of pollution in the environment.
(2) Without prejudice to regulation 11, the emission limit
values and the equivalent parameters and technical measures referred
to in regulation 7(1) and (2) shall be based on the best available
techniques, without prescribing the use of any technique or specific
technology.
(3) The competent authority shall set emission limit values
that ensure that, under normal operating conditions, emissions do not
exceed the emission levels associated with the best available
techniques as laid down in the decisions on BAT conclusions referred
to in Article 13(5) of Directive 2010/75/EU of the European
Parliament and of the Council of 24 November 2010 on industrial
emissions (integrated pollution prevention and control) through either
of the following
(a)
setting emission limit values that do not exceed the
emission levels associated with the best available techniques.
Those emission limit values shall be expressed for the same or
shorter periods of time and under the same reference conditions
as those emission levels associated with the best available
techniques; or
(b) setting different emission limit values than those
referred to under paragraph (a) in terms of values, periods of
time and reference conditions.
Where paragraph (b) is applicable, the competent authority
shall, at least annually, assess the results of emission monitoring in
order to ensure that emissions under normal operating conditions
have not exceeded the emission levels associated with the best
available techniques.
(4) By way of derogation from sub-regulation (3), and without
prejudice to regulation 11, the competent authority may, in specific
cases, set less strict emission limit values. Such a derogation may
apply only where an assessment shows that the achievement of
emission levels associated with the best available techniques as
described in BAT conclusions would lead to disproportionately higher
costs compared to the environmental benefits due to
(a)
the geographical location or the local environmental
conditions of the installation concerned; or
(b) the technical characteristics of the installation
concerned.
The competent authority shall document in an annex to the
permit conditions the reasons for the application of paragraph (a)
including the result of the assessment and the justification for the
conditions imposed.
The emission limit values set in accordance with paragraph (a)
shall, however, not exceed the emission limit values set out in the
Schedule to the Industrial Emissions (Framework) Regulations, 2013,
where applicable.
The competent authority shall in any case ensure that no
significant pollution is caused and that a high level of protection of
the environment as a whole is achieved.
In the application of this sub-regulation, the competent authority
shall take into account any guidance published by the European
Commission on the criteria to be taken into account for the
application of this sub-regulation.
The competent authority shall re-assess the application of this
sub-regulation as part of each reconsideration of the permit
conditions pursuant to regulation 15.
(5) The competent authority may grant temporary derogations
from the requirements of sub-regulations (2) and (3), and from
regulation 4(a) and (b) for the testing and use of emerging techniques
for a total period of time not exceeding nine months, provided that
after the period specified, either the technique is stopped or the
activity achieves at least the emission levels associated with the best
available techniques.
(6) Pending the adoption of a relevant decision on BAT
conclusions referred to in Article 13(5) of Directive 2010/75/EU of
the European Parliament and of the Council on industrial emissions,
the conclusions on best available techniques from BAT reference
documents adopted by the European Commission prior to 6 January
2011 shall apply as BAT conclusions for the purposes of these
regulations except for sub-regulations (3) and (4).
(1) The monitoring requirements referred to in
regulation 7(1)(c) shall, where applicable, be based on the
conclusions on monitoring as described in the BAT conclusions.
(2) The frequency of the periodic monitoring referred to in
regulation 7(1)(e) shall be determined by the competent authority in a
permit for each individual installation or in general binding rules.
(3) Without prejudice to the provisions of sub-regulation (2),
periodic monitoring shall be carried out at least once every five years
for groundwater and ten years for soil, unless such monitoring is
based on a systematic appraisal of the risk of contamination.
(1) When adopting general binding rules, the competent
authority shall ensure an integrated approach and a high level of
environmental protection equivalent to that achievable with
individual permit conditions.
(2) General binding rules shall be based on the best available
techniques, without prescribing the use of any technique or specific
technology in order to ensure compliance with regulations 7 and 8.
(3) The competent authority shall ensure that general binding
rules are updated to take into account developments in best available
techniques and in order to ensure compliance with regulation 15.
(4) General binding rules adopted in accordance with sub-
regulations (1) to (3) shall contain a reference to Directive 2010/75/
EU of the European Parliament and of the Council of 24 November
2010 on Industrial Emissions (Integrated Pollution Prevention and
Control) (Recast), or be accompanied by such a reference on the
occasion of their official publication.
Where an environmental quality standard requires stricter
conditions than those achievable by the use of the best available
techniques, the competent authority shall include additional measures
in the permit, without prejudice to other measures which may be
taken to comply with environmental quality standards.
The competent authority shall follow developments in best Developments
available techniques and the publication of any new or updated BAT in
techniques.
conclusions and shall make that information available to the public
concerned.
(1) The operator shall inform the competent authority of Changes by
any planned change in the nature or functioning, or an extension of operators
installations.
the installation which may have consequences for the environment.
Where appropriate, the competent authority shall update the permit.
(2) No substantial change planned by the operator shall be
made without a permit granted in accordance with these regulations.
The application for a permit and the decision by the competent
authority shall cover those parts of the installation and those details
listed in regulation 5 which may be affected by the substantial
change.
(3) Any change in the nature or functioning or an extension of
an installation shall be deemed to be substantial if the change or
extension in itself reaches the capacity thresholds set out in Schedule
1.
A permit shall not be transferred from one operator to Transfer of
another unless the approval of the competent authority has been permit.
sought and granted.
(1) Permits shall be valid for such a time as the Reconsideration
competent authority may specify, provided that where the operator and
permit
has submitted all the information necessary for the purpose of conditions
the competent
reconsidering permit conditions within the timeframe specified by the authority.
competent authority pursuant to sub-regulation (3), the validity of the
permit shall be extended until such a time as the competent authority
decides on the reconsideration of the permit conditions.
(2) The competent authority shall periodically reconsider, in
accordance with sub-regulations (3) to (6), all permit conditions and,
where necessary to ensure compliance with these regulations, update
those conditions.
(3) Prior to the expiry of the permit or at the request of the
competent authority, the operator shall submit all the information
necessary for the purpose of reconsidering the permit conditions,
including, in particular, results of emission monitoring and other data,
that enables a comparison of the operation of the installation with the
best available techniques described in the applicable BAT
conclusions and with the emission levels associated with the best
available techniques, and any other additional information requested
by the competent authority. The operator shall submit this
information according to the timeframe specified by the competent
authority.
When reconsidering permit conditions, the competent authority
shall use any information resulting from monitoring or inspections.
(4) Within four years of publication of decisions on BAT
conclusions in accordance with Article 13(5) of Directive 2010/75/
EU of the European Parliament and of the Council on industrial
emissions relating to the main activity of an installation, the
competent authority shall ensure that
(a)
all the permit conditions for the installation
concerned are reconsidered and, if necessary, updated to ensure
compliance with these regulations, in particular, with regulation
8(3) and (4), where applicable;
(b) the
installation
complies
with
those
permit
conditions.
The reconsideration shall take into account all the new or
updated BAT conclusions applicable to the installation and adopted in
accordance with Article 13(5) of Directive 2010/75/EU since the
permit was granted or last reconsidered.
(5) Where an installation is not covered by any of the BAT
conclusions, the permit conditions shall be reconsidered and, if
necessary, updated where developments in the best available
techniques allow for the significant reduction of emissions.
(6) The permit conditions shall be reconsidered and, where
necessary, updated at least in the following cases
(a)
where the pollution caused by the installation is of
such significance that the existing emission limit values of the
permit need to be revised or new such values need to be
included in the permit;
(b) where the
operational
safety
requires
other
techniques to be used;
(c)
where it is necessary to comply with a new or
revised environmental quality standard in accordance with
regulation 11;
(d)
where the validity of a permit has elapsed.
(1) Without prejudice to the Water Policy Framework Site closure.
Regulations, the Prevention and Remedying of Environmental S.L.
Damage Regulations, and the Protection of Groundwater Against S.L. 423.36
Pollution and Deterioration Regulations, and to relevant national or
European Union legislation on soil protection, the competent
authority shall set permit conditions to ensure compliance with sub-
regulations (3) and (4) upon definitive cessation of activities.
(2) Where the activity involves the use, production or release
of relevant hazardous substances and having regard to the possibility
of soil and groundwater contamination at the site of the installation,
the operator shall prepare and submit to the competent authority a
baseline report before starting operation of an installation or before a
permit for an installation is updated for the first time after 7 January
2013. The baseline report shall contain the information necessary to
determine the state of soil and groundwater contamination so as to
make a quantified comparison with the state upon definitive cessation
of activities provided for under sub-regulation (3).
The baseline report shall contain at least the following
information
(a)
information on the present use and, where available,
on past uses of the site;
(b) where available, existing information on soil and
groundwater measurements that reflect the state at the time the
report is drawn up or, alternatively, new soil and groundwater
measurements having regard to the possibility of soil and
groundwater contamination by those hazardous substances to be
used, produced or released by the installation concerned.
Where information produced pursuant to other national or
European Union law fulfils the requirements of this sub-regulation,
that information may be included in, or attached to, the submitted
baseline report.
In the preparation of the baseline report, the operator shall take
into account any guidance published by the European Commission on
the content of the baseline report.
(3) (a)
Upon definitive cessation of the activities, the
operator shall assess the state of soil and groundwater contamination
by relevant hazardous substances used, produced or released by the
installation. Where the installation has caused significant pollution of
soil or groundwater by relevant hazardous substances compared to
the state established in the baseline report referred to in sub-
regulation (2), the operator shall take the necessary measures to
address that pollution so as to return the site to that state. For that
purpose, the technical feasibility of such measures may be taken into
account.
(b) Without prejudice to paragraph (a), upon definitive
cessation of the activities, and where the contamination of soil and
groundwater at the site poses a significant risk to human health or the
environment as a result of the permitted activities carried out by the
operator before the permit for the installation is updated for the first
time after 7 January 2013 and taking into account the conditions of
the site of the installation established in accordance with regulation
5(1)(d), the operator shall take the necessary actions aimed at the
removal, control, containment or reduction of relevant hazardous
substances, so that the site, taking into account its current or approved
future use, ceases to pose such a risk.
(4) Where the operator is not required to prepare a baseline
report referred to in sub-regulation (2), the operator shall, upon
definitive cessation of the activities, take the necessary actions aimed
at the removal, control, containment or reduction of relevant
hazardous substances, so that the site, taking into account its current
or approved future use, ceases to pose any significant risk to human
health or the environment due to the contamination of soil and
groundwater as a result of the permitted activities and taking into
account the conditions of the site of the installation established in
accordance with regulation 5(1)(d).
(1) The competent authority shall set up a system of
environmental inspections of installations addressing the examination
of the full range of relevant environmental effects from the
installations concerned.
Operators shall afford the competent authority and any other
authorities having competence in accordance with regulation 19 all
necessary assistance to enable officials of these authorities to carry
out any site visits, to take samples and to gather any information
necessary for the performance of their duties for the purposes of these
regulations.
(2) The competent authority shall ensure that all installations
are covered by an environmental inspection plan at national, regional
or local level and shall ensure that this plan is regularly reviewed and,
where appropriate, updated.
(3) Each environmental inspection plan shall include the
following
(a)
a general
assessment
of
relevant
significant
environmental issues;
(b)
the geographical area covered by the inspection
plan;
(c)
a register of the installations covered by the plan;
(d) procedures for drawing up programmes for routine
environmental inspections pursuant to sub-regulation (4);
(e)
procedures
for
non-routine
environmental
inspections pursuant to sub-regulation (5);
(f)
where necessary, provisions on the co-operation
between different inspection authorities, in particular the
authorities identified in regulation 19.
(4) Based on the inspection plans, the competent authority
shall regularly draw up programmes for routine environmental
inspections, including the frequency of site visits for different types
of installations.
The period between two site visits shall be based on a
systematic appraisal of the environmental risks of the installations
concerned and shall not exceed one year for installations posing the
highest risks and three years for installations posing the lowest risks.
If an inspection has identified an important case of non-
compliance with the permit conditions, an additional site visit shall be
carried out within six months of that inspection.
The systematic appraisal of the environmental risks shall be
based on at least the following criteria
(a)
the potential and actual impacts of the installations
concerned on human health and the environment taking into
account the levels and types of emissions, the sensitivity of the
local environment and the risk of accidents;
(b)
the record of compliance with permit conditions;
(c)
the participation of the operator in the European
Union eco-management and audit scheme (EMAS), pursuant to
Regulation (EC) No 1221/2009.
The competent authority shall take into account any guidance
adopted by the European Commission on the criteria for the appraisal
of environmental risks.
(5) The competent authority shall carry out non-routine
environmental inspections to investigate serious environmental
complaints, serious environmental accidents, incidents and
occurrences of non-compliance as soon as possible and, where
appropriate, before the granting, reconsideration or update of a
permit.
(6) Following each site visit, the competent authority shall
prepare a report describing the relevant findings regarding
compliance of the installation with the permit conditions and
conclusions on whether any further action is necessary.
The report shall be notified to the operator concerned within two
months of the site visit taking place. The report shall be made
publicly available by the competent authority in accordance with the
Freedom of Access to Information on the Environment Regulations,
within four months of the site visit taking place.
Without prejudice to regulation 10(2) and (3) of the Industrial
Emissions (Framework) Regulations, the competent authority shall
ensure that the operator takes all the necessary actions identified in
the report within a reasonable period.
(1) The competent authority shall ensure that the public
concerned are given early and effective opportunities to participate in
the following procedures
(a)
the granting of a permit for new installations;
(b)
the granting of a permit for any substantial change;
(c)
the granting or updating of a permit for an
installation where the application of regulation 8(4) is proposed;
(d) the updating of a permit or permit conditions for an
installation in accordance with regulation 15(6)(a);
(e)
the updating of a permit or permit conditions for an
installation in accordance with regulation 15(3).
The procedure set out in Schedule 4 shall apply to such
participation.
(2) When a decision on granting, reconsideration or updating
of a permit has been taken, the competent authority shall make
available to the public, including via the internet in relation to
paragraphs (a), (b) and (f), the following information
(a)
the content of the decision, including a copy of the
permit and any subsequent updates;
(b)
the reasons on which the decision is based;
(c)
the results of the consultations held before the
decision was taken and an explanation of how they were taken
into account in that decision;
(d) the title of the BAT reference documents relevant to
the installation or activity concerned;
(e)
how the permit conditions referred to in regulation
7, including the emission limit values, have been determined in
relation to the best available techniques and emission levels
associated with the best available techniques;
(f)
where a derogation is granted in accordance with
regulation 8(4), the specific reasons for that derogation based on
the criteria laid down in that sub-regulation and the conditions
imposed.
(3) The competent authority shall also make available to the
public, including via the internet at least in relation to paragraph (a)
(a)
relevant information on the measures taken by the
operator upon definitive cessation of activities in accordance
with regulation 16;
(b) the results of emission monitoring as required under
the permit conditions and held by the competent authority.
(4) Sub-regulations (1), (2) and (3) shall apply subject to the
restrictions laid down in regulation 7(1) and (2) of the Freedom of S.L. 504.65
Access to Information on the Environment Regulations.
(1) In case of applications where the competent Coordination
authority considers that other authorities also have competence in any with
competent
of the proposed activities, the competent authority shall
authorities.
(a)
notify these authorities of applications according to
their area of competence;
(b)
submit to these authorities an electronic copy of the
application submitted by the operator for their review;
(c)
invite these authorities to propose conditions
regarding their area of competence for inclusion in the permit.
Where the conditions stipulated in the permit drafted by the
Malta Environment and Planning Authority and the conditions
proposed by other authorities are in conflict, the Malta Environment
and Planning Authority shall seek to resolve this conflict at the
earliest opportunity.
Where there is sustained and justified objection against the
granting of a permit for a particular installation by an authority
deemed as having competence, the Malta Environment and Planning
Authority shall not grant a permit until this objection is lifted by the
authority making the objection
Provided that where the Malta Environment and Planning
Authority does not receive any objection from other authorities
within the stipulated time-frame, those other authorities shall be
deemed to have no objection to the issue of the permit
Provided also that the responsibility for enforcing conditions
required by other authorities shall rest with those authorities.
(2) The following authorities shall be considered as also
having competence with regard to the application of subregulation
(1)
(a)
the Malta Resources Authority in relation to all
activities in Schedule 1;
(b) the Agriculture and Fisheries Department in relation
to activities 6.4, 6.5 and 6.6 in Schedule 1, and any activity for
the disposal or recovery of animal by-products;
(c)
the Directorate of Agriculture within the Ministry
for Resources and Rural Affairs in relation to activity 6.6 in
Schedule 1;
(d) the Malta Competition and Consumer Affairs
Authority in relation to activities 1.2, 1.3, 2.1, 2.5, 2.6, 3.1, 3.2,
3.3, 3.4, 4, 6.7 and 6.10 in Schedule 1;
(e)
the Civil Protection Department in relation to all
activities in Schedule 1;
(f)
the Environmental Health Directorate in relation to
all activities in Schedule 1;
(g) the Authority for Transport in Malta in relation to
activities involving release of trade effluent into ports;
(h) the Occupational Health and Safety Authority in
relation to activities covered by the Control of Major Accident S.L. 424.19
Hazards Regulations.
(1) Members of the public concerned having sufficient Access to
interest shall have access to a review procedure before the justice.
Environment and Planning Review Tribunal to challenge the
substantive or procedural legality of decisions, acts or omissions
subject to regulation 18.
(2) An appeal may be lodged before the Tribunal within thirty
days following a decision being made on the granting,
reconsideration or updating of a permit.
(3) For the purposes of sub-regulation (1), the interest of any
non-governmental organisation promoting environmental protection
and meeting any requirements under national law shall be deemed
sufficient.
(4) Articles 40 and 41 of the Environment and Development Cap. 504.
Planning Act, shall apply to this procedure.
(5) The competent authority shall ensure that practical
information is made available to the public on access to
administrative and judicial review procedures.
(1) Where the competent authority is aware that the Transboundary
operation of an installation is likely to have significant negative effects.
effects on the environment of another European Union Member State,
or where a European Union Member State which is likely to be
significantly affected so requests, the competent authority shall
forward to the Member State any information required to be given or
made available pursuant to Schedule 4 at the same time as it makes it
available to the public.
Such information shall serve as a basis for any consultations
necessary in the framework of the bilateral relations between Malta
and the other Member State on a reciprocal and equivalent basis.
(2) The competent authority shall ensure that in the cases
referred to in sub-regulation (1), the applications are also made
available for an appropriate period of time to the public of the
Member State likely to be affected so that it will have the right to
comment on them before the competent authority reaches its decision.
(3) The results of any consultations pursuant to sub-
regulations (1) and (2) shall be taken into consideration when the
competent authority reaches a decision on the application.
(4) The competent authority shall inform any Member State
which has been consulted pursuant to sub-regulation (1) of the
decision reached on the application and shall forward to it the
information referred to in regulation 18(2). That Member State shall
take the measures necessary to ensure that that information is made
available in an appropriate manner to the public concerned in its own
territory.
(1) The competent authority shall, where appropriate,
encourage the development and application of emerging techniques,
in particular for those emerging techniques identified in BAT
reference documents.
(2) In the application of sub-regulation (1), the competent
authority shall take into account any guidance published by the
European Commission to assist Member States in encouraging the
development and application of emerging techniques as referred to in
sub-regulation (1).
(1) The competent authority shall charge fees in respect
of applications (including for the variation, transfer, renewal or
surrender thereof).
(2) The competent authority shall not process any application
or render any other service if the fees relative to a previous permit or
service given to the same person or in respect of an installation or any
technically connected installation have not been paid in full.
(3) The competent authority shall not process any application
or render any other service if not accompanied with the fees
stipulated in these regulations.
(1) An application fee for any new permit, variation,
transfer, renewal or surrender thereof, shall be paid to the competent
authority on submission of the application.
(2) The fees for new permits stipulated in Schedule 5 shall
apply.
(3) Where an operator applies to transfer ownership of a
permit or for a variation to a permit, a fee of 10% of the application
fee in Schedule 5 shall be paid to the competent authority. The fee for
a variation shall not be payable if the variation is imposed by the
competent authority and not requested by the operator.
(4) Where an operator applies for a renewal of a permit, a fee
of 50% of the application fee in Schedule 5 shall be paid to the
competent authority.
(5) Where an operator applies for the surrender of a permit, a
fee of 25% of the application fee in Schedule 5 shall be paid to the
competent authority.
(6) An annual fee of 10% of the application fee in Schedule 5
shall be paid to the competent authority on the anniversary of the date
of issue of the permit. Installations having environmental
management certification recognised by the Malta Competition and
Consumer Affairs Authority shall pay a reduced annual fee of 5%.
(7) All inspection costs, whether for scheduled or additional
inspections, shall be paid by the operator to the competent authority
at a standard rate of two hundred euro (€200) per inspection. Such
inspection costs shall be added to the annual fee.
(8) The competent authority may engage consultancy services
to obtain specialised expertise on specific applications (including the
variation, transfer, renewal or surrender thereof), to obtain assistance
in carrying out compliance audits (including monitoring and, or
analysis of samples) and to carry out enforcement of specific permits.
The cost of the consultancy services will be communicated to the
applicant prior to the consultancy services being engaged and will be
borne by the applicant.
(9) In cases where an application for a permit (or variation,
transfer, renewal or surrender thereof) is withdrawn by the applicant
within ten working days of submission, 50% of the fees paid shall be
refunded. No refund shall be granted after ten working days of
submission. No refund shall be granted in respect of consultancy fees
as specified in sub-regulation (8).
(10) In the case where an application for a permit (or variation,
transfer, renewal or surrender thereof) is refused by the competent
authority, the fees paid shall not be refunded.
(11) With regard to pending applications submitted before the
coming into force of these regulations, the fees in accordance with
these regulations shall be payable prior to issue of the permit, and in
respect of permitted installations, fees for variation, renewal, transfer,
surrender and annual fees shall be due prior to the next variation,
renewal, transfer, surrender or anniversary of the permit, respectively.
The competent authority may also require the provision by
the operator of a suitable financial guarantee to be made in favour of
the competent authority to secure the obligations under the permit or
registration, before the permit or registration is issued. The financial
guarantee may also be tied to specific requirements in the permit.
Any person shall be guilty of an offence under these
regulations if
(a)
he fails to comply with any provision of these
regulations or fails to comply with permit conditions or with
any order lawfully given in terms of any provision of these
regulations; or
(b) he contravenes any restriction, prohibition or
requirement imposed by or under these regulations; or
(c)
he acts in contravention of any of the provisions of
these regulations; or
(d) he conspires or attempts, or aids, or abets, any other
person by whatever means, including advertising, counselling
or procurement to contravene the provisions or to fail to comply
with any such provisions, including any order lawfully given in
terms of any of the provisions of these regulations, or to
contravene any restriction, prohibition or requirement imposed
by or under the said regulations.
Any person who commits an offence under these
regulations shall, on conviction, be liable
(a)
on a first conviction to a fine (multa) of not less than
twenty-three thousand euro (€23,000.00) and not greater than
two hundred and thirty three thousand euro (€233,000.00) or to
imprisonment for a term not exceeding two years, or to both
such fine and imprisonment;
(b) on a second or subsequent convictions, to a fine
(multa) of not less than forty-six thousand euro (€46,000.00)
and not greater than four hundred and sixty six thousand euro
(€466,000.00) or to imprisonment for a term not exceeding two
years, or to both such fine and imprisonment
Provided that whenever any person is found guilty of
committing an offence under these regulations by means of a vehicle,
the owner of the said vehicle, where applicable, is held liable in the
same manner and degree
Provided further that the court shall order any person who has
been found guilty of committing an offence against these regulations
to pay for the expenses incurred by the competent authority as a result
of the said offence, the revocation of the permit issued by the
competent authority and the confiscation of the corpus delicti,
including the vehicle, if applicable.
(1) The provisions of articles 23 and 30(1) of the Applicability of
Criminal Code shall, mutatis mutandis, apply to proceedings in the
Code.
respect of offences against these regulations, so however that the Cap. 9.
disqualification from holding or obtaining a licence, permit or
authority shall in no case be for less than one year.
(2) Notwithstanding the provisions of article 370 of the
Criminal Code, proceedings for an offence against these regulations Cap. 9.
shall be held before the Court of Magistrates (Malta) or the Court of
Magistrates (Gozo) as the case may be, and shall be in accordance
with the provisions of the Criminal Code regulating the procedure
before the said courts of criminal judicature.
(3) Notwithstanding the provisions of the Criminal Code, the Cap. 9.
Attorney General shall always have a right of appeal to the Court of
Criminal Appeal from any judgement given by the Court of
Magistrates (Malta) or the Court of Magistrates (Gozo) in respect of
proceedings for any offence against these regulations.
(1) The Integrated Pollution Prevention and Control Revocation of
Regulations, hereinafter referred to as the "revoked regulations", shall Integrated
Pollution
be revoked with effect from the 7th January, 2014.
Prevention and
Control
Regulations.
(2) References to the revoked regulations shall be construed as L.N.
2002. references to these regulations.
(1) The provisions of these regulations shall apply from Existing
the 7th January, 2014 to installations carrying out the activities installations
covered by the
referred to in Schedule 1 of the revoked regulations, which are in revoked
regulations.
operation and hold a permit before 7th January 2013, or the operators
of which have submitted a complete application for a permit before
that date, provided that those installations are put into operation no
later than 7 January 2014. Without prejudice to regulation 15(1),
permits issued under the revoked regulations shall be construed as
valid until their term of expiry or until superseded by a permit issued
under these regulations.
(2) The provisions of these regulations shall apply from 7 July
2015 for installations carrying out the activities referred to in
Schedule 1 which are not covered by sub-regulation (1), and which
are in operation before 7 January 2013. Such installations shall apply