229 tal-2012
Statutory Text (3 Articles)
L.N. 229 of 2012
ENVIRONMENT AND DEVELOPMENT PLANNING ACT
(CAP. 504)
Environment and Development Planning Act (Amendment of
Eighth Schedule) Regulations, 2012
BY VIRTUE of the powers conferred by articles 61(2)(q) and
62 of the Environment and Development Planning Act, the Minister
for Tourism, Culture and the Environment, after consultation with
the Malta Environment and Planning Authority, has made the
following regulations:-
(1) The title of these regulations is the Environment
and Development Planning Act (Amendment of Eighth Schedule)
Regulations, 2012, and they shall be read and construed as one
with the Eighth Schedule of the Environment and Development
Planning Act, hereinafter referred to as “the Eighth Schedule”.
(2) These regulations shall come into force on the 1st
August, 2012.
In Category B of the Eighth Schedule of the Environment
and Development Planning Act, there shall be added the
following:-
“1. The provisions of this sub-category shall apply to
development in existence within a development zone on the
coming into force of these regulations and which development
shall include the following
i)
Size of internal yards of any dwelling
(a) if the length of any side of the internal
yard is up to 65% of that required by law and the
overall area of the yard is more than 65% of what
it should have otherwise been;
(b) if the length of any side of the internal
yard is between 50% and 65% of that required
by law and the overall area of the yard is within
the same range, subject to an engineer’s report
stating that the habitable rooms in the dwelling
have adequate lighting and ventilation aided, if
necessary, but not exclusively limited to artificial
lighting and forced mechanical ventilation
respectively;
(c) dwellings which have internal yards that
are less than half the size of what they should have
otherwise been are not included.
ii) Size of back yard of any dwelling
(a) if the depth of any back yard is up to
65% of that required by law and the overall area of
the yard is more than 65% of what it should have
otherwise been;
(b) if the depth of any back yard is between
50% and 65% of that required by law and the
overall area of the yard is within the same range,
subject to an engineer’s report stating that the
habitable rooms in the dwelling have adequate
lighting and ventilation;
(c) plans for dwellings which have a back
yard less than half the size of what it should have
otherwise been are not included.
iii) Internal height of structure of any dwelling
(a) plans for dwellings with a clear floor to
ceiling internal height of more than 2.6 metres;
(b) plans for dwellings with a clear floor to
ceiling height of less than 2.6 metres but more than
2.4 metres subject to an engineer’s report stating
that the habitable rooms in the dwelling have
adequate lighting and ventilation;
(c) plans for dwellings with a clear floor to
ceiling height which is less than 2.4 metres are not
included.
iv) Room in the back yard of any dwelling
Ground level rooms in the back yard of any
dwelling as long as the size of the back yard prior
to the erection of the room is in conformity with
sanitary regulations, provided that the room has
natural ventilation and natural lighting, does not
occupy more than 35% of the required back yard
area, and is not higher than ten (10) courses
Provided that if a request under the provisions
of article 91 of the Act in respect of any of the
above developments is made to the Authority
within six months from the coming into force
of these regulations, it shall be presumed that
the development to which the request refers to
existed prior to such date as long as the architect
submitting the request certifes that the development
to which the request relates to had existed prior
to the coming into force of these regulations, and
the same request includes photographic evidence
that shows that same development as existing on
site, and as long as there is no evidence to the
contrary, or that no such evidence to the contrary
subsequently emerges
Provided further that if such a request is not
submitted within six months from the coming into
force of these regulations, the onus of proof that the
development in question existed before the coming
into force of these regulations shall lie with the
applicant or his architect.”.
€0.36