IN exercise of the powers conferred by sub-article (1) of
article 28 of the Malta Resources Authority Act, the Minister for
Resources and Rural Affairs, after consultation with the Malta
Resources Authority, has made the following regulations:-
(1) The title of these regulations is the Electricity
Market Regulations, 2011.
(2) These regulations transpose Directive 2009/72/EC
concerning common rules for the internal market in electricity and
repealing Directive 2003/54/EC concerning common rules for the
internal market in electricity, Directive 2005/89/EC concerning
measures to safeguard security of electricity supply and infrastructure
investment and Article 16 of Directive 2009/28/EC on the promotion
of the use of energy from renewable sources. These regulations
establish common rules for the generation, distribution and supply
of electricity, together with consumer protection provisions, with a
view to improving and integrating competitive electricity markets in
the Community. These regulations also lay down
(a) the rules relating to the organisation and functioning
of the electricity sector,
(b) open access to the market where applicable, the
criteria and procedures applicable to calls for tenders and the
granting of authorisations and the operation of systems;
(c) universal service obligations and the rights of
electricity consumers and clarification of competition
requirements.
(4) These regulations also establish measures for the
safeguarding of security of electricity supply so as to ensure the
proper functioning of the market for electricity and to ensure an
adequate level of generation capacity, an adequate balance between
supply and demand, and an appropriate level of interconnection.
Regulation 4, 11
EXEMPTIONS FROM THE REQUIREMENT OF AN AUTHORISATION
OR LICENCE
1. A producer who -
(a) produces electricity solely for his own use;
(b) is not connected in parallel to the distribution system; and
(c) has installed a total peak generation capacity of less than 1500
kVA.
2. A producer with a total peak generation capacity rated up to and including
16 Amps per phase, single-phase or multi-phase, 230/400V AC produced solely
from renewable sources of energy or cogeneration plant, shall be exempted from
the requirement of an authorisation to construct the generation station and from the
requirement to hold a licence but shall still be required to notify the Authority, in such
form and manner as required by the Authority prior to construction of such generation
plant, and submit to the Authority such information as the Authority may request
from time to time.
In these regulations, unless the context otherwise
requires:-
“the Act” means the Malta Resources Authority Act;
“ancillary service” means a service necessary for the
operation of a distribution system;
“the Authority” means the Malta Resources Authority
established by article 3 of the Act;
“balance between supply and demand” means the
satisfaction of foreseeable demands of consumers to use
electricity without the need to enforce measures to reduce
consumption”;
“the Commission” means the European Commission as
established by the Treaty on the European Union as amended
by subsequent Treaties;
“the Community” means the European Community as
established by the Treaty on the European Union as amended
by subsequent Treaties;
“control” means rights, contracts or any other means
which, either separately or in combination and having regard
to the considerations of fact or law involved, confer the
possibility of exercising decisive influence on an undertaking,
in particular by
(a) ownership or the right to use all or part of the
assets of an undertaking;
(b) rights or contracts which confer decisive
influence on the composition, voting or decisions of the
organs of an undertaking;
“customer” means either a person who purchases
electricity in bulk for resale purposes or a final customer of
electricity;
“direct line” means either an electricity line linking
an isolated generation site with an isolated customer or
an electricity line linking an electricity producer and an
electricity supply undertaking to supply directly their own
premises, subsidiaries and eligible clients;
“Directive 68/151/EEC” means the European Economic
Community Directive 68/151/EEC of 9 March 1968 on the
coordination of safeguards which, for the protection of the
interests of members and others, are required by Member
States of companies within the meaning of the second
paragraph of article 58 of the Treaty, with a view to making
such safeguards equivalent throughout the Community, as
amended by subsequent legislation;
“distribution” means the transport of electricity on
high-voltage, medium-voltage and low-voltage distribution
systems with a view to its delivery to customers, but does not
include supply;
“distributed generation” means generation plants
connected to the distribution system;
“distribution system operator” means a person
responsible for operating, ensuring the maintenance of and, if
necessary, developing the distribution system in a given area
and, where applicable, its interconnections with other systems
and for ensuring the long-term ability of the system to meet
reasonable demands for the distribution of electricity;
“economic precedence” means the ranking of sources of
electricity supply in accordance with economic criteria;
“electricity derivative” means a financial instrument
specified in points 5, 6 or 7 of Section C of Annex I to
Directive2004/39/EC of the European Parliament and of the
Council of 21 April 2004 on markets in financial instruments
(where that instrument relates to electricity);
“electricity producer” means a person generating
electricity;
“electricity supplier” means the person who sells
electricity by retail to customers;
“electricity supply contract” means a contract for
the supply of electricity, but does not include an electricity
derivative;
“electricity undertaking” means any person carrying
out at least one of the following functions: generation,
distribution, supply, or purchase of electricity, which is
responsible for the commercial, technical or maintenance
tasks related to those functions, but does not include final
customers;
“energy consumer checklist” means the checklist of
practical information relating to energy consumer rights
established by the Authority;
“energy efficiency or demand-side management”
means a global or integrated approach aimed at influencing
the amount and timing of electricity consumption in order to
reduce primary energy consumption and peak loads by giving
precedence to investments in energy efficiency measures, or
other measures, such as interruptible supply contracts, over
investments to increase generation capacity, if the former
are the most effective and economical option, taking into
account the positive environmental impact of reduced energy
consumption and the security of supply and distribution cost
aspects related to it;
“final customer” means a person purchasing electricity
for his own use or consumption and not for wholesale or retail
purposes;
“generation” means the production of electricity;
“horizontally integrated undertaking” means an
undertaking performing at least one of the functions of
generation for sale, distribution, or supply of electricity, and
another non-electricity activity;
“household customer” means a person purchasing
electricity for his own household consumption, excluding
commercial or professional activities;
“integrated electricity undertaking” means a vertically or
horizontally integrated undertaking;
“interconnector” means equipment used to link
electricity systems;
“long-term planning” means the planning of the need for
investment in generation and distribution capacity on a long-
term basis, with a view to meeting the demand of the system
for electricity and securing supplies to customers;
“Member State” means a member state of the European
Union;
“the Minister” means the Minister responsible for
resources;
“non-household customer” means a person purchasing
electricity which is not for its own household use and includes
producers and wholesale customers;
“operational network security” means the continuous
operation of the distribution network under foreseeable
circumstances;
“person” means any natural or legal person;
“Regulation (EC) No 714/2009” means Regulation (EC)
No 714/2009 of the European Parliament and of the Council
of 13 July 2009 on conditions for access to the network for
cross-border exchanges in electricity and repealing Regulation
(EC) No 1228/2003;
“related undertaking” means affiliated undertakings,
within the meaning of Article 41 of the Seventh Council
Directive 83/349/EEC of 13 June 1983 based on Article 44(2)
(g) and or associated undertakings, within the meaning of
Article 33(1) of that Directive, and, or undertakings which
belong to the same shareholders;
“renewable energy sources” means renewable non-
fossil energy sources (wind, solar, geothermal, wave, tidal,
hydropower, biomass, landfill gas, sewage treatment plant gas
and biogases);
“security” means both security of supply and provision
of electricity, and technical safety;
“security of electricity supply” means the ability of an
electricity system to supply final customers with electricity;
“small enterprises” means enterprises with fewer than
50 occupied persons and an annual turnover or balance sheet
not exceeding 10 million euro;
“small isolated system” means any system with
consumption of less than 3,000 GWh in the year 1996, where
less than 5 % of annual consumption is obtained through
interconnection with other systems;
“supply” means the sale or retail, including resale, of
electricity to customers;
“system user” means a person supplying to, or being
supplied by a distribution system;
“tendering procedure” means the procedure through
which planned additional requirements and replacement
capacity are covered by supplies from new or existing
generating capacity;
“universal service” means the right to be supplied
with electricity of a specified quality at reasonable, easily
and clearly comparable, transparent and non-discriminatory
prices;
“universal service obligation” means an obligation
imposed on a supplier to ensure that all household
customers, and, where the Minister deems it appropriate,
small enterprises, enjoy universal service, that is the right
to be supplied with electricity of a specified quality within
their territory at reasonable, easily and clearly comparable
and transparent prices;
“vertically integrated undertaking” means an
electricity undertaking or a group of electricity undertakings
where the same person or the same persons are entitled,
directly or indirectly, to exercise control, and where the
undertaking or group of undertakings perform at least one of
the functions of distribution, and at least one of the functions
of generation or supply of electricity;
“wholesale customer” means a person purchasing
electricity in bulk for the purpose of resale inside or outside
the system where such person is established, not being for
his own use or consumption.
MEASURES ON CLIENT PROTECTION
1. Without prejudice to Community rules on consumer protection, in
particular Directive 97/7/EC of the European Parliament and of the Council of 20
May 1997 on the protection of consumers in respect of distance contracts and Council
Directive 93/13/EEC of 5 April 1993 on unfair terms in consumer contracts, the
measures referred to in regulation 8 are to ensure that customers
(a) have a right to a contract with their electricity service provider
that specifies
(i)
the identity and address of the supplier;
(ii)
the services provided, the service quality levels offered,
as well as the time for the initial connection;
(iii)
the types of maintenance service offered
(iv)
the means by which up-to-date information on all
applicable tariffs and maintenance charges may be obtained;
(v)
the duration of the contract, the conditions for renewal
and termination of services and of the contract and whether withdrawal
from the contract without charge is permitted;
(vi)
any compensation and the refund arrangements which
apply if contracted service quality levels are not met, including
inaccurate and delayed billing;
(vii) the method of initiating procedures for settlement of
disputes in accordance with paragraph (e) of item 1 of this Schedule;
(viii) information relating to consumer rights, including
on the complaint handling and all of the information referred to in
this point, clearly communicated through billing or the electricity
undertaking’s web site.
Conditions shall be fair and well-known in advance. In any case,
this information should be provided prior to the conclusion or confirmation
of the contract. Where contracts are concluded through intermediaries, the
information relating to the matters set out in this item shall also be provided
prior to the conclusion of the contract;
(b)
are given adequate notice of any intention to modify contractual
conditions and are informed about their right of withdrawal when the notice is
given. Service providers shall notify their subscribers directly of any increase
in charges, at an appropriate time no later than one normal billing period after
the increase comes into effect in a transparent and comprehensible manner.
Customers are free to withdraw from contracts if they do not accept the new
conditions notified to them by their electricity service provider;
(c)
receive transparent information on applicable prices and
tariffs and on standard terms and conditions, in respect of access to and use of
electricity services;
(d)
are offered a wide choice of payment methods, which do not
unduly discriminate between customers. Prepayment systems shall be fair and
adequately reflect likely consumption. Any difference in terms and conditions
shall reflect the costs to the supplier of the different payment systems. General
terms and conditions shall be fair and transparent. They shall be given in
clear and comprehensible language and shall not include non-contractual
barriers to the exercise of customers’ rights, for example excessive contractual
documentation. Customers shall be protected against unfair or misleading
selling methods;
(e)
benefit from transparent, simple and inexpensive procedures
for dealing with their complaints. In particular, all consumers shall have the
right to a good standard of service and complaint handling by their electricity
service provider. Such out-of-court dispute settlements procedures shall enable
disputes to be settled fairly and promptly, preferably within three months,
with provision, where warranted, for a system of reimbursement and, or
compensation. They should, wherever possible, be in line with the principles
set out in Commission Recommendation 98/257/EC of 30 March 1998 on the
principles applicable to the bodies responsible for out-of-court settlement of
consumer disputes;
(f)
when having access to universal service under the provisions
pursuant to sub-regulation (3) of regulation 8 of these regulations, are informed
about their rights regarding universal service;
(g)
have at their disposal their consumption data, and shall be able
to, by explicit agreement and free of charge The Authority shall define a
format for the data and a procedure for consumers to have access to the data.
No additional costs shall be charged to the consumer for that service;
(h)
are properly informed of actual electricity consumption and
costs frequently enough to enable them to regulate their own electricity
consumption. That information shall be given by using a sufficient time frame,
which takes account of the capability of customer’s metering equipment and
the electricity product in question. Due account shall be taken of the cost-
efficiency of such measures. No additional costs shall be charged to the
consumer for that service.
2. Enemalta shall ensure the implementation of an intelligenta metering
system that shall assist the active participation of consumers in the electricity supply
market. The implementation of those metering systems may be subject to an economic
assessment of all the long-term costs and benefits to the market and the individual
consumer or which form of intelligent metering is economically reasonable and cost-
effective and which timeframe is feasible for their distribution.
Enemalta shall ensure the interoperability of that metering systems and
shall have due regard to the use of appropriate standards and best practice and the
importance of the development of the internal market in electricity.
Any person who prior to the entry into force of these
regulations was licensed under, and any licence issued under
the Electricity Regulations, 2004 shall be deemed to have been
licensed or to have been issued under these regulations, and the
provisions of these regulations shall mutatis mutandis apply to
that person and licence
Provided that such person may continue to perform
such operations or activities as licensed under existing licence
conditions, unless required by the Authority to apply for a new
licence under these regulations
Provided further that any such person shall comply with
such licence conditions as established in the new licence that
may be issued by the Authority with effect from such date that
the Authority may establish.
Regulations 11 (2)
CRITERIA FOR THE AWARD OF AUTHORISATIONS
An application for an authorisation may be determined by the Authority in
accordance with the following criteria
(i) the protection of public health and safety;
(ii) the protection of the environment;
(iii) land use and siting;
(iv) the use of public ground;
(v) energy efficiency;
(vi) the nature of the primary sources;
(vii) the characteristics particular to the applicant, such as technical,
economic and financial capabilities;
(viii) compliance with measures adopted pursuant to regulation 8 of
these regulations;
(ix) the contribution of the generating capacity to the increase to the
share of energy from renewable sources in gross final consumption of energy;
(x) the contribution of generating capacity to reducing emissions.
€3.24
(1) The following operations and activities shall
require a licence issued by the Authority and in accordance
with such terms and conditions as may be specified in the
licence:-
(a) generation of electricity;
(b) supply of electricity;
(c) carrying out of any of the functions of a
distribution system operator.
(2) A licence shall not be required for the
categories specified in the First Schedule to these regulations
for the carrying out of the operations or activities mentioned
therein.
(3) Without prejudice to any other law, licences
may be granted or refused on the basis of the following
criteria
(a) compliance by the applicant with all other
relevant permits and authorisations, however so
described, including those issued by any other public
authority or Government Department;
(b) the capability of the applicant to ensure safety
conditions, in the context of the licence being applied for;
(c) private and professional integrity of the applicant;
(d) protection of the health and safety of employees;
(e) protection of the environment;
(f) record of compliance with these regulations and
any other relevant laws by the person or entity with regard to
whom the decision shall be made;
(g) compliance with safety, health, security, hazardous
substances, environment, land use and planning requirements.
(4) An application for a new licence or for its
renewal under these regulations shall be
(a) in writing and in such form and shall contain such
information as the Authority may require;
(b) accompanied by such fees, bank guarantees and
insurance policies as the Authority may determine and deem
to be appropriate. All fees shall be payable on application
and any bank guarantees and, or insurance policies shall be
effective as from the date of the issue of the licence and shall
subsist throughout its duration. Interests and penalties, as
established by the Authority, shall be payable in the event of
default in the due payment of fees
Provided that a licence granted under these regulations
shall not relieve the licensee from the requirement of any
other licence, permit or other authorisation, or from an
obligation arising from any other law.
(5) A licence granted under these regulations may
include such conditions as appear to the Authority to be requisite
or expedient, having regard to the duties of the Authority.
(6) The Authority shall communicate to the applicant
in writing within a reasonable time, which shall not be of more
than six months from the date of receipt of a valid application,
any decision taken concerning an application for a licence or
an application for the renewal of a licence or any valid reason
impeding the Authority to reach such a decision.
The Authority may, at any time in the course of the
period for which a licence is valid, order its suspension, revocation
or cancellation where the Authority is satisfied that
(a) the holder of the licence has failed or is failing
to comply with any condition of the licence or with these
regulations; or
(b) the licensee does not possess all other relevant
licences, permits and authorisations however so described
that are required by any other public authority or Government
department; or
(c) the holder of the licence is contravening any
requirement imposed by law; or
(d) the holder of the licence fails to comply with any
directive given by the Authority; or
(e) any information submitted in the application for
a licence or the application for renewal of a licence and for
which the licence has been issued or renewed, as the case
may be, is determined to be false; or
(f) if the holder of the licence does not meet any criteria
in respect to one or more of the criteria referred to in sub-
regulation (3) of regulation 4 of these regulations
Provided that in exercising the powers for suspension,
revocation or cancellation of licences the Authority may
take into account the nature of the failure, or the fact that the
holder of the licence is taking the appropriate steps which the
Authority considers to be necessary in order to comply with
the conditions of the licence, these regulations or any other
requirement that the Authority may deem relevant.
(1) When the holder of a licence issued under these
regulations, decides either to suspend or terminate his licence, such
holder shall promptly notify the Authority in the form prescribed by
the Authority, to notify such a termination or suspension.
(2) Upon acknowledgment by the Authority
to the holder of a licence of the notification mentioned in sub-
regulation (1) hereof, the licence shall be considered to have ceased
to be in force and with immediate effect from the date of such
acknowledgment such holder shall be deemed to be unlicensed.
(3) Notwithstanding any notice for the termination or
suspension of a licence, the holder of the licence shall remain liable
for the payment of any fee due to the Authority.
(1) A licence issued by the Authority under these
regulations shall not be validly transferred inter vivos to any other
person unless
(a) the transferor informs in writing the Authority in
such form and manner as the Authority shall prescribe;
(b) the Authority is satisfied that at least the same
criteria as listed in sub-regulation (3) of regulation 4 of these
regulations are complied with;
(c) the transfer is subject to the conditions prescribed
in the licence; and
(d) the Authority approves in writing the transfer of
the licence.
(2) A licence issued by the Authority under these
regulations shall not be validly transmitted causa mortis to any
other person unless
(a) the transferor informs in writing the Authority in
such form and manner as the Authority shall prescribe;
(b) the Authority is satisfied that at least the same
criteria as listed in sub-regulation (3) of regulation 4 of these
regulations are complied with;
(c) the transfer is subject to the conditions prescribed in
the licence; and
(d) the Authority approves in writing the transfer of the
licence
Provided that a licence issued in terms of these
regulations shall be an indivisible right
Provided further that in the event that the Authority
approves the transfer of the licence as aforesaid, the transfer
shall have retrospective effect from the date of the death of
the decujus.
(2)
Where the licensee is a body corporate or any
other body of persons, a change in the control of the ownership
or management of that body shall be deemed to be equivalent to
the transfer of the licence, and shall be subject to the approval of
the Authority. For the purpose of this sub-regulation, a transfer in
the control of the ownership of a body corporate or other body of
persons shall be deemed to occur in any case where a transfer of the
capital, shares, stocks or other rights held in the body corporate or
other body of persons leads to a change in the person holding the
controlling interest therein.
(1) Enemalta shall provide to all household customers
universal service, and, where the Minister deems it appropriate, it
shall also provide such universal service to small enterprises.
(2) The distribution system operator shall connect
customers to its network under terms, conditions and tariffs set in
accordance with the procedure laid down in sub-regulation (6) of
regulation 21 of these regulations.
(2) Final customers shall be provided by their
electricity supplier with all relevant consumption data. The supplier
of electricity shall give such data to final customers in a non-
discriminatory manner as regards cost, effort or time.
(3) The Authority shall monitor, report to, and propose
measures to the Minister every two years whether
(a) there are adequate safeguards to protect
vulnerable customers, including measures to help them avoid
disconnection and to protect final customers in remote areas;
and
(b) there are high levels of consumer protection,
particularly with respect to transparency regarding contractual
terms and conditions, general information and dispute
settlement mechanisms.
(4) Household customers shall have the right to the
measures set out in the Second Schedule to these regulations.
(5) The electricity supplier shall specify in or with
the bills and in promotional materials made available to final
customers
(a) the contribution of each energy source to the
overall fuel mix of the supplier over the preceding year in a
comprehensible and, at a national level, clearly comparable
manner;
(b) at least the reference to existing reference sources,
such as web pages, where information on the environmental
impact, in terms of at least CO 2 emissions and the radioactive
waste rresulting from the electricity produced by the overall
fuel mix of the supplier over the preceding year is publicly
available;
(c) information concerning their rights as regards the
means of dispute settlement available to them in the event of
a dispute
Provided that, with regard to paragraphs (a) and (b) of
this sub-regulation with respect to electricity obtained via an
electricity exchange or imported from an undertaking situated
outside the Community, aggregate figures provided by the
exchange or the undertaking in question over the preceding
year may be used.
Provided further that the electricity supplier may
be audited by the Authority to ensure that the information
provided to its customers pursuant to this regulation is
reliable.
(6) The electricity supplier shall in cooperation with
the Authority, take the necessary steps to provide customers with
a copy of the energy consumer checklist and ensure that it is made
publicly available.
(1) At least every two years from the entry into force
of these regulations or at such other date as may be required by
the Authority, the distribution system operator shall draw up and
submit to the Authority an estimate of the available generating
and distribution capacity, the interconnectors with other systems,
the actual distribution capacity, all ancillary services, operational
network security and the current demand for electricity as well
as the generating and distribution capacity which is likely to be
connected to the system, of the need for interconnectors with other
systems, of potential distribution capacity, of all ancillary services,
the projected balance of supply and demand for the next five year
period, and the prospects for security of electricity supply covering
the period between five and fifteen years from the date of the
report.
(2) The Authority shall monitor the estimates produced
as per sub-regulation (1) of this regulation and publish a report
every two years by the 31 st July at the latest. The report shall
be drawn in cooperation with the distribution sys tem operator
and shall cover, in particular, operational network security, the
projected balance of supply and demand on the market for the
next five years, the level of expected future demand and envisaged
additional capacity being planned or under construction and
the quality and level of maintenance of the networks, as well as
measures to cover peak demand and to address any envisaged
shortfalls on the market, the prospects for security of electricity
supply for the period between five and fifteen years from the
date of the report, investment intentions for the next five or more
calendar years of the distribution system operator including any
known plans for interconnection investment. The part of the report
on interconnection investment, if appropriate, shall take account
of
(a) the principles of congestion management, as set
out in Regulation (EC) No 228/2003;
(b)
planned transmission lines;
(c) expected patterns of generation, supply, cross-
border exchanges and consumption, allowing for demand
management measures;
(d) regional, national and European sustainable
development objectives, including those projects forming part
of the Axes for priority projects set out in Annex I to Decision
No 1229/2003/EC.
Within such time and following such consultation as
the Authority may direct, the distribution system operator shall
prepare, keep updated and publish a “network code”, subject to
the approval of the Authority, defining the technical safety criteria
and the technical rules establishing the minimum technical design
and operational requirements for the connection to the system of
generating installations, distribution systems, directly connected
consumers’ equipment, interconnector circuits and direct lines
and set the minimum operational rules and obligations on network
security and foreseeable circumstances in which security shall be
maintained. The “network code” shall ensure the interoperability
of systems and shall be objective and non-discriminatory. The
network code shall be notified in accordance with the Notification
Procedure Regulations. The Authority may from time to time
give directions, which may include technical safety criteria, to the
distribution system operator in respect to the matters to be specified
in the network code and its review and revision by the distribution
system operator.
(1) The construction of new generation capacity shall
require an authorisation from the Authority. The authorisation
procedure for the construction of new generating capacity, shall
be conducted in accordance with objective, transparent and non-
discriminatory criteria
Provided that no such authorisation shall be required for
the producers listed in the First Schedule to these regulations.
(2) Authorisations shall be granted or refused on
the basis of the criteria listed in the Third Schedule to these
regulations.
(3) The Authority, in the processing of applications for
authorisations, shall take into account the size and potential impact
of the generation plant which the application relates to.
(1) New capacity or energy efficiency demand-
side management measures may be provided, in the interests of
security of supply, through a tendering procedure or any procedure
equivalent in terms of transparency and non-discrimination, on the
basis of published criteria. Those procedures may, however, be
launched only where, on the basis of the authorisation procedure,
the generating capacity to be built or the energy efficiency or
demand-side management measures to be taken are insufficient
to ensure security of supply. Such a tender may be launched
by a public body or a private body independent from electricity
generation, distribution and supply activities, appointed for the
purpose by the Minister by notice in the Gazette. This body shall
take all necessary steps to ensure confidentiality of the information
contained in the tenders and shall follow the rules in sub-regulation
(3)
Provided that the Minister may decide not to adopt such
a tendering procedure or any procedure equivalent in terms of
transparency and non-discrimination, on the basis of published
criteria insofar as its adoption would obstruct the performance, in
law or in fact, of the obligations imposed on electricity undertakings
in the general economic interest and insofar as the development of
trade would not be affected to such an extent as would be contrary
to the interests of the Community. The interests of the Community
include Article 86 of the Treaty.
(2) The Minister may ensure the possibility, in the
interests of environmental protection and the promotion of infant
new technologies, of tendering for new capacity on the basis of
published criteria. Such tendering may relate to new capacity or
to energy efficiency or demand-side management measures. A
tendering procedure may however, be launched only where, on
the basis of the authorisation procedure the generating capacity
to be built or the measures to be taken, are insufficient to achieve
those objectives.
(3) The details of the tendering procedure for means
of generating capacity and energy efficiency or demand-side
management measures shall be published in the Official Journal
of the European Union at least six months prior to the closing
date for tenders. The tender specifications shall be made available
to any interested undertaking established in the territory of a
Member State so that it has sufficient time in which to submit a
tender
Provided that with a view to ensuring transparency
and non-discrimination, the tender specifications shall contain
a detailed description of the contract specifications and of the
procedure to be followed by all tenderers and an exhaustive list
of criteria governing the selection of tenderers and the award of
the contract, including incentives, such as subsidies, which are
covered by the tender. Those specifications may also relate to the
fields referred to in sub-regulation (2) of this regulation.
(4) In invitations to tender for the requisite generating
capacity, consideration shall also be given to electricity supply
offers with long-term guarantees from existing generating units,
provided that additional requirements can be met in this way.
(1) Enemalta Corporation is designated the
distribution system operator in Malta. The Authority shall ensure
that the distribution system operator acts in accordance with this
regulation and regulation 14 of these regulations.
(2) The distribution system operator shall be
responsible for ensuring the long-term ability of the system to
meet reasonable demands for the distribution of electricity, for
operating, maintaining and developing under economic conditions
a secure, reliable and efficient electricity distribution system so as
to ensure continuity of electricity supplies in Malta with due regard
for the environment and energy efficiency. In any event, it must
not discriminate between system users or classes of system users,
particularly in favour of its related undertakings.
(3) The distribution system operator shall provide
system users with the information they need for efficient access to,
including use of, the system.
(4) The distribution system operator, when dispatching
generating installations, shall give priority to generating
installations using renewable energy sources or waste or producing
combined heat and power, subject that this is technically possible
and does not impact negatively on system stability or reliability.
(5) The distribution system operator shall procure the
energy it uses to cover energy losses and reserve capacity in its
system according to transparent, non-discriminatory and market
based procedures, whenever it has such a function.
(6) Where the distribution system operator is responsible
for balancing the distribution system, rules adopted by it for that
purpose shall be objective, transparent and non-discriminatory,
including rules for the charging of system users of their networks
for energy imbalance. Terms and conditions, including rules and
tariffs, for the provision of such services by distribution system
operators shall be established in accordance with sub-regulation (6)
of regulation 21 of these regulations in a non-discriminatory and
cost-reflective way and shall be published
(7) When planning the development of the distribution
network, energy efficiency or demand-side management measures
or distributed generation that might supplant the need to upgrade or
replace electricity capacity shall be considered by the distribution
system operator. Demand-side management may include real-time
management technologies such as advanced metering systems.
(8) When planning interconnections with other
systems the distribution system operator shall give special
consideration to the specific geographical situation of Malta,
the need to maintain a reasonable balance between the costs of
building new interconnectors and the benefit to final customers
of such interconnection, and if appropriate, ensuring that existing
interconnectors are used as efficiently as possible.
(9) The distribution system operator shall, set and meet
quality of supply and network security performance objectives. The
performance objectives shall be objective, transparent and non-
discriminatory and be published
Provided that such performance objectives shall be
subject to the approval and monitoring of the Authority.
(10) The distribution system operator shall, before the
adoption of any of the measures mentioned in this regulation, take
into account the impact of such measures on the cost of electricity
to final customers.
Without prejudice to regulation 16 of these regulations
or any other legal duty to disclose information, the distribution
system operator shall preserve the confidentiality of commercially
sensitive information obtained in the course of carrying out its
business, and shall prevent information about its own activities
which may be commercially advantageous being disclosed in a
discriminatory manner.
(1) The Authority may classify a system which
distributes electricity within a geographically confined industrial,
commercial, residentialor shared services site and does not, without
prejudice to sub-regulation (4) of this regulation, supply household
customers, as a closed distribution system if
(a) for specific technical or safety reasons, the
operations or the production process of the users of that
system are integrated; or
(b) that system distributes electricity primarily to the
owner or operator of the system or their related undertakings.
(2) The Authority may exempt the operator of a closed
distribution system from the requirement under sub-regulation (5)
of regulation 13 of these regulations to procure the energy it uses
to cover energy losses and reserve capacity in its system according
to transparent, non-discriminatory and market based procedures.
(3) Incidental use by a small number of households
with employment or other similar associations with the owner of
the distribution system and located within the area served by a
closed distribution system shall not preclude an exemption under
sub-regulation (2) of this regulation from being granted.
(1) The Authority shall, insofar as necessary to carry
out its functions, have right of access to the accounts of electricity
undertakings as set out in regulation 17 of these regulations.
(2) The Authority shall preserve the confidentiality of
commercially sensitive information. The Authority may disclose
such information where this is necessary in order for the Authority
to carry out its functions.
(1) The Authority shall take the necessary steps
to ensure that the accounts of electricity undertakings are kept in
accordance with sub-regulations (2) and (3) of this regulation.
(2) Electricity undertakings, whatever their system of
ownership or legal form, shall draw up, submit to audit and publish
their annual accounts in accordance with the rules of Companies
Act or other applicable legislation concerning the preparation of the
annual accounts of limited liability companies. Undertakings which
are not legally obliged to publish their annual accounts shall keep a
copy of these at the disposal of the public in their head office.
(3) Electricity undertakings shall, in their internal
accounting, keep separate accounts for each of their generation,
distribution and supply activities as they would be required to do if
the activities in question were carried out by separate undertakings,
with a view to avoiding discrimination, cross-subsidisation and
distortion of competition. They shall also keep accounts, which
may be consolidated, for other electricity activities not relating to
distribution. Revenue from ownership of the distribution system
shall be specified in the accounts. Where appropriate, they shall
keep consolidated accounts for other, non-electricity activities. The
internal accounts shall include a balance sheet and a profit and loss
account for each activity.
(4) The audit referred to in sub-regulation (2) shall, in
particular, verify that the obligation to avoid discrimination and
cross-subsidies referred to in sub-regulation (3) is respected.
(5) The annual accounts shall indicate in the notes any
transaction of a certain size conducted with related undertakings
(1) Where access to the network is refused by the
distribution system operator due to a lack of capacity, the Authority
may authorise the applicant to whom such refusal is made to
construct a direct line not connected to the distribution system for
the sole purpose of facilitating the supply of electricity for which
the application for use of the distribution system was made and
refused.
(2) The Authority shall lay down the criteria for the
grant of authorisations for the construction of direct lines. Those
criteria shall be objective and non-discriminatory.
(3) The Authority may refuse to authorise the
construction of a direct line if the granting of such an authorisation
would obstruct the application of the provisions of these
regulations, or any other law. Duly substantiated reasons must be
given for such refusal.
( 4) An authorisation to construct a direct line granted
by the Authority under this regulation shall require the person to
whom the authorisation is granted to comply with such technical
rules and other conditions, including those which may be necessary
to ensure that direct lines are compatible with the distribution
system, to such extent as the Authority may specify in the
authorisation.
The Authority when carrying out the regulatory
tasks conferred upon it by these regulations shall
(a) be functionally independent from any other public
or private entity;
(b) ensure that its staff and the persons responsible for
its management
(i)
act independently from any market interest;
and
(ii)
do not seek or take direct instructions from
any government or other public or private entity when
carrying out the regulatory tasks
Provided that this requirement is without prejudice
to close cooperation, as appropriate, with other relevant
national authorities or to general policy guidelines issued
by the Government not related to the regulatory powers
and duties under regulation 21 of these regulations.
In carrying out the regulatory tasks specified in these
regulations, the Authority shall take all reasonable measures in
pursuit of the following objectives within the framework of its duties
and powers as laid down in regulation 21 of these regulations, in
close consultation with other relevant national authorities including
competition authorities, as appropriate, and without prejudice to
their competencies
(a) promoting, in close cooperation with the Agency,
regulatory authorities of other Member States and the
Commission, a competitive, secure and environmentally
sustainable internal market in electricity within the
Community, and effective market opening for all customers
and suppliers in the Community and ensuring appropriate
conditions for the effective and reliable operation of electricity
networks, taking into account long-term objectives;
(b) developing competitive and properly functioning
regional markets within the Community in view of the
achievement of the objectives referred to in paragraph (a) of
this regulation;
(c) eliminating restrictions on trade in electricity
between Member States, including developing appropriate
cross-border transmission capacities to meet demand and
enhancing the integration of national markets which may
facilitate electricity flows across the Community;
(d) helping to achieve, in the most cost-effective
way, the development of secure, reliable and efficient non-
discriminatory systems that are consumer oriented, and
promoting system adequacy and, in line with general
energy policy objectives, energy efficiency as well as the
integration of large and small-scale production of electricity
from renewable energy sources and distributed generation in
distribution networks;
(e) facilitating access to the network for new
generation capacity, in particular removing barriers that could
prevent access for new market entrants and of electricity from
renewable energy sources;
(f) ensuring that system operators and system users are
granted appropriate incentives, in both the short and the long
term, to increase efficiencies in system performance
(g) ensuring that customers benefit through the
efficient functioning of the national market, promoting
effective competition and helping to ensure consumer
protection;
(h) helping to achieve high standards of universal
and public service in electricity supply, contributing to the
protection of vulnerable customers.
(1) The Authority shall have the following duties and
powers in terms of these regulations
(a) fixing or approving, in accordance with transparent
criteria, electricity generation, distribution and supply tariffs
or their methodologies;
(b) fixing or approving, in accordance with transparent
criteria, the tariffs for the purchase of electricity by Enemalta
where appropriate
(c) ensuring compliance of the distribution system
operator, as well as of any electricity undertakings, with their
obligations under these regulations, other relevant legislation
and Community legislation, including as regards cross-border
issues;
(d) cooperating in regard to cross-border issues with
the regulatory authority or authorities of the Member States
concerned and with the Agency;
(e) complying with, and implementing, any
relevant legally binding decisions of the Agency and of the
Commission;
(f)
reporting annually on its activity and the fulfilment
of its duties to the relevant authorities, the Agency and the
Commission. Such reports shall cover the steps taken and
the results obtained as regards each of the tasks listed in this
regulation;
(g) ensuring that there are no cross-subsidies between
generation, distribution, supply and other activities;
(h) monitoring investment plans of the distribution
system operator, and providing in its annual report an
assessment of the investment plans of the distribution system
operator as regards their consistency with the Community-
wide network development plan referred to in Article 8 (3)
(b) of Regulation (EC) No 714/2009; such assessment may
include recommendations to amend those investment plans;
(i) monitoring compliance with and reviewing the
past performance of network security and reliability rules and
setting or approving standards and requirements for quality of
service and supply or contributing thereto together with other
competent authorities;
(j) monitoring the level of transparency, including
of wholesale prices, and ensuring compliance of electricity
undertakings with transparency obligations;
(k) monitoring the time taken by the distribution
system operator to make connections and repairs;
(l) helping to ensure, together with other relevant
authorities, that the consumer protection measures, including
those set out in the Second Schedule to these regulations, are
effective and enforced;
(m) ensuring access to customer consumption data,
the provision, for optional use, of an easily understandable
harmonised format at national level for consumption data, and
prompt access for all customers to such data under paragraph
(g) of item 1 of the Second Schedule to these regulations;
(n) monitoring the implementation of rules relating
to the roles and responsibilities of the distribution system
operator, suppliers and customers and other market parties
pursuant to Regulation (EC) No 714/2009;
(o) monitoring investment in generation capacities in
relation to security of supply;
(p) monitoring technical cooperation between
Community and third-country transmission system operators;
(q) monitoring the implementation of safeguards
measures as referred to in regulation 26 of these regulations;
and
(r) contributing to the compatibility of data exchange
processes for the most important market processes at regional
level.
(2) While preserving its independence, without
prejudice to its own specific competencies and consistency with the
principles of better regulation, the Authority shall, as appropriate,
closely cooperate with other relevant national authorities when
carrying out the duties set out in sub-regulation (1) of this
regulation.
(3) Any approvals given by the Authority under these
regulations are without prejudice to any duly justified future use
of its powers under this regulation or to any penalties imposed by
other relevant authorities or the Commission.
(4) The Authority shall be responsible for fixing or
approving sufficiently in advance of their entry into force at least
the methodologies used to calculate or establish the terms and
conditions for
(a) connection and access to the distribution system,
including distribution tariffs or their methodologies. Those
tariffs or methodologies shall allow the necessary investments
in the networks to be carried out in a manner allowing those
investments to ensure the viability of the networks;
(b) the provision of balancing services which shall be
performed in the most economic manner possible and provide
appropriate incentives for network users to balance their input
and off-takes. The balancing services shall be provided in a
fair and non-discriminatory manner and be based on objective
criteria;
(c)
access to cross-border infrastructures, including
the procedures for the allocation of capacity and congestion
management;
(d) the supply of electricity to customers;
(e) the purchase of electricity by Enemalta Corporation
where appropriate.
(5) The methodologies or the terms and conditions
referred to in sub-regulation (4) shall be published.
(6) In fixing or approving the tariffs or methodologies
and the balancing services, the Authority shall ensure that the
distribution system operator is granted appropriate incentive, over
both the short and long term, to increase efficiencies, foster market
integration and security of supply and support the related research
activities.
(7) The Authority shall monitor congestion
management of national electricity systems including
interconnectors, and the implementation of congestion management
rules. To that end, the distribution system operator or market
operators shall submit its congestion management rules, including
capacity allocation, to the Authority. The Authority may request
amendments to those rules.
(8) The Authority may require the distribution
system operator, if necessary, to modify the terms and conditions,
including tariffs or methodologies referred to in this regulation,
to ensure that they are proportionate and applied in a non-
discriminatory manner. In the event of delay in the fixing of
distribution tariffs, the Authority shall have the power to fix
or approve provisional distribution tariffs or methodologies and
to decide on the appropriate compensatory measures if the final
distribution tariffs or methodologies deviate from those provisional
tariffs or methodologies.
(9) Any party having a complaint against the
distribution system operator in relation to that operator ’s
obligations under these regulations may refer the complaint to
the Authority which, acting as dispute settlement authority, shall
issue a decision within a period of two months after receipt of the
complaint. That period may be extended by two months where
additional information is sought by the Authority. That extended
period may be further extended with the agreement of the
complainant. The Authority’s decision shall have binding effect
unless and until overruled on appeal.
(10) Any party who is affected and who has a right to
complain concerning a decision on methodologies taken pursuant
to this regulation or, where the Authority has a duty to consult,
concerning the proposed tariffs or methodologies, may, at the
latest within two months, following publication of the decision
or proposal for a decision, submit a complaint for review. Such a
complaint shall not have suspensive effect.
(11) Complaints referred to in sub-regulations (9) and (10)
of this regulation shall be without prejudice to the exercise of rights
of appeal under Community or national law.
(12) Decisions taken by the Authority shall be fully
reasoned and justified to allow for judicial review. The decisions
shall be available to the public while preserving the confidentiality
of commercially sensitive information.
(1) The Authority shall closely consult and cooperate Regulatory regime for
with other regulatory authorities including with national regulatory cross-border issues.
authorities of other Member States, and shall provide them and the
Agency with any information necessary for the fulfilment of their
tasks under Directive 2009/72/EC. In respect of the information
exchanged, the Authority shall bind the receiving authority to
ensure the same level of confidentiality as that required of the
Authority.
(2)
The Authority shall cooperate at least at a regional
level to
(a) foster the creation of operational
arrangements in order to enable an optimal management
of the network, promote joint electricity exchanges and
the allocation of cross-border capacity, and to enable an
adequate level of interconnection capacity, including
through new interconnection, within the region and
between regions to allow for development of effective
competition and improvement of security of supply,
without discriminating between supply undertakings in
different Member States;
(b)
coordinate the development of all network
codes
(c) coordinate the development of the rules
governing the management of congestion.
(3) The Authority shall have the right to enter into
cooperative arrangements with other regulatory authorities to foster
regulatory cooperation.
(4) The actions referred to in sub-regulation (2) shall
be carried out, as appropriate, in close consultation with other
relevant national authorities and without prejudice to their specific
competencies.
(1) Supply undertakings shall keep at the disposal
of the Authority, national authorities, including the national
competition authority and the Commission, for the fulfilment
of their tasks, for at least five years, the relevant data relating to
all transactions in electricity supply contracts and electricity
derivatives with wholesale customers and the distribution system
operator.
(2) The data shall include details on the characteristics
of the relevant transactions such as duration, delivery and
settlement rules, the quantity, the dates and times of execution
and the transaction prices and means of identifying the wholesale
customer concerned, as well as specified details of all unsettled
electricity supply contracts and electricity derivatives.
(3) The Authority may decide to make available to
market participants elements of that information
Provided that commercially sensitive information on
individual market players or individual transactions shall not be
released
Provided further that, this regulation shall not apply to
information about financial instruments which fall within the scope
of Directive 2004/39/EC.
(4) With respect to transactions in electricity
derivatives of supply undertakings with wholesale customers and
transmission system operators, this regulation shall apply only
once the Commission has adopted the Guidelines which define the
methods and arrangements for record keeping as well as the form
and content of the data that shall be kept.
(5) The provisions of this regulation shall not create
additional obligations towards the authorities referred to in sub-
regulation (1) for entities falling within the scope of Directive
2004/39/EC.
(6) In the event that the authorities referred to in
sub-regulation (1) need require access to data kept by entities
falling within the scope of Directive 2004/39/EC, the authorities
responsible under that Directive shall provide them with the
required data.
In the event of a sudden crisis in the energy market Access to and
and where the physical safety or security of persons, apparatus or operation
installations or system integrity is threatened, the Authority may
temporarily take the necessary safeguard measures. Such measures
shall cause the least possible disturbance in the functioning of
the internal market and shall not be wider in scope than is strictly
necessary to remedy the sudden difficulties which have arisen. The
Minister shall, without delay, notify those measures to the other
Member States, and to the Commission
Provided that the Minister shall amend or abolish such
measures, upon a decision by the Commission to amend or abolish
such measures, insofar as they distort competition and adversely
affect trade in a manner which is at variance with the common
interest.
(1) Subject to requirements relating to the maintenance
of the reliability, safety and stability of the distribution system,
based on transparent and non-discriminatory criteria defined by the
Authority
(a) the distribution system operator shall
wherever technically feasible and with regard to system
stabilityguarantee the distribution of electricity produced from
renewable energy sources;
(b) the distribution system operator shall also
provide for priority access to the distribution system of
electricity produced from renewable energy sources;
(c) when dispatching electricity generating
installations, the distribution system operator shall give
priority to generating installations using renewable energy
sources in so far as the secure operation of the national
electricity system permits and based on transparent and non-
discriminatory criteria. The distribution system operator
shall ensure that appropriate distribution system and market-
related operational measures are taken in order to minimise
the curtailment of electricity produced from renewable
energy sources. If significant measures are taken to curtail
the renewable energy sources in order to guarantee the
security of the national electricity system and security of
energy supply, the distribution system operator shall report
to the Authority on those measures and indicate which
corrective measures they intend to take in order to prevent
inappropriate curtailments.
(2) The distribution system operator shall set up
and make public its standard rules relating to the bearing and
sharing of costs of technical adaptations, such as connection to
the distribution system and distribution system reinforcements,
and improved operation of the distribution system, which are
necessary in order to integrate new producers feeding electricity
produced from renewable energy sources into the distribution
system. Those rules shall be based on objective, transparent
and non-discriminatory criteria taking particular account of
all the costs and benefits associated with the connection of
those producers to the distribution system and of the particular
circumstances of producers located in peripheral regions and in
regions of low population density. Those rules may provide for
different types of connection.
(3) The distribution system operator shall provide to
any new producer of energy generating electricity from renewable
energy sources which needs to be connected to the system,
with the comprehensive and necessary information required,
including
(a) a comprehensive and detailed estimate of the
costs associated with the connection;
(b) a reasonable and precise timetable for receiving
and processing the request for grid connection;
(c) a reasonable indicative timetable for any proposed
grid connection
Provided that electricity producers generating
electricity from renewable energy sources which needs to
be connected to the grid, may issue a call for tender for
work connection, provided that they meet the standard
specifications and technical approval by the distribution
system operator
Provided further that electricity producers generating
electricity from renewable energy sources which needs to
be connected to the grid shall act in conformity with the
network code.
(5) The Authority shall ensure that tariffs charged
by the distribution system operator for distribution of electricity
from plants using renewable energy sources reflect reasonable
cost benefits resulting from the plant’s connection to the network.
Such cost benefits could arise from the direct use of the low-
voltage grid.
(1) Enemalta Corporation shall prepare procedures, Special clauses to
subject to the prior approval of the Authority, to ensure that monopoly position by
the purchasing of electricity is carried out with sufficient Enemalta Corporation.
independence from the rest of Enemalta business and that
Enemalta Corporation does not discriminate against any other
producer in favour of Enemalta. These procedures shall be
submitted to the Authority within two monthsone year of the
coming into force of these regulations. and may be modified by
the Authority at any time it so decides.
(2) Enemalta Corporation shall maintain or procure
an appropriate level of reserve generation capacity, including
availability of back-up capacity for electricity from renewable
energy sources and cogeneration, where technically necessary, in
order to achieve and maintain standards of reliability and maintain
a balance between demand and supply and stable operation, as
established by the Authority, for the supply of electricity to meet
demand, and shall be compensated for this service.
(1) The Authority may issue a compliance order
against any person who in its opinion has contravened any of
the provisions of these regulations or a condition of a licence or
authorisation issued thereunder.
(2) Any person who fails to abide by the provisions of
a compliance order issued by the Authority shall, without prejudice
to any other liability under these regulations, the Act or any other
law, be guilty of an offence. and be liable, on conviction, to a
fine (multa) of not less than one thousand euro (€1,000) and of
not more than sixty thousand euro (€60,000) for each day during
which the failure to comply subsists.
(1) Any person who contravenes any of the provisions
of these regulations or of a licence condition or of an authorisation or
approval issued thereunder, shall be guilty of an offence. and shall,
on conviction, be liable to a fine (multa)
of not more than sixty-
nine thousand euro (€69,000) or for one thousand and three hundred
euro(€1,300) for each day during which the offence persists.
(2) Any person who, when information with respect to these
regulations is requested or required by the Authority, knowingly or
recklessly -
(a) gives any false, inaccurate or misleading
information; or
(b) supplies incomplete information; or
(c) fails, without reasonable cause, to supply
information requested within the time given; or
(d) prevents or hinders any investigation; or
(e) produces or furnishes, or causes or knowingly allows
to be produced or furnished, any document or information
which he knows to be false in any material respect,
shall be guilty of an offence. and shall, on conviction,
be liable to a fine (multa) of not less than one thousand euro
(€1,000) and of not more than sixty thousand euro (€60,000)
for each day during which the failure to comply subsists.
(3) Notwithstanding any other provision of these
regulations, where any person fails to comply with the provisions
of these regulations or of a licence or authorisation condition for a
period not exceeding three months, the Authority may revoke such
licence or authorisation.
The Authority may impose an administrative fine upon
any person who infringes any provision of these regulations or
who fails to comply with any directive or decision given by the
Authority in ensuring compliance with these regulations.
The Electricity Regulations, 2004 are hereby being