Development Planning (Fees) Regulations, 2010
Table of Provisions (10)
Statutory Text (10 Articles)
L.N. 356 of 2010
DEVELOPMENT PLANNING ACT
(CAP. 356)
Development Planning (Fees) Regulations, 2010
IN exercise of the powers conferred by articles 41, 42 and
60 of the Development Planning Act, the Prime Minister and the
Malta Environment and Planning Authority, with the concurrence
of the Minister of Finance, the Economy and Investment, have
made the following regulations:-
(1) The title of these regulations is Development
Planning (Fees) Regulations, 2010.
(2) These regulations shall apply to
(a) all applications which are received on or after the
coming into force of these regulations; or
(b) all applications where the fees payable are re-
calculated by the Authority as a result of a change in the
original application, on or after the coming into force of these
regulations; or
(c) all applications received prior to the coming into
force of these regulations and where a bill for fees has been
issued by the Authority on or after the date of coming into
force of these regulations, and such fees are not paid within
30 calendar days from date of issue of the bill; or
(d) all applications received prior to the coming into
force of these regulations and where a bill for fees has been
issued by the Authority before the date of coming into force
of these regulations, and such fees are not paid within 30
calendar days from date of the coming into force of these
regulations.
(1)
In these regulations, unless the context otherwise
requires –
“the Act” means the Development Planning Act, 1992,
or any Act superceding this Act;
“the Authority” means the Malta Environment and
Planning Authority;
“alterations” means structural interventions to the
interior and, or exterior of a building which do not result in an
increase in the floor area of the building being altered;
“amended application” means an application for
amendments to a development, relating to changes in the
internal layout or external appearance, for which permission
has already been granted and is still valid
(a) in respect of the same site and involving
development of the same general character and
description; and
(b) which does not involve a different use or an
increase in the number of dwelling units, and increase in
floor area;
“agricultural building” means a building used for
agricultural purposes, including the storage of agricultural
implements, but not for
(a)
the keeping of livestock or animal husbandry;
(b)
the slaughter of animals; and
(c)
the processing of animals or animal products;
“application” means an application for development
permission;
“boathouse for a registered fisherman” means a
boathouse used for the storage of fishing boats and equipment
used in the course of the registered occupation;
“bungalow” means a single dwelling unit, whether
detached or semi-detached, where appropriate, consisting of
not more than one habitable floor unless it is located within
the development boundaries in an area designated for more
dense development;
“commercial development” means a development which
is non-residential and non-agricultural and not listed separately
in any other group in Schedule 1 to these regulations;
“compliance certificate” means a certificate referred to
in article 61(2) of the Act;
“demolition of a building” means the pulling down or
removal of 75% or more of the roofed area of any particular
unit, where the existing unit is larger than 30 meters squared;
“designated officer” means such officers of the Malta
Environment and Planning Authority designated by it to
formally endorse Development Permit Application Reports,
who shall normally be the Senior Planning Officers and
Managers of the Area Teams and the Manager of the
Development Control Unit;
“Development Permit Application Report” means
the report prepared on an application for development
permission which is submitted to a designated officer or to
the Development Control Commission;
“Development Permit Fee” includes the Environment Fee;
“dwelling” means any building or unit used for
residential purposes, but excludes a hotel, guest-house, old
people’s home and commercial establishments of similar
nature;
“endorsement” means the formal acceptance of a
Development Permit Application Report by a designated
officer such that the application is then forwarded for
determination by the Development Control Commission
or determined by a designated officer under the powers so
delegated by the Malta Environment and Planning Authority;
“engineering operations” include the formation or
laying out of roads and of means of access to roads; the
movement, re-grading or surfacing of land including the
creation of formal gardens or cemeteries; the construction or
excavation of reservoirs not ancillary to a dwelling or when
the applicant is not registered as an arable farmer with the
Department of Agriculture; the construction of bridges and
similar structures; the construction of sea defences, piers and
similar structures; the creation and replenishment of beaches
and other operations affecting beaches; the siting of moorings,
and similar operations, whether on land or on the seabed; and
excludes land reclamation for agricultural purposes;
“Environment and Development Brief” means a
statement approved by the Malta Environment and Planning
Authority wherein parameters for acceptable development on
a site are specified;
“extension” means an increase in the floor area relating
to the same use as the existing unit being altered;
“film set” means the use of land, or the placing,
installation or construction on land of structures, for the
purpose of the production of films, television programmes,
videos or other audio-visual productions;
“flat” means a single dwelling unit within a building
which contains several similar units which do not have their
own separate entrance from the street but share a common
access;
“floor area” means -
(a) for residential purposes the amount of floor
area within a building determined by the external
measurements of the building, that includes the
thickness of the external walls and half the thickness
of dividing or party walls, and includes any staircase,
lift, shafts, internal yards, back yards, front gardens,
self-imposed setback, estate or plot gardens, verandahs,
open terraces within the building foot print at the upper
levels, and terraces formed at roof level when these
belong to penthouses or where shared by multiple
owners, accessible through a permanent common access,
canopies and other structures within the site boundaries
and interconnected garages, unless specifically set out
within these regulations; and
(b) for non residential purposes, the amount of
floor area within the site boundaries determined by the
external measurements of the building, that includes the
thickness of the external walls and half the thickness
of dividing or party walls, and includes any staircase,
lift, shafts, internal yards, back yards, front gardens,
verandahs, terraces, interconnected garages, canopies
and other spaces, including open spaces used for
commercial purposes;
“garage “ means a garage or space used for the parking
of vehicles, whether enclosed or unenclosed, and whether or
not above or below ground level;
“land reclamation for agriculture” means the reclamation
of land, including the deposit of material and the altering of
the level of the land, for the purposes of agriculture;
“livestock farm building “ means a building used for the
accommodation of livestock and for the storage of fodder or
implements related to the same activity, but does not include
farmhouses, greenhouses, buildings used for agricultural
purposes or buildings used for the slaughter of animals or
processing of animals or animal products;
“maisonette” means a single dwelling unit on one or
more floors, having a separate entrance from the street,
located in a building consisting of more than one unit;
“penthouse” means a separate single dwelling which
consists of one floor constructed above height limitation on
the roof of a building, and which does not occupy the whole
of the roof area and does not have permanent access to roof
level;
“planning control application” means those applications,
not being applications for development permission, which
require the approval of the Malta Environment and Planning
Authority for such changes to the Local Plans and, or the
detailed alignments of buildings and streets within such Local
Plans;
“plant and machinery” means mechanical equipment or
structures erected or placed on land but not within a building;
“public car park” means a building or area exclusively
used for parking of vehicles and is not ancillary to any other
use on site.
“registered fisherman” and “ registered farmer” mean
a fisherman or a farmer registered with the Department of
Agriculture and Fisheries, as the case may be;
“relevant Department” means, for the purposes of
the main sewer contribution, the Drainage Section of the
Water Services Corporation, and for the purposes of the
street contribution, Transport Malta and any other body
which subsequently assumes the responsibilities of these
Departments or entities;
“renewal application” means an application for the
renewal of a development permission granted by the Authority
in respect of the same site which is submitted before such
permission expires;
“screening” means the process during which the
proposed development is considered by the Authority prior to
the submission of the formal application;
“site area” means the total area of land which is the
subject of the application, and is marked in red on the site
plan submitted with the application;
“special building” means a building providing an
institution, club, society or other organisation of a religious,
cultural, philanthropic, sporting or social nature not including
Government departments or parastatal bodies with the
facilities necessary for the pursuit of its objects, including
schools, hospices, homes for the elderly, hospitals and similar
buildings or uses, where the institution, club, society or other
organisation is declared as being tax exempt by the Minister
responsible for finance by regulations made for that purpose;
“temporary structure / use of land” means the use of land
for one use or purpose, which may include the setting up of a
structure which is demountable and does not require the laying
of foundations and is placed on the ground and constructed
from impermanent materials, including canvas, other fabric,
PVC and similar materials, and includes a tent, marquee,
canopy or other structure of a similar nature. (“impermanent
material” means material which does not consist of stone,
bricks or concrete or, any other similar material). Provided
that where such use of land is not specified in an approved
development plan, such use shall be carried out for four
months or less in any one calendar year;
“terraced house” means a single dwelling unit on a
site consisting of one or more storeys in a row of three or
more dwellings and includes the dwellings at the ends of the
terrace;
“validation” means the acknowledgment by the Malta
Environment and Planning Authority of the receipt of a valid
application for development permission, that is an application
in respect of which all the requirements for the submission of
an application have been fulfilled;
“vicinity” means a distance within 500 metres of the
original site;
“villa” means a detached or semi detached single
dwelling of not more than two habitable floors. This includes
flatted dwellings (regulated by Policy 3.5 of Development
Control Policy and Design Guidance, 2007, or future updates
thereto) located in an area designated for villa development.
(2) In either Schedule 1 or Schedule 2 to these
regulations, any expression defined in the Act has the same
meaning as it has in the Act.
There shall be charged by the Authority a development Payment of
permit fee (DPF) and Environment Fee as the charge to be paid in Development
respect of an application for permission to carry out development, Fee.
at the rates set out in Schedule 1 to these regulations.
There shall be charged by the Authority an infrastructure Payment of
services contribution (Sewer and Street) as the rate of contribution Infrastructure
to be paid towards the cost of infrastructure services and other
services or facilities arising from any permission to develop land,
at the rates set out in Schedule 2 to these regulations.
The Building Levy Rates Regulations, 1996 are hereby
1996. revoked.
B
Schedule 1
1. Except as otherwise provided, the relevant fees at the rates specified in this Schedule, shall
be paid in respect of applications for development permission according to the nature of the
development and calculated as herein provided:-
Development
Environment
DPF
Sewer
Street
Fee
Rate ()
Rate ()
Rate ()
Rate ()
Per
Per
Per
Per
Per
Per
Per
Per
m 2
m 2
m 2
m 2
Unit
Unit
Unit
Unit
Advertisements
104.12
-
-
-
-
-
00
-
Agriculture
0.96
-
1.98
-
0.94
-
0.05
-
Boathouse For Registered Fisherman
2.08
-
3.29
-
1.88
-
0.20
-
Bungalow
90
-
5.60
-
2.80
-
0.12
-
Change Of Use To Non Residential
9.07
-
-
-
-
-
0.80
-
Commercial Development (including
9.07
-
5.97
-
3.22
-
0.80
-
extensions)
Engineering Operations
0.57
-
-
-
-
-
0.30
-
Env. & Dev. Brief/Outline Applications
0.42
-
-
-
-
-
-
-
- Normal Buildings
Film Set
2.12
-
-
-
-
-
0.15
-
Flat / Terraced House / Maisonette
1.24
-
3.08
-
1.68
-
0.12
-
Greenhouse
0.69
-
-
-
-
-
0.05
-
Land Reclamation for Agriculture
0.71
-
-
-
-
-
0.10
-
Livestock Farm Building
0.96
-
-
-
0.94
-
0.05
-
Other Garages
5.95
-
3.29
-
1.88
-
0.10
-
Penthouse
02
-
12.69
-
5.17
-
0.12
-
Plant and Machinery
0.57
-
-
-
-
-
0.30
-
Public Car Park
6.35
-
5.97
-
3.22
-
0.80
-
Quarry (New / Horizontal Extension)
1.28
-
-
-
0.47
-
0.30
-
Temporary Structure / Use Of Land
2.12
-
-
-
-
-
0.15
-
Villa (Semi / Fully Detached - 2
7.29
-
5.60
-
2.80
-
0.12
-
dwelling units) / Farmhouse
Waste Disposal
1.42
-
-
-
-
-
0.30
-
As Per
As Per Residence
- 594.97
-
50.00
Change Of Use To Residential
Residence in m in m
Satellite dishes above 2m diameter or
- 150.00
-
-
-
-
-
5.00
telecommunication antennae
Other development not otherwise
- 150.00
-
-
-
-
-
5.00
specified
Vending Machine
- 150.00
-
-
-
-
-
10.00
B
Development
Environment
DPF
Sewer
Street
Fee
Rate ()
Rate ()
Rate ()
Rate ()
Per
Per
Per m 2
Per m 2
Application
Application
Correction Of Site, CPPS Revision
150.00
-
-
-
Request
Demolition of Building or Structures
1,985.72
-
-
140.00
(Floor Area > 30m)
Env. & Dev. Brief/Outline Applications
212.49
-
-
-
- Special Buildings / Uses
Extensions to dwellings, Alterations,
150.00
-
-
00
Renewal,Amended Application &
Minor Amendments
1,487.43
-
-
120.00
Quarry - Vertical Extension
148.74
3.29
1.88
15.00
Special Buildings or Uses
Fee
Rate
Compliance Certificates
60.00
Development Notification Orders –
60.00
Alterations
Development Notification Orders –
120.00
Extensions/New Development
Planning Control Applications per
235.00
150m of site or part thereof
B
Provided that
1. Where a request for screening is submitted to the Malta Environment and
Planning Authority, it shall be accompanied by the Screening Fee of €50. This fee
is in no case refundable;
2. The rate regulating temporary structure / use of land shall only be applied
once, on any given site, in any one calendar year;
3. Where an application for a boathouse is not accompanied by proof of
registration of the applicant as a fisherman, the Development Permit Fee shall be
calculated at the rate of commercial development;
4. For the purposes of the calculation of floor area in relation to bungalow
development, only the build-up area, which includes the amount of floor area within
a building determined by the external measurements of the building, which includes
the thickness of the external walls and half the thickness of dividing or party walls,
and the internal shafts, internal yards and open terraces, shall be considered;
5. Where garages do not share a common access with a residential/
commercial development, and parking spaces (excluding lock-up garages),
forming part of a mixed development, have a direct access to both residential and
commercial development, the rate of “other garages” shall be applied;
6. For purely commercial development, the floor area shall be charged at
the rate per square meter as listed in Schedule 1 and the site area shall be charged
separately at the same rate per meter square;
7. The area used for the placing of tables and chairs in conjunction with
commercial development shall also be considered at the same rate of the commercial
development to which the tables and chairs are ancillary to;
8. When calculating the fees required in relation to advertisements, the
area to be considered is the surface area covered by the advertisement and does
not include the footprint of any hoarding/structure used to support any such
advertisement;
9. When a reservoir is not located within an agricultural holding owned and
operated by a registered farmer, it shall attract the rate of “Engineering Operations”.
This rate, however, will not be charged separately when it is already being charged
as part of site area for commercial development within the same application;
10. The rate regulating the Change of Use to Residential will only be applied
if a new residential unit is being created;
B
11. The development permit fee paid in relation to an application submitted
for the amendment of a condition in a permit issued by the Authority in relation to
the payment due by the applicant in the Commuted Parking Payment Scheme shall
be refunded to the applicant if it is established that the amendment requested in the
application was actually justified;
12. For Planning Control applications relating to local plan amendments, in
cases where the applicant does not pay the standard fee over the whole site area, the
fee payable at the submission of the said local plan amendment application shall be
of €235.00. So however that applications for development permission submitted
following a Planning Control application relating to amendments to local plan
aforementioned, or a Planning Control application relating to amendments to local
plan submitted by the Authority in accordance with the provisions of regulation 6
of Development Planning (Procedure for Minor Modifications to Subsidiary Plans)
Regulations, 2007 after the requirements of sub-regulation (3) of regulation 4 of the
said regulations, for which the provisions of this clause have been applied, a fee of
€3.00 per meter squared, or part thereof, over and above any other rate established
by these regulations shall be paid in relation to such application for development
permission;
13. Where an application involves more than one use or type of development,
the development permit fee to be paid shall be calculated by adding together the
amounts applicable to each type of development. When the application includes
commercial development, the fee for the commercial development shall be
calculated by reference to the rate for the commercial floor area only and shall not
include the site area
14. (a) All fees shall be paid at rates calculated by reference to the
development proposed in the application, and no fees properly paid shall be
refundable as specified in subparagraphs (b) and (c) except in the following cases
(i) the application has been invalidly made;
(ii) the application has been withdrawn by the applicant prior to
determination.
(b) When an application is withdrawn by the applicant, the percentage
of the development permit fee which shall be refunded shall be as follows
(i) when the application is withdrawn prior to its validation, 100% of
the development permit fee shall be refunded;
(ii) when the application is withdrawn after its validation but prior
to the endorsement by the designated delegated officer of the Development
Permit Application Report on the application, 50% of the development permit
fee shall be refunded;
(iii) when the application is withdrawn after the Development Permit
Application Report has been endorsed as set out in item (ii) above but prior to
the determination of the application, 25% of the development permit fee shall
be refunded;
except that the development permit fee shall not be refunded where a
notice in terms of articles 50, 51, 52, 53 or 58 of the Act has been served on
the applicant or on the site to which the application relates;
15. (i) Where an application is submitted for new development on a site
(described as the new application for the purpose of this subparagraph) and the
applicant states in writing that –
(a) an application for development of the same type had previously
been submitted by the applicant on another site (described as the original site
for the purpose of this paragraph) in the vicinity of the new site and had been
approved, and
(b) the applicant has no interest in the development of the original site
and has not and will not exercise the permission, the permit on the original site
shall be cancelled by the Authority.
(ii) Unless the development permit fee paid on the original application
has been previously refunded, in part or in full to the applicant or to any third
party, such a fee shall be retained by the Authority in addition to any such other fee
payable by the applicant together with the submission of the new application.
(iii) The provisions of this paragraph shall apply only if
(a) there is no difference whatsoever in the designation of the original
site and the new application;
(b) the permit on the original site has not been utilized in any manner
whatsoever; and
(c) this application is limited to the change of the site of the previously
approved development permit.
(iv) Any variations from the previously approved permit (except for the
wrong indication of the site) shall not prejudice the new application.
(v) Where the new application is withdrawn by the applicant prior to its
determination, the development permit fee shall not be refunded.
16. Where an application is for new development on a site in respect of
which there is or has been a development permission, whether or not still in force,
B
the infrastructure services contribution paid in relation to the previous development
permission shall be taken into consideration as follows
a)
For pre-1993 applications
i) If the applicant or architect submits a receipt of the infrastructure
services contribution originally paid with evidence that this is related to a
previous development permission on the same site, the amount shown
on the receipt shall be deducted from the new infrastructure services
contribution required.
ii) If the applicant or architect does not submit a receipt of the
infrastructure services contribution originally paid with evidence that
this is related to a previous development permission on the same site, the
amount to be deducted from the new infrastructure services contribution
required shall be calculated as per Schedule 2.
b) For post-1992 applications the Infrastructure Services Contribution
recorded, on the Authority’s records, to have been originally paid on a previous
development permission on the same site, shall be deducted from the the new
infrastructure services contribution required;
17. No infrastructure services contribution shall be paid when the application
relates solely to an application by a Government Department or a body corporate
established by law, including Malta Enterprise, where the applicant gives an
undertaking, in a form specified by the Malta Environment and Planning Authority,
to the same Authority that the necessary infrastructure services will be provided
by, or in conjunction with, and with the approval of, the relevant department and
at the expense of the applicant or the relevant department, and that the necessary
maintenance of those services will also be so carried out;
18. No main sewer contribution shall be payable in respect of applications
for sewage treatment works, pumping stations and similar structures or works
provided by the Drainage Section of the Water Services Corporation or any other
body which subsequently assumes the responsibilities of that Department;
19. The infrastructure services contribution shall be reduced by 75%, where
(a) the applicant gives to the Authority an undertaking, in a form
specified by the Malta Environment and Planning Authority, that the necessary
infrastructure services will be provided by the applicant, or by, and with the
approval of, the relevant department and at the applicant’s expense, and that
the necessary maintenance of these services will also be carried out; or
(b) the application relates to a site where the necessary infrastructure
services have been provided at the expense of a private individual and an
undertaking, in a form specified by the Malta Environment and Planning
Authority, to maintain these services has been given;
20. All Infrastructure Services Contributions shall be levied at rates
calculated with reference to the development proposed in the application and no
contribution shall be refundable except in the following cases
(i) the permission applied for has been refused, unless it is a dismissal
in terms of section 52(5) of the Act;
(ii) the application has been invalidly made;
(iii) the application is withdrawn before it is determined by the
Authority
Provided that in the cases mentioned in sub-paragraphs (i), (ii) and
(iii) abovementioned, 10% of the infrastructure services contributions will
always be retained to cover administrative charges and are consequently not
refundable;
(iv) if it is made in respect of an application for a class of development
for which such permission is not required by or under any provision of the Act
or any regulations or orders made thereunder, and the application is returned
by the Authority to the applicant;
(v) if the application is one to which paragraph 19 (a) relates, and the
applicant subsequently provides the appropriate services at his own expense
and the relevant Department has certified that the works have been carried
out to its satisfaction, a refund equal to 15% of the infrastructure services
contribution shall be paid;
(vi) if the application is one to which paragraph 19 (b) relates, and the
relevant Department has certified that the works have been carried out to its
satisfaction, a refund equal to 15% of the infrastructure services contribution
shall be paid;
21. Where the Authority considers that in order to meet the extraordinary
or exceptional demands which, in the opinion of the Authority, the nature, location
or scale of the proposed development is likely to place on the infrastructure services
and other services or facilities, as well as to secure the proper planning of the area
and regulate the use of land in accordance with the policies and proposals in the
Structure Plan and any subsidiary plan, the contribution earlier specified in this
Schedule is insufficient, the Authority shall determine the contribution to be levied
B
to meet the cost of the services and facilities arising from the permission applied
for, and may also enter into agreement with the applicant to ensure the payment
of the contribution so determined and the proper carrying out of the development
according to the permission of the Authority;
23. Where an application is submitted for new development on a site
(described as the new application for the purpose of this paragraph) and the
applicant states in writing that -
(i) an application for development of the same type had previously
been submitted by the applicant on another site (described as the original site
for the purpose of this paragraph) in the vicinity of the new site and had been
approved; and
(ii) the infrastructure services contribution paid in relation to the
application on the original site should be taken into account in the calculation
of the Infrastructure Services Contribution due on the application for the new
site;
the permit on the original site shall be cancelled by the Authority and the
infrastructure services contribution shall be deemed not to have been paid on
the original site. The infrastructure services contribution paid on the original
site shall be taken into account in the calculation of the infrastructure services
contribution to be paid in relation to the new application.
B
Schedule 2
Method of calculation of the infrastructure services contribution for pre-1993
applications
The calculation of the Infrastructure Services Contribution paid on pre-1993
applications that fall under the provisions of clause 16(a)(ii) of Schedule 1 shall be
made as follows
1. When the site fronts on a street which is built-up on both sides, the Sewer
Contribution paid shall be calculated at the rate of €18.63 per meter of frontage of
the site. The Street Contribution shall be calculated by multiplying the frontage of
the site in meters by half the width of the street in metres by €5.24.
2. When the site fronts on a service road, the Sewer Contribution paid shall
be calculated at the rate of €27.95 per meter of frontage of the site. The Street
Contribution shall be calculated by multiplying the frontage of the site in meters by
the whole width of the service road in metres by €5.24.
3. When the site fronts on a street having a green area, a public square, or the
coast, opposite the site, the Sewer Contribution paid shall be calculated at the rate of
€27.95 per meter of frontage of the site. The Street Contribution shall be calculated
by multiplying the frontage of the site in meters by half the width of the street in
metres by €5.24.
€1.49