Assessment and Management of Flood Risks Regulations, 2010
Table of Provisions (12)
Statutory Text (12 Articles)
L.N. 264 of 2010
MALTA RESOURCES AUTHORITY ACT
(CAP. 423)
Assessment and Management of Flood Risks Regulations, 2010
IN exercise of the powers conferred by article 28 of
the Malta Resources Authority Act, the Minister for Resources
and Rural Affairs, after consultation with the Malta Resources
Authority, has made the following regulations
(1) The title of these regulations is the Assessment and
Management of Flood Risks Regulations, 2010.
(2) The scope of these regulations is to tranpose Directive
2007/60/EC of the European Parliament and of the Council of 23
October 2007 on the assessment and management of flood risks
(Text with EEA relevance) which establishes a framework for the
assessment and management of flood risks, aiming at the reduction
of the adverse consequences for human health, the environment,
cultural heritage and economic activity associated with floods.
Regulation 6 (3) - Flood Risk Management Plans
I. Components of the first Flood Risk Management Plan
1. the conclusions of the preliminary flood risk assessment as required in terms
of these regulations in the form of a summary map of the water catchment district,
or the unit of management delineating the areas identified under regulation 4 which
are the subject of this Flood Risk Management Plan;
2. flood hazard maps and flood risk maps and the conclusions that can be
drawn from those maps;
3. a description of the appropriate objectives of flood risk management;
4. a summary of the measures and their prioritisation aiming to achieve the
appropriate objectives of flood risk management, including the measures taken
in accordance with regulation 6, and flood related measures taken under other
Community acts, including Council Directives 85/337/EEC of 27 June 1985 on the
assessment of the effects of certain public and private projects on the environment
and Directive 96/82/EC of 9 December 1996 on the control of major accident
hazards involving dangerous substances, Directive 2001/42/EC of the European
Parliament and of the Council of 27 June 2001 on the assessment of the effects of
certain plans and programmes on the environment and Directive 2000/60/EC;
5. when available, for shared water catchments or sub-catchments, a
description of the methodology, of cost-benefit analysis used to assess measures
with transnational effects.
II. Description of the implementation of the plan
1. a description of the prioritisation and the way in which progress in
implementing the plan will be monitored;
2. a summary of the public information and consultation measures taken;
3. a list of competent authorities and, as appropriate, a description of the
coordination process with Directive 2000/60/EC.
(1) Unless otherwise stated in these regulations, the
definitions in the Act shall apply.
Interpretation.
(2) In these regulations unless the context otherwise
requires
“the Act” means the Malta Resources Authority Act;
“the competent authority” means the Malta Resources
Authority;
“flood” means the temporary covering by water of land
not normally covered by water. This includes floods from
rivers, mountain torrents, Mediterranean ephemeral water
courses, and floods from the sea in coastal areas, and excludes
floods from sewerage systems;
“flood risk” means the combination of the probability
of a flood event and of the potential adverse consequences
for human health, the environment, cultural heritage and
economic activity associated with a flood event;
“river” means a body of inland water flowing for the most
part on the surface of the land but which may flow underground for
part of its course;
“sub-catchment” means the area of land from which
all surface run-off flows through a series of streams, rivers
and, possibly, lakes to a particular point in a water course
(normally a lake or a river confluence);
“water catchment” means the area of land from which
all surface run-off flows through a sequence of streams,
rivers and, possibly, lakes into the sea at a single river mouth,
estuary or delta;
“water catchment district” means the area of land and
sea, made up of one or more neighbouring water catchments
together with their associated groundwaters and coastal
waters.
(3) For the purposes of these regulations, any reference
to Directives of the European Parliament and of the Council, shall
be read and construed as if reference is made to the provisions of
the regulations transposing the provisions of such directive into
Maltese law.
Regulation 9 (3) - Components of the subsequent update of Flood Risk
Management Plans
1. any changes or updates since the publication of the previous version of the
Flood Risk Management Plan, including a summary of the reviews carried out in
compliance with regulation 9;
2. an assessment of the progress made towards the achievement of the
objectives referred to in regulation 6 (2);
3. a description of, and an explanation for, any measures foreseen in the earlier
version of the flood risk management plan which were planned to be undertaken and
have not been taken forward;
4. a description of any additional measures since the publication of the
previous version of the Flood Risk Management Plan.
€0.75
(1) The competent authority shall undertake a
preliminary flood risk assessment for each water catchment district
and unit of management by 22 December 2011. This preliminary
flood risk assessment shall provide an assessment of potential risks
and shall be based on available or readily derivable information,
such as records and studies on long term developments, in
particular the impact of climate change on the occurrence of floods,
and shall include the information required in sub-regulation (2) of
this regulation.
(2) The preliminary flood risk assessment shall include
at least
(a) maps of the water catchment district at the
appropriate scale including the borders of the water
catchments, sub-catchments, and where existing, coastal
areas, showing topography and land use;
(b) a description of the floods which have occurred
in the past and which have had significant adverse impacts
on human health, the environment, cultural heritage and
economic activity and for which the likelihood of similar
future events is still relevant, including the flood extent and
conveyance routes and an assessment of the adverse impacts
they have entailed;
(c) a description of the significant floods which have
occurred in the past, where significant adverse consequences
of similar future events might be envisaged;
(3) The competent authority shall, where considered
necessary, in collaboration and with the contribution of the
relevant competent authorities undertake an assessment of the
potential adverse consequences of future floods for human health,
the environment, cultural heritage and economic activity, taking
into account as far as possible issues such as the topography, the
position of watercourses and their general hydrological and geo-
morphological characteristics, including floodplains as natural
retention areas, the effectiveness of existing manmade flood
defence infrastructures, the position of populated areas, areas of
economic activity and long-term developments including impacts
of climate change on the occurrence of floods.
On the basis of the preliminary flood risk assessment,
the competent authority shall identify those areas where a potential
significant flood risk exists or might be considered likely to occur.
Identification of areas of potential significant flood risk.
(1) The competent authority shall prepare flood hazard
maps and flood risk maps for the areas identified in terms of
regulation 4.
(2) Flood hazard maps shall cover the geographical
areas which could be flooded according to the following scenarios
(a) floods with a low probability, or extreme event
scenarios;
(b) floods with a medium probability having a likely
return period of more than one hundred years;
(c) floods with a high probability, where appropriate.
(3) For each scenario referred to in sub-regulation (2),
the following shall be shown
(a) the flood extent;
(b) water depths or water level, as appropriate;
(c) where appropriate, the flow velocity or the relevant
water flow.
(4) Flood risk maps shall show the potential
adverse consequences associated with flood scenarios referred to in
sub-regulation (2) and shall be expressed in terms of
(a) the indicative number of inhabitants potentially
affected;
(b) type of economic activity of the area potentially
affected;
(c) installations as referred to in Annex I of Council
Directive 96/61/EC of 24 September 1996 concerning
integrated pollution prevention and control which may
cause accidental pollution in case of flooding and potentially
affected protected areas identified in Annex IV (1)(i), (iii) and
(v) to Directive 200/60/EC;
(d) other information which the competent authority
considers useful, such as the indication of areas where floods
with a high content of transported sediments and debris floods
can occur and information on other significant sources of
pollution.
(5) For coastal areas and areas where flooding is from
groundwater sources the preparation of flood hazard maps shall be
limited to floods with a low probability or extreme event scenarios.
(6) The flood hazard maps and flood risk maps shall be
completed by 22 December 2013.
(1) The competent authority shall draw up Flood Risk
Management Plans on the basis of the flood risk maps for each of
the areas identified in terms of regulation 4.
(2) The Flood Risk Management Plan shall incorporate
objectives for each of those areas identified in terms of regulation
4, focusing on the reduction of potential adverse consequences
of flooding for human health, the environment, cultural heritage
and economic activity and where appropriate on non-structural
initiatives or on the reduction of the likelihood of flooding.
(3) The Flood Risk Management Plan shall include
the elements listed in the First Schedule to these regulations and
shall take into account relevant aspects such as costs and benefits,
flood extent and flood conveyance routes and areas which have
the potential to retain flood water, such as natural floodplains, the
environmental objectives of Article 4 of Directive 2000/60/EC,
soil and water management, spatial planning, land use, nature
conservation, navigation and port infrastructure.
(4) Flood risk management plans shall address
all aspects of flood risk management focusing on prevention,
protection, preparedness, including flood forecasts and early
warning systems and taking into account the characteristics of
the particular water catchment or sub-catchment as well as the
promotion of sustainable land use practices, improvement of
water retention as well as the controlled flooding of certain areas
in the case of a flood event.
(5) Flood risk management plans shall be completed
and published by 22 December 2015.
(1) The implementation of these regulations shall
be effected in consistency with the Water Framework Policy
Regulations, 2004 and shall focus on opportunities for improving
efficiency, information exchange and for achieving common
synergies and benefits having regard to the environmental
objectives laid down in such regulations, in particular
(a) the development of the first flood hazard maps
and flood risk maps and their subsequent reviews shall be
carried out in such a way that the information they contain
is consistent with relevant information pertaining to the
Water Framework Policy Regulations, 2004;
(b) the development of the first flood risk
management plans and their subsequent reviews shall be
carried out in coordination with, and may be integrated
into, the reviews of the water catchment management plans
provided for in the Water Framework Policy Regulations,
2004;
(c) the active involvement of all interested parties
as required by regulation 8 of these regulations shall be
coordinated with the active involvement of parties under the
Water Framework Regulations, 2004.
(1) The competent authority shall make available to
the public the preliminary flood risk assessment, the flood hazard
maps, the flood risk maps and the Flood risk management plans.
(2) Interested parties shall be encouraged to participate
actively in the production, review and updating of the Flood risk
management plans.
(1) The preliminary flood risk assessment shall be
reviewed and if necessary updated by 22 December 2018 and every
six years thereafter, taking into account the likely impact of climate
change on the occurrence of floods.
(2) The flood hazard maps and the flood risk maps
shall be reviewed and if necessary updated, by 22 December 2019,
and every six years thereafter.
(3) The Flood risk management plans shall be
reviewed and, if necessary, updated, including the elements set out
in the Second Schedule to these regulations by the 22nd December
2021, and every six years thereafter, taking into account the likely
impact of climate change on the occurrence of floods.
B