Energy Performance of Buildings Regulations, 2008
Table of Provisions (33)
Statutory Text (33 Articles)
L.N. 261 of 2008
MALTA RESOURCES AUTHORITY ACT
(CAP. 423)
Energy Performance of Buildings Regulations, 2008
IN exercise of the powers conferred by article 28 of the Malta
Resources Authority Act, the Minister for Resources and Rural Affairs,
after consultation with the Malta Resources Authority, has made the
following regulations>
(1) The title of these regulations is the Energy Performance Title and
commencement.
of Buildings Regulations, 2008.
(2) Save as otherwise specified in these regulations, these
regulations shall come into force on such date as the Minister responsible
for the Malta Resources Authority may by order appoint and different
dates may be so appointed in respect of different regulations.
The scope of these regulations is to give effect to the provisions Scope.
of Directive 2002#91#EC of the European Parliament and of the Council
of 16 December 2002 on the energy performance of buildings 1 .
(1) The following definitions shall, unless the context Definitions.
otherwise requires, apply.
“the Act” means the Malta Resources Authority Act<
“advisory report” means a report made by an EP assessor,
accompanying an Energy Performance Certificate (EPC), worked
on the basis of an EP assessment of a building or heating or cooling
installation, and containing recommendations on how the energy
performance of the building or heating or cooling installation may
be improved in a cost-effective manner.
“asset rating” means an energy performance rating using data
for the building as actually constructed and based on calculations
of the energy used in a building for heating, cooling, ventilation,
hot water and lighting, with standard input data related to internal
and external climates and occupancy and represents the intrinsic
energy performance potential of the building under standardised
conditions of weather and occupancy<
OJ No. L 1#65, January 2003
“authorised officer” means a person authorised by the
Authority to monitor and enforce these regulations<
“the Authority” means the Malta Resources Authority or any
other entity that is authorised to act on its behalf on matters of
these regulations<
“building” means a roofed construction having walls, for
which energy is used to condition the indoor climate< a “building”
may refer to the building as a whole or parts thereof that have been
designed or altered to be used separately<
“design rating” is an energy performance rating based on
calculations done at the design stage, of the energy used in a
building for heating, cooling, ventilation, hot water and lighting,
with standard input data related to internal and external climates
and occupancy and based on the design characteristics of the
building complete with permanently installed finishes, fixtures,
fittings and mechanical and electrical installations to render that
building habitable and good for its intended use under standardised
conditions of weather and occupancy according to acceptable
comfort norms and other regulations in force at the time of its
design<
“development permission application” means an application
for development permission or approval in terms of regulation 3(1)
of the Development Permission (Method of Application)
Regulations, 1992<
“dwelling” or “dwelling unit” means a suite operated as a
house-keeping unit, used or intended to be used as a domicile and
usually containing cooking, eating, living, sleeping and sanitary
facilities<
“effective rated output”, expressed in kW, means the
maximum calorific output laid down and guaranteed by the
manufacturer as being deliverable during continuous operation
while complying with the useful efficiency indicated by the
manufacturer<
“EP” means energy performance<
“EP assessment” means an assessment of the energy
performance of a building or a mechanical or electrical system
carried out by an EP assessor for the purpose of assigning an EPC<
“EPACI assessor” means a person who is duly registered with
the Authority after the Authority has taken into consideration that
such person is in possession of a degree in building services or
mechanical or electrical engineering conferred by the University
of Malta or an equivalent degree and who has successfully
undergone a period of training on the inspection and assessment
of the efficiency of air-conditioning, space cooling and ventilation
systems, and such training is approved by the Authority<
“EPB assessor” means a person who is duly registered with
the Authority after the Authority has taken into consideration that
such person is in possession of>
(a) a degree in architecture and civil engineering, or
civil engineering, or building services, or mechanical, or
electrical engineering conferred by the University of Malta,
or an equivalent degree, and has also successfully undertaken
a period of training on the assessment of the energy
performance of buildings built in Malta, and such training is
approved by the Authority, or
(b) a registration certificate as an energy performance
of buildings assessor in any EU member state and who has
successfully undergone a period of training on the assessment
of the energy performance of buildings built in Malta, and
such training is approved by the Authority<
“EPBI assessor” means a person who is duly registered with
the Authority after the Authority has taken into consideration that
such person is in possession of a degree in building services or
mechanical or electrical engineering conferred by the University
of Malta, or an equivalent degree, and has successfully undergone
a period of training on the inspection and assessment of the
efficiency of boiler and space heating systems, such training is
approved by the Authority<
“EPC” means an energy performance certificate in a
prescribed form on the basis of an EP assessment, which is held
and may be viewed in electronic form on the EPC register, and
may be reproduced and issued in printed form by or on behalf of
the Authority<
“EPC data file” means an electronic file which contains a
report on the outcome of an EP assessment in a form approved by
the Authority, which is completed by an EP assessor and provided
to the Authority for the purpose of notifying it of the record to be
made or updated on the EPC register in respect of a particular
building, and it shall be deemed to include any calculations and
related data or documents accompanying such report<
“EPC record” means, as the case may be, the current and any
earlier EPC, any advisory report, any EPC data file and any related
data or documents, pertaining to a building or boiler or air-
conditioning installation, as the case may be<
“EPC register” means a database of EPC records and related
data or documents established, operated, maintained and owned
by the Authority for the purpose of these regulations<
“EPC system” means the registers, procedures and rules
established, operated, maintained and owned by the Authority for
the purpose of administering EPCs and related activities in
accordance with these regulations<
“independent EP assessor” means an EP assessor who is not
the owner or tenant of the building being assessed or an employee
of the owner or of any contractor responsible for the construction,
finishing and, or installation of mechanical or electrical services
of a building for which an EPC is being requested or inspection of
boilers, lighting, space heating or space cooling systems is made<
“installation” consists of systems providing artificial lighting,
water heating, space heating or space cooling or space ventilation
in any combination<
“large building” means a building with a total useful floor
area in excess of 1000 square metres<
“major renovation or alteration” means a renovation or
alteration>
(a) which affects a building by 25% or more of its
volume before such an intervention, or
(b) where renovation of 25% or more of windows or
roofs or external walls is made, or
(c) where renovation of 25% or more of any energy
consuming installations for artificial lighting, or heating or
cooling of air or water or space ventilation is made, or
(d) where a change-of-use development permission
application concerning buildings, is being submitted to the
Malta Environment and Planning Authority, save all
exclusions in regulation 6<
“the Minister” means the Minister responsible for the Malta
Resources Authority<
“new building” or “new public building” means a building
for which a development permission application is submitted to
the Malta Environment and Planning Authority on or after the 2nd
January, 2009<
“non residential building” means any building or any part of
a building which is not used, or is unsuitable for use as a residential
building or dwelling and includes industrial buildings, places of
assembly, offices, schools and shops<
“operational rating“ means an energy performance rating
based on the measured consumption of energy used for lighting,
heating and cooling of water and the internal spaces, and space
ventilation in the building throughout a defined period of time<
“owner” means>
(a) a person who in his own right, or as an agent for
another person, is entitled to receive the rent of the building
or, where the building is not let, would be so entitled if it
were let<
(b) where the building is subject to usufruct, the bare
owner or the usufructuary<
(c)
an emphyteuta<
(d) any one of the spouses, where the building to which
the EPC relates forms part of the community of acquests<
“prescribed” means anything as prescribed by the Minister<
“prospective buyer or tenant” means a person who>
(a) is in the process of entering into a sale agreement
with another person or with the agent of such other person
for the purpose of purchasing a building or
(b) enters into a promise of sale agreement with another
person or the agent of such other person for the purpose of
purchasing a building or
(c) enters into an agreement of rent, whether oral or
written, to rent a building<
“public buildings” means a building or part of a building that
is used by an entity or by persons to provide any service to the
public<
“recognised EP training provider” means>
(a)
the Authority< or
(b) a training provider, who is registered with the
Authority and providing an EP training course that is validated
by the Authority<
“register of EP assessors” means a database of EP assessors
registered with the Authority and related data established, operated,
maintained and owned by the Authority<
“residential building” means a building or any part of a
building which is used, or is suitable, for residential purposes that
has sleeping accommodation and includes a hotel or an institutional
building<
“useful floor area” means the area that is needed to carry out
the activities of the building in question including waiting and
circulation spaces and excluding garages, storage spaces, plant
rooms and yards.
(2) The definitions contained in the Technical Guidance
Document F referred to in regulation 4 hereof, shall also apply in respect
of these regulations.
(3) In these regulations any expression which is not defined
shall have the same meaning as it has in the Act.
These regulations aim to improve the energy performance of
buildings and may set out requirements, by means of any technical
guidance document or otherwise, with regard to the following>
(a) the application of minimum energy performance
requirements for newly constructed buildings<
(b) the application of minimum energy performance
requirements for large existing buildings that are subject to major
renovation<
(c) the general framework for a national methodology for
the calculation of the integrated energy performance of buildings<
(d) the energy performance certification of buildings
referred to in paragraphs (a) and (b) hereof or buildings that change
ownership or are rented out< and
(e) the regular inspection of boilers and of air-conditioning
systems in buildings with regard to reducing energy consumption
and limiting carbon dioxide emissions.
Part 1
Minimum Requirements on the Energy Performance of Buildings
(1) The minimum requirements on the energy performance Minimum energy
of Buildings as hereinafter referred to as Technical Guidance Document performance
requirements.
F notified in the Gazette by Government Notice No. 1002 of 2006,
shall apply to the following buildings>
(a) buildings whose development permission applications
in terms of regulation 3(1) of the Development Permission (Method
of Application) Regulations, 1992, was received by the Malta
Environment and Planning Authority on or after the 2nd January,
2007<
(b) existing large buildings that undergo major renovation
or alteration, whose development permission applications in terms
of regulation 3(1) of the Development Permission (Method of
Application) Regulations, 1992, was received by the Malta
Environment and Planning Authority on or after the 2nd January,
2007. In such situations, the minimum requirements are to be
limited solely to the areas of the building, the elements or the
installations that are being altered or renovated as the case may
be<
(c) in situations of a change of use in buildings, and whose
development permission application in terms of regulation 3(1) of
the Development Permission (Method of Application) Regulations,
1992, is received by the Malta Environment and Planning Authority
on or after the 2nd January, 2009.
(2) Large buildings for which an outline or full development
permission applications in terms of regulation 3(1) of the Development
Permission (Method of Application) Regulations, 1992, is received by
the Malta Environment and Planning Authority on or after the 2nd
January, 2009, a study that takes into consideration the technical,
environmental and economic feasibility of alternative energy systems
such as,
(a) decentralised energy supply systems based on renewable
energy,
(b) combined heat and power,
(c)
district or block heating or cooling, if available,
(d) heat pumps under certain conditions<
has to be carried out and made available on request to the Authority or
to the Malta Environment and Planning Authority.
(3) The study referred to under regulation 5 shall be carried
out by persons who are suitably qualified by means of their education,
training and experience, and it shall include specific recommendations
in relation to the utilization of alternative energy systems, including
those specified in this regulation, to serve the building under review.
Notwithstanding the provisions of regulation 5 hereof, the
Non applicability of
minimum requirements on the Energy Performance of Buildings
established in these regulations shall not apply to the following categories
of buildings>
(a) a building classified as scheduled property (Grade One)
by the Malta Environment and Planning Authority under article
46 of the Development Planning Act<
(b) a building the construction of which is subject to the
Control of Fireworks and other Explosives Regulations, 1998<
(c) a building constructed for the Enemalta Corporation, the
Water Services Corporation or any other similar entity, and used
as a generation, transmission or distribution station<
(d) a building, or parts of a building, housing solely
industrial or agricultural processes or livestock husbandry which
require adherence to specific sectoral regulations<
(e) temporary buildings with a planned time of use of two
years or less<
(f)
glasshouses used solely for agricultural purposes<
(g) stand-alone buildings with a total useful floor area of
less than 40 square metres<
(h) a building constructed for use by the Armed Forces of
Malta in connection with their military requirements’
There is no obligation to adopt any solution contained in any Adoption of
technical guidance document issued in connection with these regulations minimum
requirements.
if the relevant requirements of these regulations are complied with in
any other manner. If, however, a case of an alleged breach of these
regulations occurs, it will then be the responsibility of the individual to
demonstrate by which other means the requirements have been satisfied.
The guidance contained in any technical guidance document Application of other
laws and
issued in connection with these regulation relates only to the particular regulations.
requirements of these regulations, and any construction works and the
installation of any permanent mechanical or electrical services shall
also have to comply with the requirements of any other laws and
regulations that are operative for the control of construction works and
installations.
Part 2
Energy Performance Certificate
(1) An Owner or his agent has to obtain an Energy Energy Performance
Certificate and
Performance Certificate (EPC) in the form prescribed by these Energy Performance
regulations when a building is constructed, sold or rented.
Assessment.
(2) To be valid, the EPC has to be obtained from an
independent EPB assessor after it is registered with the Authority.
(3) As from the date indicated hereunder, a person or agent
acting on behalf of such person who commissions the design of a new
building shall have in his possession an EPC based on the design rating
of the building and in the form prescribed by these regulations by the
date such person or agent submits a full development permission
application to the Malta Environment and Planning Authority>
Dwellings as from 2 nd January, 2009< and
(a)
(b) All other buildings as from 1 st June, 2009<
(4) As from the date indicated hereunder, a person or agent
acting on behalf of such person who offers for sale or letting a building,
shall provide an EPC to the prospective buyer or tenant within the period
of the promise of sale or at the time of signing of the sale agreement, or
rent agreement. The EPC shall be in the Form prescribed in these
regulations and shall be based on the design rating of the building if the
building is not yet constructed and, or finished or the asset rating, if the
building is already constructed and finished>
Dwellings as from 2 nd January, 2009< and
(a)
(b) All other buildings as from 1 st June, 2009.
(5) In the event that the person or agent indicated in sub-
regulation (4) does not provide the prospective buyer or the tenant with
an EPC within the period indicated in sub-regulation (4) of regulation
9, the buyer or the tenant will have the right to engage an assessor to
issue the necessary certificate and, in all cases, the prospective buyer or
tenant shall have the right to deduct the expenses incurred for the issue
of the EPC from the amount of the sum agreed for the sale or the
payments of the rent due.
(6) Notwithstanding the provisions of sub-regulations 9(1),
9(2), 9(3), and 9(4), the procurement of an EPC shall not apply to the
following categories of buildings>
(a) a building classified as Grade One or Grade Two
scheduled property by the Malta Environment and Planning
Authority under article 46 of the Development Planning Act and
which has a total useful floor area of less than 1,000 square metres
and is occupied by, and is providing services to not more than 500
persons daily<
(b) a building the construction of which is subject to the
Control of Fireworks and other Explosives Regulations, 1998<
(c) a building constructed for the Enemalta Corporation, the
Water Services Corporation or any other similar entity, and used
as a generation, transmission or distribution station<
(d) a building, or parts of a building, housing solely
industrial or agricultural processes or livestock husbandry which
require adherence to specific sectoral regulations<
(e) temporary buildings with a planned time of use of two
years or less<
(f)
glasshouses used solely for agricultural purposes<
(g) stand-alone buildings with a total useful floor area of
less than 40 square metres<
(h) a building constructed for use by the Armed Forces of
Malta in connection with their military requirements< and
(i) a building used as a place of worship.
(1) An EPC issued in connection with this part of the Provisions relating
to an EPC.
regulations shall be valid for a period not exceeding ten years from the
date of its first issue, provided that no major renovation or alteration
occur in the building.
(2) (a) The EPC shall include reference values and shall
be accompanied by a recommendation report.
(b) The recommendation report shall indicate cost-
effective measures for improving the energy performance of the building.
(3) Any report or data file in connection with the production
of an EPC must conform to data protection laws currently in force in
Malta.
(4) If after the construction of the building or the installation
of mechanical and electrical services in new buildings it results that
such construction or installation of services is different from the design
on which a design rating EPC has been obtained, a new EPC based on
the asset rating of the building shall have to be secured by the owner
before the expiry of the periods indicated in sub-regulation 9(4). The
provisions of sub-regulation 9(5) shall also apply.
(1) For apartments or dwelling units designed or altered Apartments or
dwelling units
for separate use in blocks having common or identical water heating, designed for
space heating or space cooling systems, the EPC may be issued either separate use.
for the building as a whole or on the assessment of a representative
apartment or dwelling unit in the same block.
(2) For apartments or dwelling units designed or altered for
separate use in blocks that do not have a common water heating, space
heating or space cooling system, the EPC shall be issued for each
individual apartment or dwelling unit.
(1) As from the 2 nd January, 2009, all persons or entities
that are in charge of existing public buildings listed hereunder are to
ensure that an EPC based on the asset rating of the building is
commissioned and displayed at all times in a prominent place which is
clearly visible to the public by not later than the 2 nd January, 2010>
(a) Large buildings (including buildings scheduled as Grade
1 or Grade 2 Buildings) that are used by or are providing services
to more than 500 persons daily<
(b) Commercial banks and post office buildings having a
useful floor area of over 100 square metres irrespective of the
number of persons using or visiting such building<
(c) Showrooms, shops and shopping complexes having a
useful floor area of over 1000 square metres irrespective of the
number of persons using or visiting the building<
(d) Cinemas, dance halls, discotheques, gambling halls and
wedding halls having a total useful floor area of over 500 square
metres irrespective of the number of persons using or visiting the
building.
(2) Persons or entities in charge of new public buildings
shall ensure that an EPC based on the asset rating of the building is
commissioned and displayed at all times in a prominent place clearly
visible to the public no later than 12 months from the date of connection
of the building to the electric power grid.
(3) Within a period not exceeding five years of the first
display of the EPC, and every successive three years, an EPC based on
the operational rating of the building is to be commissioned and
displayed alongside the original EPC to enable users and visitors of
that building to compare the building’s performance.
Part 3
Inspection and Energy Performance Certification of lighting,
water heating, space heating and space cooling installations
in Buildings
(1) (a) As from the 2 nd January, 2009, owners of water
heating and space heating installations in buildings having boilers fired
by non-renewable liquid or solid fuel of an effective rated output of
20kW or more shall ensure that such boilers are inspected and that a
certificate on their energy performance is issued by an independent EPBI
assessor.
(b) In the case of existing boiler installations, the
certificate mentioned in paragraph (a) thereof shall be in the owner’s
possession not any later than 12 months from the date indicated in the
said paragraph (a).
(2) In the case of installations with an effective rated output
of more than 20 kW having a boiler or boilers that are older than 15
years from the date of coming into force of these regulations, a one-off
inspection and certification of the whole heating installation shall be
made within 12 months of the date indicated in paragraph (a) of sub-
regulation (1) hereof.
(3) In the case of new heating installations having boilers
fired by non-renewable liquid or solid fuel of an effective rated output
of 20kW or more and gas fired boilers, inspection reports and
certifications on their energy performance shall be in the possession of
the owner within 28 days from the date of commissioning, and such
inspection and certification shall be repeated every four years thereafter.
(4) Certifications and reports on the energy performance of
boilers in installations with an effective rated output of more than 100kW
shall be in the possession of the owner within 28 days from the date of
commissioning, and such inspection and report shall be repeated at least
every two years thereafter.
(5) Inspections and certifications shall include an assessment
of the boiler efficiency and sizing in the context of the heating
requirements of the building.
(6) The inspection report shall contain appropriate advice
on possible improvements or modifications to the system, replacement
of the system and alternative solutions.
(7) The EPC and report are to be deposited and registered
with the Authority by the assessor before they are issued to the owner.
(1) As from the 2 nd January, 2009, owners of air- Inspection and
conditioning units, or interlinked systems, or a centralised system, as Energy
Certification of
the case may be, with an effective rated output of more than 12kW space heating and
cooling systems
whether in dwellings, residential buildings, or other non residential
buildings are to ensure that such units or systems are inspected by an
independent EPACI assessor at regular intervals as specified by these
regulations.
(2) In the case of existing buildings having existing units
or interlinked systems or centralised installations with an effective rated
output of 250kW or more, a one-off inspection and certification of the
whole system shall be made and a certificate including an advisory
report shall be in the possession of the owner or tenant of the building,
as the case may be, within 12 months from the date indicated in
regulation 14(1), to be followed by inspections and certifications at
regular intervals not exceeding five years.
(3) In the case of existing buildings having existing units,
or interlinked systems or centralised installations with an effective rated
output of between 12kW and 249kW, an inspection and certification
have to be made and a certificate including an advisory report is to be in
the possession of the owner or tenant of the building, as the case may
be, within 24 months from the date indicated in regulation 14(1) and
have to be followed by an inspection and certification at regular intervals
not exceeding five years.
(4) In the case of all new or existing buildings having new
units or interlinked systems or centralised installations with an effective
rated output of more than 12kW, the inspection and certification
including an advisory report is to be in the possession of the owner or
tenant of the building, as the case may be, within 28 days from the date
of commissioning and has to be followed by an inspection and
certification at regular intervals not exceeding five years.
(5) The inspection must include an assessment of the air-
conditioning units’ or system’s efficiency and the sizing of any unit or
system compared to the cooling requirements of the building, and contain
appropriate advice on possible improvements to any unit or system,
replacement of the system and alternative solutions.
(6) To be valid the EPC and report are to be deposited and
registered with the Authority by the assessor before it is issued to the
owner or the tenant.
Part 4
Administration of the EPC System for Energy Performance
Certification of buildings and, Mechanical and Electrical Services
in buildings
(1) The Authority or its authorised representative may
demand, from the owner of a building falling under these regulations,
or the agent of such owner, the production of an EPC in respect of the
building or the installations within a building as required by these
regulations, and if the building owner or the agent of such owner as the
case may be refuses or fails to produce without reasonable excuse the
EPC then and there, such person will be committing an offence, unless
such person provides the requested EPC within 60 days after the day on
which production was demanded.
(2) Where a person produces an EPC to an authorised officer
of the authority but refuses or fails to permit the said officer to read and
examine the EPC or the associated report, that person or other persons
involved in such a case, will be committing an offence, and the authorised
officer may demand of the person or persons their name and
identification card number and official address.
(1) The energy performance assessment and certification Energy performance
assessment.
shall be carried out using procedures, including calculation methods
and software, approved by the Authority.
(2) In carrying out the EP assessment of a building or
installation an assessor shall comply with any direction given by the
Authority in relation to the manner in which the assessment is to be
carried out.
(3) An assessor may refuse to carry an EP assessment of a
building or installation if in the opinion of the assessor any part of the
building or installation is in such a condition that it would not be safe or
practicable to carry out that assessment.
(4) An endorsed EPC shall not be issued by the assessor to
the building owner or his agent, as the case may be, unless and until it is
accepted in the register maintained by the Authority.
(1) The Authority may revoke an EPC and EPC data file Cancellation of an
EPC.
or report compiled by an assessor where it has reasonable grounds for
believing that the EPC or data file or report was not completed or issued
in accordance with these regulations, and shall enter such revocation in
the EPC record of that building and the Authority’s register.
(2) Where an EPC or EPC data file or report is revoked, the
Authority is to inform the assessor, giving him or her the reason for the
revocation, and shall also inform the person who commissioned the
EPC, the owner or tenant of the building, as the case may be.
(3) The Authority may demand in writing, the giving up of
an EPC that is revoked, as the case may be, within 14 days of the making
of such demand.
(4) Where an EPC or data file, or report is revoked under
this regulation>
(a) a request for the reimbursement of the fee or part thereof
may be made by the person who paid a fee or contributed in the
fee for the relevant EPC assessment to the assessor who carried
out the assessment, and
(b) the assessor shall be obliged to make the reimbursement
in whole or in part, as the case may be, referred to in paragraph (a)
hereof, within 28 days of the receipt of the request, if such assessor
is satisfied that the fee or a contribution to the fee was paid by the
person making the request.
(1) After an EPC has been registered with the Authority
and signed by the assessor, no person shall, either by writing, drawing
or in any other manner alter, deface, mutilate or add anything to the
EPC or to any related report or to a printed copy of an EPC or to any
related report or entry made therein.
(2) No person shall produce>
(a) a printed copy of any EPC or report for any building or
installation, which copy has been altered, defaced, mutilated or
added to contrary to sub-regulation (1), or upon which the figures
have become illegible or the colour has become altered by fading
or otherwise< or
(b) an EPC or report save in relation to the particular
building for which it was issued< or
(c) an EPC or report which has become void or the validity
of which has expired< or
(d) any colourable or other imitation of a registered EPC or
report.
(3) The Authority may require the owner of a building or,
as the case may be, through his or her agent, to surrender to it an EPC or
report where the Authority has reason to believe that the EPC or report
contains particulars which are not correct and, upon being so required,
the owner of the building or, as the case may be, the owner’s agent,
shall surrender the relevant documents to the Authority forthwith.
(1) All data, documentation and records issued by an
assessor and deposited with the Authority in connection with the carrying
out of an EPC under these regulations shall become the property of the
Authority which has the power to demand from the assessor any such
data, documentation or records as it considers appropriate.
(2) The lawful EPC record in relation to a building or
installation shall be that maintained on the EPC register kept by the
Authority.
(3) The most recent EPC record entered in relation to a
building or installation on the EPC register by the Authority shall be
deemed to supersede any previous EPC record for that building or
installation.
(1) Subject to sub-regulations (3) and (4) the Authority may Registration of
Energy Performance
register EP assessors to assess the energy performance of buildings, Assessors.
and provide reports in relation to hot water boilers, space heating and
space cooling systems in accordance with these regulations.
(2) In registering an assessor, the Authority shall designate
the type of EP certification and also the category of buildings in respect
of which the assessor is authorised to carry out EP assessments and
certifications.
(3) The Authority shall not consider a person for registration
as an assessor unless>
(a) the person makes an application for registration to the
Authority in the form specified by the Authority for such purpose<
(b) the application for registration is accompanied by any
fee specified by the Authority< and
(c) the person meets any other requirements specified by
the Authority
(4) In considering an application for registration as an
assessor, the Authority must be satisfied that the applicant has the
necessary qualifications and, if required, has successfully completed a
training course provided by the Authority or an Energy Performance
Certification training provider recognised by the Authority as suitable
for providing such training for buildings constructed, or installations
carried out in Malta in the relevant category of buildings and designated
type of certification.
(5) An assessor who is registered by the Authority in respect
of one type of certification or one category of building may apply to the
Authority to be registered in respect of another type or category of
buildings, and may be so registered, subject to compliance with the
provisions set out in sub-regulations (3) and (4) hereof and the payment
of any fee specified by the Authority.
(6) An assessor shall be required to renew his or her
registration at such reasonable frequency as may be determined by the
Authority, subject to the payment of any registration renewal fee
specified by the Authority.
(7) The Authority shall provide each assessor with a
certificate of registration for the designated type and category of
buildings to which his or her registration pertains and the certificate, if
requested by the owner of a building or the owner’s agent, or authorised
officer, shall be presented for inspection to the person making such
request.
(8) Where the Authority suspends or terminates the
registration of a person as an assessor, it shall note, in the register at the
entry for that person as an assessor, the suspension or termination of
the appointment and the date on which it was suspended or revoked.
(9) The Authority may, having regard to all the
circumstances of the case, suspend or terminate the registration of an
assessor following>
(a) failure by the assessor to attend a course of periodic
training if required by the Authority or to satisfactorily complete
such a training course, or
(b) failure by an assessor to comply with a direction under
these regulations, or
(c) failure by an assessor to carry out a building energy
performance assessment for EPC purposes in a fit and proper
manner, or failure to maintain or provide satisfactory data,
documentation or records of any such assessment, or
(d) the committing, or aiding or abetting the committing,
by the assessor, of an offence under these regulations, or
(e) the forming of an opinion by the Authority that the
assessor has ceased to be capable of performing his or her functions
under these regulations properly and efficiently.
(10) A suspension or termination of registration under sub-
regulation (9) shall be notified to the person concerned in writing and
shall state the reasons for the suspension or termination and inform the
person of the appeal procedure under sub-regulation (11).
(11) A person whose registration has been suspended or
terminated under sub-regulation (10) hereof may, within 14 days from
the said suspension or termination, appeal against the suspension or
termination to the Resources Appeals Board as appointed under the
Act or the Court of Appeal as the case may be.
(12) A person whose registration as an assessor has lapsed
or been suspended or terminated may be directed by the Authority to
return back to the Authority or to destroy any data or documentation
provided by building owners or their agents, and any copies thereof, in
relation to EPC assessments carried out by him or her in his or her
capacity as an assessor.
(13) A person who, not being such, purports to be an EPC
assessor for a designated category of buildings, or EPC inspections of
installations, or an authorised officer under these regulations will be
committing an offence.
(14) (a) A person who, purporting to give information to
an EPC assessor, the Authority or an authorised officer for the
performance of such person’s functions under these regulations, makes
a statement that he or she knows to be false or misleading in a material
particular or fails to disclose a material particular shall commit an
offence.
(b) An assessor who issues an EPC or makes a
statement or report that such assessor knows to be false or misleading
in a material particular, shall commit an offence.
(1) The Authority may from time to time issue directions Directions by the
Authority.
to assessors in relation to>
(a) the manner in which the EPC assessments are to be
carried out<
(b) the manner in which an EPC, and accompanying
advisory reports are to be issued<
(c) the qualifications and training requirements for EPC
assessors<
(d) the records, data bases and documentation to be
maintained by assessors<
(e)
codes of practice to be respected by assessors, and
(f) such other matters as are reasonably necessary for the
proper administration of the EPC system
(2) An assessor shall comply with any direction given under
sub-regulation (1) hereof.
(1) The registered assessor shall pay to the Authority such
fee as may be determined by the Authority in respect of each EPC
assessment carried out on a building or installation and submitted as an
EPC data file by the said assessor to the Authority for the purpose of
registering and issuing an EPC and related advisory report.
(2) The revenue from the fee specified in sub-regulation
(1) hereof shall be solely used, by the Authority, to defray costs incurred
by the Authority in establishing, operating, and maintaining the EPC
system including publicizing the said system.
(1) The Authority shall establish, operate and maintain a
register of assessors, an EPC register comprising EP Certificates,
advisory reports, inspection reports on installations, EPC data files and
related data or documents and any other register that the Authority
considers necessary for the proper administration of the EPC system.
(2) Any register established under sub-regulation (1) hereof
may be held in non legible form provided it is capable of being
reproduced in legible form
(3) Each register established under sub-regulation (1) hereof
shall be a public record and shall be kept under the management of the
Authority.
(4) In relation to the registers established under sub-
regulation (1) hereof, the following access rights shall apply>
(a) extracts from the register of the EPC assessors,
comprising the name, such assessor’s employer, if any, and place
of business, contact details, and the designated type (whether
buildings or installations) of the energy assessment certification
system to which such assessor’s EPC registration applies, shall be
open to public inspection on the internet or, during office hours, at
the offices of the Authority<
(b) subject to compliance with the provisions of the Data
Protection Act, the Authority may allow publication or access, on
a restricted or an open basis, to any extract from any register
maintained by the Authority under these regulations where the
Authority is satisfied that such publication or access is in the public
interest<
(c) other than as provided for in paragraphs (a) and (b)
hereof, a data file or other extract from a register relating to an
EPC for a particular building shall normally only be made available
to>
(i) the EPC assessor that carried out the relevant EPC
assessment, or such assessor’s formal employer< or
(ii) an EPC assessor undertaking any subsequent EPC
assessment of the relevant building, or such assessor’s
employer< or
(iii) the relevant building owner, or the agent of that
building owner, via an EPC assessor.
(1) In any proceedings a certificate signed by an authorised Evidential Value.
officer of the Authority containing only information stated in that
certificate to be taken from a register maintained by the Authority shall
be sufficient evidence of the facts stated therein unless the contrary is
shown.
(2) In any proceedings a document purporting to be a
certificate under sub-regulation (1) hereof shall be deemed to be such a
certificate and to have been signed by an authorised officer of the
Authority, unless the contrary is shown.
(3) A certificate under sub-regulations (1) and (2) hereof
that purports to bear a facsimile signature of the authorised officer of
the Authority concerned or a copy of such signature applied by means
of a stamp or produced by a computer, shall be deemed for the purpose
of this article to have been signed by an authorised officer, unless the
contrary is shown.
Part 5
A person or persons who contravene any of the requirements Enforcement.
of these regulations shall commit an offence.
(1) The Authority may appoint persons to be authorised Appointment and
powers of
officers for the purposes of enforcing these regulations.
authorised officers.
(2) An authorised officer shall be furnished with a warrant
of appointment and in the exercise of a power conferred upon such
officer under this regulation, such officer shall, if requested by any person
affected, produce the warrant of appointment.
(1) An authorised officer may enter, inspect and examine
Power of authorised
a building or any part of a building or installation for the purpose of
forming an opinion as to whether or not an EPC data file or certificate
issued for the building, or part of the building, or installation is warranted.
(2) An authorised officer may do all such things and make
all such requirements in relation to the building and installations, as are
reasonably necessary for the purpose of carrying out an inspection under
sub-regulation (1) hereof.
(3) A person who>
(a) fails to permit an inspection of a building, or installation,
under this regulation<
(b) without reasonable excuse fails or refuses to comply
with any request or requirement made by an authorised officer
under this regulation,
(c) obstructs, impedes, interferes with or assaults an
authorised officer in the exercise of a power under this regulation,
(d) gives to an authorised officer information which is false
or misleading in a material respect, or
(e) alters, suppresses, or destroys any EPC data file, related
calculation, EPC certificate, advisory report, book, document or
record, including a printed copy thereof, and including electronic
data, which the person concerned has been requested or required
to produce, or may reasonably expect to be required to produce,
commits an offence.
(1) Criminal proceedings for an offence under these
regulations shall be taken before the Court of Magistrates (Malta) or
the Court of Magistrates (Gozo), as the case may be, and shall be in
accordance with the provisions of the Criminal Code regulating the
procedure before the said courts of criminal judicature.
(2) Where an offence under these regulations is committed
by a body corporate, or by an unincorporated body of persons, or by a
person purporting to act on behalf of a body corporate or on behalf of
an unincorporated body of persons, and it is proved to have been
committed with the consent or connivance of or to be attributable to
any neglect on the part of any person who when the offence was
committed, was, or purported to act as, a director, manager, secretary
or other officer or member of such body, such other person as well as
the body, or the person purporting to act on behalf of the body, commits
an offence and is liable to be proceeded against and punished if found
guilty.
(3) Notwithstanding the provisions of the Criminal Code, Cap. 9.
the Attorney General shall always have a right of appeal to the Court of
Criminal Appeal from any judgement given by the Court of Magistrates
(Malta) or the Court of Magistrates (Gozo) in respect of proceedings
for any offence against these regulations.
Any administrative penalty or sanction imposed by the Administrative
Authority upon any person who infringes any provisions of these penalties.
regulations or who fails to comply with any directive or decision given
by the Authority in ensuring compliance with these regulations shall be
due to the Authority as a civil debt constituting an executive title for the
purposes of Title VII of Part I of Book Second of the Code of Cap. 12.
Organization and Civil Procedure as if the payment of the amount of
the fine had been ordered by a judgement of a court of civil jurisdiction.
Penalties.
A person guilty of an offence under –
(1) Regulations 9(1), (3), (4), 10(4), 12(2), 13(1), (2), (3),
(4), (7), 14(1), (2), (3), (5) is liable on summary conviction to a fine not
less than €500 and not exceeding €1,500<
(2) Regulations 15, 16(1), (2), (4), 17, 18 and 20(12), (13),
(14) is liable on summary conviction to a fine not less than €1,500 and
not exceeding €5,000<
(3) Regulation 27 (3) is liable on summary conviction to a
fine not less than €1,500 and not exceeding €5,000, or to a term of
imprisonment not exceeding three months, or to both fine and
imprisonment.
Part 6
Miscellaneous
(1) Any Technical Guidance Document issued in Language.
connection with these regulations can be issued in either the Maltese or
English language only, or both.
(2) Any EPC certificate or report issued in accordance with
these regulations may be issued in either the Maltese or English language
only, or both.
(1) The Minimum Requirements for the Energy
Repeals L.N. 238 of
2006. Performance of Buildings Regulations, 2006 are hereby repealed.
(2) Notwithstanding sub-regulation (1) hereof, the repeal
of the said regulation shall not affect the validity of Technical Guidance
Document F on the energy performance of buildings as notified by
Government Notice 1002 of 2006, published in Gazette No. 18,002.
Mitbug[ fl-Istamperija tal-Gvern — Printed at the Government Printing Press
€2.24