114 tal-2007 - Regolamenti tal-2007 dwar l-Istudju dwar l-Impatt Ambjentali Arranġament ta’ l-Artikoli
Table of Provisions (48)
Statutory Text (48 Articles)
L.N. 114 of 2007
DEVELOPMENT PLANNING ACT
(CAP. 356)
ENVIRONMENT PROTECTION ACT
(CAP. 435)
Environmental Impact Assessment Regulations, 2007
(1) The title of these regulations is the Environmental Impact Citation and entry
into force.
Assessment Regulations, 2007.
(2) These regulations shall come into force on the date of
publication of these regulations, other than Part VI, which shall come
into force on such date as the Minister responsible for the environment
may by notice in the Gazette appoint, and different dates may be so
appointed for different provisions and different purposes of these
regulations.
(1)
In these regulations, unless the context otherwise Interpretation.
requires>-
“aquifer” means all underground freshwater-bearing strata
capable of yielding water, and includes groundwater reservoirs,
groundwater catchment areas, the waters in geological rock
formations, including fissures and fractures, and the structures
containing deep fossil waters<
“the Act” means the Development Planning Act<
“affecting” means will or may have an effect on<
“applicant” means any applicant seeking development
permission and includes a department and a Government entity<
“archaeology” means the study of ancient cultures by the
excavation and analysis of physical remains<
“the Authority” means the Malta Environment and Planning
Authority established under article 3 of the Act and includes any
body or other person acting on its behalf under powers delegated
by the Authority under the Act<
“baseline studies” means technical studies, prepared by
consultants, that describe in detail the existing environmental, social
and economic characteristics of the area being assessed, and how
these might develop without intervention<
“certificate” means a certificate of registration issued
according to the provisions of sub-regulation (4) of regulation
35 of these regulations<
“Committee” means the Inter-departmental Planning
Committee established under subarticle (1) of article 17D of the
Act<
“consultant” has the same meaning as is assigned to an
environmental impact assessment consultant in sub-regulation (3)
of regulation 35 of these regulations<
“consultees” means departments and agencies of Government,
local councils or any other body which the Director of Environment
Protection might request the consultants to consult<
“contributors” means technical experts that give minimal input
to the environmental impact assessment process but do not in any
way assess the impacts of the project<
“co-ordinator” means an environmental impact assessment
consultant who possesses the appropriate qualifications and has
knowledge and training in environmental impact assessment
techniques and methods and who is co-ordinating the preparation
of an environmental impact assessment, preparing the coordinated
assessment and writing the relative environmental impact statement
or environmental planning statement, as the case may be<
“conservation” means the management or control of human
use of a natural resource or the environment in such a manner that
it may yield the greatest sustainable benefit to present generations
whilst maintaining its potential to meet the needs and aspirations
of future generations< and includes preservation, maintenance,
sustainable utilisation, restoration, rehabilitation, reinstatement and
enhancement of a natural resource or the environment<
“council” has the same meaning as is assigned to it by article
2 of the Local Councils Act<
“cultural heritage” means>
(a) monuments - being architectural works, works of
monumental sculpture and painting, elements or structures
of an archaeological nature, inscriptions, cave dwellings and
combinations of features<
(b) groups of buildings - being groups of separate or
connected buildings or the spaces between them, singular
buildings or their immediate surroundings which are to be
conserved because of their architectural character, their
homogeneity or their place in the landscape<
(c) sites - being works of man or the combined works
of nature and of man, and areas including archaeological sites
which are of value from the point of view of history, art,
science, culture, aesthetics, ethnography, anthropology and
includes also their surroundings<
“cumulative impact” means the combined effect on the
environment of two or more projects, or parts of projects, including
synergistic effects<
“department of Government” means any department or
ministry and includes a Minister, Parliamentary Secretary, and any
public officer or other person acting on his behalf<
“developer” means that person who applies for development
permission for a public or private project<
“development” has the same meaning assigned to it by
subarticle (2) of article 30 of the Act<
“development permission” means a permission to carry out
development granted by the Authority either on an application in
that behalf or in a development order<
“development order” means an order made under and for the
purpose of article 31 of the Act<
“Director of Planning” means the Director of Planning
appointed under article 6 of the Act and includes any person acting
on his behalf or under his authority<
“Director of Environment Protection” means the Director of
the Environment Protection Directorate of the Malta Environment
and Planning Authority and includes any person or body of persons
acting on his behalf or under his authority<
“ecology” means the study of the interactions of living
organisms with other individuals of their own or of different
species, and with their environment<
“ecosystem” means a dynamic complex of plant, animal and
micro-organism communities and their non-living environment
interacting as a functional unit<
“effects” include>
(a)
direct effects, which are caused by an action<
(b) indirect effects, which are caused by an action or
actions and are later in time or further removed in distance,
but are still reasonably foreseeable< and includes growth-
regulating effects and other effects related to induced changes
in the pattern of land use, population density or growth rate,
and related effects on air and water and other natural systems
including ecosystems<
(c) ecological effects (including the effects on natural
resources and on the components, structures, and functioning
of affected ecosystems)<
(d) aesthetic, historic and cultural effects, whether
direct, indirect, or cumulative<
(e) socio-economic effects (including impacts on
incomes, employment, foreign exchange, recreational and
educational opportunities, social structure, culture, health,
safety, transport and general amenity), whether positive or
negative, direct or indirect through the generation of
environmental impacts<
(f) those effects resulting from actions which may have
both beneficial and detrimental effects, even if on balance
the consultants believe that the effect will be beneficial<
(g) secondary, cumulative, short, medium and long
term, permanent, temporary, positive and negative effects<
“environment” includes any one of, more of, or a combination
of the following>
(a)
air, land and water<
(b) plant and animal life<
(c)
social, economic and cultural conditions<
(d) any man-made development<
(e) any solid, liquid, gases, odour, heat, light, sound,
vibration and radiation<
(f)
any natural resource< and
(g) any part or combination of the foregoing and the
interrelationship between any two or more of them<
“environmental impact assessment” means the process of
identifying, predicting, evaluating and mitigating the biophysical,
social, economic and other relevant effects of proposed projects
and physical activities prior to major decisions and commitments
being made<
“environmental impact statement” means the result of a full
environmental impact assessment study presented as a report which
describes a development listed in Category I of Schedule IA to
these regulations and its effects on the environment indicating how
these effects have been taken into account<
“environmental interference” means any impairment of living
resources, ecosystems, human well-being (including health, safety,
cultural, commercial, transportation, recreational and educational
activity), material property, amenities or other legitimate uses of a
natural resource or the environment, caused, directly or indirectly,
by man through polluting substances, ionising radiation, noise,
explosions, vibration or other forms of energy, or movement of
matter, flora, fauna, diseases, flooding, smothering or other similar
means and includes the suppression of all those factors sustaining
the environment<
“environmental planning statement” means the result of a
limited environmental impact assessment study presented as a
report which describes a development listed in Category II of
Schedule IA to these regulations and its effects on the environment
indicating how these effects have been taken into account<
“environmental survey reports” means the original technical
studies prepared by the consultants for particular aspects of the
environmental impact assessment (for example, ecology, emissions
to air, archaeology, etc.)<
“extension” means any addition to a development and may
include increase in area, height, volume or capacity<
“fauna” means all types of animals<
“flora” means all types of vegetation<
“geology” means the science of the earth’s crust, strata and
origin of its rocks<
“Government entity” means a body corporate established by
law, a Government entity, and a company or other body in which
the Government or a body corporate or entity as aforesaid, or a
combination thereof, has a controlling interest or which is a
subsidiary of such a company< but it does not include the Authority<
“habitat” means that set of locations that satisfy the resource
requirements of a species and where it can fulfil its ecological
role<
“hazardous waste” has the same meaning as is assigned to it
in the Environment Protection Act or under regulations made under
the said Act or under any other law or regulations which may from
time to time replace the said Act<
“human environment” includes the natural and physical
environment and the relationship of people (including employees,
neighbours, consumers, and tourists) with that environment<
“identified stakeholders” means departments and agencies of
Government, local councils, non-government organisations or any
other body identified by the Authority, as having an interest in the
project<
“impacts” has the same meaning as is assigned to the word
“effects” in these regulations<
“Junior Impact Assessor” means an environmental impact
assessment consultant who possesses the required qualifications
and experience in a particular environmental discipline but lacks
experience and knowledge in environmental impact assessment
techniques and methods<
“landscape” means the characteristics, patterns, forms and
structures of the environment, including the traits, patterns, forms
and structures of a specific geographic area, its biological
composition, its physical environment, its geology, its
geomorphology, its palaeontology, its lithostratigraphy and its
anthropogenic and social patterns<
“locality” has the same meaning as is assigned to it by article
2 of the Local Councils Act<
“the Minister” refers to the Minister responsible for the
environment<
“mitigation” includes>
(a) avoiding the impact altogether by not taking a
certain action or part of an action<
(b) minimizing negative impacts by limiting the degree
or magnitude of the action and its implementation<
(c)
maximizing the positive impacts of developments<
(d) rectifying the impact by repairing, rehabilitating,
or restoring the affected environment<
(e) reducing or eliminating the impact over time by
conservation operations during the life of the action<
(f) compensating for the impact by replacing or
providing substitute resources or environments<
“natural environment” means>
(a) natural features consisting of physical and
biological formations or groups of such formations<
(b) geological and physiographical, geomorphological,
lithostratigraphical, palaeontological and hydrological
formations and precisely delineated areas which constitute
the habitat of threatened species of flora and fauna<
(c) natural sites or precisely delineated areas of value
from the point of view of science, scenic value, conservation
or natural beauty<
“pollution” means the introduction by man, directly or
indirectly, of any substance or energy into the environment resulting
in deleterious effects of such a nature as to endanger human health,
harm living resources, ecosystems and material property, and
impair amenities or interfere with other legitimate uses of the
environment<
“precautionary principle” means the adoption of, or taking of
preventative measures when there are reasonable grounds for
concern that threats of serious or irreversible damage to the
environment might occur even if there is a lack of scientific
certainty< provided that such uncertainty shall not be used as a
reason for postponing measures to avoid, reduce, prevent, anticipate
or control such threats or damage to the environment<
“project” means the proposed development for which a
development permission is being sought<
“project description statement” means a description of the
site and the proposed development in sufficient detail to identify
the likely effects on the environment and their acceptability under
specific policies contained in the Structure Plan and other
development plans and in planning policies<
“protected sites and areas” means>
(a) any property scheduled under the provisions of
article 46 of the Act<
(b) any property which, though not being scheduled
property under the provisions of articles 46 and 48 of the
Act, is protected under the provisions of article 47 of the Act
by an emergency conservation order<
(c) any tree scheduled under the provisions of article
48 of the Act<
(d) any area, building, site or archaeological remains
protected under the provisions of the Environment Protection Cap. 435.
Act, or any other law which may from time to time replace it<
(e) cultural heritage as defined by article 2 of the
Cultural Heritage Act, which is protected according to the Cap. 445.
provisions of that Act or of any other law which may from
time to time replace it<
(f) any urban conservation area designated under the
Structure Plan and any other development plan<
(g) any rural conservation area designated under the
Structure Plan and any other development plan<
(h) any village core area designated under the
Temporary Provisions Schemes< and
(i) any other objects, areas or sites which are protected
under the provisions of any other law<
“public” means one or more natural or legal persons and, in
accordance with national legislation or practice, their associations,
organisations or groups<
“the public concerned” means the public affected or likely to
be affected by, or having an interest in, the environmental decision-
making procedures referred to in these regulations< for the purposes
of this definition, non-governmental organisations promoting
environmental protection and meeting any requirements under
national law shall be deemed to have an interest>
Provided that where the term “public” appears in these
regulations it shall include “the public concerned”<
“public hearing” means a public consultation exercise, which
may include, but is not limited to> audio-visual presentations, public
exhibitions, meetings with identified stakeholders, question and
answer sessions, or combinations thereof, all of which shall be
open to the public and chaired # supervised by the Director of
Environment Protection.
“Register” means the Register of Environmental Impact
Assessment Consultants established under sub-regulation (1) of
regulation 35 of these regulations<
“Registration and Review Board” means the Registration
Board established under sub-regulation (1) of regulation 36 of these
regulations<
“scoping” means the process of identifying key issues,
significant actions, alternatives and impacts to be considered in an
environmental impact assessment<
“screening” means the decision of whether or not a proposal
should be subject to an environmental impact assessment<
“Senior Impact Assessor” means an environmental impact
assessment consultant who possesses the required qualifications
in a particular environmental discipline and knowledge of and
experience in environmental impact assessment techniques and
methods<
“significantly” requires considerations of both context and
intensity>
(a) context - this means that the significance of an
action shall be analysed in several contexts such as society as
a whole, the surroundings of the project, the affected interests,
the site of the project and the distribution of relevant features
of archaeological, ecological, scientific, hydrological,
geological and scenic value<
(b) intensity - this means the severity of impact and
the following elements shall be considered in evaluating
intensity>
(i) impacts that may be beneficial, adverse or
neutral<
(ii) the degree to which the project affects public
health or safety<
(iii) unique or otherwise rare or valuable
characteristics of the geographic area which affect its
relationship with the natural environment and the cultural
heritage<
(iv) the degree to which the project affects the
quality of the human environment<
(v) the degree to which the possible effects on
the human environment are uncertain or involve unique
or unknown risks<
(vi) the degree to which the action may establish
a precedent for future actions with potentially significant
effects or represents a decision in principle about a future
consideration<
(vii) whether the action is related to other actions
with individually insignificant but cumulatively
significant impacts<
(viii) whether the action threatens a violation of
any law or policy-making provision for the protection
of the environment<
(ix) whether the action is permanent or reversible<
“treaty” has the same meaning as is assigned to it in article 2
of the Ratification of Treaties Act<
“use of a natural resource” means any human conduct which,
directly or indirectly, takes advantage of the benefits of a natural
resource in the form of preservation, exploitation and possible
depletion, consumption or otherwise.
(2) The definition of any word or expression in sub-
regulation (1) of this regulation shall extend to all grammatical variations
and related expressions of the word or expression so defined.
(3) Any word or expression used in these regulations which
is defined by article 2 of the Act shall have the same meaning as is
assigned to such word or expression by that article of the Act.
PART II
TYPES OF ENVIRONMENTAL IMPACT ASSESSMENT
(1) The Malta Environment and Planning Authority shall Environmental
Impact Assessment.
be the responsible competent authority for performing the duties as set
out in these regulations.
(2) An environmental impact assessment is intended to
identify, describe and assess in an appropriate manner, in the light of
each individual proposal for development and in accordance with the
provisions of these regulations, the direct and indirect effects of that
development on the following factors>
(a) fauna and flora, and the living components of the
environment<
(b) soil, water, air, climate, the landscape, and the non-living
components of the environment<
(c) the interaction between the factors mentioned in
paragraphs (a) and (b) of this sub-regulation<
(d) material assets and the cultural heritage< and
(e) human beings and their interactions with the factors
mentioned in paragraphs (a) to (d) of this sub-regulation.
(3) An environmental impact assessment, depending on the
type of the development, shall take one of the following forms>
(a)
either a full environmental impact assessment< or
(b) a limited environmental impact assessment.
(4) Any development listed under Category I of Schedule
IA to these regulations shall require a full environmental impact
assessment by the preparation of an environmental impact statement,
unless the Authority refuses permission as stated in sub-regulation (2)
of regulation 4 of these regulations.
(5) Subject to sub-regulation (6) of this regulation any
development proposal which is submitted and falling within the scope
of the threshold indicated in the schedule listed under Category II of
Schedule IA to these regulations, shall require a limited environmental
impact assessment by the preparation of an environmental planning
statement, unless the Authority refuses permission as stated in sub-
regulation (2) of regulation 4 of these regulations<
Provided that where a planning application for a development
listed under Category II of Schedule IA of these regulations is submitted
for which no threshold is indicated in this schedule, the Director of
Environment Protection shall decide whether the development would
or would not be likely to have significant effects on the environment
having regard to the criteria set out in Schedule IB, on the basis of
which an environmental planning statement may be required.
(6) The Director of Environment Protection, acting of his
own accord or on the advice of the Director of Planning, may require
the applicant, in the case of any application for development permission
concerning a development which is not included in Category I of
Schedule IA to these regulations (even though such development may
be included under Category II of Schedule IA to these regulations) to
prepare a full environmental impact statement if he is of the opinion
that significant impacts are likely to occur having regard to the criteria
set out in Schedule IB and a normal planning application or an
environmental planning statement do not provide an adequate basis for
evaluating such development.
(7) Notwithstanding the provisions of sub-regulations (4),
(5) and (6) of this regulation and subject to sub-regulation (8) of this
regulation, the Director of Environment Protection acting on his own
accord or on the advice of the Director of Planning, may require the
applicant, in the case of any application for a development permission
concerning a development which is not included in Categories I or II of
Schedule IA to these regulations, to prepare an environmental impact
statement or an environmental planning statement if the Director of
Environment Protection is of the opinion that significant impacts are
likely to occur due to the characteristics and location of the proposal
having regard to the criteria set out in Schedule IB and a normal
development permission application would not provide an adequate basis
for evaluating such development.
(8) Notwithstanding the provisions of sub-regulation (5) of
this regulation, following a request made by the applicant in writing
with a detailed justification as to why the project is unlikely to have
significant environmental impacts the Director of Environment
Protection may exempt an applicant from preparing a limited
environmental impact assessment notwithstanding that the development
is one which is listed in Category II of Schedule IA to these regulations
if he is of the opinion that the project description statement presented
under the provisions of sub-regulation (1) of regulation 5 of these
regulations, has considered environmental issues in a sufficient manner
such that the preparation of a limited environmental impact assessment
would not add any new information and the Authority has all the
necessary information to determine the application provided that it is
unlikely that the project will have significant environmental effects
taking into account the information provided in the project description
statement in terms of the criteria listed in Schedule IB. In such a case, a
detailed justification as to why a limited environmental impact
assessment was not requested shall be provided and shall be published
in the Government Gazette.
(9) Notwithstanding the provisions of sub-regulations (6),
(7) and (8) of this regulation, the Environmental Impact Assessment
procedure may also be undertaken for proposed development projects
even prior to the submission of a formal development permission
application, so long as the development proposal is, prima facie,
acceptable in principle by the Director of Planning. In this case, all the
provisions in these regulations for the preparation of an environmental
impact statement or environmental planning statement, shall mutatis
mutandis apply.
(1) Subject to sub-regulation (8) of regulation 3 of these
regulations, no development permission shall be granted by the Authority
authorising any development listed in Schedule IA to these regulations
if no environmental impact assessment has been submitted to the
Authority according to the provisions of these regulations.
(2) Subject to sub-regulation (8) of regulation 3 of these
regulations, the Authority shall refuse development permission in the
case of a development that would otherwise require an environmental
impact assessment, even though no environmental impact assessment
has been submitted to the Authority according to the provisions of these
regulations>
(a) where the development is clearly against any approved
development plan or planning policy< or
(b) where the development is likely to compromise the
preparation of a development plan in the foreseeable future< or
(c) where the effects of a development project are clearly
unacceptable< or
(d) if the project description statement indicates that the
proposed development will have unacceptable environmental
impacts.
(1) Without prejudice to the provisions of regulation 3 of
the Development Permission (Method of Application) Regulations, 1992
and in addition to the requirements mentioned in sub-regulation (2) of
that regulation, an application for development permission concerning
any development that may require to be subjected to an environmental
impact assessment under regulation 3 to these regulations shall be
accompanied by a project description statement.
(2) If an application for development permission is not
accompanied by a project description statement as provided in sub-
regulation (1) of this regulation and, in the opinion of the Director of
Environment Protection in terms of regulations 3(4), (5), (6) and (7),
such application is one which may require an environmental impact
assessment, the Director of Environment Protection shall inform the
applicant that his application may require an environmental impact
assessment and that in terms of subarticle (2) of article 36 of the Act,
the period of time mentioned in subarticle (1) of article 36 of the Act
for the determination of the application shall be suspended until the
applicant furnishes the Authority with a project description statement
in terms of sub-regulation (1) of this regulation.
(3) A project description statement shall contain the
following information as applicable,
(a) details of the person wishing to carry out the
development<
(b) a brief description of the project and its general
objectives<
(c) an indication of the proposed timing of the project and
why this timing was preferred<
(d) the location of the proposed development with site
boundaries clearly shown on a map<
(e) a concise but reasonably comprehensive indication of
the alternative uses, alternative technologies and suitable alternative
locations and sites for the proposed development and alternative
arrangement of land uses, on the proposed site<
(f) a description of the physical characteristics including
size, scale, design and phasing of the development using models,
photographs, diagrams, plans and maps where appropriate<
(g) a description of present land uses and environmental
characteristics of the site<
(h) a brief description of surrounding land uses, their nature,
their extent and their environmental characteristics<
(i) a description of the services, water, foul water sewers,
surface water drainage, including storm water drainage, and energy
sources available on site<
(j) estimates of the number of persons to be employed with
estimates for each phase of the development<
(k) the nature and quantities of raw materials and energy to
be used, and wastes generated during construction and operation<
the proposed method of storage or handling of materials and wastes,
and machinery needed during both the construction and the
operational phases<
(l) access arrangements and general parking requirements
on and off the site, during both construction and operation<
(m) list of the major environmental impacts likely to be
generated by the project, including reference to cumulative impacts,
proposals for mitigating the negative effects of the development<
and
Provided that the information contained in the project
description statement is relevant to the given stage of the consent
procedure and to the specific characteristics of the particular project
or type of project and of the environmental features likely to be
effected.
(4) Notwithstanding the provisions of sub-regulations (1)
and (2) of this regulation, the Authority may request the preparation of
a Project Description Statement for proposed developments even prior
to the submission of a formal development permission application. In
this case, the provisions of sub-regulation (3) of this regulation still
apply.
(1) The applicant may of his own accord submit an
Environmental Scoping Statement to the Director of Environment
Protection, prior or in conjunction with the submission of the Project
Description Statement.
(2) The Environmental Scoping Statement shall>
(a) describe the environmental characteristics of the project
and the project environment<
(b) outline the potential impacts on the project environment
that could arise from the construction (including
demolition#clearance and decommissioning where relevant) and
the operation of the project<
(c) identify those potential impacts that may significantly
affect the project environment, and
(d) identify the potential secondary and cumulative
environmental impacts of the project, and the interactions between
potential environmental impacts.
(3) Any baseline surveys and # or investigations undertaken
in support of paragraphs (a) to (d) of sub-regulation (2) of this regulation
shall be included in the Environmental Scoping Statement.
(4) The environmental scoping statement shall be prepared
by consultants registered as EIA Coordinators under Part VI of these
regulations.
(5) The baseline surveys prepared in accordance with the
provisions of sub-regulation (3) of this regulation, shall be taken account
of in the formulation of the project proposal with a view to mitigate the
impacts of the proposed development at the design stage and shall, for
the purposes of these regulations be deemed to constitute part of the
environmental impact statement or environmental planning statement,
as the case may be, once the latter is commissioned.
(1) After the project description statement, which shall be Screening.
in conformity to regulation 5 of these regulations, is submitted by the
applicant to the Authority, the Director of Environment Protection shall
decide whether the development is one which is included under sub-
regulations (3) to (9) of regulation 3 or regulation 4 of these regulations.
(2) The Director of Environment Protection shall inform
the applicant of his decision not later than four weeks after the project
description statement prepared in conformity with regulation 5 of these
regulations has been received by the Authority and shall give reasons
for his decision.
(3) Once the Director of Environment Protection notifies
the applicant that his application requires an environmental impact
assessment according to Schedule IA of these regulations, the applicant
shall, within 30 days of notification, write to the Director of Environment
Protection to inform him that he accepts his views and shall provide an
environmental impact assessment within a time period to be specified
by the applicant.
(4) Until the applicant furnishes an environmental impact
assessment which complies with the provisions of these regulations,
the period of time mentioned in subarticles (1) and (2) of article 36 of
the Act for the determination of the application shall be suspended. The
said periods shall again commence to run from the date on which the
Authority has received the environmental impact statement or
environmental planning statement, as the case may be, and the Authority
has accepted this statement as being a valid submission in accordance
with sub-regulation (4) of regulation 26 of these regulations.
(5) If the applicant does not write to the Director of
Environment Protection in accordance with sub-regulation (3) of this
regulation, the application shall be processed according to the provisions
of sub-regulation (1) of regulation 4 of these regulations.
(1) After the expiration of the period mentioned in sub-
regulation (3) of regulation 7 of these regulations, the Director of
Environment Protection shall inform such departments and agencies of
Government which he deems proper, of the receipt of a project
description statement in relation to a development that requires the
preparation of an environmental impact statement or an environmental
planning statement, as the case may be.
(2) The Director of Environment Protection shall also inform
the applicant in writing of the names and addresses of the departments
and agencies so notified.
(3) The departments and agencies so notified shall, if
requested by the applicant, enter into consultation with him to determine
whether they have in their possession any information which the
applicant or they consider relevant to the preparation of an environmental
impact statement or an environmental planning statement and, if they
have such information, such departments and agencies of Government
shall make it available to the applicant, provided that such departments
and agencies of Government shall not be required to disclose any
information which, in terms of any law, is considered to be confidential
or secret.
(4) A reasonable charge reflecting the cost of making the
relevant information available may be made by a body supplying
information sought by the applicant, in accordance with sub-regulation
(3) of this regulation.
(5) After the expiration of the period mentioned in sub-
regulation (3) of regulation 7 of these regulations, the Director of
Environment Protection shall publish, in the Gazette and in a local
newspaper, a list of applications that require an environmental impact
assessment according to sub-regulations (4), (5), (6) or (7) of regulation
3 of these regulations.
(1) The applicant shall be responsible for commissioning Managing
preparation of an
an environmental impact statement or an environmental planning environmental
statement in accordance with the provisions of regulation 11 or regulation impact assessment.
33 of these regulations, as the case may be. In the event of any reasonable
doubt about the quality or impartiality of the environmental impact
statement or the environmental planning statement or any part thereof,
or any similarly significant concern, the Authority may commission,
an independent assessment at the expense of the applicant.
(2) During the preparation of the environmental impact
statement or the environmental planning statement, the Director of
Environment Protection and the Director of Planning shall provide an
advisory and quality control function.
(3) Without prejudice to the provisions of sub-regulation
(1) of this regulation, in cases where more than one development
permission application requiring an environmental impact assessment
are being considered in the same locality or are otherwise interrelated,
the Director of Environment Protection may request that one
comprehensive environmental impact statement or environmental
planning statement, as the case may be, be carried out for the projects
in question. .
PART III
FULL ENVIRONMENTAL IMPACT ASSESSMENT
(requiring an Environmental Impact Statement)
(1) Prior to formulating the terms of reference for the Setting terms of
environmental impact statement, an appraisal of all foreseeable (or reference
environmental
expected) environmental impacts of the development shall be carried impact statement.
out by the Director of Environment Protection on the basis of, but not
limited to, information contained in the project description statement.
(2) The Director of Environment Protection shall invite
relevant government departments and the local council which is
responsible for the locality where the development is proposed to be
executed and other local councils, that in the opinion of the Director of
Environment Protection are likely to be affected by the project, to provide
information, within twenty-one days of notification, on what they wish
to see included in the terms of reference giving reasoned justification
for doing so.
(3) (i) The Director of Environment Protection shall place
an advert in a local newspaper, at the expense of the applicant, inviting
the general public to inform him, within twenty-one days of publication
of the advert, of issues that they would wish to see included in the terms
of reference. The Director of Environment Protection may also convene
a public hearing, prior to the setting of the terms of reference, when it is
considered that the proposed project is of major significance because
of its scale, location, hazardous properties or other reasons. The cost of
such a meeting shall be borne by the applicant.
(ii) The Director of Environment Protection shall organise
a meeting with the applicant and his representatives on the request of
the applicant to discuss what is to be included in the terms of reference.
Minutes are to be kept of the meeting. At his discretion, the Director of
Environment Protection may seek the endorsement of the applicant of
the said minutes.
(4) Following these consultations the Director of
Environment Protection shall draw up the final terms of reference. The
terms of reference shall include a request for information. This
information shall be relevant to the given stage of the consent procedure
and to the specific characteristics of the particular project or type or
project and of the environmental features likely to be effected.
(5) The Director of Environment Protection shall
communicate a copy of the approved terms of reference to the applicant,
to the applicant’s architect or consultants and to such other persons he
deems proper.
(6) The Director of Environment Protection shall grant
access to the public to the final terms of reference of an environmental
impact statement.
(1) An environmental impact statement shall be prepared
by consultants registered under Part VI of these regulations.
(2) The applicant shall select the consultants to prepare an
environmental impact statement from the Register and shall
communicate the names of the consultants so chosen to the Director of
Environment Protection.
(1) The environmental impact assessment coordinator
nominated by the applicant shall be chosen from among the
environmental impact assessment coordinators listed in the Register of
Consultants in terms of Part VI of these regulations.
(2) The coordinator shall be responsible for briefing the
other consultants, liaising with the applicant and his project design team,
the Director of Planning, the Director of Environment Protection, other
departments and agencies of Government, and the local council with
responsibility for the locality in which the development is being proposed
to be executed, and affected local councils if the nature or impacts of
the project are such that they may affect them.
(3) The coordinator shall prepare a coordinated
environmental statement based on the findings and interpretations
derived from specialized analyses carried out by the other consultants,
other studies and documents compiled by the consultants and the
comments made by the persons mentioned in sub-regulation (3) of
regulation 21 of these regulations.
A full environmental impact assessment for development Procedures to be
followed in the
shall involve the following procedures>
preparation of a full
environmental
impact assessment.
(a) describing the development including all ancillary
facilities<
(b) describing the extent of the existing environment likely
to be affected by the proposed development<
(c) identifying and assessing the effects of the proposed
development on the existing environment<
(d) designing mitigation measures<
(e)
formulating monitoring and auditing requirements< and
(f) preparing a non-technical summary of the environmental
impact statement.
(1) The consultants shall describe the proposed Description of the
Proposed
development including >
Development
Project.
(a)
a justification for the proposal<
(b) a description of the physical characteristics and features
of the project including production processes (if relevant) and
amounts of emissions, wastes and residues expected during both
construction and operation<
(c) a description of the financial feasibility of the project.
A description of alternative sites considered, and alternative
technologies that could be employed during construction and when
in operation, shall also be included. In doing so, they may also
refer to the project description statement mentioned in regulation
5 of these regulations.
(2) Without prejudice to article 39 of the Act, where the
proposed development has a limited life, the after use of the development
shall also be described.
The consultants shall describe the existing environmental
conditions in and around the site in terms of>
(a)
physical features>-
(i) population<
(ii) flora, fauna and ecosystems (terrestrial and marine),
including both habitats and species and, in particular, protected
and endangered species and their habitats<
(iii) soil, agricultural quality and produce<
(iv) geology and geomorphology, including
palaeontology and noting geological sites<
(v) water and hydrological features<
(vi) air, including prevailing meteorological factors and
air quality<
(vii) cultural heritage and protected sites and areas<
(viii) landscape and topography, including the coast
and submarine features<
(ix) land use, including recreational uses< and
(x) any other relevant environmental features<
(b) policy framework>-
(i) the planning policy framework which affects the
development shall also be analysed. Such analysis shall
include the relevant planning policies set out in the Act, in
development plans and in other planning policies approved
under the provisions of the Act, the Environment Protection
Act, or under any other law<
(ii) in particular, but without prejudice to the generality
of paragraph (a) of this regulation, the policy review shall
relate to>
(1) the site of the proposed development<
(2) the surrounding areas in which impacts may
be experienced by the proposed development<
(3) any treaty adhered to by Malta<
(4) policies adopted by any department and
Government entity which might have a bearing on the
development<
(5) protective scheduling or other designations
pertaining to the site and its surroundings< and
(6) any other law having a bearing on the
development.
(1) The probable effects, both of the finished development Assessment of
effects of the
and during construction, shall be predicted.
development.
(2) All significant impacts of the proposed development
shall be considered and assessed including the main effects on>
(a) buildings and other man-made features (including
infrastructure)<
(b) flora, fauna, ecology and geology including
geomorphology and palaeontology<
(c)
land<
(d) water<
(e)
air and climate<
(f) other indirect and secondary effects associated with the
development<
(g) human beings (including health and safety measures).
(3) Hazard and risk assessment of the development shall
also be undertaken.
(4) If any of the effects assessed in regulations (1) to (3) of
this regulation are envisaged to have transboundary impacts, these should
be assessed and clearly stated in the environmental impact statement.
Provisions dealing with such impacts shall follow the procedures set in
Part V of these regulations.
Where adverse effects are identified, the consultants shall
state clearly what significance they attribute to these effects and the
mitigation measures they propose to be incorporated in the development
and evaluate their effectiveness.
(1) The consultants shall devise a scheme to monitor the
impacts of the development which may arise during the construction
and operational phases.
(2) The consultants shall also identify which records the
applicant shall keep for the purpose of monitoring the environmental
impacts of the development.
(3) The Authority shall have access to any such records both
during the construction and operational phases of the development.
(1) Notwithstanding the provisions of regulations 13 to 18
of these regulations, the Director of Environment Protection may modify
the specific terms of reference set out for an environmental impact
assessment in these regulations according to the planning and
environmental considerations of each and every development.
(2) The Director of Environment Protection shall grant
access to government departments, local councils and the public, to
any amended terms of reference according to the provisions of sub-
regulations (5) and (6) of regulation 10 of these regulations.
(1) The consultants shall first prepare>
Draft environmental
(a)
a draft environmental impact statement which shall>
(i) cover all the topics specified in the terms of
reference issued by the Director of Environment Protection<
(ii) be presented in an intelligible form<
(iii) be in the either Maltese or English language or
both< and
(b) contain a non-technical summary which shall be a
separate document presented in both the Maltese and English
languages.
(2) The analysis of the impacts on the environment shall be
presented in summary, chart, tabular or pictorial format and in a
descriptive manner.
(3) The various techniques and methods used in the analysis
and predictions shall be included in the environmental impact statement.
All assumptions and the reasoning behind such assumptions shall also
be included.
(4) The original environmental survey reports shall be
attached to the environmental impact statement.
(5) An indication of any difficulties, including technical and
other difficulties, encountered by the consultants in compiling the
required information shall also be included.
(6) It shall be the consultants’ responsibility to ensure that
all references to published works and sources of information shall be
duly acknowledged.
(7) The various reports constituting the environmental
impact statement shall be written in co-ordination with one another and
shall be presented in a coherent manner.
(8) The consultants shall ensure the professional integrity,
including scientific integrity, of the discussions and analyses in
environmental impact statements.
(9) Where the consultants are evaluating reasonably
foreseeable significant effects on the environment and there is
incomplete or unavailable information, the consultants shall always
make clear that such information is lacking or incomplete.
(10) If the incomplete information referred to in sub-
regulation (9) of this regulation is essential to a reasoned choice among
alternatives and the overall costs of obtaining it are not exorbitant, the
consultants shall include the information in the environmental impact
statement.
(11) If the information relevant to reasonably foreseeable
significant adverse impacts cannot be obtained because the overall costs
of obtaining it are exorbitant or the means to obtain it are not known,
the consultants shall include within the environmental impact statement>
(a) a statement that such information is incomplete or
unavailable<
(b) a statement of the relevance of the incomplete or
unavailable information to evaluating reasonably foreseeable
significant adverse impacts on the environment<
(c) a summary of existing credible scientific evidence which
is relevant to evaluating the reasonably foreseeable significant
adverse impacts on the environment< and
(d) the consultants’ evaluation of such impacts based upon
theoretical approaches or research methods generally accepted in
the scientific community.
(e) the provisions of sub-regulation 11 shall not preclude
the Authority from verifying the justification for any alleged
limitation, nor from requiring rectification of unjustified limitations.
(12) For the purposes of this regulation, “reasonably
foreseeable” includes impacts which have major or catastrophic
consequences, even if their probability of occurrence is low, provided
that>
(a) the analysis of the impacts is supported by credible
scientific evidence<
(b) it is not based on pure conjecture< and
(c)
is within the rule of reason.
(13) Wherever the available information is deemed by the
Director of Planning and the Director of Environment Protection to be
insufficient for acceptable determination of the application and wherever
the risk factor or hazard factor or both are deemed to be too high, they
shall, notwithstanding sub-regulations (1) to (4) of this regulation, adopt
the precautionary principle.
(1) After preparing a draft environmental impact statement
and before preparing a final environmental impact statement, a
consultation stage shall take place.
(2) The consultants shall submit copies of the draft
environmental impact statement to the Director of Environment
Protection and a copy or part thereof to any other department or
Government entity as the Director of Environment Protection may
request. The consultants shall inform the Director of Environment
Protection of the name of every body whom they have so served, of the
date of service and, where they have not served a copy of the whole of
the draft environmental impact statement, of which part of the copy
that was served.
(3) The Director of Environment Protection shall also
request the comments of the Director of Planning and of any other
department and Government entity which he may deem relevant for the
purpose on the whole document forming the environmental impact
statement or on part thereof.
(4) The Director of Environment Protection shall establish
a time limit within which the comments mentioned in sub-regulation
(3) of this regulation shall be received by him. Such time limit shall not
be less than thirty days from the date of receipt of the draft environmental
impact statement by the respective department or Government entity.
Should no comments be received within the stipulated period the
Director of Environment Protection shall assume that the consultees
have no comments to submit.
(5) Comments on the draft environmental impact statement
shall be as specific as possible and may address the adequacy of the
draft environmental impact statement, the merits of the alternatives
discussed, or any combination thereof.
(1) The draft environmental impact statement shall be Review of the draft
environmental
reviewed by the Director of Environment Protection and shall be impact statement.
assessed against the terms of reference, the quality of the data used and
the objectivity of analysis for the prediction of impacts. Comment may
also be made on the suitability of the mitigation measures proposed and
on any other matter that is deemed by the Director of Environment
Protection to be relevant.
(2) The Director of Environment Protection shall specify
in his comments whether he needs additional information, what
information he needs and, where relevant, the level of detail required.
The Director of Environment Protection may require an applicant to
produce such evidence as he may reasonably call for to verify any
information in his environmental impact statement.
(3) On completion of the consultation stage and of this
review, the Director of Environment Protection shall send a report
incorporating these and other comments, including any mitigation
measures he may deem fit, to the consultants for their consideration
and revision of the draft environmental impact statement.
(1) The consultants shall respond to the comments made
Revision of the draft
during the consultation stage by one or more of the following means>
(a) develop and evaluate alternatives not previously given
serious consideration by them<
(b) supplement, improve, or modify their assessment<
(c)
modify alternatives, including the proposed action<
(d) make factual corrections< or
(e) explain why the comments do not warrant further
response by them citing the sources, authorities, or reasons which
support the consultants’ position.
(2) All substantive comments received on the draft
environmental impact statement (or summaries thereof where the
response has been exceptionally voluminous) shall be attached to the
draft environmental impact statement whether or not the comment is
thought to merit individual discussion by the consultants in the text of
the environmental impact statement.
(1) On receipt of the consultant’s comments or revisions,
in accordance with regulation 23 of these regulations, the Director of
Environment Protection shall review the draft environmental impact
statement as amended.
(2) The Director of Environment Protection shall consider
whether the statement has been satisfactorily compiled, prepared in a
professional manner, is without bias and adequately meets the terms of
reference. If he is satisfied with the statement he shall certify it
accordingly and inform the consultants and all the consultees.
(3) If the Director of Environment Protection does not issue
a certificate as mentioned in sub-regulation (2) of this regulation, the
statement shall not be certified until the consultants abide by the
directions given to them by the Director of Environment Protection.
(4) On certification of the environmental impact statement
by the Director of Environment Protection according to sub-regulation
(2) of this regulation, the applicant shall comply with sub-regulations
(5), (6), (7) and (8) of this regulation.
(5) The applicant shall publish, at the applicant’s expense,
in at least one daily newspaper in the Maltese language and in at least
one daily newspaper published in the English language, a notice (as
specified in Schedule II) stating>
(a) the applicant’s name with respect to the application for
development permission<
(b) the date on which the application was validated<
(c) the address or location and the nature of the proposed
development<
(d) that a copy of the application and of the plans and other
documents submitted with it together with a copy of the draft
environmental statement may be inspected by members of the
public at reasonable hours<
(e) an address at which those documents may be inspected
and the latest date on which they shall be available for inspection
(being a date not less than fourteen days later than the date on
which the notice is published)<
(f) an address (whether or not the same as that given under
paragraph (e)) at which copies of the environmental statement may
be obtained<
(g) if a charge is to be made for a copy, the amount of the
charge< and
(h) that any person wishing to make representations about
the application, shall make them in writing, before the date named
in accordance with paragraph (e), to the Malta Environment and
Planning Authority.
(6) The applicant shall affix on the land a notice (as specified
in Schedule II to these regulations) containing the information specified
in sub-regulation (5) of this regulation, except that the date named as
the latest date on which the documents shall be available for inspection
shall not be less than twenty-one days later than the date on which the
notice is first affixed.
(7) The notice mentioned in sub-regulation (6) of this
regulation shall>
(a) be left in position for the whole duration of the
consultation period specified in sub-regulation (6) of this regulation
and in any case, for not less than seven consecutive days< and
(b) be affixed firmly to some object on the land and sited
and displayed in such a way as to be easily visible to, and readable
by, members of the public without going on to the land.
(8) Following the elapse of the period specified in sub-
regulation (7) of this regulation, the applicant shall submit to the
Authority a certificate by or on behalf of the applicant which states that
he has affixed a notice on the land in compliance with this regulation
and when he did so, and that the notice was left in position for not less
than seven days, or that, without any fault on his part, it was removed,
obscured or defaced before seven days had elapsed and he took
reasonable steps for its protection or replacement specifying the steps
taken.
(9) If any person issues a certificate which purports to
comply with the requirements of paragraph (b) of sub-regulation (8) of
this regulation, and which contains a statement which he knows to be
false or misleading in a material particular, or recklessly issues a
certificate which purports to comply with those requirements and which
contains a statement which is false or misleading in a material particular,
he shall be guilty of an offence and the provisions of sub-article (1) of
article 56 of the Act shall apply.
(10) A date for the public hearing required in terms of
regulation 25 shall only be set once the applicant submits the
documentation required in sub-regulation (8) of this regulation.
(1) After having certified the draft environmental impact
statement the Director of Environment Protection shall arrange for a
public hearing to take place, at which the public may comment on the
environmental impact statement and express their views on the impact
of the proposed development.
(2) The Director of Environment Protection shall inform
the public as aforesaid and shall also inform the public of the day, time
and place where the public hearing shall take place by publishing a
notice in the Gazette and in the local newspapers. All reasonable
expenses incurred by the Authority for organising the public hearing
and publishing the said notices shall be borne by the applicant.
(3) The Director of Environment Protection shall give at
least fifteen days notice but not more than thirty days notice of the
public hearing.
(4) The Director of Environment Protection shall inform
the Director of Planning, the consultants and the persons mentioned in
sub-regulations (2) and (3) of regulation 21 of these regulations of the
date, time and place of the public hearing giving at least fifteen days
advance notice.
(5) A copy of the draft environmental impact statement shall
be made available for public inspection at the Authority, and may be
inspected throughout the period stipulated in sub-regulation (3) of
this regulation on such days and during such times as the Director of
Environment Protection deems proper, whilst at the same time making
the non-technical summary freely accessible on the Authority’s official
web site.
(6) A copy of the draft environmental impact statement shall
be submitted to the local council which is responsible for the locality
where the development is proposed to be executed and other local
councils, that in the opinion of the Director of Environment Protection
are likely to be affected by the project, so that it may be made available
for public inspection throughout the period stipulated in sub-regulation
(3) of this regulation.
(7) The Director of Environment Protection shall chair and
regulate the proceedings of the public hearing. He shall, as much as is
reasonable give every person present in the hearing who wishes to make
any submissions the opportunity to air his views on the environmental
implications of the proposed development. The language of the public
hearing shall be in Maltese.
(8) The views of the public as expressed during the public
hearing and in any written comments made by the public before, during
or up to seven days after the public hearing, shall be recorded by the
Director of Environment Protection. All the comments received or
recorded shall be collated into a report by the Director of Environment
Protection. This report shall be forwarded to the Director of Planning,
to the applicant and to his consultants not later than two weeks after the
date of the public hearing. A summary of all the comments shall be
presented in an appendix to the final environmental impact statement.
(1) Prior to the submission of the final environmental impact Submission of the
final environmental
statement to the Authority, the consultants shall further revise the impact statement to
environmental impact statement and the proposed development in the the Authority.
light of the written comments made by the public and the comments
made during the public hearing.
(2) The final environmental impact statement, including
environmental survey reports, as revised if so required, shall be submitted
by the co-ordinator to the Authority.
(3) The consultants may place discussion of methodology
in an appendix.
(4) The applicant shall ensure that his application conforms
to the recommendations made in the environmental impact statement.
The application shall not be determined until the Director of Planning
in consultation with the Director of Environment Protection is satisfied
that the development application conforms to the said recommendations
and the provisions of subarticle (2) of article 36 of the Act shall apply.
If not, the Director of Planning shall request the applicant to comply
with the said recommendations.
(5) The co-ordinator shall submit such number of copies of
the environmental impact statement to the Authority as the Director of
Environment Protection may reasonably establish.
(6) The Authority shall be empowered to reproduce the
contents of the environmental impact statement, once this is submitted,
at its own discretion.
(1) An applicant for development permission who submits
an environmental statement in connection with his application shall
ensure that a reasonable number of copies of the statement are available
at the address named in the notices published or affixed pursuant to
paragraph (f) of sub-regulation (5) of regulation 24 of these regulations,
as the address at which such copies may be obtained.
(2) Copies of the final environmental impact statement shall
be made available for sale to interested persons by the Director of
Environment Protection, whilst at the same time making the non-
technical summary accessible on the Authority’s official web site.
(3) The price of the said statement shall not exceed the cost
of their printing and distribution. Such charges shall be levied from
any member of the public for a copy of an environmental statement
made available in accordance with sub-regulation (1) of this regulation.
(1) The environmental impact statement shall list the
registration number and the names of the consultants and contributors
responsible for the preparation of the environmental impact statement,
environmental survey reports, appendices, non-technical summary and
any other component of the statement.
(2) The consultants who are responsible for a particular
analysis, including analysis in the environmental survey reports, shall
be identified.
(3) All consultants and contributors employed in the
environmental impact assessment shall sign a declaration stating that
the particular study (or part thereof) was solely carried out by them and
that they take responsibility for any statement and conclusion contained
therein. This signed declaration shall be included with each
environmental survey report included with the environmental impact
statement.
(1) In the interests of fairness, objectivity and the avoidance Conflict of Interest.
of bias, all consultants shall be required to sign, and abide by, a
declaration that they have no personal or financial interest in the proposed
development.
(2) The Director of Environment Protection shall not
approve consultants, groups of consultants or consultancy firms that
are in any way associated with any company, association or grouping
that has any direct or indirect personal, professional or financial interest
in the proposed development.
(3) The Director of Environment Protection shall not
approve any environmental impact statement or environmental planning
statement produced by a consultant or group of consultants, one or more
of whom does not comply with the provisions of sub-regulations (1) or
(2) of this regulation.
(1) Consultants shall incorporate material into an Incorporation by
reference.
environmental impact statement by reference when the effect will be to
cut down on bulk without impeding the review by the public during the
public participation process or by the Authority, any department and
Government entity, by the council which is responsible for the locality
where the development is to be executed, or by adjacent councils.
(2) The incorporated material shall be cited in the statement
and its content briefly described.
(3) No material may be incorporated by reference unless it
is reasonably available for inspection by potentially interested persons
within the time allowed for comment prescribed under sub-regulation
(4) of regulation 21 of these regulations.
(4) Material which is based on proprietary data which is
itself not available for review and comment shall not be incorporated
by reference.
(1) The environmental impact statement shall list all
permits, licences and other forms of authorisation which must be
need if development
obtained by the applicant in terms of any other law from any department
or Government entity in implementing the development if development
permission is granted.
(2) If the consultants are uncertain whether such
authorisation as mentioned in sub-regulation (1) of this regulation is
necessary, they shall so indicate in the environmental impact statement.
(1) The Authority shall keep a copy of each draft
environmental impact statement, the final environmental impact
statement and any documents connected therewith in a public reference
room.
(2) A copy of any environmental planning statement
submitted to the Authority under the provisions of Part IV of these
regulations shall also be kept in the public reference room.
(3) Access to the documents mentioned in sub-regulations
(1) and (2) of this regulation shall be given to any person during such
reasonable times as the Authority may determine.
PART IV
LIMITED ENVIRONMENTAL IMPACT ASSESSMENT
(requiring an Environmental Planning Statement)
(1) Prior to formulating the terms of reference for the
environmental planning statement, an appraisal of all foreseeable (or
expected) environmental impacts of the development shall be carried
out by the Director of Environment Protection on the basis of, but not
limited to, information contained in the project description statement.
(2) The Director of Environment Protection shall invite
relevant government departments and the local council which is
responsible for the locality where the development is proposed to be
executed and other local councils, that in the opinion of the Director of
Environment Protection are likely to be affected by the project, to
provide information, within twenty-one days of notification, on what
they wish to see included in the terms of reference and the justification
for doing so.
(3) Following these consultations the Director of
Environment Protection shall draw up the final draft of the terms of
reference.
(4) The Director of Environment Protection shall
communicate a copy of the approved terms of reference to the applicant,
architect and to such other persons he deems proper.
(5) The provisions of regulations 11 to 32 other than, sub-
regulation (3) of regulation 19, sub-regulation (10) of regulation 24,
and regulation 25 of these regulations shall mutatis mutandis apply to
an environmental planning statement, provided that an environmental
planning statement shall be more limited in nature than an environmental
impact statement.
PART V
Transboundary Effects
(1) Where the Minister is aware that a project in Malta is Procedures to be
followed when a
likely to have significant effects on the environment in another State, project is likely to
or where a State likely to be significantly affected so requests, the have transboundary
impacts.
Minister shall send to the affected State as soon as possible and not
later than when the public is informed in terms of sub-regulation (5) of
regulation 7 of these regulations, the following>
(a) a description of the project, together with any available
information on its possible transboundary impacts<
(b) relevant information regarding the environmental impact
assessment procedure<
(c) information on the nature of the decisions which may
be taken<
and shall give the affected State a reasonable time in which to indicate
whether it wishes to participate in the environmental impact assessment
procedure.
(2) If the affected State which receives information indicates
to the Minister that it intends to participate in the environmental impact
assessment procedure, the Minister shall, if he has not already done so,
send to the affected State the information gathered regarding the
proposed development.
(3) The affected State shall enter into consultations with
the Minister concerning, inter alia, the potential transboundary effects
of the project and the measures envisaged to reduce or eliminate such
effects and shall agree on a reasonable timeframe for the duration of
the consultation period.
(4) The affected State may arrange for the information to
be made available, within a reasonable time, to the relevant authorities
and the public in the territory of such affected State which is likely to
be significantly affected< and, within the timeframe established through
the provisions of sub-regulation (3) of this regulation, the affected State,
shall forward its opinion to the Minister who shall in turn forward such
opinion to the Authority.
(5) The transmission of information to the affected State,
concerning potential transboundary impacts, and the receipt of
information by such affected State, shall be subject to the limitations
contained in any law in force in Malta.
(6) The Minister shall provide to the affected State the final
decision on the proposed project along with the reasons and
considerations including information about the public participation
process on which it was based and any conditions attached thereto. There
shall also be a description, where necessary, of the main measures to
avoid, reduce and, if possible, offset the major adverse effects.
(7) When, following monitoring of a development with
potential transboundary impacts, significant adverse transboundary
impacts or factors that may result in such an impact are discovered, the
Minister shall immediately inform the affected State and enter into
consultations on the necessary measures that may be undertaken to
reduce or eliminate such impact.
(8) In the exercise of his duties under this regulation, the
Authority shall furnish the Minister with all such documentation and
information as he may request.
(9) Where the Minister is informed that a project proposed
in another State is likely to have a significant effect on the environment
of the Maltese Islands, he shall inform the State, in which the project is
to be undertaken, of Malta’s request to participate in the environmental
impact assessment procedure in that State and request the following>
(a) a description of the project, together with any available
information on its possible transboundary impacts<
(b) relevant information regarding the environmental impact
assessment procedure< and
(c)
information on the nature of the decisions.
(10) The Minister shall forward to the Authority the
information listed in sub-regulation (9) of this regulation. The Authority
shall make this information available to the consultees and the public in
Malta in accordance with the provisions of regulations 21 and 25 of
these regulations. The Minister shall also enter into discussion with the
State in which the project is to be undertaken to agree on a reasonable
timeframe for the duration of the consultation period.
(11) The Minister, acting on the advice of the Authority
and taking into consideration the comments of the public, shall enter
into consultations with the State in which the project is to be undertaken
concerning, inter alia, the potential transboundary effects of the project
and the measures envisaged to reduce or eliminate such effects.
(12) When the Minister receives details from the State in
which the project is to be undertaken regarding the final decision on the
proposed project, together with the reasons and considerations on which
it was based, he shall provide a copy of this information to the Authority
who shall publish the information in the Gazette, in a local newspaper
and on the Authority’s official web site.
PART VI
REGISTER OF CONSULTANTS AND REVIEWS
(1) The Authority shall keep and make available for public Register of
Environmental
inspection at such reasonable times as it may determine, a Register of Impact Assessment
Environmental Impact Assessment Consultants.
Consultants.
(2) The Register shall be divided into Parts. Each Part shall
list those consultants who are competent in a particular discipline,
provided that where a person is competent in more than one particular
discipline he shall be registered under both or more such disciplines.
(3) The Register shall also be divided into categories of
environmental impact assessment consultants, namely a Junior Impact
Assessor, a Senior Impact Assessor and an Environmental Impact
Assessment Co-ordinator.
(4) The Authority shall note the issue of a certificate of
registration in the Register together with the relevant discipline or
disciplines in which he is competent and shall also note therein all
suspensions, cancellations and reinstatements of those certificates.
(5) No person may act as an impact assessor or
environmental impact assessment co-ordinator unless he is registered
in the Register of Environmental Impact Assessment Consultants or
unless he proves that he is registered with a recognised national
registration body for the carrying out of professional work related to
the duties of an impact assessor or environmental impact assessment
co-ordinator.
(6) The Authority shall refuse to accept an environmental
impact statement or an environmental planning statement where a person
who is not registered in the Register has participated in the preparation
of the relevant environmental impact assessment.
(7) Notwithstanding the provisions of sub-regulation (6) of
this regulation, the Director of Environment Protection may, where he
deems it necessary, accept the contribution by a non-registered person>
(a) in relation to a specific discipline not covered in the
Register, provided that that person is, in the view of the Director
of Environment Protection, suitably qualified to make such a
contribution and his participation has been agreed in writing prior
to the commissioning of the environmental impact assessment<
(b) where that person has been responsible for undertaking
research including the gathering and collation of data, under the
supervision of a registered consultant participating in the relevant
environmental impact assessment, but has not been involved in
the assessment of impacts.
(1) The Minister shall appoint a Registration and Review
Board that shall be responsible for>
(i) evaluating applications for registration in the Register<
and
(ii) receive and consider requests for considerations
submitted by applicants as per regulation 45.
(2) Decisions on applications for registration shall be taken
by the Registration and Review Board composed of a minimum of three
persons and a maximum of five persons. Members of the Registration
and Review Board shall be independent members who are not involved
in any way in the preparation of environmental impact assessments,
one of whom shall act as the chairperson of the Registration and Review
Board.
(3) The Registration and Review Board shall assess
applications for registration and shall prepare a list of persons who, in
the opinion of the Board, meet the requirements for registration and are
therefore to be issued with a certificate of registration. The Registration
and Review Board shall give reasons for their decisions.
(4) The decision of the Registration and Review Board to
grant or to refuse an application for registration in the Register shall be
notified in writing to the applicant without delay.
(5) The Registration and Review Board may direct the
Authority to update the Register at such regular intervals as it may deem
fit by the inclusion of other disciplines in the Register, which disciplines
might have in the meantime evolved.
(1) Any person may apply in writing on the appropriate Registration.
form to the Registration and Review Board to be registered in the
Register.
(2) The application for registration shall include the
following information>
(a) personal details including name, surname, date of birth,
private and office addresses and qualifications of the applicant for
registration<
(b) a list of any relevant work by the applicant<
(c) a detailed curriculum vitae (which is to include details
of the person’s training, experience and knowledge in
environmental assessment techniques and methods)<
(d) the category to which the applicant is applying, as set
out in Schedule III of these regulations<
(e) an indication of the particular environmental discipline
or disciplines for which the person is applying for registration in.
(3) The application for registration shall be accompanied
by the appropriate fee as set out in Schedule III of these regulations.
(1) The Registration and Review Board shall register a
person in the Register if it is satisfied that the said person>
(a) has appropriate qualifications in an environmental
discipline or in environmental impact assessment<
(b) has experience and knowledge of environmental
assessment techniques and methods< and
(c)
has experience in one or more relevant disciplines.
(2) Certificates issued to eligible persons shall be valid for
one year but may be renewed by the Registration and Review Board
upon payment of the relevant renewal fee according to Schedule III to
these regulations, except where, in the opinion of the Registration and
Review Board, the provisions of regulation 40 have been contravened.
(3) Notwithstanding the provisions of sub-regulation (1) of
this regulation, the Registration and Review Board may grant a
temporary certificate valid for one year to any person who, in the opinion
of the Registration and Review Board, has the appropriate qualifications
but does not have sufficient experience in the relevant discipline or in
environmental impact assessment techniques and methods. Temporary
certificates shall only be issued for a maximum of two years.
(4) The Authority shall endeavour to organise training
courses in environmental impact assessment techniques and methods.
All junior impact assessors and persons issued with a temporary
certificate shall be obliged to undertake this training course as a pre-
requisite to obtaining or confirming their registration.
The certificate of registration shall contain the following
information>
(a) the name, surname and identity document number or
other means of identification of the consultant<
(b) the date when the certificate is issued<
(c) the discipline or disciplines in which the consultant is
considered by the Registration and Review Board as having an
acceptable level of expertise.
(1) The Registration and Review Board may cancel any Cancellation of
certificate.
certificate granted under the provisions of this Part of these regulations
when the holder of that certificate>
(a) is found guilty by a court of criminal jurisdiction of a
crime being a crime committed through imprudence, carelessness,
unskillfulness in an art or profession, or non-observance of
regulations< or
(b) is found guilty by a court of criminal jurisdiction of any
offence under the provisions of the Act or of any regulations made
thereunder< or
(c) has, in the opinion of the Authority and the Registration
and Review Board, submitted substandard or deliberately
misleading work in an environmental impact assessment< or
(d) has participated in the preparation of an environmental
impact assessment when he was not registered in the Register< or
(e) was the recipient of a certificate issued under the
provisions of this Part of these regulations based on information
given by the applicant which is false or misleading< or
(f)
fails to pay the yearly renewal fee.
(2) Notwithstanding the provisions of sub-regulation (1) of
this regulation, the registration Board may opt for suspension, rather
than cancellation of the certificate, in the circumstances specified in
paragraphs (d) and (f) of sub-regulation (1) of this regulation.
(3) If a person participates in the preparation of an
environmental impact assessment without being registered in the
Register, he shall subsequently be barred from registering or participating
in any environmental impact assessments in Malta for a period to be
decided by the Registration and Review Board which period shall in no
case be less than three years.
(1) Any person who for the purposes of obtaining the Offences.
certificate for registration in the Register gives any wrong information
or otherwise acts in a deceitful or fraudulent manner shall be guilty of
an offence and shall, on conviction, be liable to a fine (multa) not
exceeding one thousand liri.
(2) Any person who, not being the holder of a certificate,
assumes or uses the designation “Environmental Impact Assessment
Consultant”, “Environmental Impact Assessment Co-ordinator”, “Senior
Impact Assessor” or “Junior Impact Assessor” or in any manner indicates
that he is entitled to prepare an environmental impact assessment shall
be guilty of an offence and shall, on conviction, be liable to a fine (multa)
not exceeding five hundred liri and in respect of a second or subsequent
offence to a fine (multa) not exceeding one thousand liri.
(3) For the purposes of sub-regulation (2) of these
regulations, the use on any card, letterhead, sign, board, plate,
advertisement or other written, printed or engraved device, instrument
or document, of the words “Environmental Impact Assessment
Consultant”, “Environmental Impact Assessment Co-ordinator”, “Senior
Impact Assessor” or “Junior Impact Assessor”, in relation to a name,
shall be sufficient evidence of the knowledge of such use by the person
in relation to whose name the said words are used, unless such person
proves that the use of such words was made without his knowledge and
that upon becoming aware of the use he took adequate steps to stop it.
(4) The offences and penalties mentioned in this regulation
shall be without prejudice to any other offences and penalties in terms
of the Act or any other law.
For the purposes of this Part of these regulations “person”
includes a person who is not a citizen of Malta but does not include a
body of persons.
PART VII
ENFORCEMENT
(1) When development permission has been granted by the
Authority for a development which had been subjected to an
environmental impact assessment under these regulations, the Authority
shall monitor the implementation of the said development both during
the construction and the operational phases.
(2) The Authority may>
(a) include appropriate, and clearly specified conditions in
the development permission<
(b) establish the period within which the construction phase
of the development shall be completed together with any planning
obligations, conditions or penalties which it may deem fit to impose
for non-completion or unsatisfactory completion of the
development and associated facilities within the established period<
(c) request the applicant to provide a guarantee by a bank
or credit institution licensed in Malta according to the provisions
of the Banking Act, or any other law which may from time to time Cap. 371.
replace it, by which the said bank or institution shall bind itself on
behalf of the applicant, without prejudice to any future action or
remedy which such bank or institution may exercise against him,
to effect payment to the Authority of any sum to be established by
way of penalty in the development permission if the development
is not completed in accordance with the specified conditions within
the period established in the development permission and for any
breach of any condition imposed in the development permission
or of any planning obligation entered into by the applicant. The
said guarantee shall not be less than the greater of the cost of
reinstating the area to an acceptable condition, or the cost of re-
instatement and repair of damages arising from non-compliance
with conditions imposed in the development permission<
(d) in the event that after a development permission is issued
the development is not carried out in accordance with the
permission, or is otherwise causing damage to the environment or
to the infrastructure, demand, as a condition of the continuance of
the permission, that the person in whose favour the permission is
issued should provide a bond in favour of the Authority in order to
guarantee payment in respect of damages which may be caused to
the environment or to the infrastructure, in terms of subarticle (5)
of article 34 of the Act<
(e) request that the person or company responsible for the
development is covered with an insurance policy against damage
to environmental resources< and
(f) make available to the public at such intervals as the
Authority deems proper the results of monitoring carried out
throughout the construction or operation phase of the project,
whether such monitoring has been carried out by the Authority
itself or by the developer as a direct result of a condition in the
development permission.
PART VIII
MISCELLANEOUS PROVISIONS
(1) For the avoidance of doubt, it is hereby declared that>
(a) when the Director of Planning or the Director of
Environment Protection requests the applicant, his architect,
agent or the consultants to make certain changes in the project
design,
(b) when the Director of Planning or the Director of
Environment Protection gives any guidance which he may deem
fit in the circumstances,
this does not imply in any way that the Director of Planning or the
Director of Environment Protection is approving the development or
will recommend to the Authority that it should approve the development.
(2) Agreement on the terms of reference for the preparation
of> baseline studies, the formulation of a project description statement,
an environmental impact statement or an environmental planning
statement is not to be construed in any way as evidence in favour of the
proposed development.
(3) In arriving at a decision, the Authority shall not be bound
by the conclusions reached in an environmental impact statement or an
environmental planning statement, as the case may be. However, the
Authority shall give due regard to the conclusions reached in the
environmental impact statement or in the environmental planning
statement, as the case may be, when arriving at a decision. Whether it
accepts or does not accept the conclusions reached by the said impact
statement or planning statement, as the case may be, the Authority shall
give detailed reasons thereof.
(4) Where, after environmental information has been taken
into consideration, an application for development which has been
subjected to an environmental impact assessment under these regulations
is determined by the Authority, the Authority shall>
(a) inform the public of the decision, by publishing a notice
in a newspaper, or by such other means as are reasonable in the
circumstances< and
(b) make available for public inspection, at all reasonable
hours and free of charge, a statement containing>
(i) the content of the decision and any conditions
attached thereto<
(ii) a statement containing the main reasons and
considerations on which the decision is based, including
information about the public participation process< and
(iii) a description, where necessary, of the main
measures to avoid, reduce, and if possible, offset the major
adverse effects of the development.
(5) The provisions of these regulations shall not affect the
obligation of the Government of Malta to respect the limitations imposed
by any law in force in Malta with regard to commercial and industrial
confidentiality, including intellectual property, and the safeguarding of
the public interest.
(1) If an applicant considers that the terms of reference, Review.
approved by the Director of Environment Protection under the provisions
of regulations 10 and 33, is unreasonable, he may request the Director
of Environment Protection to review such terms of reference. A request
for a review shall be made in writing within fifteen (15) days from the
date of communication of the said terms of reference to the applicant.
(2) The Director of Environment Protection shall, without
delay, consider the request made by the applicant and communicate the
final terms of reference as the case may be, within thirty (30) days from
receipt of the request for reconsideration. The Director of Environment
Protection shall give a reasoned justification for his decision#s relating
to the request for review.
(3) If the applicant considers the final terms of reference,
communicated to him in accordance with sub-regulation (2) of this
regulation, as unreasonable, he may request the Registration and Review
Board to review the said terms of reference. A request for a review
shall be made in writing within fifteen (15) days from the date of
communication of the said terms of reference review decision by the
Director of Environment Protection to the applicant.
(4) The Registration and Review Board shall, without delay,
consider the request made by the applicant and invite submissions from
the Director of Environment Protection. The Board may at its discretion
inform any such persons he deems proper. The decision of the
Registration and Review Board shall be final, and shall be communicated
to the applicant within thirty (30) days from receipt of the request for
review.
(5) Any time period set out under any provision of these
regulations or the Act shall be suspended until a decision under this
regulation is communicated to the applicant.
(6) The provisions relating to the publication and
communication of the terms of reference under regulations 10 and 33
shall apply mutatis mutandis to the decision of the Director of
Environment Protection or Registration and Review Board taken in
accordance with sub-regulations (2) and (4) of this regulation.
PART IX
TRANSITORY PROVISION
Any application for development permission which concerns
any development listed in Schedule IA to these regulations pending on
the date of coming into force of these regulations shall be regulated
according to the provisions of these regulations provided that>
(a) any environmental impact assessment carried out or in
the process of being carried out by consultants who are not
registered in the Register shall be deemed to have been made in
accordance with the provisions of those regulations regulating the
registration of consultants in the Register<
(b) participation by any person in an environmental impact
assessment prior to the coming into force of these regulations shall
not be deemed to constitute an automatic acceptance of an
application made by such person for registration in the Register<
and
(c) environmental impact statements or environmental
planning statements the terms of reference whereof have already
been communicated to the applicant prior to the entry into force of
these regulations shall, as far as possible, comply with the
provisions of these regulations unless the Director of Environment
Protection specifically exempts in writing the applicant from any
provisions of these regulations with regards to a particular
development and this may be done after the Director of
Environment Protection would have taken into consideration the
advanced stage arrived at in the environmental impact statement
or environmental planning statement, as the case may be.
(d) until such time as the regulations under Part VI of these
regulations are brought into force, the Director of Environment
Protection shall approve the participation of consultants and
contributors in the environmental impact assessment process.
(1) The Environment Impact Assessment Regulations, 2001 Repeal and saving.
L.N. 204 of 2001.
are hereby repealed.
(2) The repeal of the Environment Impact Assessment
Regulations, 2001, shall be without prejudice to anything done or omitted
to be done under the said regulations and in particular shall not affect
the validity of any environmental impact statement or environment
planning statement made under the said regulations.
Mitbug[ fl-Istamperija tal-Gvern — Printed at the Government Printing Press