Att dwar l-Ambjent u l-Ippjanar tal-Iżvilupp<BR><I>Il-leġiżlazzjoni sussidjarja kollha ġiet trasposta għal Kap.549 jew Kap.552 rispettivament <BR><I> Parzjalment fis-seħħ
Table of Provisions (106)
Statutory Text (106 Articles)
The short title of this Act is the Environment and
Development Planning Act.
Amended by
L.N. 57 of 2011.
Article 6
Provisions with respect to the Authority and the Environment
and Planning Commission
1. The provisions of this schedule regulate the procedures to be used by the
Authority and the Environment and Planning Commission. For the purposes of this
Schedule, wherever the word "Authority" is used, it is to be construed as to include
the Environment and Planning Commission, unless the context otherwise requires.
2. The Authority may act notwithstanding any vacancy amongst its members,
provided there is a quorum present at the meeting.
3. The quorum of the Authority shall consist of the chairman or deputy
chairman and not less than half the number of the other members constituting the
Authority at the time of the meeting.
4. The meetings of the Authority shall be called by the chairman either on his
own initiative or at the request of any two members of the Authority; and the
Authority shall also meet at such times as it may itself decide.
5. The chairman, or the deputy chairman acting in his place, shall have an
original vote, and where the votes are equally divided, a second or casting vote. All
members of the Authority present at its meetings shall cast their vote in favour or
against any motion put to the vote.
6. Without prejudice to the provisions of article 16, a member of the Authority
who has a direct or indirect interest in any matter coming before the Authority for
consideration shall, not later than the first meeting held after the relevant
circumstances have come to his knowledge, disclose the nature of his interest. Such
disclosure shall be recorded in the minutes of the meeting and the member
(a) shall not take part in any discussion or decision of the Authority with
respect to that matter; and
(b) shall be disregarded for the purpose of constituting a quorum for any
such discussion or decision.
7. All acts done by any person in good faith as a member of the Authority shall
be valid and effective as if he were a member even if some defect in his qualification
for appointment is subsequently discovered.
8. Subject to the provisions of this Act, including this Schedule, the Authority
may regulate its own procedure.
9. The meetings of the Authority shall be open to the public, and the Authority
shall allow the applicant and his representative, or any one of them, and an interested
third party who made representations in accordance with the provisions of article
68(4), to make submissions on any matter under consideration. The Chairman, at his
absolute discretion, may also allow any other member of the public to make
submissions, subject to the power of the Chairman to exclude any member of the
public if it deems it necessary so to do for the maintenance of order and to limit the
participation of the applicant and his representative or of the interested third party
who made representations in accordance with the provisions of article 68(4) or the
public as it may deem appropriate.
10. At the request of any member of the Authority, the deliberations of the
Authority shall be held in private but every vote shall be conducted in public. No
ENVIRONMENT AND DEVELOPMENT PLANNING
secret vote shall be allowed. Where the Authority votes against a recommendation, if
any, made by the Director, the Chairman of the Authority shall register in the
relevant file the specific environmental and planning reasons adduced by the
Authority.
11. The Authority shall decide and determine any matter under its consideration
during the first sitting at which such a matter is brought for determination. The
Authority may request the applicant to file fresh plans and documents, in which case
the Authority shall give reasons for such a request provided that the substance of the
matter under its consideration shall not change and any person who has made written
submissions on the application in terms of article 68(4) shall be informed that such
fresh plans and documents have been so filed and shall also be invited to be present
at the Authority’s sitting, as the case may be, when such application shall be
discussed. When the Authority puts off a decision on an application either when the
applicant is required to submit fresh plans and documents, or for the furnishing of
further information, in which case the Authority shall give reasons for requiring such
further information, or when the Authority needs to consult in terms of article 45 in
which case the Authority shall give reasons for requiring such consultation, the
Authority shall, during the meeting establish the date for the next sitting for the
determination of the application, such date being not later than thirty days from the
date of the last meeting
Provided that the Authority may also delegate to the Chairman or any of its
members, the power to endorse any revised plans or documents relating to any
matter under its consideration.
In this Act, unless the context otherwise requires
"advertisement" means any word, letter, model, sign, placard,
board, notice, device or representation, whether illuminated or not,
in the nature of and employed wholly or in part for the purposes of
advertisement, announcement or direction, including any boarding
or similar structure used or adapted for use for the display of
advertisements;
"agency of Government" means a body corporate established by
law and a company in which the Government or such body
corporate, or a combination thereof has a controlling interest or
which is a subsidiary of such a company;
"application" means a permission or licence application;
"application report" means the final permission or licence
application report;
"the Authority" means the Malta Environment and Planning
Authority established under article 6 and includes any body or
other person acting on its behalf under powers delegated by the
Authority under this Act, and the Minister may, by order in the
Gazette, designate different bodies or persons as a competent
authority for different provisions and different purposes of this Act
or any regulations made thereunder;
"biological diversity" or "biodiversity" means the variability
*See article 1(2) of the Act, as originally enacted, and Legal Notice 511 of 2010.
†See article 1(2) of the Act, as originally enacted, and Legal Notice 511 of 2010.
‡See article 1(2) of the Act, as originally enacted, and Legal Notice 91 of 2011.
§See article 1(2) of the Act, as originally enacted, and Legal Notice 78 of 2012.
**See article 1(2) of the Act, as originally enacted, and Legal Notice 112 of 2014.
ENVIRONMENT AND DEVELOPMENT PLANNING
among living organisms from all sources, including inter alia,
terrestrial, marine and other aquatic ecosystems and the ecological
complexes of which they are part, and includes diversity within
species, between species and of ecosystems;
"building" includes any structure or erection and any part of a
building, but does not include plant or machinery comprised in a
building;
"building or work" includes waste materials, refuse and other
matters deposited on land;
"building operations" includes rebuilding operations, structural
alterations of or additions to buildings, and other operations
normally undertaken by a person carrying on business as a builder;
"the Chairman of the Board" means the Chairman of the
Authority appointed in terms of article 6;
"the Chief Executive Officer" means the officer appointed under
the provisions of article 13;
"conservation" in relation to environment protection means a
series of measures required to maintain or restore the natural
habitats and the population of species of wild fauna and flora at a
favourable status and for cultural heritage means any activity
required to maximize the endurance or minimize the deterioration
of any cultural property as far as possible and includes examining,
testing, treating, recording and preserving any such cultural
property or any part thereof;
"the Commission" means the Environment Planning Commission
established under article 35;
"derivatives" means parts of any specimen, whether processed by
man or not;
"development permission" means a permission to carry out
development granted by the Authority either on an application in
that behalf or in a development order;
"discharge" includes emission, deposit, dumping, disposal,
addition or introduction into the environment of a substance or
energy, directly or indirectly from any point source or diffuse
source, whether stationary or mobile, and whether caused or
permitted intentionally or otherwise and whether continuous or
intermittent or once only;
"energy" includes all types of radiation forming part of the
electromagnetic energy spectrum, or resulting from a nuclear
source, as well as all vibrations and noise;
"engineering operations" includes any physical changes to the
land surface to the site topography, or the formation or laying out
of roads and of means of access to roads;
"environment" means the whole of the elements and conditions,
natural or man made, existing on earth, whether together or in
isolation, and in particular
(a) the air, water and land;
ENVIRONMENT AND DEVELOPMENT PLANNING
(b) all the layers of the atmosphere;
(c) all organic and inorganic matter and all living
organisms;
(d) all ecosystems; and
(e) the landscape;
"erection" in relation to buildings, includes extension, alteration
and re-erection;
"fauna" means all types of animals and other biota including
akaryotes, prokaryotes and eukaryotes, dead or alive, in whole or in
part and their derivatives;
"flora" means all types of plants and other biota including
akaryotes, prokaryotes and eukaryotes, dead or alive, in whole or in
part and their derivatives;
"functions" includes responsibilities, powers and duties;
"genetically modified organism" means any of the following
(a) an organism derived from the formation of a
combination of genetic material by any means other
than natural means;
(b) an organism inheriting such combination of genetic
material;
(c) an organism that results from the replication of an
organism as derived in paragraph (a); or
(d) such other organism as may be prescribed by the
Minister under this Act;
"land" includes a building;
"local council" means a local council established under the Local
Government Act;
"minerals" includes all minerals and substances (including oil
and natural gas) in or under land of a kind ordinarily worked for
removal by underground or surface working;
"the Minister" means the Minister responsible for the
environment;
"natural resources" means any component of nature and includes
air, water, land, soils, minerals, energy, living organisms and
genetic resources;
"owner" means -
(a) a person who in his own right or as agent for another is
entitled to receive the rent of the land or, where the
land is not let, would be so entitled if it were let;
(b) where the land is subject to usufruct, bare owner or
usufructuary;
(c) an emphyteuta;
(d) any one of the spouses, where the land to which the
development relates forms part of the community of
acquests;
ENVIRONMENT AND DEVELOPMENT PLANNING
"plan" means a plan approved in accordance with the provisions
of the Act;
"policy" means a policy approved in accordance with the
provisions of the Act;
"pollution" means the direct or indirect introduction by man, or
due to natural processes, into the environment of substances,
organism, genetic material or energy that cause or are likely to
cause hazard to human health, harm to living resources or to
ecosystems, or damage to amenities, or interfere with other
legitimate uses of the environment;
"position statement" means a statement issued by either the
Minister or the Authority in order to provide a detailed technical
explanation justifying a position with respect to a specific planning
issue;
"precautionary principle" means the principle whereby
appropriate measures are taken to protect the environment and to
ensure sustainable management of natural resources in the absence
of absolute or conclusive scientific proof of the need for such
measures;
"prescribed" means prescribed by regulation, rule, order or other
instrument made as provided in the provisions of this Act
empowering the making of any such instrument;
"project of common interest" means a project necessary to
implement the energy infrastructure priority corridors and areas set
out in Annex I of Regulation (EU) No 347/2013 and which is part
of the Union list of projects of common interest referred to in
Article 3 of the said Regulation (EU) No 347/2013;
"public officer" has the meaning assigned to it by article 124 of
the Constitution;
"road" means any highway or road, whether public or private,
and includes any street, square, court, alley, lane, bridge, footway,
passage or quay, whether thoroughfare or not;
"scheduled buildings" has the meaning assigned to it by article
81;
"specimen" means any species, whether alive or dead, any part or
derivative thereof, and includes any goods which from an
accompanying document, the packaging, mark or label or from
other circumstances appear to be parts or derivatives of animals or
plants;
"Standing Committee" means the Standing Committee on
Environment and Development Planning established in terms of
article 34;
"subsidiary plans" includes subject plans, local plans, action
plans or management plans;
"substances" means any matter, chemical, mixture, compound or
product and including fuels, combinations of elements, mixtures or
compounds of a chemical reaction, as well as the mixture of
substances of different molecular identities;
ENVIRONMENT AND DEVELOPMENT PLANNING
"Temporary Provisions Schemes" means a planning scheme
prepared and approved in accordance with the Building Permits
(Temporary Provisions) Act * ;
"Tribunal" means the Environment and Planning Review
Tribunal established under the provisions of article 40 of the Act;
"use", in relation to land, does not include the use of land by the
carrying out of any building, engineering, mining or other
operations thereon;
"waste" means any thing, substance or object which the holder
discards or intends to discard, or is required to keep in order to
discard, and includes such other thing, substance or object as the
Minister may prescribe.
Amended by
L.N. 223 of 2014;
Article 41
L.N. 404 of 2014;
L.N. 470 of 2014.
Proceedings before the Environment and Planning Review Tribunal
and appeals therefrom
1. (a) The application shall contain the grounds for the appeal and the request
of the appellant, and, in the case of an appeal from the refusal of a
permission or licence, it should include a copy of the application form
and documents and plans submitted for approval together with all
documentation which is relevant for the grounds of appeal, including a
copy of the Authority’s decision appealed from.
(b) The time period when an appeal can be lodged before the Tribunal as
established in this Act shall be suspended only during such period when
the Tribunal’s administrative secretariat’s offices are closed between the
23rd December of any year and the 1st January of the following day,
both days included.
(c) A copy of the appeal and the ancillary documentation shall be
communicated to the Authority before the appeal is heard. The
Authority shall file its reply within thirty days of service upon it or
within such time as established by the Tribunal. The reply shall be
served upon the appellant.
2. The appellant shall appear before the Tribunal either in person or by agent
ENVIRONMENT AND DEVELOPMENT PLANNING
on the day and at the time fixed for the hearing, make his submissions and produce
such evidence as the Tribunal may allow
Provided that the Tribunal may postpone the hearing of the appeal if it is
satisfied that the appellant was prevented from appearing before it owing to illness
or absence from Malta or other similar reasonable cause.
3. The Tribunal shall give the Authority an opportunity to make its
submissions in justification of its decisions, and bring such evidence as the Tribunal
may consider necessary.
4. The Tribunal shall have the power to summon witnesses and to administer
the oath to any person appearing before it. Should a witness duly notified by a
summons signed by the Chairman of the Tribunal fail to enter an appearance before
the Tribunal, such person shall be guilty of an offence and liable, on conviction, to a
fine (multa) of not less than five hundred euro and not more than five thousand euro.
5. The Tribunal shall have power to confirm, revoke or alter the decision
appealed against and give such directions as it may deem appropriate
Provided that the Tribunal may request the appellant to submit fresh
documents and plans, in which case the Tribunal shall give reasons for such a
request provided that the substance of the matter as presented before the Authority
shall not change.
6. The decisions of the Tribunal shall be final and no appeal shall lie therefrom
except on a question of law only.
7. If the appellant or the Authority are dissatisfied with any point of law
decided by the Tribunal, they may appeal to the Court of Appeal (Inferior
Jurisdiction) by an application filed as provided in article 41.
8. All hearings of the Tribunal shall be held in public and all decisions of the
Tribunal shall be given in public.
9. Subject to the foregoing provisions and to the provisions of this Act, the
Tribunal shall regulate its own procedure.
10. The Minister responsible for justice may by regulations made under this
Schedule establish fees payable in the registry of the courts in relation to the filing
of judicial acts in connection with appeals before the Court of Appeal (Inferior
Jurisdiction) under this Act
Provided that until such fees have been so established by the Minister, the
fees contained in Schedule A to the Code of Organization and Civil Procedure shall
apply.
11. A registered third party in terms of article 68(4) of this Act shall be
informed by the Tribunal that an appeal has been filed and he may request the
Secretary of the Tribunal to register him as an interested third party in such an
appeal. Such a person shall have a right to address the Tribunal and may be
requested by the Authority or Commission to give evidence in the appeal
proceedings concerning the said appeal. Unless the Tribunal decides otherwise, such
a person may be present during all sittings of the Tribunal. Such a person may not
attend site inspections where the Tribunal enters upon the property of the appellant if
the appellant objects to the presence of such a person entering upon his property.
Such a person shall have a right to be given a copy of the Tribunal’s decision with
regard to those appeal proceedings for which he has been registered with the
Secretary of the Tribunal as interested third party. Such a person may file an appeal
from a decision of the Tribunal before the Court of Appeal (Inferior Jurisdiction).
ENVIRONMENT AND DEVELOPMENT PLANNING
12. When an appeal has been lodged by a person other than the applicant, such a
person need not prove that he has an interest in that appeal in terms of the doctrine of
juridical interest which doctrine shall not apply to such proceedings, but he shall
submit reasoned grounds based on environmental and, or planning considerations to
justify his appeal.
13. The Tribunal may deem an appeal as abandoned if the appellant shows no
interest in the appeal submitted by him.
14. The Tribunal may impose a fine of €2,500 in such cases were it declares
such proceedings frivolous or vexations and in such cases the Tribunal’s decision
shall be final without any redress before the Court of Appeal (Inferior Jurisdiction).
15. The Tribunal may impose such fees on the party making the request as
established for the carrying out of site inspections. Should the Tribunal decide to
hold such inspection at its own motion, it will be the appellant who will incur the
fee.
16. The Authority shall ensure that detailed information is made available to the
public concerning access provided for under this Act to appeal procedures before the
Tribunal and before the Court of Appeal, including information on the rights of any
person to institute appeal proceedings, and shall give information on legal time
limits and on mandatory fees payable in respect of such proceedings, including
through publication on the electronic website of the Authority.
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
Article 12
(Repealed by Legal Notice 107 of 2016, made under article 87 of Act I of 2016 and
article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
Article 34
(Repealed by Legal Notice 107 of 2016, made under article 87 of Act I of 2016 and
article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
Article 42
The Registration Board
Consultants to carry out the following assessments have to be registered with the
Board
1. Environmental Impact Assessments;
2. Appropriate Assessments in relation to sites falling within a Special
Area of Conservation or a Special Protected Area;
ENVIRONMENT AND DEVELOPMENT PLANNING
3. Strategic Environment Assessments;
4. Assessments in relation to Scheduled property and sites.
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
Article 70
Applications which fall under the provisions of article 70
1. An application to regularise a development which exceeds the approved
footprint or, increases the approved volume of the building and is not part of a
registered livestock farm and is carried out after May 2008 in an area which falls
outside areas designated for development as defined in the Structure Plan or in any
other plan; or
2. An application to regularise a development in a scheduled property; or
3. An application to regularise a development carried out after May 2008 in an
area protected under the provisions of this Act or any regulation made thereunder.
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
Articles 41 and 69
1. Applications which fall under the provisions of articles 41 and 69
(a) Development in an area which falls outside areas designated for
development as defined in the Structure Plan or in any other plan; or
(b) Development in a scheduled property grade 1 or grade 2; or
(c) Development in a property containing archeological remains; or
(d) In the case of demolition within Urban Conservation Area which
includes demolition of facade; or
(e) Development in an area protected under the provisions of this Act or
any regulation made thereunder.
2. Subparagraphs (b), (d) and (e) of paragraph (1) shall also apply in such
cases where the protection status of the site is still being proposed.
ENVIRONMENT AND DEVELOPMENT PLANNING
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
Amended by
L.N. 229 of 2012;
Article 91
L.N. 52 of 2013;
L.N. 121 of 2013.
Category A
1. Development carried out prior to 1st January, 1993 within a Temporary
Provisions Scheme development boundary or a development boundary as indicated
in a local plan other than
(i)
when such development consists in change of use; or
(ii)
where such development is not in conformity with the alignment of
roads or buildings as specified in or interpreted from a Temporary
Provisions Scheme or local plan.
Category B
1. These provisions shall apply to development in existence on the coming into
force of these regulations and shall include the following
(i)
Size of internal yards
(a) if the length of any side of the internal yard is up to 65% of that
required by law and the overall area of the yard is more than 65%
of what it should have otherwise been;
(b) if the length of any side of the internal yard is between 50% and
65% of that required by law and the overall area of the yard is
within the same range, subject to an engineer’s report stating that
the habitable rooms in the premises have adequate lighting and
ventilation aided, if necessary, but not exclusively limited to
artificial lighting and forced mechanical ventilation respectively;
(c) premises which have internal yards that are less than half the size
of what they should have otherwise been are not included
Provided that the provisions of sub-category (i) shall be applicable to
dwellings in all areas and to premises within development zones limited
to Class 2, Class 3, Class 4, Class 5, Class 6, Class 7, Class 8, Class 9,
Class 10 of which class the term "commercial premises" applies only to
"schools", Class 17, as well as the uses listed in article 4(b), (d), (e),
(m), (n) and (p) of the Development Planning (Use Classes) Order
(S.L.552.15).
(ii) Size of back yard
(a) if the depth of any back yard is up to 65% of that required by law
and the overall area of the yard is more than 65% of what it
should have otherwise been;
(b) if the depth of any back yard is between 50% and 65% of that
required by law and the overall area of the yard is within the same
range, subject to an engineer’s report stating that the habitable
rooms in the premises have adequate lighting and ventilation;
(c) premises which have a back yard less than half the size of what it
should have otherwise been are not included
Provided that the provisions of sub-category (ii) shall not be applicable to
backyards where the remaining distance from the back party wall is less
than 1.5 metres at any point, except where requests in terms of the
Environment and Development Planning Act, Article 91 Eighth Schedule
ENVIRONMENT AND DEVELOPMENT PLANNING
Category B relating to any level of the backyard was submitted prior to
29th January 2013
Provided also that the provisions of sub-category (ii) shall be applicable
to dwellings within areas zoned for terraced development within the
development zone and to premises within development zones limited to
Class 2, Class 3, Class 4, Class 5, Class 7, Class 8, Class 10 of which
class the term "commercial premises" applies only to "schools", Class
17, as well as the uses listed in article 4(d), (e), (m), (n) and (p) of the
Development Planning (Use Classes) Order (S.L.552.15)
Provided further that the provisions of sub-category (ii) shall also be
applicable to residences in Category 1 and Category 2 Rural Settlements
ODZ, and to residences in areas zoned for villa and bungalow
developments as long as the statutory site coverage is not being
exceeded or conforms with sub-category (viii)(a) and as long as the side
curtilage is not being encroached upon in excess of that covered by sub-
category (vi)(a).
(iii) Internal height of structures
(a) premises with a clear floor to ceiling internal height of more than
2.6 metres;
(b) premises with a clear floor to ceiling height of less than 2.6
metres but more than 2.4 metres subject to an engineer’s report
stating that the habitable rooms in the premises have adequate
lighting and ventilation;
(c) premises with a clear floor to ceiling height which is less than 2.4
metres are not included
Provided that the provisions of sub-category (iii) shall be applicable to
dwellings in all areas and to premises within development zones but
limited to Class 2, Class 3, Class 4, Class 5, Class 6, Class 7, Class 8,
Class 9, Class 10 of which class the term "commercial premises" applies
only to "schools", Class 17, as well as the uses listed in article 4(d), (e),
(m), (n) and (p) of the Development Planning (Use Classes) Order
(S.L.552.15).
(iv) Room in back yards
Rooms at the ground floor level or at the floor level immediately above
garage or shop levels of any premises, provided that the room has
natural ventilation and natural lighting, as long as the cumulative area
of the room and any reduction in size of the backyard does not exceed
35% of the required back yard area, and provided that the external
height of the room including any opramorta is not higher than 3.4
metres above the finished floor level of the backyard
Provided that the provisions of sub-category (iv) shall be applicable to
dwellings within areas zoned for terraced development within the
development zone and to premises within development zones limited to
Class 2, Class 3, Class 4, Class 5, Class 7, Class 8, Class 10 of which
class the term "commercial premises" applies only to "schools", Class
17, as well as the uses listed in article 4(d), (e), (m), (n) and (p) of the
Development Planning (Use Classes) Order (S.L.552.15)
Provided further that the provisions of sub-category (iv) shall also be
applicable to residences in Category 1 and Category 2 Rural Settlements
ODZ, and to residences in areas zoned for villa and bungalow
ENVIRONMENT AND DEVELOPMENT PLANNING
developments as long as the statutory site coverage is not being
exceeded or conforms with sub-category (viii)(a) and as long as the site
curtilage is not being encroached upon in excess of that covered by sub-
category (vi)(a).
(v) Encroachments beyond property
(a) ramps or steps which do not protrude more than 30 centimetres
beyond the official alignment onto the pavement as long as the
pavement width of 1.2 metres is retained. This is not applicable in
respect of areas schemed with front garden;
(b) pilasters whose height does not exceed 1.4 metres, which are not
wider than 50 centimetres and which do not protrude more than
30 centimetres beyond the official alignment
Provided that the provisions of sub-category (v) shall only be applicable
to
(i) residential development within the development zone;
(ii) Class 4 shops within the development zone (with < 75m 2 usable
retail floor-space and with no commercial freezers on site);
(iii) Class 5 offices within the development zone (with < 75m 2 usable
office floor-space and at ground floor level);
(iv) Social, Community, Educational, Governmental and Religious
facilities within the development zone;
(v) areas zoned for Industry or Warehousing; and
(vi) above-mentioned uses located in Category 1 Rural Settlements
ODZ
Provided further that the development identified in this sub-category
shall be removed at the request of any public authority, including the
Local Council, and nothing contained in the provisions of this Act
including this Schedule may prejudice such a request.
(vi) Encroachments within property
(a) where the facades proper of the buildings themselves, excluding
enclosures, porches, and any other structures whose height
exceeds 1.25 metres, encroach within the first 1/3 of front
gardens, and not more than 25 centimetres within villa or
bungalow side gardens;
(b) structures in front and side gardens and roof setbacks whose height
does not exceed 1.25 metres above floor level externally and which
are cumulatively not larger than 10m 2 in each of these spaces;
(c) where the setbacks of permitted roof structures on residences are
reduced to not less than 4 metres from the underlying building
elevations; and
(d) where the setbacks of permitted garages in the side curtilage of
schemed villa or bungalow development are reduced to not less
than 4 metres from the building alignment
Provided that the provisions of sub-category (vi) shall only be
applicable to
(i) residential development within the development zone;
(ii) Class 4 shops within the development zone (with < 75m 2 usable
retail floor-space and with no commercial freezers on site);
ENVIRONMENT AND DEVELOPMENT PLANNING
(iii) Class 5 offices within the development zone (with < 75m 2 usable
office floor-space and at ground floor level);
(iv) above mentioned uses located in Category 1 Rural Settlements
ODZ.
(vii) Creation of additional residential units
In areas zoned for terraced residential development or for residential
developments in Category 1 Rural Settlements ODZ, the change of use of
permitted structures to residential development and, or the creation of
additional residential units by the sub-division of a permitted residential
unit into two or more, or by the creation of new residential unit/s
underlying existing permitted residential development without any excess
in footprint larger than 1m in any direction. This shall be applicable as long
as any room larger than 5.6m 2 in the unit has an aperture fronting on an
open space. Furthermore, this shall not be applicable to the creation of or
change of use to residential units situated at penthouse level if this involves
a change of use from washrooms, and to residential units at basement level
unless more than 50% of the façade area of the unit is above public road
level or in cases where the back elevation of the residence fronts on and
above an internal unroofed drive or larger open space that cannot be
developed or that has an open outlook overlooking diminishing terrain
levels. The change of use from a permitted residential unit (or part thereof)
to a private car garage
Provided that for cases of change of use of a permitted structure into a
residential unit, the provisions of sub-category (vii) shall only be applicable
if contractual or other valid proof is provided to the Authority’s satisfaction
to the effect that the change of use to a residence had already occurred by
the 29th January 2013
Provided also that for cases of sub-divisioning of a permitted residential
unit into two or more, the provisions of sub-category (vii) shall only be
applicable if contractual or other valid proof is provided to the
Authority’s satisfaction to the effect that by the 29th January 2013 the
subdivisioning had already occurred, AND
(i) that the present owner of the unit is not its original owner; OR
(ii) that if the present owner of the unit is still its original owner, the
provisions of sub-category (vii) shall only be applicable if the
original owner does not still own any unit adjacent to the unit
under consideration on the same floor such that these units can be
amalgamated into one larger unit
Provided further that the six-month grace period granted hereunder,
wherein an architect’s declaration is deemed to suffice for the purposes
of these provisions, shall not be applicable to this sub-category
Provided further that the limitations specified in the provisions of sub-
categories (i) and (ii) are not applicable to requests which include the
provisions of sub-category (vii).
(viii) Site area and coverage
(a) built site coverage not exceeding 15% of that permissible and as
long as any encroachment into front and side gardens and
backyards is not larger than that specified in the provisions of this
Schedule;
(b) inadequate plot or site area where the resultant plot area is not
ENVIRONMENT AND DEVELOPMENT PLANNING
less than 75% of the minimum permissible area and as long as the
provisions in paragraph (a) of this sub-category relating to both
coverage and setbacks are also respected
Provided that the provisions of sub-category (viii) shall only be
applicable to residential development in areas zoned for villa and
bungalow development.
(ix) Increase in height
An increase in the height of the overall building development, or parts
thereof (except in the height of any roof structure), as long as
(a) the overall height, including parapet wall, is not increased by
more than 1.25 metres from that approved in the development
permit;
(b) the increase in height does not involve additional floors;
(c) in the case of a ground floor garage in terraced development, the
garage is not roofed over in excess of 4.1 metres and the garage
door lintel does not exceed 3.3 metres; and
(d) the external garage height in the side curtilage of a schemed villa
and, or bungalow development or in an internal garage
development does not exceed 3.3 metres, including any
opramorta, and the garage door lintel does not exceed 2.8 metres
Provided that in paragraph (c) of this sub-category, the owner of an
overlying residence may also submit an application for the provisions of
these regulations to apply with respect to the underlying garage even if
such person is not the owner of the garage. In any such case the
applicant shall inform the owner of the garage
Provided further that the provisions of sub-category (ix) shall only be
applicable to
(i) residential development within the development zone;
(ii) Social, Community, Educational, Governmental and Religious
facilities within the development zone; and
(iii) areas zoned for Industry or Warehousing, in which areas the
limitations relating to door lintel heights aforementioned are not
applicable.
(x) External modifications
Excluding cases falling under sub-category (vi), external elevational
additions, modifications and alterations (including materials) existing
on the facades and, or on elevations fronting on public areas, except for
(a) the creation or enlargement of projecting rooms on road facades;
(b) balcony extensions exceeding 25 centimetres of that permitted in any
direction;
(c) porches;
(d) air-conditioning units and telecommunication equipment affixed
to facades;
(e) solid front or side garden walls which exceed 1.6 metres in
height
Provided that extensions to property in schemed villa or bungalow areas
are only applicable as per sub-category (viii). Any other extensions in
this sub-category are not applicable to footprints exceeding 10m 2 and,
ENVIRONMENT AND DEVELOPMENT PLANNING
when within statutory front or side gardens, not to encroach beyond the
limits set out in sub-category (vi)(a) and (d) as applicable
Provided further that the provisions of sub-category (x) shall only be
applicable to
(i) residential development within the development zone excluding
within UCAs;
(ii) Class 5 offices (with <75m 2 usable office floor-space and at ground
floor level) within the development zone excluding within UCAs and
Design Priority Areas;
(iii) for Class 4 shops, Class 5 offices, and residential development,
balcony extensions not exceeding 25 centimetres of that permitted in
any direction and solid front or side garden walls which do not
exceed 1.6 metres in height.
(xi) External modifications not visible from public roads
Excluding cases falling under sub-category (vi), external elevational
additions, modifications and alterations (including materials) for
elevations that are not fronting on public areas and that are not visible
from and conspicuous from public areas
Provided that extensions to property in schemed villa or bungalow areas
are only applicable as per sub-category (viii). Any other extensions in
this sub-category are not applicable to footprints exceeding 10m 2 and,
when within statutory front or side gardens, not to encroach beyond the
limits set out in sub-category (vi)(a) and (d) as applicable
Provided further that the provisions of sub-category (xi) shall only be
applicable to
(i) residential development within the development zone;
(ii) Class 4 shops within the development zone (with < 75m 2 usable
retail floor-space and with no commercial freezers on site);
(iii) Class 5 offices within the development zone (with < 75m 2 usable
office floor-space and at ground floor level);
(iv) Social, Community, Educational, Governmental and Religious
facilities within the development zone; and
(v) above-mentioned uses located in Category 1 Rural Settlements
ODZ.
(xii) Garage level modifications
Internal alterations and, or modifications to garage levels and to
circulation therein as long as no entries and, or exits are eliminated, the
development is in use, and in cases with more than one level of parking
insofar as the changes are confirmed by a Fire Safety Report and a
Transport Safety Report (covering manoeuvrability, exits, etc.) as not
affecting the safety of users and, or third parties. These provisions are
not applicable to major developments. Furthermore, these provisions
are also not applicable in cases where there is a difference in the number
of garage levels or in the amount of garages from what was approved in
the development permit
Provided that the provisions of sub-category (xii) shall only be
applicable where the overlying development is limited to
(i) residential development within the development zone;
ENVIRONMENT AND DEVELOPMENT PLANNING
(ii) Class 4 shops within the development zone (with < 75m 2 usable
retail floor-space and with no commercial freezers on site);
(iii) Class 5 offices within the development zone (with < 75m 2 usable
office floor-space and at ground floor level);
(iv) above-mentioned uses located in Category 1 Rural Settlements
ODZ,
or a mix of the above.
(xiii) Internal modifications
Internal planimetric alterations and, or modifications within units
Provided that these provisions shall only be applicable as long as these
alterations and, or modifications -
(i) are contained within the permitted built footprint;
(ii) do not give rise to additional units;
(iii) do not include a change of use;
(iv) do not run counter to permit conditions;
(v) do not run counter to sanitary requirements
Provided that the above limitations in items (i), (ii), (iii), (iv) and (v)
shall not be applicable if they are covered by other provisions in this
Schedule
Provided further that the provisions of sub-category (xiii) shall only be
applicable to
(i) residential development;
(ii) Class 4 shops (with < 75m 2 usable retail floor-space and with no
commercial freezers on site);
(iii) Class 5 offices (with < 75m 2 usable office floor-space and at
ground floor level);
(iv) Social, Community, Educational, Governmental and Religious
facilities; and
(v) Industry or Warehousing development.
Applicability.
2. The provisions of paragraph 1 shall apply subject to the following
(a) the provisions listed in paragraph 1 shall not apply to scheduled
buildings and to development that involved excavations within Areas of
Archaeological Importance;
(b) if a request, under the provisions of article 91 of the Act in respect of
developments in paragraph 1 in sub-categories (i), (ii), (iii) and (iv)
within residences within areas zoned for terraced development in the
development zone, is made to the Authority by the 31st January 2013, it
shall be presumed that the development to which the request refers to
existed prior to 1st August 2012 as long as the architect submitting the
request certifies that the development to which the request relates had
existed prior to 1st August 2012, and the same request includes
photographic evidence that shows the same development as existing on
site, and as long as there is no evidence to the contrary, or that no such
evidence to the contrary subsequently emerges
Provided that if such a request is not submitted by the 31st January
ENVIRONMENT AND DEVELOPMENT PLANNING
2013, the onus of proof that the development in question existed before
the 1st August 2012 lies with the applicant or his architect;
(c) if a request under the provisions of article 91 of the Act in respect of all
other of the developments in paragraph 1 that are not included in
paragraph (b) above, is made to the Authority by the 28th July 2013, it
shall be presumed that the development to which the request refers to
existed prior to 29th January 2013 as long as the architect submitting
the request certifies that the development to which the request relates
had existed prior to 29th January 2013, and the same request includes
photographic evidence that shows the same development as existing on
site, and as long as there is no evidence to the contrary, or that no such
evidence to the contrary subsequently emerges
Provided that if such a request is not submitted by the 28th July 2013,
the onus of proof that the development in question existed before the
29th January 2013 lies with the applicant or his architect.
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
((Repealed by Legal Notice 107 of 2016, made under
article 87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
*repealed by Act I of 1992.
ENVIRONMENT AND DEVELOPMENT PLANNING
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
The Authority may engage such consultants or advisers, as
it may consider necessary to assist it in the fulfilment of its
functions.
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
ENVIRONMENT AND DEVELOPMENT PLANNING
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(1) Subject to those articles which specifically exclude the
right to appeal before the Tribunal, and to articles 81(14), 82(4) and
86, the Tribunal shall have jurisdiction to
(a) hear and determine all appeals made by the applicant
or a person aggrieved by a notice issued under the
provisions of Part VI on any decision of the Authority
on any matter of development control, including the
enforcement of such control, or appeals made by any
person on any decision of the Authority relating to
environment protection, including environment
assessments, access to environmental information and
the prevention and remedying of environmental
damage
Provided that the Authority shall not be construed as
any person for the purposes of this paragraph;
(b) exercise such functions as are vested in it in terms of
Articles 48, 49, 57, 58, 63 and 77 and hear and
determine appeals made in terms of articles 42, 76, 77,
81, 91, 92 u 93 and such other functions assigned to it
under the provisions of this Act;
(c) hear and determine an appeal lodged by an interested
third party from a decision of the Authority on any
matter of development control, provided that
(i) such an appeal may only be made by an
interested third party who had submitted written
comments in terms of article 68(4) when the
application to carry out the development is
published,
(ii) no appeal shall lie by an interested third party
from any development control decision
concerning a development which is specifically
ENVIRONMENT AND DEVELOPMENT PLANNING
authorized in a development plan,
(iii) a local council in whose locality the
development is intended to be carried out shall
always be deemed for all intents and purposes of
law to be an interested third party provided that
the said council has complied with the
provisions of article 68(4) and it is acting in the
interests of the locality,
(iv) the Government and any department, agency,
authority or other body corporate wholly owned
by the Government shall always be deemed for
all intents and purposes of law to be an
interested third party
Provided that the Authority shall not be
construed as an interested third party for the
purposes of this sub-paragraph.
(2) Unless otherwise provided under any provision of this Act,
an appeal may be lodged before the Tribunal within thirty days
from date of notification of the decision or order by the Authority.
(3) The Tribunal may, at the request of the appellant made
concurrently with the application for the appeal, suspend through a
partial decision, in whole or in part, the execution of any
development or the operation of any installation, pending a
decision being delivered by the said Tribunal, under those terms,
conditions and other measures as it may deem fit
Provided that the application, with the exception of
applications relating to developments or installations which relate
to environmental impact assessment and, or integrated pollution
prevention and control (‘IPPC’) matters, is not for a development
which, in the opinion of the Minister is of strategic significance or
of national interest, related to any obligation ensuing from a
European Union act, affects national security or affects interests of
other governments.
(4) In the cases referred to in sub-article (3), the Tribunal shall
hold its first hearing be within six working days from receipt of the
appeal, and shall not suspend the execution of such a permit unless
it is satisfied, after hearing all the parties, that unless the execution
of the permit is suspended the prejudice that would be caused
would be disproportionate when compared with the actual doing of
the thing so permitted or if the request is deemed as frivolous or
vexatious
Provided that the Tribunal shall justify the decision
suspending the execution of the development and shall grant its
final decision on the merits of the appeal within three months from
the date of the first hearing of the appeal
Provided further that the suspension of the execution of
such a permit may not be more than three months from the date of
the first hearing of the Appeal before the Tribunal, and the
suspension order shall be deemed to have elapsed ipso iure after the
lapse of such a period.
ENVIRONMENT AND DEVELOPMENT PLANNING
(5) In all other appeals, the first hearing of the Tribunal shall
be held within three months from receipt of the appeal.
(6) The decisions of the Tribunal shall be final. An appeal by
the appellant or any of the appellate parties to the appeal shall lie to
the Court of Appeal constituted in terms of article 41(9) of the
Code of Organization and Civil Procedure from such decisions only
on points of law decided by the Tribunal in its decision. An appeal
from a partial decision of the Tribunal may only be filed together
with an appeal from the final decision of the Tribunal. An appeal to
the Court of Appeal (Inferior Jurisdiction) shall be submitted
within twenty days from when the decision of the Tribunal is
delivered in public and such an appeal shall be regulated by the
rules of court made under article 29 of the Code of Organization
and Civil Procedure.
(7) The decisions of the Tribunal shall be binding if they are
supported by the opinion of two of its members, and the dissenting
member, if any, may express his opinion separately; and all
decisions of the Tribunal shall be delivered in public and shall be
published as soon as practicable after the sitting at which they are
given.
(8) Where a hearing is held by the Tribunal, other than in those
cases referred to in sub-articles (3) and (4), advance notice of not
less than fourteen days shall be given of the first sitting of the
Tribunal to the parties, and those interested third parties who
registered their interest during the processing of the application
before the Authority, in such manner as the Tribunal may deem
appropriate or as may be provided in the Second Schedule
Provided that in cases of urgency the said time limit of
fourteen days may be abridged by order of the Tribunal if the
Tribunal is satisfied that the party requesting urgency has given a
valid reason in writing therefor.
(9) The sittings of the Tribunal shall be open to the public,
subject to the power of the Tribunal to exclude any member of the
public if it deems it necessary so to do for the maintenance of
order.
(10) The Tribunal may require any department or agency of the
Government to provide the Tribunal with such information or
a d v i c e a s t h e Tr i b u n a l m a y d e e m n e c e s s a r y f o r t h e p r o p e r
execution of its functions.
(11) Subject to the above and to article 74, appeals to the
Tribunal and the conduct of the business of the Tribunal shall be
made in accordance with the rules contained in the Second
Schedule; and in the absence of such rules on any matter, the
Tribunal may regulate its own procedure.
(12) Where judicial proceedings are instituted against the
Tribunal before a court of civil jurisdiction, the Secretary shall
represent the Tribunal in such proceedings; and, saving the
provisions of article 46 of the Constitution and article 4 of the
European Convention Act, no precautionary act may be issued
against the Tribunal by any court.
ENVIRONMENT AND DEVELOPMENT PLANNING
(13) The Tribunal, if it decides to grant a permission or licence
may impose a penalty, the payment of fees and contributions and
other conditions, which the Authority may impose when granting a
permission or licence; and the Tribunal shall ensure that it complies
with the provisions of article 69 in reviewing decisions of the
Authority.
(14) When the Tribunal modifies a decision taken by the
Authority and orders the issue of a permission or licence, or in any
other manner changes the decision of the Authority, the Authority
shall, unless an appeal has been lodged to the Court of Appeal
(Inferior Jurisdiction) from the Tribunal’s decision, issue the
permission or licence or comply with the decision of the Tribunal
within one month from the Tribunal’s decision, or, if in the
Tribunal’s decision a condition has been imposed or a penalty
inflicted, within one month from compliance by the appellant with
such condition or payment of such penalty inflicted by the Tribunal
in its decision.
(15) Appeal proceedings before the Tribunal pursuant to sub-
article (1) shall be conducted in a timely manner, without undue
delay, and shall not be prohibitively expensive.
(16) Appeal proceedings before the Court of Appeal pursuant to
sub-article (6) shall be concluded in a timely manner and shall not
be prohibitively expensive. Legal and judicial costs and fees in the
said proceedings shall be taxed in accordance with paragraph (7) of
item 3 of Tariff A and with paragraph (b) of item 15 Tariff E in
Schedule A to the Code of Organization and Civil Procedure.
(1) Members of the public concerned having sufficient
interest shall have access to a review procedure before the Tribunal
to challenge the substantive or procedural legality of any decision,
act or omission relating to a development or an installation which is
subject to an environmental impact assessment (‘EIA’) or an
integrated pollution prevention and control (‘IPPC’) permit.
(2) Such an appeal may be lodged before the Tribunal within
thirty days from the date of notification of the final decision by the
Authority
Provided that such an appeal may relate to or include an
objection to any act or omission committed at any time during the
process of the EIA or IPPC leading to the decision in question.
(3) For the purposes of sub-article (1), the interest of any non-
governmental organisation promoting environmental protection and
which is registered under the Voluntary Organisations Act shall be
deemed sufficient.
(4) The provisions of article 41 shall, mutatis mutandis, apply
to review procedures pursuant to this article.
(1) There shall be a Registration Board whose function
shall be to evaluate applications for registration in the Register of
Consultants eligible to carry out environment assessments and
other assessments.
(2)
The Board shall be composed of a minimum of three
ENVIRONMENT AND DEVELOPMENT PLANNING
members and a maximum of five members, one of whom shall be
the Chairman and who shall be appointed by the Minister.
(3) The members of the Board shall be independent members
and who are not involved in any way in the preparation of
environmental or other assessments falling within the jurisdiction
of the Board.
(4) The Board shall assess applications for such registrations
and approve those that meet the requirements for registration. The
Board shall give reasons for its decisions.
(5) The decision of the Board to grant or to refuse an
application for registration in the Register kept by the Authority
shall be notified in writing to the applicant without delay.
(6) The Board may direct the Authority to update the Register
at such regular intervals as it may deem fit by the inclusion of other
disciplines in the Register, which disciplines might have in the
meantime evolved.
(7) The decisions of the Board shall be final. An appeal shall
lie to the Tribunal only on the grounds that the Board has, in its
decision, wrongly applied the provisions of this Act or any
regulations issued thereunder, or the decision of the Board
constitutes an abuse of discretion or is manifestly unfair, and
without prejudice to the aforesaid, the discretion of the Board may
not, so long as it has been exercised properly, be queried by the
Tribunal. An appeal from a partial decision of the Board may only
be filed together with an appeal from the final decision of the
Board.
(8) The decision of the Board shall be binding if it is supported
by the opinion of a majority of its members, and the dissenting
member or members, if any, may express his opinion separately;
and all decisions of the Board shall be delivered in public and shall
be published as soon as practicable after the sitting at which they
are given.
(9) The Minister may, after consultation with the Board, make
regulations to give better effect to the provisions of this article and,
without prejudice to the generality of the foregoing, he may
(a) establish criteria that applicants are expected to meet
in order to qualify for registration;
(b) establish the procedure to be followed by a Board;
(c) prescribe a tariff of fees for registration with the
Board.
(1) The Registration Board may, out of its own motion, or
at the request of the Authority, cancel any certificate granted under
the provisions of article 42 or refuse any application for a renewal
of the registration, when the holder of that certificate
(a) is found guilty by a court of criminal jurisdiction of a
crime being a crime committed through imprudence,
carelessness, un-skillfulness in an art or profession, or
non-observance of regulations; or
ENVIRONMENT AND DEVELOPMENT PLANNING
(b) is found guilty by a court of criminal jurisdiction of
any offence under the provisions of the Act or of any
regulations made there under; or
(c) has, in the opinion of the Authority and the Board,
submitted sub-standard or deliberately misleading
work in an assessment; or
(d) has participated in the preparation of an assessment
when he was not registered in the Register; or
(e) was the recipient of a certificate issued under the
provisions of article 42 based on information given by
the applicant which is false or misleading; or
(f) fails to pay the yearly renewal fee.
(2) Notwithstanding the provisions of sub-article (1), the Board
may opt for a suspension, rather than cancellation of the certificate,
in the circumstances specified in sub-article (1)(d) and (f).
(3) Notwithstanding the provisions of sub-article (1), if a
person participates in the preparation of an assessment without
being registered in the Register, he shall subsequently be barred
from registering or participating in any assessments in Malta for a
period to be decided by the Board which period shall in no case be
less than three years.
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
PART IV
Environment and Development Planning
1. Plans and Policies
Without prejudice to the provisions of this Act, the
effective management and planning of the environment and
development shall be regulated by plans, policies and regulations,
which are prepared and amended from time to time in accordance
with the provisions of this Act.
(1) The Authority shall, either out of its own motion, but
after consultation with the Minister, or if so requested by the
Minister, make a plan or a policy on any matter relating to the
environment and development planning.
(2) The Authority may also, either out of its own motion, but
after consultation with the Minister, or if so requested by the
Minister, review a plan or a policy which is already in force.
(3) The Minister shall, upon making such a request in writing,
send to the Authority the reasons for making such a request
together with a statement of goals and objectives to be attained by
the plan or policy or a revision of such plan or policy.
ENVIRONMENT AND DEVELOPMENT PLANNING
(4) The preparation and review of the structure plan shall be
regulated by the provisions of articles 51 to 53 whereas the
preparation or review of any other plan or policy shall be regulated
by the provisions of article 58
Provided that the Minister may, without prejudice to the
provisions of articles 51 to 53 and article 58, set out any additional
procedure that the Authority ought to follow, including the carrying
out of assessments, and may also carry out any assessments and, or
consultations, including public consultations, he may deem
necessary.
(5) If the Authority, upon a request by the Minister in terms of
sub-article (1), informs the Minister, within thirty days of receipt of
such a request, that it is unable, for whatever reason, to prepare
such a plan or policy, the Minister shall instruct the Authority to
delegate such functions in terms of article 9 with regard to that
particular plan or policy and in so doing it shall ensure that the
provisions of this Part are complied with.
(1) Where the Authority is unable to prepare a plan or
policy or fails to delegate such function as is envisaged in article
48(5), the Minister shall request any person, including any
government agency, other than the Authority, to prepare on his
behalf a plan or policy or a revision of such a plan or such policy.
(2) The Minister shall consult the Authority on the terms of
reference which are to form the basis of the preparation of a plan or
a policy or a revision of such plan or policy by the said person. The
Minister shall then furnish the said person with the relative terms
of reference and shall also indicate to the said person the
documentation which shall be presented to the Minister when the
plan, policy or a revision of such plan or policy is drawn up. On
receipt of such documentation, the Minister shall forward a copy of
such documentation to the Authority.
(3) The Minister shall also request the said person to comply
with article 58(2)(a) and (b) and, for the purposes of the said
paragraphs, the expression "the Authority" shall be construed as a
reference to the said person and such person shall revise, if
necessary, the plan, policy or a revision thereof after taking into
consideration the representations he may have received in terms of
article 58(2)(b).
(4) If the Authority agrees with such a plan, policy or revision
thereof, it shall adopt it for submission to the Minister for his
approval; and the provisions of article 58(2) shall, mutatis
mutandis, apply.
(5) If the Authority does not agree with the said plan, policy or
revision of such plan or such policy, it shall draw up a position
statement indicating the changes to be made to the said plan, policy
or revision thereof and shall refer both the said plan, policy or
revision of such plan or such policy and its position statement to
the Minister; and the provisions of article 58(2)(i) to (n) shall
mutatis mutandis apply.
(6)
The plan, policy or the revision of such plan or policy shall
ENVIRONMENT AND DEVELOPMENT PLANNING
only be prepared by or under the direction of an expert in the
environment or spatial planning having such qualifications as the
Minister may prescribe.
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
2. The Strategic Plan for the Environment and Development
(1) The
Strategic
Plan
for
the
Environment
and
Development
(a) is a strategic document regulating the sustainable
management of land and sea resources;
(b) shall be based on an integrated planning system that
ensures the sustainable management of land and sea
resources together with the protection of the
environment;
(c) must set out policies in relation to the development
and use of land and sea and shall be illustrated by
diagrams as necessary and accompanied by an
explanatory memorandum giving a reasoned
justification for each of the policies and proposals
contained in the plan;
(d) must ensure that
(i) plans, policies and programmes issued under
this Act are spatial, holistic and comprehensive
so that all factors in relation to land and sea
resources and related environment conservation
are addressed and included and to balance
demands for development with socio-economic
considerations and the need to protect the
environment;
(ii) sectoral policies, activities and inputs are
integrated and coordinated with each other,
combining the inputs of all disciplines and
groups;
(iii) all actions are based on a clear understanding of
the natural and legitimate objectives and needs
of individual land users;
(iv) it follows other national policies and plans.
(2) The Authority shall monitor the Strategic Plan for the
Environment and Development and review it as often as may be
necessary, provided such review does not take place within a period
of less than five years. Every such review shall be made in
accordance with the goals and objectives of a revision of the
Strategic Plan for the Environment and Development as may be
approved by Cabinet and take effect as provided in the following
provisions of this Part. In order to achieve the objectives set out in
this article, Cabinet shall take the necessary measures intended to
coordinate and improve the spatial impacts of other sectoral
policies and their relation to, or inclusion in, the Strategic Plan for
the Environment and Development.
ENVIRONMENT AND DEVELOPMENT PLANNING
(3) Notwithstanding the provisions of sub-article (2), the
Strategic Plan for the Environment and Development can be
reviewed in parts as the need arises by means of a Resolution of the
House of Representatives, and shall come into force in accordance
with the following provisions of this Part. Such a partial review of
the Strategic Plan for the Environment and Development shall not
adversely affect a development permission validly issued in favour
of any person before the date of the coming into force of such a
review.
(4) Cabinet may approve a statement of goals and objectives to
be achieved by a partial review of the Strategic Plan for the
Environment and Development, and, or, a proposal together with a
position statement with regard to that review. After such approval,
the Minister shall send to the Authority that statement of goals and
objectives, and, or, that proposal and position statement. When the
Authority receives that statement of goals and objectives and, or,
the proposal and position statement, it shall conform with the
procedure laid down in sub-articles (5) to (7), if the matters
referred to therein have not already been carried out, in the same
manner as if the proposal had been initiated by the Authority; and
the provisions of sub-article (3) and of article 52 shall apply. If the
Authority disagrees with the Minister ’s proposal or with his
position statement, it shall prepare its position statement indicating
the changes that it proposes or its reactions thereto. The Minister
shall then conform with the provisions of article 53 and, for the
purposes of article 52(1), the expression "representations" shall
include the Authority’s position statement.
(5) For the preparation or review of the Strategic Plan for the
Environment and Development the Authority shall carry out
surveys of those matters which affect the character and quality of
the environment, its conservation and its development, including,
but not limited to
(a) demographic considerations;
(b) the agricultural, industrial, commercial, touristic and
other existing and, or projected economic activities of
the country including the employment patterns arising
therefrom;
(c) leisure and recreation;
(d) social and community services and facilities;
(e) communications, traffic and transport;
(f) public utility services;
(g) the conservation and preservation of natural and man-
made resources;
(h) the state of the environment report, nitrate vulnerable
zone mapping, flood sensitivity mapping, other issues
emanating from water, air quality and waste
framework regulations;
(i) such other matters as may be required by the
Government or which may be deemed necessary by the
Authority.
ENVIRONMENT AND DEVELOPMENT PLANNING
(6) In preparing or reviewing the Strategic Plan for the
Environment and Development, the Authority shall have regard to
(a)
the current economic policies affecting development;
(b)
the current social policies affecting development;
(c)
the environmental policies affecting development;
(d)
the policies of the Government with respect to the
matters set out in sub-article (5);
(e) the resources likely to be available for the
implementation of the plan;
(f) all possible land and sea-use options in selecting the
best use for a given area of land or sea.
(7) During the preparation or review of the Strategic Plan for
the Environment and Development the Authority shall make known
to the public the matters it intends to take into consideration and
shall provide adequate opportunities for individuals and
organisations to make representations to the Authority.
(8) A partial review of the Strategic Plan for the Environment
and Development which is necessitated by the adoption of or an
amendment to a subsidiary plan need not comply with the
provisions of sub-articles (5) and (6) if the matters referred to
therein and that are relevant to the partial review have already been
carried out in the preparation of the subsidiary plan.
(1) When the Strategic Plan for the Environment and
Development or a review thereof has been completed, the
Authority shall publish the plan together with a statement of the
representations it has received and the responses it has made to
those representations.
(2) The Authority shall invite representations on the plan to be
submitted to it within a specified period of not less than six weeks.
(3) The Strategic Plan for the Environment and Development,
or any review thereof, together with all representations made to the
Authority, shall, as soon as practicable, after the expiry of the
period specified in sub-article (2), be referred to the Minister.
(4) The Minister may refer back the Strategic Plan for the
Environment and Development, or review thereof to the Authority
where he does not agree with the Strategic Plan for the
Environment and Development, or any review thereof and he shall
prepare a position statement stating the changes he proposes to it or
his reactions to the Strategic Plan for the Environment and
Development, or review thereof.
(5) Where the Strategic Plan for the Environment and
Development, or any review thereof, has been referred back to the
Authority, the same procedure as far as practicable shall be
followed with respect to any further draft prepared and published
by the Authority, except that reference back to the Authority shall
not be made more than once.
ENVIRONMENT AND DEVELOPMENT PLANNING
(1) At the conclusion of the procedures set out in the
foregoing provisions, the Strategic Plan for the Environment and
Development, and any review thereof, shall be considered by the
Cabinet of Ministers together with the Minister ’s position
statement and the representations made with respect to the plan or
its review.
(2) Subject to article 34(2)(a), (3) and (4), the Minister shall
then cause the Strategic Plan for the Environment and
Development, or a review thereof as originally prepared, or as
revised, by the Authority, together with the Minister’s position
statement, to be laid before the House together with a motion for a
resolution that the Strategic Plan for the Environment and
Development, be approved by the House, with such amendments, if
any, as may be specified in the resolution.
(3) The Strategic Plan for the Environment and Development,
and any review thereof as approved by the House shall have effect
as from such date as may be specified for that purpose by the
Minister by order in the Gazette; and for the purposes of this Act,
other than those provisions relative to the preparation,
consideration and submission of the Strategic Plan for the
Environment and Development, or its review, the expression
Strategic Plan for the Environment and Development and any
reference to a review thereof means the Strategic Plan for the
Environment and Development, and any review thereof, as
approved by the House of Representatives.
3. Subsidiary Plans and Policies
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(1) An action plan or a management plan is made by the
Authority for an area where the Authority considers that it has to
pay particular attention in order to better manage it or where
special factors have to be taken into account which otherwise
cannot be taken.
(2)
An action plan may form part, or be the whole of, a local
plan.
(3) In addition to the information required to be contained in a
local plan, an action plan made in terms of sub-article (1)(b) shall
also show the land which is in public ownership and the land which
is intended to be brought into public ownership.
(1) Where the Authority considers that for the proper and
effective management and protection of the environment and of
development or for the proper protection and development of land
and sea it is necessary to prepare more detailed policies or plans
and guidance other than those already contained in a plan or policy,
the Authority may prepare and adopt such policies or plans as it
considers appropriate subject to the provisions of this article.
(2)
Such policies or plans shall be in a form which the
ENVIRONMENT AND DEVELOPMENT PLANNING
Authority considers appropriate to the subject matter, and may be
supported by such documents, assessments, maps, diagrams,
drawings and illustrations as may be considered necessary by the
(3) When the Authority adopts a policy or plan (be it a new
policy or plan or a revision of an existing policy or plan), it shall
refer it to the Minister for his approval and t he procedure
mentioned in article 58(2) shall mutatis mutandis apply.
(1) In the preparation or review of a subsidiary plan or
policy, the procedure set out in this article shall be followed with
respect to the said plan or policy.
(2) Where the Authority prepares a subsidiary plan or policy or
review thereof as aforesaid, it shall seek the Minister’s approval in
terms of the following procedure
(a) during the preparation or review of a subsidiary plan
or policy, the Authority shall make known to the
public the matters it intends to take into consideration
and shall provide adequate opportunities for
individuals and organisations to make representations
to the Authority;
(b) when the subsidiary plan or policy or a revision
thereof has been prepared, the Authority shall publish
the plan or policy together with a statement of the
representations it has received and the responses it has
made to those representations. The Authority shall
invite representations on the plan or policy to be
submitted to it within a specified period of not less
than six weeks; where in such a subsidiary plan or
revision thereof it is proposed that any land be
excluded from a development boundary as indicated in
a local plan, the Authority shall publish in the Gazette
and in two local daily newspapers a notice showing the
land that is to be excluded
Provided that where minor modifications not affecting
the substance of a planning policy are being proposed,
the said period shall be a period of not less than three
weeks;
(c) the Authority shall adopt the subsidiary plan or policy
after taking into consideration all the representations
submitted to it as aforesaid;
(d) the Authority shall refer the subsidiary plan or policy
to the Minister. It shall also forward to the Minister
(i) the statement of representations;
(ii) the responses and amendments it has made as a
result of those representations;
(iii) a precise indication of all other amendments it
has made to the plan or policy; and
(iv) all the relative documentation and studies in
relation to the preparation of the subsidiary plan;
ENVIRONMENT AND DEVELOPMENT PLANNING
(e) the Authority shall also publish the plan or policy and
invite representations on the matters indicated in
paragraph (d)(iii) to be submitted within a specified
period of not less than six weeks;
(f) the Authority shall adopt the subsidiary plan or policy
after taking into consideration all the representations
submitted to it as aforesaid and shall refer the
subsidiary plan or policy to the Minister for his
approval. It shall also forward to the Minister
(i) the statement of representations;
(ii) the responses and amendments it has made as a
result of those representations;
(g) where the Minister agrees with the subsidiary plan he
shall approve it as submitted by the Authority and the
Authority shall upon such approval publish the same
together
with
the
statements,
responses,
documentation and studies referred to in paragraphs
(d) and (f);
(h) where the Minister does not agree with the subsidiary
plan as adopted by the Authority in accordance with
paragraph (f), he shall prepare a position statement
stating his proposed changes or his reactions to the
Authority’s subsidiary plan and shall refer back the
subsidiary plan to the Authority together with his
position statement; where in such a subsidiary plan or
revision thereof it is proposed that any land be
excluded from a development boundary as indicated in
a local plan, the Authority shall publish in the Gazette
and in two local daily newspapers a notice showing the
land that is to be excluded;
(i) where the Authority does not agree with the Minister
following the referral back to it of the subsidiary plan
by the Minister, it shall draw up a position statement
and shall refer it back to the Minister;
(j) the Minister shall then issue a final position statement.
He shall forthwith communicate it to the Authority;
(k) the Authority shall forthwith amend the subsidiary
plan in accordance with the Minister’s final position
statement and submit the same for the Minister’s final
approval;
(l) Upon such approval by the Minister, the Authority
shall publish the subsidiary plan together with its own
position statements and those of the Minister together
with the advice of the Tribunal given in terms of
paragraph (n), if any, and together with the statements,
responses, documentation and studies referred to in the
preceding paragraphs;
(m) * where the subsidiary plan or any part thereof extends
*this paragraph is not yet in force.
ENVIRONMENT AND DEVELOPMENT PLANNING
the scope of or is in conflict with the Strategic Plan for
the Environment and Development, the Minister shall
comply with the provisions of articles 51 to 53 with
regard to such subsidiary plan or any part thereof,
provided that those parts of the subsidiary plan that do
not extend the scope of or are not in conflict with the
Strategic Plan for the Environment and Development
shall come into force on the date of approval by the
Minister;
(n) * if doubt arises as to which procedure should be
followed in respect of a subsidiary plan or as to
whether a subsidiary plan or a position statement
extend the scope of, or are in conflict with, the
substance of the structure plan, the matter may be
referred at any time by the Authority or by the
Minister to the Tribunal, provided that where the
Authority is of the opinion that the Minister’s final
position statement extends the scope of or is in conflict
with the substance of the Strategic Plan for the
Environment and Development, it may refer the matter
to the Tribunal within one month from the date of
receipt of the Minister’s final position statement. The
Tribunal shall rule within one month from the date of
referral to it of the matter as to which procedure shall
apply and the decision of the Board shall be final.
† (1) Every subsidiary plan or policy shall be reviewed as
frequently as may be necessary or as may be made necessary by a
review of the structure plan
Provided that subject to the provisions of sub-article (3), a
local plan may not be reviewed before the lapse of two years from
its last review unless such review is necessitated by a review of the
structure plan
Provided further that in the case of a partial review of the
local plan, the above-mentioned two-year moratorium shall only
apply to that part of the plan forming part of the partial review.
(2) Where as a result of such a review the Authority proposes
to alter a plan or policy in any significant respect, or where it is
proposed that a plan or policy be withdrawn, any such proposal
shall be subject to the same procedures, and shall be treated, as a
new plan or policy.
(3) Minor modifications not affecting the substance of a local
plan may be carried out by the Authority at any time either on its
own motion when it considers to do so in the interests of proper
planning of the area or following a minor modifications application
submitted to it by any person. Modifications shall not be
considered to be minor when they would alter the general thrust of
the plan or affect a development boundary indicated in a local plan.
(4)
For the purpose of sub-article (3), the following shall be
*this paragraph is not yet in force.
†this article is not yet in force.
ENVIRONMENT AND DEVELOPMENT PLANNING
considered to constitute minor modifications
(a) changes in the alignment of roads and buildings in a
local plan; and
(b) changes in zoning, other than
(i) changes in height limitations; and
(ii) changes in zoning of a site which is not
designated for the purpose of development.
(5) Where the Authority is considering a minor modification in
terms of sub-article (4)(a), the provisions of article 68 shall apply
mutatis mutandis to such a modification.
(6) Where the Authority is considering a minor modification in
terms of sub-article (4)(b), it shall follow the following procedure
(a) where the proposal for such a minor modification
originates from the Authority itself, it shall comply
with the provisions of article 58(2);
(b) where the proposal for such a minor modification
originates in a minor modifications application, the
Authority shall publish such proposal and invite
representations on the said application within a
specified period of not less than six weeks. The
Authority shall then decide the application after taking
into consideration all representations submitted to it.
The provisions of article 49(4) and (5) shall also apply.
(7) No appeal from a decision concerning
a
minor
modifications application shall lie to the Tribunal.
4. Regulations and Orders
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(1) Regulations under this Act shall be made by the
Minister after consultation with the Authority and except for
regulations under article 61(2)(a), (b) and (u) and in the cases
referred to in sub-article (2) hereof shall not be made unless a draft
of the said regulations has been issued for public consultation
thereby allowing any person a period of at least four weeks to make
representations to the Minister or to the Authority or to both stating
how in his opinion the proposed regulations could be improved to
reach their ultimate aim.
(2) The provisions of sub-article (1) with regard to consultation
with the Authority and with regard to the publication of a draft of
the regulations for public consultation shall not apply in respect to
any regulations, which the Minister declares to be urgent or when a
form of public consultation was carried out before the date of
coming into force of this Act.
(3)
Any person may, in the circumstances referred to in sub-
ENVIRONMENT AND DEVELOPMENT PLANNING
article (1) in respect of draft regulations, not later than six weeks
after the promulgation of any regulations made in accordance with
sub-article (2) make submissions to the Minister and, or to the
Authority stating why and how the regulations should be revoked
or amended.
(4) The Authority shall consider any representations made to it
under sub-articles (1) and (3) and shall report thereon, after hearing
such persons or taking such expert advice as it considers expedient,
to the Minister together with any other views it may have on the
draft published under sub-article (1) or the regulations made under
sub-article (2), and the Minister may, upon receipt of the report by
the Authority and any representations received by him, proceed to
revise the draft regulations and to promulgate such regulations in
accordance with such revision, or to amend any regulations already
promulgated; provided that where the Authority has not after the
lapse of four weeks after the end of the period for representation
referred to in sub-article (1) has elapsed, not made the report or has
not given its views to the Minister, the Minister may proceed to
promulgate the regulations contained in the draft with or without
changes as he may deem expedient, without prejudice to the
possibility of making any changes upon the receipt of such report
and views when made.
(5) When the Minister makes regulations concerning the
procedure before the Authority or any board, commission or other
body established under this Act, he shall also consult the Authority
or such board, commission or body
Provided that regulations concerning the procedure before
the Court of Appeal and appeals before it under this Act shall be
made by the Minister responsible for Justice who shall not be
required to consult with the Authority
Provided further that regulations concerning the
establishment or variation of any fee shall be made by the Minister
with the concurrence of the Minister responsible for finance.
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(1) The Minister shall, in consultation with the Authority,
by regulations under this article provide that members of the public
or such categories of persons as may be prescribed shall be entitled
to request from such Government departments, authorities, public
corporations or other persons as may be prescribed such
information that they may have in their possession and relating to
the environment and development planning. Without prejudice to
the generality of the foregoing, such regulations may prescribe
(a) the nature of the information that may be requested;
(b) the circumstances in which such information may be
requested;
(c) the circumstances in which such information may be
withheld by the requested entity and the publication of
the reasons for which such information is withheld;
(d) the fees that may be charged in respect of any such
ENVIRONMENT AND DEVELOPMENT PLANNING
information; and
(e) the time within which such information is to be
supplied.
(2) Without prejudice to the generality of sub-article (1), the
Authority shall keep and make available for public inspection at
such reasonable times as it may determine, a register or registers
(a) of all applications for a licence or development
permission received by it containing the name of the
applicant and details of the proposal including
documents and detailed plans; and
(b) of all decisions including documents and detailed
plans made on such applications.
5. Environment and Development Brief
(1) An Environment and Development Brief is a document
setting out detailed planning guidance for the development of a
specific site or small area where the Authority, either of its own
motion, or at the request of an applicant, considers such guidance is
necessary to secure proper and orderly environmental management
or development of that site or area, or to implement a policy or
policies in a plan.
(2) A brief shall consist of a written statement supported by
such maps and diagrams as may be considered necessary.
(3) A brief shall contain guidance and information on the
following matters as may be considered necessary
(a) a description of the site and its location;
(b) guidelines on the development of the site, including
(i) land uses and site layout,
(ii) building form, heights and design,
(iii) any building and landscape features to be
retained,
(iv) access, parking and circulation requirements,
(v) landscaping and nature conservation aspects;
(c) environmental matters and constraints including the
necessity of any environmental assessment;
(d) tenure of the site;
(e) services and infrastructure;
(f) the format and content of submission requirements;
(g) any other information which may be relevant to the
site and to the purpose of the development brief.
(4) The Minister may, after consultation with the Authority,
make regulations to give better effect to the provisions of this
article and, without prejudice to the generality of the foregoing, he
may
(a) establish the procedure to be followed by an authority
in its consideration and determination of the Brief;
ENVIRONMENT AND DEVELOPMENT PLANNING
(b) prescribe those matters on which a brief may be
prepared;
(c) prescribe a tariff of fees.
PART V
Environment Protection and Development Control
1. Requirement of licences and permission
No person shall carry out any of the following activities
unless he is in possession of a licence from the Authority
(a) in relation to biodiversity
(i) for whatever purpose, trade in, sell, buy,
exchange, transfer or dispose, transport, import,
export or re-export such specimens of flora or
fauna, as may be prescribed whether dead or
alive in whole or in part, including any
derivatives thereof;
(ii) have such specimens of flora or fauna as may be
prescribed in transit;
(iii) have in his possession such specimens of flora
or fauna as may be prescribed;
(iv) handle such specimens of flora and fauna as may
be prescribed, in any manner including the
ringing and tagging thereof;
(v) mount/stuff, trap, shoot or capture such
specimens of fauna as may be prescribed;
(vi) deliberately pick, collect, cut, destroy, kill,
pursue, take, damage, capture such specimens of
flora or fauna as may be prescribed;
(vii) uproot, fell, prune or carry out any surgical
interventions on such specimens of flora as may
be prescribed;
(viii) use prohibited means of capture and killing as
may be prescribed;
(ix) manage invasive and alien species as may be
prescribed;
(x) introduce or reintroduce species as may be
prescribed;
(xi) carry out activities in protected areas considered
to have an effect on biological diversity and the
integrity of the site;
(xii) carry out any activity which goes counter to the
principles of ecological restoration or species
and protected area management, as may be
prescribed, including but not limited to
1. activities which are expected to cause
permanent alterations to the protected
area,
2. afforestation or planting,
ENVIRONMENT AND DEVELOPMENT PLANNING
3. activities expected to generate noise and
light,
4. activities involving fires/fireworks,
5. activities considered to have an effect on
biological diversity,
6. off-roading activities or events;
(xiii) modify, endanger the stability of or demolish
rural structures affording a habitat for flora and
fauna as may be prescribed;
(xiv) manage biological diversity as may be
prescribed;
(b) in relation to waste management
(i) store, treat, collect, transfer, recover or
otherwise manage or handle such waste as may
be prescribed;
(ii) act as broker for the carrying out of the
functions mentioned in sub-paragraph (i);
(iii) trade in, import or export waste;
(iv) have such waste as may be prescribed in transit;
(v) operate waste management facilities;
(c) in relation to pollution control, conduct operations that
discharge or cause or permit to be discharged such
substance or energy as may be prescribed into the
environment;
(d) in relation to genetically modified organisms
(i) trade in genetically modified organisms;
(ii) manage or otherwise have in his possession
genetically modified organisms;
(e) in relation to any other activity as may be prescribed
by regulations.
(1) Subject to the provisions of this article and to the
following provisions of this Part, no development shall be carried
out except with development permission.
(2) For the purposes of this article, and, unless the context
otherwise requires, for all other purposes in this Act,
"development" means the carrying out of building, engineering,
quarrying, mining or other operations for the construction,
demolition or alterations in, on, over, or under any land or the sea,
the placing of advertisements, or the making of any material
change in use of land or building other than
(a) maintenance operations, which affect only the interior
of a building or do not materially affect the external
appearance of the building
Provided that such maintenance works are not contrary
to any order made under this Act in relation to the
building
Provided further that maintenance operations shall not
ENVIRONMENT AND DEVELOPMENT PLANNING
include demolition and rebuilding works, irrespective
of where such demolition and rebuilding works are
carried out;
(b) the use of land for agriculture, animal husbandry and
forestry (including afforestation), except where such
use consists of
(i) the erection of buildings or amounts to intensive
raising of crops or animals; or
(ii) the reclamation of land for agriculture by the
deposit of material on such land; or
(iii) the conversion to agricultural use of land which
is not currently used for agricultural purposes;
and
(c) in the case of buildings or other land that are used for a
purpose of any class specified in an order made by the
Authority under this Act, the use thereof for any other
purpose of the same Class.
(3)
For the purpose of this article
(a) the use of a building resulting in an increase or a
reduction in the number of dwelling units in which the
building was previously used; or
(b) the deposit of materials on land; or
(c) the use for the display of advertisements of any
external part of a building that is not normally used for
the purpose,
involves a material change in the use of that building or land, or
part thereof, without prejudice, in the case of advertisements, to
any regulations or order made under this Act with respect to their
(4) For the purpose of this article, development includes
clearing of valleys from accumulated sediment and development in
relation to the sea includes land reclamation from the sea,
aquaculture and beach developments and their related uses.
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(1) In its determination upon an application the Authority
(a) with respect to an application for a development
permission apply the following
(i) plans
Provided that the height limitation may only be
modified by applying a policy which deals with
the maximum building height which may be
permitted on a site, which policy may take into
consideration the site coverage, the building
volume which may be permitted on a site or any
other material consideration;
ENVIRONMENT AND DEVELOPMENT PLANNING
(ii) policies
Provided that subsidiary plans and policies shall
not be applied retroactively so as to adversely
affect vested rights arising from a valid
development permission;
(b) with respect to any other application apply such plans,
policies and regulations issued under this Act as it may
deem relevant and appropriate.
(2) In its determination upon an application the Authority shall
also have regard to
(a) any other material consideration, including,
environmental, aesthetic and sanitary considerations,
which the Authority may deem relevant
Provided that no such material consideration including
commitment from other buildings in the surroundings
may be interpreted or used to increase the height
limitation set out in a plan;
(b) representations made in response to the publication of
the development proposal.
(3) The Authority shall have power to grant or to refuse a
licence or development permission, and in granting such licence or
permission the Authority shall be entitled to impose such condition
which it may deem appropriate
Provided that upon a refusal or the imposition of particular
conditions, the Authority shall give specific reasons based on
existing plans, policies and regulations or other material
considerations for such refusal or for any particular conditions that
may have been imposed
Provided further that the execution and validity of a permit
in case of a development mentioned in the Seventh Schedule shall
be automatically suspended and no works as approved by the said
development permit may commence before the lapse of the time
period established in paragraph (1) of the Second Schedule, and
shall remain so suspended until the Tribunal appoints its first
hearing on an appeal from such a permit, if any, under the
provisions of article 41(3), and this without prejudice to the
provisions of article 41(3).
(4) A licence or a development permission may be granted for
a limited period or in perpetuity, but shall in all cases cease to be
operative if activity or development has not been completed within
five years of its issue, provided that the Authority may, on the
application of the person holding the licence or development
permission, extend the said licence or permission to such further
period or periods as it may consider reasonable.
(5) In granting a licence or development permission, the
Authority may require the activity or development to be completed
within a specified period of time as it may establish provided that
the Authority shall state the reasons justifying such requirement.
(6)
Except as may be otherwise provided in the permission, a
ENVIRONMENT AND DEVELOPMENT PLANNING
development permission shall ensure for the benefit of the land and
for all persons for the time being interested therein, but without
prejudice to the other provisions of this Act affecting its validity or
operation. The permission shall automatically pass on to new
owners.
(7) In granting a licence or development permission, the
Authority may require the applicant to carry out the activity or
development in stages. The Authority shall inform the applicant in
the said licence or permission which are the said stages and,
following the completion of each stage, the applicant shall request
the Authority to carry out an inspection of the activity or works
carried out; and, if following such an inspection, it is found that the
activity or works have been carried out in terms of the licence or
development permission, the Authority shall authorize the
applicant to carry out the next stage of the activity or development.
(8) Where the Authority, in the case of major projects,
considers it appropriate to closely monitor specific conditions in a
licence or development permission by appointing a person
competent for the said purpose, it shall do so at the expense of the
applicant.
(9) Without prejudice to the provisions of this article, where an
application to develop land consists in the mining of minerals the
Authority may, and, where planning and environmental standards
so require, shall, require the applicant to provide a scheme for the
treatment of the working and surrounding areas during the working
period and for the treatment of the said areas when working is
completed.
(10) The Authority shall not grant permission for the mining of
minerals unless it is satisfied that planning and environmental
standards will be met and the site will be kept and eventually left in
acceptable conditions.
(11) Where the Authority has required a scheme to be submitted
as provided in sub-article (1), the scheme, as accepted by the
Authority, shall be made a condition of any permission granted by
it; and the Authority shall further require such guarantees to be
given by the applicant as it deems necessary to ensure that the
scheme will be adhered to.
(1) In any case in which the Authority may under this Act
grant permission to develop land, other than in the case of a
development listed in the Sixth Schedule, it may grant permission
for the retention on land of any buildings or works constructed or
carried out thereon, or for the continuance of any use of land,
without permission under this Act or after such permission has
ceased to be valid or operative; and references in this Act to
permission to develop land or carry out any development on land,
and to applications for such permission, shall be construed
accordingly
Provided that any application or permission under this sub-
article shall not be processed or granted unless the applicant or his
predecessor in title has
ENVIRONMENT AND DEVELOPMENT PLANNING
(a) forthwith upon being required so to do, ceased to carry
out any works he was required to interrupt; and
(b) paid such fines or made such other payments as may
be due on the site subject of the application.
(2) A permission under this article may be granted so as to take
effect from the date on which the buildings or works were
constructed or carried out or the use was commenced, or from the
date the development permission ceased to be valid or operative, as
the case may be.
(3) A development permission may specify the purposes for
which a building may be used; and if no purpose is specified the
permission shall be construed as including permission to use the
building for the purpose for which it is designed.
(4) Where a development permission is given for a limited
period only, nothing in this Act shall be construed as requiring
permission to be obtained thereunder for the resumption, at the
expiration of that period, of the use of the land for the purpose for
which it was normally used before the permission was granted, but
no account shall be taken of any use made in contravention of this
Act.
(5) The Authority may, prior to the issue of or in issuing a
development permission or licence, demand from the person in
whose favour the permission or licence will be issued, as a
condition for the issue of the development permission or licence, to
provide a bond in favour of the Authority in order to guarantee
compliance with the conditions of the permission or licence once
issued, or in order to guarantee payment in respect of damages
which may be caused to the environment or to the infrastructure.
The Authority may, after the issue of a development permission or
licence, if the development or activity is not being carried out in
accordance with the permission or licence, or is otherwise causing
damage to the environment or the infrastructure, demand the said
person in whose favour the permission or licence has been issued,
as a condition for the continuance of the development permission
or licence, to provide a bond in favour of the Authority in order to
guarantee compliance with the conditions of the permission or
licence, or in order to guarantee payment in respect of damages
which may be caused to the environment or to the infrastructure
Provided that nothing in this sub-article shall be interpreted
as authorizing the Authority to demand a bond in an amount not
commensurate with the nature of the development project or
activity
Provided further that such a bond may only be forfeited by
the Authority if there is clear evidence that the applicant has not
complied with the conditions of the development permission or
licence and the reasons for forfeiting the bond shall be
communicated in writing to the applicant.
(1) Decisions on applications shall be taken without delay.
(2) The Minister may, after consultation with the Authority,
make regulations to give better effect to the provisions of this
ENVIRONMENT AND DEVELOPMENT PLANNING
article and, without prejudice to the generality of the foregoing, he
may
(a) establish the procedures to be used by the Authority
and the applicant in the processing and determination
of applications;
(b) establish the procedures to be used by an applicant
prior to the submission of an application;
(c) establish time limits within which submissions have to
be made and decisions have to be taken and
communicated.
The Authority shall not delegate to the Commission or to
any other body or person the determination of the following
applications
(a) applications in respect of an activity or development
of a national or strategic significance or affecting
matters of national security or other national interests;
(b) applications in respect of and activity or development
which could affect the interests of other governments;
(c) applications in respect of development which is
subject to an environmental impact statement;
(d) requests for reconsideration where the decision to be
reconsidered was taken by the Authority itself.
(1) If an applicant considers that conditions imposed upon
a licence or a development permission is unreasonable, he may,
without prejudice to his right of appeal, request the Authority or
the Commission, as the case may be, to reconsider such conditions.
(2) A request for a reconsideration shall be made within thirty
days from notification of the decision of the Authority or of the
Commission, as the case may be, and may not be made
concurrently with an appeal. The request for a reconsideration shall
include a written document containing the reasons for such a
request.
(3) The Authority shall inform the registered interested parties
where a request for a reconsideration has been filed and the
registered interested party shall be notified of the Authority’s
sitting when such a request for a reconsideration shall be discussed.
(4) No reconsideration may be demanded by a registered
interested party, even if such interested party has made written
objections in accordance with the provisions of article 68(4).
(1) If an applicant considers that the conditions imposed
upon a licence or a development permission, or a refusal of such an
authorisation or permission, is unreasonable, he may lodge an
appeal with the Tribunal under article 41. An appeal under this sub-
article, shall be made within thirty days of notification of the
decision of the Authority or of the Commission, as the case may be.
The request for an appeal shall include a written document
containing the reasons for such a request.
ENVIRONMENT AND DEVELOPMENT PLANNING
(2) Where a request for reconsideration has been made, an
a p p e a l m a y b e m a d e t o t h e Tr i b u n a l w i t h i n t h i r t y d a y s o f
notification of the decision taken in the reconsideration.
(1) Where an appeal is lodged by an applicant or by an
interested third party from any decision of the Authority referred to
in sub-article (2), the Secretary of the Tribunal shall inform the
Minister of such an appeal within fifteen days from its receipt. In
such case, the Minister may, within fifteen days from the date when
he has received such information, either instruct the Tribunal to
proceed with the determination of the appeal or decide to refer the
application to the Cabinet of Ministers for determination. Where
the Minister does not decide to refer an application to the Cabinet
of Ministers as aforesaid within the said period, it shall be deemed
for all purposes and effects of law that he has opted to refer the said
appeal to the Tribunal for its decision.
(2) The Minister may refer to the Cabinet of Ministers
applications called in by him in terms of sub-article (1) where such
applications are
(a) applications in respect of development which appears
to him to be of a strategic significance;
(b) applications in respect of development which appears
to him to affect matters of national security or national
interests;
(c) applications in respect of development which appears
to him likely to affect the interests of other
governments;
(d) applications in respect of development which is
subject to an environmental impact assessment and
which in his opinion is of national interest;
(e) applications in respect of which the applicant is a
department of Government or a body corporate
established by law.
(3) Where the Minister decides to refer to the Cabinet of
Ministers an application called in by him, he shall request the
Tribunal to draw up its recommendation on that application after
h a v i n g h e a r d t h e p a r t i e s a n d t h e Tr i b u n a l s h a l l s e n d i t s
recommendation on that particular application to the Minister who
shall refer it to the Cabinet of Ministers. Such recommendation
shall be available to the public.
(4) The Cabinet Secretary shall, within fifteen days from the
date of such decision, communicate the decision of the Cabinet of
Ministers to the Authority together with the reasons in justification
thereof and the Authority shall comply therewith, publish the
decision of the Cabinet of Ministers in such manner as it may deem
fit or as it may be prescribed and shall communicate the decision of
the Cabinet of Ministers to the parties within fifteen days from the
receipt of such decision.
ENVIRONMENT AND DEVELOPMENT PLANNING
(5) A decision by the Cabinet of Ministers, pursuant to this
article, which relates to a development or an installation which is
subject to an environmental impact assessment and, or an IPPC
permit, may, upon an application by the appellant or by an
i n t e r e s t e d p a r t y, w h i c h m a y i n c l u d e a n o n - g o v e r n m e n t a l
organization having as one of its purposes the promotion of
environmental protection and is registered under the Voluntary
Organisations Act, be subject to appeal on matters of substantive
and procedural legality to the Court of Appeal in its superior
jurisdiction. An appeal in terms of this sub-article shall be made by
an application to be filed within ten days from the date of
communication of the decision of the Cabinet of Ministers to the
parties. The appeal proceedings shall be concluded by the Court of
Appeal within four months from the filing of the appeal and shall
not be prohibitively expensive. Legal and judicial costs and fees in
the said proceedings shall be taxed in accordance with paragraph
(7) of item 3 of Tariff A and with paragraph (b) of item 15 Tariff E
in Schedule A to the Code of Organization and Civil Procedure.
(6) The execution of any development or the operation of any
installation which is subject to an environmental impact assessment
and, or an IPPC permit, and which is pending a decision by the
Cabinet of Ministers in terms of this article shall be suspended until
the decision of the Cabinet is taken.
(7) Where a decision of the Cabinet of Ministers is subject to
an appeal in accordance with sub-article (5), the Court of Appeal
may, upon a request of the appellant or of an interested party, which
may include a non-governmental organization having as one of its
purposes the promotion of environmental protection and which is
registered under the Voluntary Organisations Act, order that the
execution of the development or the operation of the installation be
suspended whilst proceedings before the said Court are pending.
(1) An environment and planning obligation may be
entered into in those cases where the Authority, in connection with
a grant of a licence or development permission, seeks to impose on
the applicant an obligation
(a) to carry out an activity or works
(i) on the land in respect of which development
permission is sought, or
(ii) on any other land or area, or
(iii) on the land or area mentioned in both
subparagraphs (i) and (ii); or
(b) to make some payment or confer some extraneous
right or benefit, where the Authority considers it to be
more appropriate. The Authority shall seek to obtain
these benefits or gains by means of conditions attached
to a grant of the licence or development permission or
by means of an environment and planning obligation
entered into by a public deed made by the applicant for
the licence or development permission with the
Authority.
(2)
Any person may, by agreement with the Authority, enter
ENVIRONMENT AND DEVELOPMENT PLANNING
into an environment and planning obligation
(a) restricting the development or use of that land in any
specified way;
(b) requiring specified operations or activities to be
carried out, in, on, under or over that land or area;
(c) requiring that land or area to be used in any specified
way; or
(d) requiring a sum or sums to be paid to the Authority on
a specified date or dates or periodically.
(3) The Minister may, in consultation with the Authority, make
regulations for giving better effect to the provisions of this article
and may, without prejudice to the generality of the foregoing
(a) prescribe the procedure how an environment and
planning obligation may be entered into, enforced,
modified and discharged;
(b) establish any restrictions, conditions or the payment of
any sums of money which may be imposed in such an
environment and planning obligations; and
(c) regulate appeals to the Tribunal made in terms of sub-
article (4).
(4) The applicant and any person interested in land may appeal
to the Tribunal from a planning obligation entered into in terms of
sub-article (1).
2. Revocation or modification of permission,
licence or authorisation and Discontinuance or removal orders
(1) The Authority or the Tribunal may, only in the cases of
fraud or where public safety is concerned or where there is an error
on the face of the record, by a decision revoke or modify any
licence or development permission granted under this Act,
including any clearance issued by the Authority under an Order,
stating in such decision its reasons for so doing; and, prior to
deciding to revoke or modify a licence or development permission
in terms of this sub-article, the Authority or the Tribunal, as the
case may be, shall inform the person who will be affected by its
decision of the date and time of its meeting where the Authority or
the Tribunal shall also hear the said person’s submissions if the
latter opts to attend, and any other person’s submissions
Provided that the Authority or the Tribunal may in relation
to any licence or development permission, including any clearance
issued by the Authority under an Order, issued after the date of
coming into force of this Act commence proceedings to revoke or
modify any such licence or development permission, including any
clearance issued by the Authority under an Order, within five years
from the date of issuing of the licence or development permission,
including any clearance issued by the Authority under an Order.
(2)
For the purposes of sub-article (1)
"fraud" means the submission to the Authority of any
information, declaration or plan on the basis of which the Authority
ENVIRONMENT AND DEVELOPMENT PLANNING
has approved a licence or development permission, where such
information, declaration or plan is false, misleading or incorrect,
irrespective of whether such deceit is the result of a wilful or
negligent act
Provided that the Authority shall not revoke or modify a licence
or development permission on the basis of fraud where the
fraudulent information did not have a material bearing on the
issuing of the licence or development permission; and
"error on the face of the record" means an error on the face of a
record which offends against the law.
(3) The applicant shall, if the decision is taken by the
Authority, have a right to appeal the Authority’s decision to the
Tribunal within thirty days from the date of service of a revocation
decision or a modification decision.
(4) No compensation shall be payable by the Authority when it
acts under the provisions of sub-article (1) where the reason for the
revocation or a modification of a licence or development
permission is based on fraud or error of law on the face of the
(5) Where the reason for revocation or modification of a
licence or development permission is public safety, the following
rules shall apply
(a) any demolition or other work that may be necessary
for compliance with the order shall be carried out by,
or at the expense of, the Authority;
(b) if on a claim made to the Authority within twelve
months of the date of the revocation decision or the
modification decision, it is shown that any person
interested in the land has incurred expenditure that is
rendered useless by the revocation or modification, or
has otherwise sustained loss or damage that is directly
attributable to the revocation or modification, the
Authority shall, subject to paragraph (c), pay to that
person compensation in respect of that expenditure,
loss or damage;
(c) no compensation shall be payable under this article
(i) in respect of loss or damage consisting of the
depreciation in value of any interest in the land
by virtue of the revocation or modification,
(ii) in respect of any work carried out before the
grant of the licence or permission that is revoked
or modified, or in respect of any other loss or
damage arising out of anything done or omitted
to be done before the grant of that licence or
permission;
(d) where compensation is payable under this article in
respect of expenditure incurred in carrying out any
work on land, if the competent authority under the
Land Acquisition (Public Purposes) Ordinance
acquires any interest in that land, any compensation
ENVIRONMENT AND DEVELOPMENT PLANNING
payable in respect of the acquisition of that interest
shall be reduced by an amount equal to the value of the
works in respect of which compensation is payable
under this article.
(1) The Authority may, having regard to the provisions of
this Act, regulations, plans, policies and to other material
considerations, by notice served on the owner or occupier of any
land, require any existing use or activity or any works to be
discontinued or any building, plant, equipment or other thing
whatsoever to be removed from any land, or requiring both such
discontinuance and removal.
(2) Where a discontinuance or removal order is made in respect
of an activity, works or use, or of a building, plant, equipment or
other thing lawfully carried on or in existence on the land
mentioned in the notice the Authority shall be liable to pay
compensation for any losses sustained as a result of the notice
Provided that any benefits derived from the same notice
shall be offset against the losses aforesaid
Provided further that no such compensation is due if the
authorisation or permission itself allows the Authority to request
the discontinuance of any existing use or activity or any works to
be discontinued or any building, plant, equipment or other thing
whatsoever to be removed from any land, or if such an order is
made by the Court.
3. Charges and contributions
(1) The Authority shall have power to levy a charge in
respect of any permission to carry out development, to be known as
the Development Permission Fee, including any application
therefor, in accordance with a schedule of charges established by it
with the concurrence of the Minister and of the Minister
responsible for finance, taking account of the nature of the
development, the timing of the development in relation to the
planned phasing thereof, of the conditions attaching to the
permission and of any other relevant consideration.
(2) The Authority shall have power to levy a contribution
towards the cost of the infrastructure services and other services or
facilities arising from any permission to develop land, to be known
as the Infrastructure Service Contribution, from the person
applying for such permission or carrying out such development, in
accordance with such rates a s the Authority may, with t he
concurrence of the Minister and of the Minister responsible for
finance, from time to time determine, taking account of the services
involved, the areas of development and other material
considerations.
(3) The sums collected by the Authority under sub-article (2)
shall be paid to the Government each year after a deduction
therefrom is made to cover the reasonable costs incurred in the
determination and levying of the contribution
ENVIRONMENT AND DEVELOPMENT PLANNING
Provided that with respect to contributions leviable by the
Authority on behalf of the Authority for Transport in Malta in
terms of article 20 of the Code of Police Laws, such regulations
shall be made with the concurrence of the Minister responsible for
the Authority for Transport in Malta and the Minister responsible
for finance, and such contributions leviable, as aforesaid shall,
notwithstanding anything contained in this Act, be paid by the
Authority to the Authority for Transport in Malta each year after a
deduction therefrom is made to cover the reasonable costs as may
be agreed between the two authorities incurred in the determination
and levying of the contributions.
(4) The Authority shall have power to levy a charge in respect
of any other application for a licence or authorisation made to it.
(5) The schedule of charges and the rates of contributions
established under this article, as from time to time in force, shall be
published as regulations and shall have effect as so published.
(6) The charges and contributions levied under sub-articles (1)
and (2) shall be collectively known as the "building levy".
No licence or development permission shall be granted, and
no activity or development authorised by an order shall be carried
out, unless and until any fee or contribution payable under article
79 has been paid to and received by the Authority; and any activity
or works carried out without such payment having been made and
received shall be deemed to be an activity or development carried
out without the permission of the Authority.
4. Scheduling and Conservation
(1) The Authority shall prepare, and from time to time
review, a list of areas, buildings, structures and remains of
geological, palaeontological, cultural, archaeological, architectural,
historical, antiquarian, or artistic or landscape importance, as well
a s a r e a s o f n a t u r a l b e a u t y, e c o l o g i c a l o r s c i e n t i f i c v a l u e
(hereinafter referred to as "scheduled property") which are to be
scheduled for conservation and may in respect of all or any one or
more of the scheduled property make conservation orders to
regulate their conservation
Provided that upon the issue of a conservation order the
owner shall have the right to immediate access at reasonable times
to all documentation of the Authority concerning the said order for
the purpose of studying the relative findings and considerations and
the owner may contest the said decision in writing with the
Authority within thirty days from the date when the order is
notified to him or is published in the Gazette, whichever is the
later.
(2) The list of conservation orders, and any additions or
amendments thereto, shall be published in the Gazette and in a
local newspaper. The Authority shall also notify any one of the
owners of any property subject of a conservation order of the fact
of its inclusion in the list and of any conservation order made with
respect to it. Notice of such conservation order shall also be affixed
on site. If none of such owners is known, or if it is not reasonably
ENVIRONMENT AND DEVELOPMENT PLANNING
possible to effect service on such owners, the said notice shall only
be affixed on site and no service on such owners as aforesaid need
be made. Notice of such conservation order shall be registered in an
index held for that purpose which identifies the property subject to
that order. The said index shall be held in an electronic form in
such a way that researches to determine whether a property is
subject to such an order may be carried out. The Authority shall
keep a copy of the said index in the office of the Land Registry and
shall issue a certificate which indicates whether a particular
property is subject to the said order on the payment of such fee as
may be prescribed.
(3) Where the Authority has scheduled property in terms of this
article, it shall register the said property in the index mentioned in
sub-article (2) indicating the said property as having been
scheduled, and the provisions of the said sub-article concerning the
indexing of conservation orders shall mutatis mutandis apply. The
list of scheduled property, and any additions or amendments
thereto, shall be published in the Gazette and in a local newspaper.
The Authority shall also notify any one of the owners of the
scheduled property of the fact of its inclusion in the list. A notice
of the said scheduling shall also be affixed on site. If none of such
owners is known, or if it is not reasonably possible to effect service
on such owners, the said notice shall only be affixed on site and no
service on such owners as aforesaid need be made.
(4) For the purposes of sub-articles (2) and (3), "site" means a
single property or more than one property, irrespective of who is
the owner of that property, which forms part of the land which is
scheduled or which is subject to a conservation order in terms of
this article.
(5) The carrying on of any work in, and the demolition,
alteration or extension of, any scheduled property is prohibited or
restricted as provided in this article or in a conservation order.
(6) No works of any description shall be carried out in or on
any scheduled property and no scheduled property shall be
demolished, altered or extended except with the permission of the
Authority granted on an application made to it and giving such
details as the Authority may require or in accordance with the
provisions of a conservation order; and for the purpose of this
article, damage to or destruction of any part of a scheduled
property shall be deemed to be a demolition thereof.
(7) A permission of the Authority and a conservation order
granted or made under this article may contain such conditions and
other provisions as the Authority may deem necessary or
expedient; and a conservation order may regulate any matter
affecting scheduled property.
(8) In respect of any scheduled property, the Authority shall
also have power to require the owner, by notice in writing, to
undertake such works generally, or as may be specified in the
notice, as may be necessary to ensure that no further deterioration
occurs. In default, the Authority may give a further notice to the
owner to carry out and complete the works within a specified time,
ENVIRONMENT AND DEVELOPMENT PLANNING
and if the owner is still in default it may itself carry out, or cause to
be carried out, the necessary works and recover the cost thereof
from the owner of the scheduled property.
(9) If any scheduled property is demolished in contravention of
any of the provisions of this article then, in addition to any penalty
or other effect under this Act, every person convicted of such
offence shall be liable to pay compensation to the Authority
calculated on the basis of whichever is the highest of the following
(a) the value of the thing destroyed,
(b) the cost of restoration or repair,
(c) the financial benefit which could be achieved as a
consequence of the demolition.
(10) An owner of scheduled property has a right to demand the
reconsideration of any scheduling of his property. Such demand
shall be entered in writing with the Authority within thirty days of
notification or publication in the Gazette, whichever is the later, of
the scheduling and the Authority shall decide within three months
of receipt by it of the demand for reconsideration.
(11) Any person who feels aggrieved by a decision of the
Authority under this article may appeal to the Tribunal for a
revocation or modification of such a decision.
(12) The Minister’s endorsement shall be sought when the
Authority deschedules a scheduled property or when it downgrades
the protection afforded to a scheduled property, and no such
descheduling or downgrading shall be valid before it is endorsed by
the Minister.
(13) When the Tribunal decides to deschedule a scheduled
property or to downgrade the protection afforded to a scheduled
property, the Tribunal shall seek the Minister’s endorsement and
the period for lodging an appeal from the Tribunal’s decision to the
Court of Appeal shall commence to run from the date in which the
Tribunal would have informed the appellant accordingly of the
Minister’s decision.
(14) Notwithstanding the provisions of article 41, an appeal to
the Tribunal from a scheduling of property or the issue of a
conservation order shall not stay the execution of such scheduling
or conservation order.
(1) If a property, site or area which is not scheduled or
protected under the provisions of this Act or any regulations made
thereunder, but which the Authority believes could have an
importance or value sufficient to have it scheduled or protected, is
at risk of being demolished, damaged or destroyed, the Authority
may make an emergency conservation order and take such further
steps for the protection of such property, site or area as it may deem
necessary and the provisions of the proviso to article 81(1) shall
apply
Provided that in case of urgency the Chairman of the
Authority may make an emergency conservation order without the
need of consulting the other members of the Authority.
ENVIRONMENT AND DEVELOPMENT PLANNING
(2) An emergency conservation order shall be published in the
Gazette and shall have effect immediately on its publication.
(3) An emergency conservation order shall, for a period of six
months from its publication in the Gazette, have the same effect as
the inclusion of the property to which it refers in the list of
scheduled property. It shall cease to have any effect on the
expiration of the period aforesaid.
(4) Notwithstanding the provisions of article 41, an appeal to
the Tribunal from an emergency conservation order shall not stay
the execution of such order.
PART VI
Powers of the Authority and Enforcement of Control
1. Right of Entry
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
2. Enforcement of Control
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016).
(Repealed by Legal Notice 107 of 2016, made under article
87 of Act I of 2016 and article 35 of Act VII of 2016);
(1) If it appears to the Authority that an activity is being
carried out without the grant of a permission or licence required
under this Act or that any conditions subject to which such
permission or licence was granted in respect of any such activity
are not being complied with or such activity is in contravention to
this Act or Regulations issued under this Act, the Authority may
issue stop orders to any such person carrying out such an activity
Provided that the Authority may issue a partial stop order
requiring work or activity to be stopped forthwith only in relation
to that part of the activity to which the order applies and not in
relation to the whole activity.
(2) If it appears to the Authority that any development is being
carried out without the grant of permission required under this Act,
or that any conditions subject to which such permission was
granted in respect of any development are not being complied with,
the Authority shall serve a stop notice on the owner of the land or
on the occupier of the land or on both, as the Authority deems most
expedient, requiring works or the development to be stopped
forthwith
Provided that the Authority may issue a partial stop notice
requiring work to be stopped forthwith only in relation to that part
of the development to which the notice applies and not in relation
to the whole development.
(3) A copy of the order or notice mentioned in sub-articles (1)
and (2) may also be served on any representative, builder,
contractor or workman on the site and the Authority may also affix
such notice in a prominent position at a point of entry onto the site.
ENVIRONMENT AND DEVELOPMENT PLANNING
(4) The Authority shall, in the case of a notice issued under
sub-article (2) also inform
(a) the local council in whose locality the land mentioned
in sub-article (2) is found;
(b) the perit responsible for the said works, if known, that
a stop notice as aforesaid has been issued by the
Authority
Provided that the non-compliance with the provisions of
this sub-article shall in no case invalidate any notice issued under
sub-articles (1) and (2).
(5) The Authority shall register all stop orders and notices and
all other enforcement notices in terms of this Act in the index
mentioned in article 81(2), and the provisions of the said article
concerning indexing of conservation orders shall mutatis mutandis
apply to stop and other enforcement notices in terms of this Act.
(6) Any order or notice made under this article shall contain a
detailed description of the infringements being alleged and where
applicable, a site plan indicating the land which is the subject of
such a notice shall be annexed thereto.
(7) If it appears to the Authority that any development of land
has been carried out after the coming into force of this Act without
the grant of permission required in that behalf under this Act, or
that any conditions subject to which such permission was granted
in respect of any development have not been complied with, the
Authority may, having regard to the provisions of development
plans, planning policies and any other material consideration, serve
on the owner of the land or on the occupier of the land or on both as
the Authority deems most expedient an enforcement notice and
shall inform the persons mentioned in sub-article (4) of such an
enforcement notice, requiring such steps as may be specified in the
notice to be taken within such time as may also be so specified for
restoring the land to its condition before the development took
place or for removing such development or for securing compliance
with the conditions aforesaid, as the case may be; and in particular,
but without prejudice to the generality of the aforesaid any such
notice may, for the purpose aforesaid, require the demolition or
alteration of any buildings or works, the discontinuance of any use
of land, or the carrying out on the land of any building or other
operations.
(8) An order or notice given under any of the foregoing
provisions of this article shall
(a) in respect of any requirement stopping or prohibiting
further activity, works or development or requiring the
cessation of a use, or in respect of any requirement of
the notice if the notice refers to development listed in
the Sixth Schedule or if the notice is issued under the
provisions of article 88(1) in relation to a development
situate on a site listed in the Sixth Schedule, or if the
notice is issued under the provisions of article 88(2),
take effect immediately upon service of the notice in
terms of sub-articles (1) and (2) notwithstanding that
ENVIRONMENT AND DEVELOPMENT PLANNING
an application for a licence or development permission
for the activity or development referred to in the order
or notice has been submitted or an appeal has been
lodged against the order or notice;
(b) in respect of any other requirement, shall take effect at
the expiration of such period (being not less than
fifteen days and not more than thirty days after service
thereof) as may be specified therein.
(9) When an application for development permission has been
submitted before the expiry of the period mentioned in sub-article
(8)(b) -
(a) for the retention on the land of any buildings or works
to which the enforcement notice relates; or
(b) for the continuance of any use of the land to which the
enforcement notice relates,
the operation of the notice, in respect of any requirement other than
a r e q u i r e m e n t s t o p p i n g o r p r o h i b i t i n g a n y f u r t h e r w o r k or
development, or requiring the cessation of a use, shall be
suspended pending the final determination of the application, and if
the permission applied for is granted on that application and comes
into operation, the enforcement notice shall cease to have effect
Provided that if the notice refers to development listed in
the Sixth Schedule, or if the notice is issued under the provisions of
article 88(1) in relation to a development situate on a site listed in
the Sixth Schedule or if the notice is issued under the provisions of
article 88(2), the operation of the notice shall not be suspended
pending the final determination of the application.
(10) Any application to regularise an activity or a development
shall be dismissed forthwith if a requirement in the order or notice
stopping or prohibiting further activity, work or development, or
requiring the cessation of a use, has not, both prior or during the
pendency of the application, been complied with or if any penalty
or other payment for which any person has become liable under this
Act in respect of the relevant activity or development has not been
paid or if the application is made to regularize a development listed
in the Sixth Schedule.
(11) The Authority may exercise its powers under article 90(1)
notwithstanding that a second or subsequent application intended to
regularize the illegal activity or development may have been filed
with the Authority concerning the same or part of the same activity
or site, irrespective of whether the said application is filed by the
same applicant or by another applicant.
(12) Any person who feels aggrieved by any order or notice
served on him may, within fifteen days from the service of the
notice, appeal against it to the Tribunal, and on any such appeal the
Tribunal
(a) if satisfied that a licence or permission was granted
under this Act, or under any other law which preceded
this Act regulating the activity in question or building
permits, for the activity or the development to which
ENVIRONMENT AND DEVELOPMENT PLANNING
the order or notice relates, or that no such licence or
permission was required in respect thereof, as the case
may be, and that the conditions subject to which such
licence or permission was granted have been complied
with, shall quash the order or notice to which the
appeal relates or such part thereof in respect of which
the Board is satisfied as aforesaid;
(b) in any other case, shall dismiss the appeal.
(13) The appellant shall submit to the Tribunal together with his
appeal a copy of all relevant licences or development permissions,
other permits or other relevant information in terms of which a
licence or a development permission has been granted to carry out
the activity or development mentioned in the order or notice served
on him which is the subject of the appeal proceedings; and if the
Tr i b u n a l i s s a t i s f i e d t h a t n o s u c h l i c e n c e o r d e v e l o p m e n t
permission or permits exist or that there is no authorization,
howsoever called, in terms of which the activity or the
development could have been carried out, the Board shall forthwith
dismiss the appeal.
(14) If before an appeal is lodged or during the pendency of an
appeal, the appellant submits to the Authority an application for a
licence or development permission regarding the activity or land
mentioned in the order or notice, the Tribunal shall dismiss the
appeal if it is satisfied that the said application is intended to
regularize the activity or development mentioned in the order or
notice.
(15) Where an appeal is dismissed, the Tribunal may direct that,
in respect of any requirement, other than a requirement stopping or
prohibiting any further activity or work or development, or
requiring the cessation of a use, the order or notice shall not come
into force until such date, being a date not earlier than fifteen days
after the determination of the appeal, as the Tribunal thinks fit.
(16) The Tribunal may correct any defect or error in the
enforcement notice provided that the appellant shall be given
sufficient time to prepare and put forward his case.
(17) Where the illegal activity or development is being carried
out at sea the provisions of this article shall apply in such manner
that any reference therein to the owner of the land or the occupier
of the land shall be deemed to be a reference to the person carrying
out the activity or development, and any reference to land shall be
deemed to be a reference to the area at sea where the activity or
development occurs.
(18) All notices or orders issued under this Part shall be
accompanied by a site plan.
If it appears to the Authority that anything which is
prohibited or restricted or subject to a condition by or under any of
the provisions of article 81 or under regulations made under this
Act intended to protect natural habitats and species, is being done
or carried on or has been done or carried on in contravention of any
such prohibition, restriction or condition or without any permission
ENVIRONMENT AND DEVELOPMENT PLANNING
or other requirement, or without compliance with any condition,
mentioned in those articles or any orders made thereunder, the
Authority shall serve a notice on the owner of the land or on the
occupier of the land or on both as the Authority deems most
expedient and shall also inform of the issue of such notice the
persons mentioned in article 86(4), requiring such steps as may be
specified in the notice, including the discontinuance of anything
being done or carried on, to be taken within such time as may also
be specified in the notice. The provisions of the proviso to article
86(4) shall also apply to any notice under this article.
(1) If it appears to the Authority that the amenity of any
area is injured by the appearance or condition of any building or
any land, being a garden, vacant site or other open land, or by the
appearance of a site upon which development or construction or
any other works are taking or have taken place, the Authority shall
serve an enforcement notice on the owner of the land or on the
occupier of the land or on both as the Authority deems most
expedient and shall also inform of the issue of such notice the
persons mentioned in article 86(4), requiring such steps to be taken
for abating the injury as may be specified in the notice. The
provisions of the proviso to article 86(4) shall also apply to any
notice under this article.
(2) The Minister may, in consultation with the Authority, by
regulations under this article provide that property which is in a
state of disrepair and, or constitutes a danger, shall be demolished
by its owner or by the Authority in accordance with the provisions
of article 90. Without prejudice to the generality of the foregoing,
such regulations may prescribe
(a) the manner through which the state of the property is
certified as constituting a danger,
(b) the methodology and procedures to be used by the
Authority in any action it may take as aforesaid.
A notice under articles 87 and 88 is also in this Act
referred to as "enforcement notice" and, unless the context
otherwise requires and subject to such modifications and
adaptations as may be necessary to give full effect to the provisions
of those articles, wherever that expression appears in this Act it
shall include a notice given under those articles.
(1) If any steps or other action, including any
discontinuance, stoppage or similar requirement, required to be
taken by an enforcement notice have not been taken within the time
specified therein, the Authority may enter on the land, or the area at
sea and take such steps or other action as aforesaid, including the
d i s a b l i n g o r r e m o v a l o f a n y e q u i p m e n t , m a c h i n e r y, t o o l s ,
belongings, vehicles or other objects that may be on site and the
carrying out of any works necessary to comply with what is
requested in the enforcement notice and may for such purpose
request the assistance of the Police Force, any local council, any
department of Government or any agency of Government; and the
Police Force shall for such purpose exercise such powers as are
vested in them at law.
ENVIRONMENT AND DEVELOPMENT PLANNING
(2) Where the removal of an illegal development involves by
necessity the removal also of a development which is not illegal,
the Authority may proceed to remove also such other development,
the removal of which is necessary as aforesaid.
(3) Notwithstanding the provisions of any other law and saving
the provisions of article 46 of the Constitution and article 4 of the
European Convention Act, no precautionary act may be issued by
any court against the Authority restraining it from the exercise of
any of the powers conferred upon it by this article.
(4) Subject to the provisions of regulations made under this
Act, when an enforcement notice has not been appealed or where
an enforcement notice has been appealed but has been confirmed
by the Appeals Board or by the Court of Appeal, as the case may
be, and the owner of the land subject to an enforcement order fails
to comply with the said order within the period therein prescribed,
such person shall be liable to a maximum penalty of not more than
fifty euro for every day the default continues after the expiration of
the said period as the Authority may prescribe under the said
regulations; and the Authority may recover such penalty from the
said person as a civil debt owing to it.
(5) All expenses reasonably incurred by the Authority in the
exercise of its powers under this article, or any other amount due to
the Authority under any other provision of this Act or regulations
made thereunder shall, be recoverable as a civil debt by the
Authority from the owner of the land, or from any occupier of the
land, or from any person responsible for the acts mentioned in the
notice, including a notice of payment, or an applicant, subject to
such right of recovery such person may have against any other
person. The Authority shall not be liable for any damages as a
result of the exercise of its powers under this article unless it is
proved that such damage resulted from gross negligence on the part
of the Authority, its officers and agents.
(6) Where the Authority desires to sue for the recovery of a
debt due to the Authority under any law or regulation which it is
entitled to enforce, the Chairman, Chief Executive Officer or an
officer of the Authority duly authorised by the Authority to act on
its behalf may make a declaration on oath before the Court registrar
or before any other officer authorised to administer the oath in
judicial matters, wherein he states the nature of the debt and the
name of the debtor and confirm that it is due.
(7) The declaration referred to in sub-article (6) shall be served
upon the debtor by means of a judicial act and it shall have the
same effect as a final judgement of the competent court unless the
debtor shall, within a period of twenty days from service upon him
of the said declaration, oppose the claim by filing an application
demanding that the court declare the claim unfounded.
(8) The application filed in terms of sub-article (7) shall be
served upon the Authority, which shall be entitled to file a reply
within a period of twenty days. The court shall appoint the
application for hearing on a date after the lapse of that period.
(9)
Any debts due to the Authority shall be prescribed by the
ENVIRONMENT AND DEVELOPMENT PLANNING
lapse of the period of five years from the date on which the debt
was due.
(1) Notwithstanding the other provisions of this Act, any
person who is served with an enforcement notice in respect of
development referred to in Schedule 8, shall have the right to claim
that such notice shall not be executed. The said person shall furnish
the Authority with the requisite proof to that effect including any
relevant documentary evidence and such other evidence as the
Authority considers necessary in accordance with and subject to the
procedure established by the Authority.
(2) An enforcement notice falling within the provisions of sub-
article (1), the development in question shall not be considered as
having been regularised in terms of this Act unless and until a
development permission has been granted to cover the development
in question and a penalty fixed by the Authority within the limits
established in article 93 has been paid
Provided that a person requested to pay such a penalty may
appeal from such request in the manner provided for in article 93.
(3) When the Authority receives an application for
development permission requesting amendments, alterations,
additions or extensions to a development referred to in Category A
of Schedule 8, the applicant shall request the Authority to sanction
the said illegal development in terms of the provisions of this Act,
if such sanction is possible in terms of law. Where the illegal
development has not been sanctioned no further development
permission, other than for that type of development which may be
prescribed by the Minister, after consultation with the Authority,
from amongst the development mentioned in article 63(9)(a) and
(b), may be granted with respect to the land in question unless and
until the illegal development is removed.
(4) Where any person claims to the Authority that an
enforcement notice falls within the provisions of sub-article (1),
and the Authority does not accept such claim, the period of fifteen
days mentioned in article 86(12) shall commence to run from the
date that the Authority serves such person with a notice to the
effect that it is not accepting such claim.
(5) The Minister may, after consultation with the Authority,
make regulations to give better effect to the provisions of this
article.
(1) The following provisions shall have effect with respect
to any development which has taken place or is to take place after
the date of the coming into force of the Development Planning
Act * , hereinafter referred to as "new development".
(2) No service consisting in the supply of water or electricity to
any new development shall be provided by any authority unless
there is in respect of such development a certificate issued by the
Authority stating that the development is in accordance with a
development permission or falls under Category B of the Eighth
*Repealed by this Act; but see footnote to article 8(2)(a).
ENVIRONMENT AND DEVELOPMENT PLANNING
Schedule.
(3) In any of the circumstances in which the Authority may
serve an enforcement notice or order under any of the provisions of
this Act, the Minister shall, in consultation with the Authority, by
regulations under this article provide that such a notice is
registered with the Land Registry and served on the Director of the
Public Registry of Malta in the case of land situated in the Island of
Malta and on the Director of the Public Registry of Gozo in the
case of land situated in Gozo. Without prejudice to the generality of
the foregoing, such regulations may prescribe
(a) the procedures to be used by the Authority in making
such a registration;
(b) the prohibition of the transfer inter vivos by any title
whatsoever of any land in respect of which a notice as
aforesaid may be, or has been, served, and the transfer
or creation of any real right thereon, by any title inter
vivos whatsoever and that any transfer of any land and
any transfer of any real right thereon, made by an act
inter vivos under any title whatsoever, shall be null
and without effect.
(4) The provisions of article 41 shall apply to an order made
under this article, and to any refusal to revoke such an order, as
they apply to a decision of the Authority referred to in sub-article
(1)(a) of that article.
(1) Notwithstanding any other law providing for the trial
and punishment of offences, where the Authority believes that a
person has committed an offence against this Act, other than an
offence under article 94(1)(d), the Authority may give notice in
writing to such person describing the offence of which the person is
accused, indicating the steps to be taken to remedy the offence and
a penalty which he is required to pay in respect of that offence
Provided that the Authority may not require the payment of
a penalty higher than fifty thousand euro and shall be in accordance
with a schedule of penalties, which the Minister, after consulting
the Authority, and with the concurrence of the Minister responsible
for finance, may by regulations prescribe
Provided further that any person who feels aggrieved by a
decision of the Authority under this sub-article, may appeal to the
Tribunal for a revocation or modification of such a penalty.
(2) Where a notice under this article has been given, the person
named in the notice may, within twenty-one days of the service of
the notice, accept responsibility for the offence specified in the
notice and within the same period or such further period as the
Authority may allow, remedy the offence and pay, or undertake in
writing to pay, the penalty indicated in the notice or such other
penalty as the Authority may accept in lieu, and in any such case
(a) the person named in the notice shall be deemed to have
committed the offence and to have admitted his guilt
in respect thereof, and the penalty paid, or agreed to be
paid, shall be the penalty to which he became liable to
ENVIRONMENT AND DEVELOPMENT PLANNING
pay;
(b) if the offence is remedied and the penalty is paid
within the period, or further period, aforesaid, no
further proceedings may be taken against the said
person in respect of the same facts
Provided that the agreement to pay to the compromise
penalty shall not extinguish any civil liability to make
good any damages to any person or authority and any
liability arising under article 38;
(c) if the penalty is not paid within the period, or further
period, aforesaid, it shall be treated as if it were a
penalty ordered to be paid by a court and proceedings
may be taken accordingly to recover the same as a
civil debt due to the Authority.
(3) Where the person to whom notice is given under sub-article
(1) does not accept or, having accepted such responsibility, fails to
remedy the offence within the time aforesaid, ordinary criminal
proceedings may be taken against him in accordance with the
provisions of law applicable to the offence.
PART VII
Offences
(1) Any person who -
(a) carries out any development on any land or allows any
development to be carried out on land of which he is
an owner without a development permission as in
force at the time of such development, or, if the
development is carried out with a development
permission, fails to comply or to cause compliance
with any condition, restriction or other limitation to
which the permission is subject; or
(b) acts in contravention of any of the provisions of article
81 and 82 in respect of any scheduled property, an
emergency conservation order; or
(c) having been served with an enforcement notice or
other notice under articles 78, 86, 87 or 88 fails to
comply with any of the requirements of such notice
within the time therein specified; or
(d) hinders, obstructs, molests or interferes with, or
attempts to hinder, obstruct, molest or interfere with,
any officer or employee of the Authority, or any police
officer, or any public officer, or any employee or
servant of any department of Government or of any
agency of Government or of any local council, in the
execution of his duties under the law or fails to comply
with any reasonable requirement demanded of him by
any such person as aforesaid or otherwise to assist him
in the carrying out of the said duties, or knowingly
furnishes such person with false information or
neglects or refuses to give any information required
ENVIRONMENT AND DEVELOPMENT PLANNING
for the purpose aforesaid; or
(e) makes a declaration for any of the purposes of this Act
which is false, misleading or incorrect in any material
respect,
shall be guilty of an offence against this Act and shall be liable, on
conviction, to a fine (multa) of not less than one thousand five
hundred euro and not exceeding one hundred thousand Euro, and in
respect of an offence under paragraph (d) or, in the case of an
offence under paragraph (c) if the offender persists in the offence
for more than three months, also to imprisonment for a term of not
less than three months and not exceeding three years
Provided that, and without prejudice to the provisions of
articles 81(9) and article 90(3) and (4) and without prejudice to the
maximum fine above established, the minimum fine (multa) to
which an offender is liable under this article shall not be less than
the value of any work carried out without permission or in violation
of any conditions to which such permission was subject.
(2) The Court, besides awarding the punishment referred to in
sub-article (1), shall order the offender to remove the causes of the
offence and to undo anything which was done without a permission
or to comply with the conditions imposed in the permission, as the
case may be, within a time sufficient for the purpose, but in any
case not exceeding three months from the date of the judgment, to
be fixed by the court; and, if the offender fails to comply with any
such order within the time so fixed, he shall be liable to a fine
(multa) of not less than fifty euro and not more than one hundred
and thirty euro, as the court may fix, for every day the default
continues after the expiration of the said time and may also order
the modification, suspension or revocation of any authorisation or
permission.
(3) Proceedings against any person for any offence as is
mentioned in sub-article (1) shall be taken before the Court of
Magistrates (Malta) or the Court of Magistrates (Gozo), as the case
may be, as courts of criminal judicature in accordance with the
provisions of the Criminal Code
Provided that, notwithstanding the provisions of article
376(1)(b) of the Criminal Code, the Court shall, at the request of
the prosecution or of the accused, take down evidence given by the
witnesses in the manner provided for either in article 390(6) of the
said Code or in any law for the time being in force.
(4) Article 21 of the Criminal Code and the provisions of the
Probation Act shall not apply to any offences referred to in this
article.
(5) The filing of an application intended to regularise any
illegal development or activity to which a prosecution refers, and
the filing of an appeal against a refusal of such an application shall
not be a bar to the continuation of such a prosecution and the court
shall continue to hear such a case and shall give judgement and
shall issue an order in terms of sub-article (2) as if such an
application or such an appeal had never been filed
ENVIRONMENT AND DEVELOPMENT PLANNING
Provided that where such an activity or development has
been regularised no fine under sub-article (2) shall be due in
respect of the time after the development has been regularised.
(6) Notwithstanding the provisions of the Criminal Code, the
Attorney General shall always have a right of appeal to the Court of
Criminal Appeal from any judgement given in proceedings arising
out of this Act or of any regulations, rules or orders made
thereunder.
In any proceeding or prosecution under this Act, a copy of
any order, notice, decision or other document purporting to have
been made under this Act and purporting to have been signed by
the Chairman of the Authority or by the Chief Executive Officer or
any Director, shall be accepted as evidence of the order, notice,
decision or other document, and of the facts appearing therein,
without further proof.
PART VIII
Miscellaneous
(1) Where any notice or other instrument or document
whatsoever is required or authorised to be served or given by or
under this Act, it may be served or given in any of the following
manners
(a) by delivering it to the person on whom it is to be
served or to whom it is to be given; or
(b) by leaving it at the usual or last known place of abode
of that person or, if such person has furnished an
address for service, at that address; or
(c) by sending it in a registered letter addressed to that
person at the place of abode or the address for service
aforesaid; or
(d) in the case of a body corporate or other body of
persons, by delivering it to an officer or servant
thereof at the registered or principal office, or sending
it in a registered letter addressed to the body aforesaid
at that office; or
(e) in any case in which it is not reasonably possible to
effect service in any of the foregoing manners whether
on all or on any one or more of the persons on whom
service is to be made or notice is to be given, by
affixing the document to be served or given in a
conspicuous place on the land to which it relates and
keeping it so affixed for a period of not less than seven
days.
(2) Where the notice or other document is required or
authorised to be served or given to any person as having an interest
in land, and the name of that person cannot be ascertained after
reasonable inquiry, or is required or authorised to be served on an
occupier of land, the notice shall be deemed to be duly served or
given if it is served or given in any of the manners indicated in sub-
article (1) and addressed to the person having an interest in the land
ENVIRONMENT AND DEVELOPMENT PLANNING
by the description of "owner" or "occupier", or "owners" or
"occupiers", as the case may require.
(1) The Minister may with effect from such date as may be
established by notice in the Gazette repeal the Development
Planning Act and the Environment Protection Act * and different
dates, rules and procedures may be so established for the
revocation and, or applicability of different provisions thereof.
(2) The Minister may by regulations made under this Act,
provide that for the words "Director", "Director of Planning" and
"Director Environment Protection", wherever they may occur in
regulations made under the Development Planning Act or
Environment Protection Act, there shall be substituted the word
"Authority" and any definition of "Director", "Director of
Planning" and "Director Environment Protection" in regulations
made under the same Acts shall be deleted.
(3) Any order, rule, regulation, bye-law, notice, plan or policy
or other instrument having the force of law made under the
authority or kept in force under any of the provisions of the
Development Planning Act or the Environment Protection Act shall
continue in force and shall continue to have effect as if made under
this Act and may be amended, substituted or revoked accordingly.
(4) Any licence, permission, authority, order, notice or
certificate, or any prosecution or charges granted or made under or
kept in force under any of the provisions of the Development
Planning Act or the Environment Protection Act and still in force
immediately before the date of coming into force of this Act shall
as from such date continue in force as if it were a licence,
permission, authority, order, notice or certificate, or prosecution or
charges granted or made under a corresponding provision of this
Act, and any such licence, permission, authority, order, notice or
certificate, or prosecution or charges as aforesaid shall be treated
and dealt with accordingly
Provided that in the case of any such licence, permission,
authority, order, notice or certificate issued as operative for a
specific period, such licence, permission, authority, order or
certificate shall remain operative for such a period from the date
such licence, permission, authority, order, notice or certificate was
issued.
(5) The Users’ Committee established under the provisions of
article 36, the Heritage Advisory Committee established under the
provisions of article 37, the Environment and Planning Review
Tribunal established under the provisions of article 40 and the
Environment Fund established under the provisions of article 38,
shall perform and succeed all the functions, assets, rights,
liabilities and obligations of the Users’ Committee, the Heritage
Advisory Committee and the Planning Appeals Board respectively
established under the provisions of the Development Planning Act
and the Environment Fund established under the provisions of the
Environment Protection Act.
*but see footnote to article 8(2)(a).
ENVIRONMENT AND DEVELOPMENT PLANNING