S.I. No. 294/2026 - EirGrid, Electricity and Turf (Amendment) Act 2022 Section 10(4) extension order

5 Articles / Provisions · Ireland
Open official source Machine-readable Markdown (.md)

Statutory Text (5 Articles)

ISB SI

1. This Order may be cited as the EirGrid, Electricity and Turf (Amendment) Act 2022 Section 10(4) extension order

ISB SI

3. In this Order, “Act of 2022” means the

EirGrid, Electricity and Turf (Amendment) Act 2022

ISB SI

4. This Order extends the operational period of Temporary Emergency Generation Plant (TEG 2) by 12 months, amending the cessation date set out in Section 3(2) of the Act of 31 March 2027 to 31 March 2028 as allowed for under in Section 10(1) and in accordance with section 10(4)

GIVEN under my Official Seal,

24 June, 2026.

DARRAGH O’BRIEN,

Minister for Climate, Energy and the Environment.

ISB SI

Notice of the making of this Statutory Instrument was published in

“Iris Oifigiúil” of

26

th June,

2026.

I, DARRAGH O’BRIEN, Minister for Climate, Energy and the Environment, in exercise of the powers conferred on me by subsection (4) of

section 10

of the

EirGrid, Electricity and Turf (Amendment) Act 2022

, hereby make the following Order, with respect to which, pursuant to subsection (4) of that section, a draft has been laid before each House of the Oireachtas and a resolution approving the draft has been passed by each such House