1. The name of the applicant for permission (and

not

his or her agent) should be inserted here.

ISB SI

2. The location, townland or postal address of the land or structure to which the application relates should be inserted here.

ISB SI

3. A brief description of the nature and extent of the development should be inserted here.

ISB SI

5. Either the signature of the applicant or the signature and contact address of the person acting on behalf of the applicant should be inserted here.

ISB SI

6. The date that the notice is erected or fixed at the site should be inserted here.

GIVEN under my Official Seal,

16 December, 2023.

DARRAGH O’BRIEN,

Minister for Housing, Local Government and Heritage.

EXPLANATORY NOTE

(

This note is not part of the Instrument and does not purport to be a legal interpretation

)

These Regulations are made under

sections 37

P(1),

177

N(1) and

262

of the

Planning and Development Act 2000

, as amended, and come into force on the date of signature. The purpose of these Regulations is to amend Parts 7, 19, 22 and Schedule 3 of the Planning and Development Regulations 2001, as amended, to provide for consequential and supplementary amendments arising from the changes to the substitute consent provisions of the

Planning and Development Act, 2000

provided for in the

Planning and Development, Maritime and Valuation (Amendment) Act 2022

. The Planning and Development, Maritime and Valuations (Amendment) Act 2022 includes provisions which

• enable the streamlining of substitute consent procedures for applications to regularise existing development requiring retrospective environmental impact assessment or appropriate assessment;

• provide for a single-stage application process;

• allow pre-application consultations with the Board on proposed applications;

• extend simultaneous applications for both retrospective and future facing development to An Bord Pleanála;

• provide for the Board to refuse to consider an application for retention of unauthorised development where either or both an environmental impact assessment/appropriate assessment was or is required;

• specify the additional information that can be provided by an applicant when a request received by the Board under section 177K of the

Planning and Development Act 2000

applies;

• enable the Board to request any necessary further information in assisting with the decision making of the consent; and

• repeal temporary substitute consent provisions provided for by the Planning and Development, and Residential Tenancies Act 2020.

These regulations will align the Planning and Development Regulations 2001 with the

Planning and Development Act 2000

as amended. The Regulations will also extend the timeline for receipt of submissions or observations in relation to substitute consent applications.

ISB SI

7. Article 231 of the Principal Regulations is amended by substituting “8 weeks” for “5 weeks” in both places where it occurs.

Amendment of Article 233 of the Principal Regulations

ISB SI

8. Article 233 of the Principal Regulations is amended—

(1) by inserting the following sub-article after sub-article 233(1)(b)—

“233(1A) Where the Board requests further information under sections 177K(2CA) or 177K(2CA) and 177K(2CC) of the Act, notwithstanding that an application for substitute consent has already been submitted to the Board articles 227(2)(cb) and 227(2A) shall apply.”

Amendment of Article 234 of the Principal Regulations

ISB SI

9. Article 234 of the Principal Regulations is amended by substituting “8 weeks” for “5 weeks”.

Amendment of Article 235 of the Principal Regulations

ISB SI

10. Article 235 of the Principal Regulations is amended by deleting “233F, or 233H”.

Amendment of Article 264 of the Principal Regulations

ISB SI

11. Article 264 of the Principal Regulations is amended by substituting—

(1) “development of land” for “quarry”,

(2) “EIAR” for “EIS”, and

(3) “8 weeks” for “5 weeks”.

Amendment of Article 270 of the Principal Regulations

ISB SI

12. Article 270 of the Principal Regulations is amended by substituting “8 weeks” for “5 weeks” in both places where it occurs.

Amendment of Article 271 of the Principal Regulations

ISB SI

13. Article 271 of the Principal Regulations is amended by substituting “8 weeks” for “5 weeks” in both places where it occurs.

Amendment of Article 273 of the Principal Regulations

ISB SI

14. Article 273 of the Principal Regulations is amended in sub-article (1) by substituting “EIAR” for “EIS” in each place where it occurs.

Amendment of Article 274 of the Principal Regulations

ISB SI

15. Article 274 of the Principal Regulations is amended—

(1) in sub-article (1) by substituting—

(a) “a development of land of which the development type is listed in Schedule 5 Part 2 shall be accompanied by an EIAR” for “a quarry which does not exceed 5 hectares is not accompanied by an EIS”, and

(b) “to submit EIAR” for “to submit EIS”.

Amendment of Article 276 of the Principal Regulations

ISB SI

16. Article 276 of the Principal Regulations is amended by substituting—

(1) “EIAR” for “EIS” in each place where it occurs, and

(2) “8 weeks” for “5 weeks” in each place where it occurs.

Amendment of Article 277 of the Principal Regulations

ISB SI

17. Article 277 of the Principal Regulations is amended by substituting “EIAR” for “EIS”.

Amendment of Article 278 of the Principal Regulations

ISB SI

18. Article 278 of the Principal Regulations is amended by substituting “EIAR” for “EIS” in both places where it occurs.

Amendment of Article 279 of the Principal Regulations

ISB SI

19. Article 279 of the Principal Regulations is amended by substituting “EIAR” for “EIS” in each place where it occurs.

Amendment of Article 280 of the Principal Regulations

ISB SI

20. Article 280 of the Principal Regulations is amended by substituting “EIAR” for “EIS”.

Amendment of Article 281 of the Principal Regulations

ISB SI

21. Article 281 of the Principal Regulations is amended by substituting “8 weeks” for “5 weeks”.

Revocations

ISB SI

22. Articles 233A to 233H (inserted by Article 4 of Planning and Development (Amendment) (No.2) Regulations 2020 (S.I. No. 692/2020)) of the Principal Regulations are revoked.

Schedule

ISB SI

23. Schedule 3 of the Principal Regulations is amended—

(1) by substituting Form A set out in the Schedule to these regulations for Form No. 6,

(2) by deleting Form No. 6A,

(3) section 13 of Form No. 7 is amended by substituting “Is the remedial Environmental Impact Assessment Report included with this application?” for “Does the development require the preparation of a remedial Environmental Impact Assessment Report?”, and

(4) by substituting Form B set out in the Schedule to these regulations for Form No. 10.

Schedule

Form A

Form No. 6

Article 225

Application to An Bord Pleanála for substitute consent: site notice

APPLICATION TO AN BORD PLEANÁLA FOR SUBSTITUTE CONSENT SITE NOTICE

I, ..............................................................

1

, intend to apply for substitute consent for development at this site ....................................................................

2

..............................................................................................................................

The development consists of...............................................................................................................................................................................

3

The application is accompanied by a remedial Environmental Impact Assessment Report and remedial Natura impact statement [delete as appropriate].

Submissions or observations may be made on the application, to An Bord Pleanála, 64 Marlborough Street, Dublin 1, www.pleanala.ie without charge. Submissions or observations must be in writing and made within the period of 8 weeks beginning on the date of receipt of the application by An Bord Pleanála and such submissions and observations will be considered by An Bord Pleanála in making a decision on the application. An Bord Pleanála may grant the consent subject to or without conditions, or may refuse to grant it.

The application for consent may be inspected, or purchased at a fee not exceeding the reasonable cost of making a copy, at the offices of An Bord Pleanála, or the relevant planning authority during its public opening hours.

Any enquiries relating to the application process should be directed to An Bord Pleanála (Tel. 01-8588100).

Signed: ..........................................................................

4

Date of erection of site notice .......................................

5

Directions for completing site notice

ISB SI

Notice of the making of this Statutory Instrument was published in

“Iris Oifigiúil” of

19

th December,

2023.

NOW I, DARRAGH O’BRIEN, Minister for Housing, Local Government and Heritage, in exercise of the powers conferred on me by subsection (1) of section 37P and subsection (1) of section 177N and

section 262

of the

Planning and Development Act 2000

(No. 30 of 2000) (as adapted by the Housing, Planning and Local Government (Alteration of Name of Department and Title of Minister) Order 2020 (

S.I. No. 408 of 2020

)), hereby make the following regulations

Citation

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →