705.110
RLE
CH-TI
Art. 24 RLE Regolamento di applicazione della legge edilizia (RLE)
RLE
Art. 24 RLE
1 Il permesso può essere revocato, previa diffida, se i lavori non vengono proseguiti nei modi e nei termini usuali; l'autorità esige in tal caso il ripristino di una situazione conforme al diritto, ordinando se del caso il riordino del fondo. [37]
2 Il Municipio informa il Dipartimento sulle violazioni della legge sull'esercizio della professione d'impresario costruttore.
[37] Cpv. modificato dal R 13.11.1996; in vigore dal 1.1.1997 - BU 1996, 377.
Decisioni giudiziarie che applicano questa disposizione (6)
52.2017.458 · ti (art. 24 RLE)
Administrative Court Overturns Revocation of Building Permit Due to Premature Action
This provision was the legal basis for the municipal resolution to revoke the building permit due to non-continuation of work, and its potential violation was the core issue leading to the appeal's success.
52.2008.110 · ti (art. 24 RLE)
Appeal Regarding Building Permit Denial for Reconstruction Under Current Zoning Regulations
Cited in relation to the possibility of revoking a building permit if work is not continued appropriately.
52.1998.118 · ti (art. 24 cpv. 1 RLE)
Developer v. Municipality over Lapsed Building Permits and Site Removal
Although the appeal was accepted and the order annulled, the reasoning section discussed the proper application/inapplicability of this article as the basis for the original municipal order.
52.1995.572 · ti (art. 24 RLE)
Property Owner v. Municipality over Unauthorized Construction and Reviewing Authority's Substitution of Judgment
This provision, concerning the revocation of a permit due to lack of work progress, is referenced as the basis for the actions the municipality may take subsequently.
52.2008.110 · ti (art. 24 RLE)
Cantonal Court Upholds Refusal for Rustic Building Reconstruction Post-Landslide
Cited in the reasoning regarding the revocation of a building permit if work is not continued.
52.2017.458 · ti (art. 24 RLE)
Owner v. Municipality on Building Permit Revocation Timing
The decision to revoke the building permit (revocation) was judged premature and thus contrary to law based on this provision concerning permit revocation if works are not pursued in the usual manner and timelines.