Contractor can only claim overruns approved by client under express guarantee clause in employment contract.
Legislator summary
AI generatedThe appellate court dismissed the contractor's appeal against a lower court ruling that rejected their claim for additional payments. The contractor argued that the court failed to evaluate evidence regarding unapproved overruns and procedural defects, while the client contended that only approved changes justify extra charges under the express guarantee clause. The court held that without a formal contract modification for unforeseen circumstances, the contractor could not legally demand payment for work exceeding the original agreement's scope.
Legislator headnote
AI generatedčlen 133 ZOR; člen 338/I ZPP; Under an express guarantee clause in an employment contract, a contractor may claim only for overruns explicitly approved or specially ordered by the client, absent a formal contract modification for unforeseen circumstances.
Keywords
AI generatedCited Legislation
AI generatedRelated Decisions
AI generatedFull text
Pritožba se zavrne, izpodbijana sodba se p o t r d i .
Tožnik sam krije stroške pritožbenega postopka.
[JEDRO]
Višje plačilo od v pogodbi o delu dogovorjenega izračuna z izrecnim
jamstvom, sme podjetnik, izvajalec terjati od naročnika le za tiste
prekoračitve del, ki jih je naročnik odobril ali posebej naročil.
[OBRAZLOŽITEV]
Okrožno sodišče je s sodbo razveljavilo sklep o izvršbi Okrajnega
sodišča opr. št. z dne v točkah 1 in 3 njegovega izreka, torej za
celotno glavnico 1,949.415,16 SIT s pripadki in 39.862,00 SIT
izvršilnih stroškov in tožbeni zahtevek zavrnilo (točka I izreka),
kar je storilo tudi z med pravdo postavljenim tožbenim zahtevkom na
plačilo 506.549,60 SIT z zak. zam. obrestmi od treh zneskov, ki
tvorijo to glavnico (točka II) in tožnika obvezalo k povrnitvi
toženčevih stroškov postopka 375.894,00 SIT z istimi zamudnimi
obrestmi, a od 11.10.2005 dalje (točka III izreka).
Citirano sodbo tožnik izpodbija s pritožbo, uveljavljajoč z njo vse
tri v členu 338/I Zakona o pravdnem postopku - ZPP predvidene
pritožbene razloge in predlog njene spremembe z ugoditvijo tožbenemu
zahtevku, sicer pa razveljavitev in novo sojenje pred drugim
sodnikom, celo drugim sodiščem. Zaznamuje pritožbene stroške. Od
bistvenih kršitev določb pravdnega postopka navaja: medsebojno
nasprotje razlogov o odločilnih dejstvih oziroma z vsebino listin v
spisu, ki vse niso bile deležne presoje, kot da ne bi bile niti
prečitane. Kot primer nejasnosti razlogov povzema odlomek iz
izpodbijane sodbe, ki bi naj bil posebej moteč. Predvsem pa da
sodišče ni zavzelo stališča do nekaterih tožnikovih navedb in je
zadevo presojalo le z vidika sklenjene pogodbe med strankama
21.06.2000. Te pomanjkljivosti da so povzročile nedorečenost
dejanskih ugotovitev, ki so pomanjkljive in zmotne tako glede
prvotnega tožbenega zahtevka, kot njegove razširitve med pravdo.
Nadaljnji stroški da so bili potrebni, saj bi naj s pritegnitvijo
ZRMK toženca prepričal o napakah pri izdelavi drenaže in
kanalizacije, ki je povzročila velik časovni zastoj pri izvedbi
pogodbenih del. Potrebni stroški so tudi v zvezi s skladiščenjem
naročenega stekla, ki je bilo vgrajeno bistveno kasneje od roka v
pogodbi. Vztraja tudi pri tretji postavki stroških rezanja betona.
Odklonitev zaslišanja predlagane priče, brez pojasnila, čeprav gre za
direktorja, ki deluje v okviru Ministrstva RS, ki je do polovice
financiralo zaščito rimske opekarske peči, čeprav gre za nevtralno
osebo. Dokazne ocene da niso bile deležne tudi številne predložene
listine, kot so naročila toženca za izdelavo dodatnih projektov,
spremembe idejnega projekta in "odločitev" dogovorjenih del, kar vse
toženec zanika, neobravnavanje teh dokazov pa je povzročilo zmotno in
nepopolno ugotovitev dejanskega stanja, to pa naj bi bil zadosten
razlog za razveljavitev izpodbijane sodbe in novo sojenje drugje, ker
bi naj razpravljajoči sodnik prebival v neposredni bližini rimske
peči, katere zaščita se je zelo dolgo vlekla, in povzročila
razburjenje sosedov tudi po časopisih. Tako ustvarjena "medijska
vojna" in opazen toženčev vpliv na odločanje naj bi narekoval potrebo
po preselitvi zadeve v bolj nevtralno okolje.
Toženec na pritožbo ni odgovoril.
Pritožba ni utemeljena.
Ključni očitek o obstoju nasprotij med sodbenimi razlogi in
neusklajenostjo z vsebino listin v spisu, s katerimi da se sodišče
sploh ni seznanilo, je pavšalen brez konkretne navedbe listin, ki
niso bile upoštevane, a bi razodele za tožnika ugodnješo podobo
dejanskega stanja. Tožnik je soglašal z zapisom dokaznega sklepa v
zapisniku na zadnji glavni obravnavi glede ponovitve dotedanje
razpravljanja s povzetkom in sprejemom dotedanjih dokaznih sklepov,
pregledom dokumentacije in branjem izpovedb strank. Že takrat bi
moral opozoriti na še kak dokaz, ki ni bil omenjen oziroma prebran.
Zaslišanim pričam je sicer postavil nekaj vprašanj in dobil odgovore,
dopolnitev postopka zaradi razjasnitve nejasnosti ni zahteval, to
problematizira šele v pritožbi. Zavrnitev nadaljnjih dokazov ne
pomeni ne bistvene kršitve, vplivala pa tudi ni na pomankljivosti pri
ugotavljanju odločilnih dejstev. Pri tem pritožba niti ne pojasni,
kdaj je bila priča sploh predlagana za zaslišanje in o čem naj bi
izpovedovala. Zavrnitev nepotrebnih dokazov, za katere sodišče misli,
da niso potrebni za odločbo, zavrne in navede v sklepu razloge
zavrnitve - drugi odstavek člena 287 Zakona o pravdnem postopku -
ZPP. Zavrnitev nepotrebnih dokazov ni redkost pravdnih postopkov,
njihovo selekcijo opravi sodišče glede na potrebe, ki jih narekuje
sam postopek. Številni dokazi, s katerimi se tožnik prikazuje v
sijaju renomiranega in v tujini priznanega strokovnjaka pri zaščiti
arheoloških ostalin gotovo ne štejejo med take potrebne dokaze, kajti
pri izpolnitvi obveznosti iz obligacijskopravnega razmerja je moral
tožnik kot izvajalec delovati kot dober gospodarstvenik. Od
preštevilnih vloženih pripravljanih spisov tožnika velja opozoriti na
tistega z dne 18.02.2003 z več kot 100 listinskimi dokazi, od katerih
so le redki zgolj na eni strani. Vseh teh dokazov in številnih drugih
seveda ni mogoče obravnavati individualno. Vsi tudi ne morejo v enaki
meri vplivati na spodnjo praemisso sodniškega silogizma. Nekaterih
dokazov, kot je ugotovljeno že v izpodbijani sodbi, ko gre za
toženčeva naročila dodatnih del, pa tožnik vendarle ni predložil,
vendar bo o njih govora kasneje.
Kot primer nejasnosti in nasprotij razlogov sodbe pritožba citira
pasus na str. 3 sodbe, srednjega dela četrtega odstavka, ki glasi:
pravna podlaga razmerja, katerega obstoj je med strankama očitno
nesporen in je privedlo do tega, da je tožnik nesporno dobil plačano
805.630,00 SIT za idejno zasnovo, arhitekturo in projektantski nadzor
nad prvo fazo izvedbenih del, tako sodišču ni znana. Formulacija tega
stavka je sicer nekoliko zapletena, njen smisel pa dovolj nazoren
glede nespornosti plačila omenjenega zneska iz razmerja, ki nima
pokritja v pismeni pogodbi, s katero bi stranki definirali medsebojne
pogodbene obveznosti. Ne v tem, ne v drugih pavšalno očitanih
primerih ne gre za nasprotja ne med razlogi samimi, ne med njimi in
listinami in izvedenimi dokazi. Tudi drugih tovrstnih kršitev, ki se
respektirajo uradoma pregled zadeve ni pokazal.
Nepristranska ocena dejanskih ugotovitev tudi ne kaže podobe
pomanjkanja razlogov o relevantnih odločilnih dejstvih, ki bi jih
sicer moral dokazati tožnik in v tem pogledu pritožbeno sodišče
soglaša s sprejeto dokazno oceno, da tožnik naročil za dodatna dela
preko tistih iz pogodbe z dne 21.06.2000 ni dobil, k poglavitnim
pritožbenim trditvam, ki taki oceni nasprotujejo, pa naslednje:
Pogodba o zaščiti in predstavitvi rimske opekarske peči z dne
21.06.2000 je po definiciji del, ki jih je z njo prevzel tožnik kot
izvajalec, pogodba o delu iz člena 600 Zakona o obligacijskih
razmerjih - ZOR, ki je odločilen za razrešitev tega pravnega
razmerja, segajočega pred uveljavitvijo Obligacijskega zakonika - OZ,
ne pa določila gradbene pogodbe, ki je le nadgraditev pogodbe o delu
(glej prvi odstavek člena 630 ZOR). V pogodbi (njen sestavljalec je
tožnik sam) je v drugem odstavku člena 9 vpisana klavzula na ključ,
kar pomeni izračun z izrecnim jamstvom, torej po cenah iz predračuna,
ki je sestavni del pogodbe (a ga ni v spisu). Pomen izračuna z
izrecnim jamstvom definira prvi odstavek člena 624 ZOR tako: če je
bilo plačilo dogovorjeno na podlagi izračuna z izrecnim jamstvom
prevzemnika posla za njegovo pravilnost, ta ne sme zahtevati večjega
plačila, celo, če je v posel vložil več dela in če je izvršitev
terjala večje stroške, kot je pričakoval. Z vsemi tremi računi,
priloženimi k predlogu za izvršbo, tožnik zaračunava stroške, ki so
mu nastali in so višji od tistih v pogodbi ter bi bili upravičeni le
v primeru, če bi mu jih naročil naročnik, tožnik. Med temi
nadaljnjimi stroški so posebej problematični tisti v računu št. za
štirikratno potovanje na otok in brez pojasnila njihove koneksnosti s
prevzetimi deli. V času sklenitve pogodbe (ki šteje kot gospodarska)
bi tožnik kot dober gospodarstvenik moral predvideti tudi ovire, ki
bi lahko povzročile zastoj pri pravočasni in pravilni izpolnitvi
prevzetih obveznosti, zlasti zato, ker je bil s stanjem seznanjen že
pred sklenitvijo pogodbe, kar kaže njegov račun št. z dne 08.10.1999,
s katerim je tožencu zaračunal 805.630,00 SIT za zasnovo zaščite,
arhitekturo in nadzor. Tudi betonski obod je bil izdelan pred
sklenitvijo pogodbe. Tožnik na drugi strani tudi ni dokazal, kot
ugotavlja že izpodbijana sodba, da je med izpolnitvijo pogodbenih
obveznosti prišlo do neizogibnih in nepredvidenih del, zato mu
toženec teh zaračunanih del z računi ni dolžan plačati. Toženec je
zaradi zapletov s tožnikom tega obvestil o razdrtju pogodbe in odtlej
novih del ni naročal, čeprav mu jih je tožnik sugeriral. Med taka
naročila ne sodi niti toženčev poziv k pripravi dokumentacije za
pridobitev gradbenega dovoljenja, ker bi tožnik kot arhitekt moral na
to zakonsko zahtevo toženca opozoriti že pred sklenitvijo pogodbe
21.06.2000.
Kot nepredvideni stroški ne štejejo niti vsi zapleti s sanacijo
drenaže in kanalizacije, ki bi mogli biti aktualni šele pri
obravnavanju tožnikove nekajletne prekoračitve pogodbenega roka, ki
je potekel 30.10.2000, objekt pa je bil nared za prevzem šele v letu
2004. Višje plačilo od izračuna z izrecnim jamstvom iz pogodbe bi
tožnik kot izvajalec lahko terjal le v primeru spremembe pogodbe o
delu zaradi spremenjenih okoliščin, kakršen je predviden v prvem
odstavku člena 133 ZOR in bi moral pri tem dokazati, da gre za
nepredvidena, nepredvidljiva dela, zaradi katerih pogodba ne ustreza
več pričakovanjem pogodbenih strank. Tako spremembo pogodbe bi tožnik
težko dokazal, glede na njegovo udeležbo v predhodni fazi, za katero
mu je tožnik plačal omenjenih 805.630,00 SIT in da za pojav podtalne
vode na dnu arheološkega eksponata, ki je dejansko vplivala na
zastoje pri izgradnji, ni vedel, ali mogel računati. Zato se pritožba
brez uspeha sklicuje na toženčeva naročila zaračunanih del, ker teh
navedb ne dokumentira s konkretnimi listinami, ki bi izvirale od
toženca. Tako stanje je nazorno pojasnjeno tudi v izpodbijani sodbi,
denimo na str. ob koncu strani, takole: "Nenazadnje pa je tožnik ob
sklenitvi pogodbe z dne 21.06.2000 bil seznanjen s stanjem na
gradbišču, saj je že pred tem sodeloval pri projektu. Tako izhaja iz
izpovedi zaslišanih prič, zlasti, ki je podpisala obravnavano pogodbo
arheologinje toženca. Zahtevek tožnika po računih št. in, v skupni
višini 1,949.415,16 SIT z obrestmi, je tako brez pravne podlage in ga
je zato potrebno zavrniti.
S temi in dosedanjimi razlogi je mogoče pojasniti tudi zavrnitev med
pravdo povečanega tožbenega zahtevka v znesku 506.549,00 SIT in
razlogi izpodbijane sodbe v zvezi z zavrnitvijo tega dela. Tožnikovo
naročilo za pregled ZRMK (Zavod za raziskavo materiala in
konstrukcij) brez odobritve toženca kot naročnika posla, v fazi, ko
je bil tožnik že v izpolnitveni zamudi, ki jo je na tak način še
podaljšal, bremeni tožnika samega, saj ta pregled ni bil nujno
potreben in je z njim tožnik le dal duška svoji vnemi prepričevanja
toženca, da je imel prav. Da je bila kanalizacijska cev, ki je
potekala skozi prostor zaščitenega objekta, popolnoma uničena, se je
vedelo že pred poročilom o pregledu zatečenega gradbenega stanja te
inštitucije z dne 27.10.2000. Za izvedbo prevzetih del po pogodbi to
poročilo ni odločilno.
Del stroškov skladiščenja stekla je toženec že poravnal po nanj
izstavljenem računu, čeprav je tožniku dal na voljo prostor v delu
ptujskega gradu za skladiščenje stekla, vendar tožnik ni pokazal
pripravljenosti zmanjšanja stroškov skladiščenja pri tretji osebi.
Tudi strošek rezanja betona je bil zaračunan tožencu, saj je nanj
izdana faktura, ki jo je tudi plačal, tako da toženec tega stroška ni
dolžan plačati dvakrat, tožniku pa posebej še zato, ker je v času
sklenitve pogodbe mogel predvideti tudi rezanje odvečnega dela
betona, saj je bil seznanjen z gradnjo betonskega oboda, ki ga je
navsezadnje sam predvidel v idejnem projektu.
Tudi preizkus uporabljenega prava ni pokazal nepravilnosti ne pri
povzemanju določbe 624 ZOR, ne preostalih določb pogodbe o delu in
torej ni razlogov za predlagano poseganje v izpodbijano odločitev, ki
je potrjena po členu 353 ZPP. Zavrnitev pritožbe v glavni stvari je
vplivala tudi na nepriznanje akcesorij.