Contractor's claim for extra work without written consent dismissed due to statute of limitations and lack of necessity.
Legislator summary
AI generatedThe appellate court dismissed the contractor's appeal against the first-instance judgment rejecting a claim for 602,210 SIT for additional construction work. The contractor argued that the extra foundation work was necessary and beneficial, yet the first court found no written order or agreement for these deviations. The court upheld the dismissal because the contractor failed to prove the work was urgent enough to bypass written consent and the claim was barred by the statute of limitations. Consequently, the appeal was rejected as unfounded, and the original judgment confirming the defendant's non-liability was restored.
Legislator headnote
AI generated633. člen ZOR; 634. člen ZOR; 371. člen ZOR; 361. člen ZOR: A contractor cannot claim increased prices for work done without written consent unless the work was urgent and consent could not be obtained; additionally, claims must be filed within the statutory limitation period from the date the creditor could demand performance.
Keywords
AI generatedCited Legislation
AI generatedRelated Decisions
AI generatedFull text
Pritožba tožeče stranke se zavrne in se p o t r d i
izpodbijana sodba sodišča prve stopnje.
[JEDRO]
Pravdni stranki se za izvedbo dodatnih del nista dogovorili
in toženec ni dal (pisnega) naloga za izvedbo dodatnih del.
V času spornega razmerja veljavni 633. čl. Zakona o
obligacijskih razmerjih (ZOR) določa, da mora imeti
izvajalec za vsak odmik od gradbenega načrta oz. od
pogodbenih del pismeno soglasje naročnika, pri čemer za
dela, ki jih je opravil brez takega soglasja, ne more
zahtevati povečanja dogovorjene cene.
[OBRAZLOŽITEV]
Z izpodbijano sodbo je sodišče prve stopnje zavrnilo tožbeni
zahtevek, da je dolžna tožena stranka v roku 15 dni plačati
tožeči stranki 602.210,00 SIT z zakonskimi zamudnimi
obrestmi od 20.1.1994 do plačila. Hkrati je zavrnilo predlog
tožeče stranke za povračilo pravdnih stroškov.
Proti navedeni sodbi je tožeča stranka po svojem
pooblaščencu vložila pritožbo iz vseh pritožbenih razlogov
in predlagala njeno razveljavitev ter vrnitev zadeve
prvostopnemu sodišču v novo obravnavanje. Zatrjuje, da so
bile pri odločanju upoštevane le okolnosti, ki so govorile v
prid sprejetemu zaključku, da tožnik ni imel pisnega naloga
naročnika za izvedbo dodatnih del. Niso pa bile upoštevane
okoliščine, ki so kazale na drugačne zaključke: da je prišlo
po podpisu gradbene pogodbe št. 5/93 z dne 10.8.1993 do
spremembe oziroma bistvenega odstopanja od prvotnega
projekta in sicer konkretno pri izdelavi samih temeljev
objekta, ki jih je bilo treba na vzhodni strani poglobiti za
en meter, kar vse je posledično vplivalo na obseg armiranja
in betoniranja temeljev, da je navedeno spremembo zahteval
toženec, da so bila dela izvršena po navodilih toženca in da
so bila ta dela nujna ter da je tožnik navedena dela
izvršil, toženec pa jih je prevzel. Ker dodatna dela niso
pogodbena dela, je zato treba v zvezi z njimi skleniti novo
pogodbo oziroma aneks k prvotni pogodbi, s katero se določi
tudi cena za ta dela (35. uzanca PGU). Ne take pogodbe in ne
aneksa pa pravdni stranki v konkretnem primeru nista
sklenili, med drugim tudi zato ne, ker je tožnik tudi od
sklenjene pogodbe z dne 10.8.1993 odstopil, ker mu toženec
opravljenih del ni plačal. Pismeno soglasje naročnika del ni
nujna predpostavka za zahtevek za zvišanje cene del, če je
moral izvajalec dela izvršiti na zahtevo naročnika in je s
tem odstopil od projekta. Poleg tega bi moralo prvostopno
sodišče v tej smeri tudi ugotavljati, če so bila izvršena
dela nujna ali vsaj koristna za toženca, česar pa ni
storilo. Dokazno sklepanje prvostopnega sodišča na podlagi
18. in 19. uzance PGU je zato pravno zmotno, ker ne upošteva
spremenjenih okoliščin. Taka situacija je izrecno normirana
v 4. točki 23. uzance PGU. Stališče prvostopnega sodišča, da
tožnik okoliščin v zvezi z izvedbo dodatnih del ni uspel
dokazati, je tudi protispisno. Za ugotovitev navedenih
spornih dejstev je tožnik predlagal izvedbo dokaza z ogledom
po sodišču in z izvedencem gradbene stroke, kar vse je
sodišče zavrnilo. Zmotno je tudi stališče sodišča, da je
vtoževana terjatev zastarala. Tožnik je tožencu še pred
izpolnitvijo gradbene pogodbe z dne 10.8.1993 jasno pokazal,
da jo razdira, saj je od nje odstopil, kar je pokazal s tem,
da ni izvedel vseh dogovorjenih del do I. faze. Kot že
rečeno, za dodatna dela poseben aneks k prej navedeni
pogodbi ni bil sklenjen. Ker je tožnik dodatna dela na
toženčevem objektu nesporno izvedel, to pomeni, da je bil
toženec z navedenim tožnikovim delom neupravičeno obogaten,
tožnik pa neupravičeno prikrajšan. Tožnik je tako tožencu
kot tudi družbi K. d.o.o., ki mu je dokazano tudi plačevala
opravljeno delo, izstavil poseben račun za dodatno
opravljena dela št. 1/94 z dne 13.1.1994. Ker je tožnik
vložil tožbo v predmetni zadevi 12.1.1999, zastaralni rok za
zahtevek iz neupravičene pridobitve pa zastara v petih
letih, je bila tožba vložena pravočasno in zato vtoževana
tejatev ni zastarala, kot je to zmotno presodilo prvostopno
sodišče.
Pritožba tožeče stranke ni utemeljena.
Pravdni stranki sta 10.8.1993 sklenili Gradbeno pogodbo št.
05/93, s katero se je tožnik zavezal za toženca opraviti
gradbena dela do I. faze na objektu H. v pogodbeni vrednosti
33.511 DEM. Tožba temelji na trditvi, da je bila navedena
vrednost v obračunu gradbenih del iz meseca oktobra 1993
korigirana in povišana na znesek 37.336 DEM, da je do te
razlike prišlo pri izdelavi temeljev objekta zaradi
spremembe tehnične dokumentacije (projekta) in da je izvedbo
teh del naročil toženec. Sodišče prve stopnje pa je v zvezi
s tem ugotovilo, da se pravdni stranki za izvedbo dodatnih
del nista dogovorili in da toženec ni dal (pisnega) naloga
za izvedbo dodatnih del. V času spornega razmerja veljavni
633. čl. Zakona o obligacijskih razmerjih (ZOR) določa, da
mora imeti izvajalec za vsak odmik od gradbenega načrta oz.
od pogodbenih del pismeno soglasje naročnika, pri čemer za
dela, ki jih je opravil brez takega soglasja, ne more
zahtevati povečanja dogovorjene cene. Tožnik kot izvajalec
pa v obravnavanem primeru za izvedbo dodatnih del obstoja
pisnega soglasja toženca ni dokazal, ravno tako pa tudi ne
ustne privolitve toženca. Neutemeljen in protispisen je zato
pritožbeni očitek, češ da sodišče prve stopnje ni upoštevalo
dejstva, da naj bi spremembo del zahteval toženec. ZOR v 1.
odst. 634. čl. določa, da lahko izvajalec izvede
nepredvidena dela tudi brez poprejšnjega soglasja naročnika,
če si ga zaradi njihove nujnosti ni mogel preskrbeti. Tožnik
šele v pritožbi trdi, da so bila dodatna dela nujna (zato
gre v tem delu za nedopustne pritožbene novote po 1. odst.
337. čl. Zakona o pravdnem postopku, ZPP, glede na izostanek
tam navedenih pogojev), v postopku na prvi stopnji je
zatrjeval le, da je bilo treba temelje objekta na vzhodni
strani poglobiti za en meter, vendar pa zgolj na podlagi
takšnih trditev sodišče prve stopnje ni moglo samo
zaključiti, da je šlo za nujna nepredvidena dela po 2. odst.
634. čl. ZOR, predvsem pa ni tožnik zatrjeval, da si zaradi
njihove nujnosti ni mogel preskrbeti soglasja naročnika. Kot
nedopustne pritožbene novote pa tožnik šele v pritožbi
uveljavlja tudi, da so bila opravljena dodatna dela koristna
za toženca in da bi bilo treba uporabiti 3. tč. 23. Posebne
gradbene uzance (PGU); četudi ne bi šlo za novoto, je po
mnenju pritožbenega sodišča vprašljivo, ali je možno pod
izredne dogodke, kakršne obravnava citirano določilo uzance,
podrazumevati tudi potrebo po poglobitvi temeljev za en
meter.
Neutemeljeno pritožba izpodbija tudi ugotovitve sodišča prve
stopnje, da tožnik ni uspel dokazati okoliščin v zvezi z
dodatnimi deli; ne gre namreč za vprašanje, ali so bila ta
dela opravljena (ampak za vprašanje, ali jih je toženec
naročil), zato tudi ni prihajala v poštev izvedba dokaza z
ogledom oz. z izvedencem gradbene stroke. Tožbeni zahtevek
tožeče stranke je bil zato utemeljeno zavrnjen.
Utemeljeno pa je bil zavrnjen tožbeni zahtevek tudi zaradi
po tožencu uveljavljenega ugovora zastaranja terjatve; po
ugotovitvah sodišča prve stopnje je tožnik dokončni obračun
izdelal oktobra 1993. Pri začetku teka zastaralnega roka ne
gre za vprašanje, kdaj je nastala terjatev, kot to zmotno
meni sodišče prve stopnje, ampak za vprašanje, kdaj je imel
upnik pravico od dolžnika terjati izpolnitev obveznosti; 1.
odst. 361. čl. ZOR namreč določa, da začne zastaranje teči
prvi dan po dnevu, ko je upnik imel pravico terjati
izpolnitev obveznosti, če za posamezne primere ni z zakonom
predpisano kaj drugega. V obravnavanem primeru je sodišče
prve stopnje sicer ugotovilo, da tožnik ni dokazal, da bi
toženec prejel njegovo zahtevo za plačilo razlike po
dokončnem obračunu. Če bi tožnik to zahtevo tožencu
posredoval neposredno po izstavitvi dokončnega obračuna in
upoštevaje 63. uzanco PGU, da se na podlagi končne situacije
opravi izplačilo v 15 dneh od dneva njenega prejema, bi
tožnik imel pravico terjati izpolnitev obveznosti od toženca
še pred 31.12.1993. Glede na to je petletni zastaralni rok,
določen v 371. čl. ZOR, iztekel pred 31.12.1998 oz. v vsakem
primeru pred vložitvijo tožbe (12.1.1999). Ugotavljanje
pravočasnosti vložitve tožbe glede na uveljavljeno
zastaranje terjatve v povezavi z vprašanjem, ali je bil
toženec z opravljenimi deli neupravičeno obogaten, pa ne
prihaja v poštev, ker tožnik po tem temelju tožbenega
zahtevka v postopku na prvi stopnji ni uveljavljal.
Upoštevaje gornjo obrazložitev je pritožbeno sodišče, na
podlagi 353. čl. ZPP, pritožbo tožeče stranke zavrnilo kot
neutemeljeno in potrdilo izpodbijano sodbo sodišča prve
stopnje.